The document summarizes a project to replace the concrete riser structure and principal spillway pipe at Terra Grande Pond in Fairfax County, Virginia. The project was completed on May 18, 2021 and involved installing a new riser and end walls, restoring the dam embankment, installing dual culverts under the maintenance road, and restoring the inflow channel using natural stream design methods. The project team included Thornton Glenn as project manager, Mike Jones as construction inspector, and Brendan Schillo as construction engineer.
Silverbrook Road & Southrun Road Intersection ImprovementsFairfax County
Silverbrook Road and Southrun Road Intersection improvements project was substantially completed on April 12, 2021. The overall project scope was to the increase in pedestrian safety along Silverbrook Road and its intersection with Southrun Road. The new pedestrian walkway consisted of 83 lineal feet of 5-foot-wide concrete sidewalk along with 224 lineal feet of 6-foot-wide asphalt walking path. Additionally, the Right Turn from Silverbrook Road onto Southrun Road was improved and lengthened. Along with the access improvements upgrades were made to the storm drain system and minor re-alignments of waterlines.
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
Westmoreland Street bike lanes project was substantially completed on April 12, 2021. The project scope was the extension of road bike lanes along both sides of Westmoreland Street north of Rosemont Drive toward Old Chesterbrook Road. Works on the project included roadway widening, approximately 400 feet long concrete variable width sidewalk, curb and gutters, driveway entrances, bus stop loading pad, milling and paving, pavement marking and signs.
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County
The scope of this project was construction of concrete sidewalk, curb and gutter, curb-cut ramps, retaining wall, pavement mill and overlay, pavement markings and signings, closed drainage system improvements and watermain relocation.
Silverbrook Road & Southrun Road Intersection ImprovementsFairfax County
Silverbrook Road and Southrun Road Intersection improvements project was substantially completed on April 12, 2021. The overall project scope was to the increase in pedestrian safety along Silverbrook Road and its intersection with Southrun Road. The new pedestrian walkway consisted of 83 lineal feet of 5-foot-wide concrete sidewalk along with 224 lineal feet of 6-foot-wide asphalt walking path. Additionally, the Right Turn from Silverbrook Road onto Southrun Road was improved and lengthened. Along with the access improvements upgrades were made to the storm drain system and minor re-alignments of waterlines.
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
Westmoreland Street bike lanes project was substantially completed on April 12, 2021. The project scope was the extension of road bike lanes along both sides of Westmoreland Street north of Rosemont Drive toward Old Chesterbrook Road. Works on the project included roadway widening, approximately 400 feet long concrete variable width sidewalk, curb and gutters, driveway entrances, bus stop loading pad, milling and paving, pavement marking and signs.
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County
The scope of this project was construction of concrete sidewalk, curb and gutter, curb-cut ramps, retaining wall, pavement mill and overlay, pavement markings and signings, closed drainage system improvements and watermain relocation.
Lukens Lane Intersection Improvements Phase IIFairfax County
Lukens Lane Intersection Improvements - Phase II project provides pedestrian improvements at the intersection of Richmond Highway and Lukens Lane. The improvements include, but are not limited to, new concrete median and island, CG-12 curb ramps, modification to curb and gutter returns, sidewalk, reconstruction of entrances, mill and overlay, pavement marking, signage, signal modification and fire hydrant relocation.
McLean Hunt Estates Pond Improvement ProjectFairfax County
The McLean Hunt Estates Pond Improvement Project consisted of retrofitting an existing dry pond to an extended detention dry pond. The goals of the project were to stabilize the incoming degraded channel constructing a step pool conveyance system; replace the existing corrugated metal pipe principal spillway pipe with reinforced concrete pipe; install a new riser structure with BMP plate to provide water quality benefits; and upgrade the asphalt trail into an access road to accommodate equipment/vehicles for future maintenance.
The Telegraph Walkway Project was substantially completed on time and under budget on September 13, 2021. This project consisted of construction of 5’ concrete sidewalk, curb ramp, curb & gutter, drilled shaft for slope stability, RW-3, handrail, pavement mill and overlay, pavement marking, water line relocation and some other related items.
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayFairfax County
The Glade Drive Walkway improvement project from Middle Creek Lane to Glade Bank Way included construction of pedestrian access improvements along the north side of Glade Drive to include approximately 643 linear feet of curb-abutted sidewalk, pedestrian ramps, curb and gutter, asphalt trail, and mill and overlay.
Difficult Run Tributary at Brittenford Drive Stream RestorationFairfax County
Difficult Run Tributary at Brittenford Drive Stream Restoration Project has been substantially completed. The purpose of this project was to rehabilitate approximately 5,400 linear feet of the Difficult Run stream and tributaries in Vienna, VA through the use of natural channel design (NCD) techniques to restore “natural” stream flow.
Workhouse Arts Foundation Cross-County TrailFairfax County
The Workhouse Arts Foundation Cross County Trail Project included the construction of approximately 2,850 linear feet of a 10-foot wide asphalt trail and 4-foot wide stone dust trail, curb cut ramp, pavement marking and signage, and related items.
Hunter Mill Road and Sunrise Valley Drive Pedestrian ImprovementsFairfax County
The project provides pedestrian improvements at the intersection of Hunter Mill Road (Route 674) and Sunrise Valley Drive (Route 6320). Improvements include installing 1,037 linear feet of concrete sidewalk, curb and gutter, concrete sidewalks, curb ramps, refuge island, realigning the southbound right turn lane, and milling and asphalt paving near the intersection. Drainage improvements include installing 1,069 linear feet of storm drain pipes, curb drop inlets, and a Filterra unit.
Route 1 Northbound - Virginia Lodge to Huntington AvenueFairfax County
Construction included a pedestrian walkway of 1,320 linear feet of concrete sidewalk and curb ramps, signal modification, extension of an existing box culvert, repair of cracks and spalled areas in the existing culvert, installation of guard rails and end treatments, and watermain relocation.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
Lukens Lane Intersection Improvements Phase IIFairfax County
Lukens Lane Intersection Improvements - Phase II project provides pedestrian improvements at the intersection of Richmond Highway and Lukens Lane. The improvements include, but are not limited to, new concrete median and island, CG-12 curb ramps, modification to curb and gutter returns, sidewalk, reconstruction of entrances, mill and overlay, pavement marking, signage, signal modification and fire hydrant relocation.
McLean Hunt Estates Pond Improvement ProjectFairfax County
The McLean Hunt Estates Pond Improvement Project consisted of retrofitting an existing dry pond to an extended detention dry pond. The goals of the project were to stabilize the incoming degraded channel constructing a step pool conveyance system; replace the existing corrugated metal pipe principal spillway pipe with reinforced concrete pipe; install a new riser structure with BMP plate to provide water quality benefits; and upgrade the asphalt trail into an access road to accommodate equipment/vehicles for future maintenance.
The Telegraph Walkway Project was substantially completed on time and under budget on September 13, 2021. This project consisted of construction of 5’ concrete sidewalk, curb ramp, curb & gutter, drilled shaft for slope stability, RW-3, handrail, pavement mill and overlay, pavement marking, water line relocation and some other related items.
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayFairfax County
The Glade Drive Walkway improvement project from Middle Creek Lane to Glade Bank Way included construction of pedestrian access improvements along the north side of Glade Drive to include approximately 643 linear feet of curb-abutted sidewalk, pedestrian ramps, curb and gutter, asphalt trail, and mill and overlay.
Difficult Run Tributary at Brittenford Drive Stream RestorationFairfax County
Difficult Run Tributary at Brittenford Drive Stream Restoration Project has been substantially completed. The purpose of this project was to rehabilitate approximately 5,400 linear feet of the Difficult Run stream and tributaries in Vienna, VA through the use of natural channel design (NCD) techniques to restore “natural” stream flow.
Workhouse Arts Foundation Cross-County TrailFairfax County
The Workhouse Arts Foundation Cross County Trail Project included the construction of approximately 2,850 linear feet of a 10-foot wide asphalt trail and 4-foot wide stone dust trail, curb cut ramp, pavement marking and signage, and related items.
Hunter Mill Road and Sunrise Valley Drive Pedestrian ImprovementsFairfax County
The project provides pedestrian improvements at the intersection of Hunter Mill Road (Route 674) and Sunrise Valley Drive (Route 6320). Improvements include installing 1,037 linear feet of concrete sidewalk, curb and gutter, concrete sidewalks, curb ramps, refuge island, realigning the southbound right turn lane, and milling and asphalt paving near the intersection. Drainage improvements include installing 1,069 linear feet of storm drain pipes, curb drop inlets, and a Filterra unit.
Route 1 Northbound - Virginia Lodge to Huntington AvenueFairfax County
Construction included a pedestrian walkway of 1,320 linear feet of concrete sidewalk and curb ramps, signal modification, extension of an existing box culvert, repair of cracks and spalled areas in the existing culvert, installation of guard rails and end treatments, and watermain relocation.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
Guinea Road and Lakepointe Drive Sidewalk and Intersection ImprovementsFairfax County
This project consisted of construction of approximately 800 feet of 5-foot wide concrete sidewalk, curb and gutter, curb ramps, concrete bus pads, and an upgrade of the existing storm water conveyance system along with storm water control features. This project will enhance the safety of pedestrian traffic through the intersection of Guinea Road and Lakepointe Drive.
This project included renovations and building systems replacement/upgrades at the Department of Vehicle Services’ West Ox Maintenance Facility, which provides vehicle maintenance and repair services for Fire and Rescue apparatus, heavy and light duty trucks, and FCPS school buses.
Brown's Chapel Property Pond and Outfall ImprovementFairfax County
This site is located within the Difficult Run Watershed. The project involved the installation of a forebay to ease future maintenance, construction of gravel access road, replacement of head wall and BMP trash rack, stabilization of outfall channel with steps. The improvement stabilizes the existing channel and prevents/minimizes future erosion of the channel bed and banks reducing downstream sedimentation.
The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Hunting Creek at Fairfield Stream RestorationFairfax County
The Hunting Creek at Fairchild Stream Restoration project, Substantially Completed on January 13, 2021, includes restoring, enhancing and stabilizing approximately 1,186 linear feet of stream channel in two segments and 166 linear feet of tributary through natural channel design to provide aquatic benefits, grade control, improve water quality and prevent further erosion. The work also included demolition of a condemned house and accessory structures including obtaining all associated demolition permits and restoration landscaping.
Project Description:
The Newington Commons Pond Improvement Project has been Substantially Completed. The purpose of this project was the restoration of approximately 351 linear feet of stream and improvement of the receiving stormwater pond.
Project Overview:
Dredging of the pond to increase storage volume
Replacement of the concrete riser structure
Restoration of stream channels utilizing natural channel design
Merrywood Force Main Rehabilitation ProjectFairfax County
The Merrywood Force Main Rehabilitation project included rehabilitation of 1,080 linear feet of 6-inch force main, its discharge manhole, and the installation of a future bypass system in front of the pump station.
Route 123 and Jermantown Rd. Intersection Improvements November 2020Fairfax County
This project consisted of the construction of a right turn lane on north and south bound Route 123, concrete sidewalk, asphalt trail, curb and gutter, intersection improvements, mill and overlay, pavement markings and stormdrain installation.
Jermantown Vehicle Services Maintenance Facility UpgradesFairfax County
The project consisted of various facility upgrades, including significant capital renewal and replacement of outdated building systems. Ten of the existing vehicle service lifts were replaced with new lifts, and a new covered structure for dumpsters and a new tire storage area were constructed. Additional work included various mechanical, electrical and plumbing system upgrades and replacement throughout the facility. The existing sprinkler system was also extended and upgraded to provide coverage for the entire facility. Existing men’s and women’s locker rooms were upgraded to comply with all Americans with Disabilities Act requirements.
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Project No. SD-000033-091
Mount Vernon District
Tax Map No. 99-3
6/16/2021
Terra Grande Pond
PSP and Riser Replacement
2. Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
3. Project Details
Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Project Overview:
• Replacement of the concrete riser structure and principal spillway pipe (PSP)
• Installation of riser end walls
• Restoration of the dam embankment
• Installation of dual culvert pipes under maintenance road
• Restoration of ~300 feet of inflow channel through natural stream design methods
Project Description:
The Terra Grande Pond PSP and Riser Replacement Project was substantially completed
on May 18, 2021. The purpose of this project was to perform necessary capital
maintenance, increase the performance of the pond, enhance the facility, and isolate
future maintenance needs.
Project Team:
• Project Manager - Thornton Glenn, Maintenance and Stormwater Management Division
• Construction Inspector - Mike Jones, Utilities Design and Construction Division
• Construction Engineer - Brendan Schillo, Utilities Design and Construction Division
4. Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
7590 Woodstown Dr., Springfield, VA 22153; Tax Map #99-3
5. Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Installation of Concrete Riser Structure and End Walls
6. Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Restoration of Dam Embankment
7. Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Installation of Dual Culvert Under Maintenance Rd
8. Before After
Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
9. Before After
Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
10. Before After
Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
11. Before After
Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
12. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Terra Grande Pond PSP and Riser Replacement
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Sharon North or Irene Haske in the
DPWES Public Information Office
703-324-5500, TTY 711
Sharon.North@fairfaxcounty.gov
Irene.Haske@fairfaxcounty.gov