SlideShare a Scribd company logo
Team Structures and Project Performance
    in the Design-Build / Integrated
     Project Delivery Marketplace
          Mark E. Alpert, P.E., DBIA
                CH2M HILL
• Introduction           Agenda
• Team Structure
  –   Engineer-lead
  –   Integrated design-build without self-performance
  –   Integrated design-build with self-performance
  –   Constructor-led
  –   Other markets
• Owners’ Team Structure Preferences
• Implications for Companies Going Forward
Introduction: teams must have a
                 design-build mindset



Engineer      Constructor

                              Engineer
  Engineer                  + Constructor
+ Constructor               + Design-Build Mindset
≠ DESIGN-BUILD              = DESIGN-BUILD

                                                     3
OWNERS’ DELIVERY PREFERENCES
Typical Design-Build Team Structures
  • Engineer-lead

  • Contractor-lead

   • Integrated design-build without
     self-performance
  • Integrated design-build with
    self-performance

                                       5
Engineer-Lead
• Will require clear division of responsibility
  between engineer and contractor
• Technical complexity
   – New/unproven/cutting edge technology
• Stringent project requirements
   – Increased effluent quality, consent decree mandate
• David L. TippincommercialFacility, Tampa. FL
   Unique Water Treatment requirements
             2002 DBIA Water Systems Quality Award
• Owner preference of approach in team structure

                                                          6
Contractor-led
• Will require clear division of responsibility
   between contractor and engineer
• Normal structure for transportation market
• Project risk is lower than a complex processing
   facility
• Greater site constraints/challenges
• Past experience with project owner
• Larger projectWater Treatment Plant and
Southern Delivery System bonding requirements?
                       Finished Water Pump Station
• Legislation mandating self-performance
                         Colorado Springs, Colorado
Integrated design-build
                          without self-performance
  • Single firm with full project responsibility
  • May or may not be schedule-driven
  • Owner wants input into subcontractor/vendor
      selection
  • Greater involvement from local market
  • Legislation may not allow self-performance
  • Simple team structure with single point of
      accountability
Bonita Springs East Water Reclamation Facility, Bonita Springs, FL.
  • MustDBIA Excellence Awardfor Projects over $15 Million
        2008 meet security for performance requirements
Integrated design-build
                                with self-performance
    • Technical and procurement expertise required
    • Local or state legislation or policy mandates self-
       performance
    • Self-performance potentially cheaper than
       subcontracted work
    • Must be able to manage all project risks
       successfully
    • Project cost is critical
    • Must meetDBIA National Water/Wastewater Award
Spokane County Regional Water Reclamation Facility, Spokane, WA
                  2012 security for performance
       requirements
Planning   Market     Deliver
                                 Implications for
                                 Practioners
  • Decide what structure fits   • Define what risk is
    best for your firm             acceptable to your firm
  • Identify personnel who       • Inform insurance
    can be effective with          companies and banks of
    selected structure and         different business
    project requirements           approach
  • Define what’s a “good        • What additional business
    deal” for your firm and        infrastructure is needed
    how much are you willing       to be successful
    to invest to win


                                                          10
Planning   Market     Deliver
                                        Get Smart on
                                  What Clients Expect
  • Performance guarantees      • Transparency in pricing
  • Cost of work                • Design for design-build
  • Financial risk and margin   • Project management –
    expectations                  add the right talent




                                                            11
Planning    Market       Deliver
                                 Deliver Work and Refine
                                   from Lessons Learned
  • Choose experienced Design-        • Accountability will be key in
    Build Manager to lead firm’s        performance
    team
  • Commit core experienced
    resources to projects
  • Establish pricing criteria that
    is market based and meets
    firm’s business goals
  • Standardized systems and
    tools to
    control, cost, scope, and
    schedule

                                                                    12
Significant Opportunities for
   Design-Build Delivery
Tailor your business to the market and
  mandated delivery structures that match
          clients and opportunities.
The future is bright for those firms that adapt
        to the changing marketplace.

More Related Content

What's hot

Ohio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New RealityOhio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New Reality
Kegler Brown Hill + Ritter
 
Design Build Intro
Design Build IntroDesign Build Intro
Design Build Intro
semackler
 
2013 Federal D-B Downsized
2013 Federal D-B Downsized2013 Federal D-B Downsized
2013 Federal D-B Downsized
Lisa Cooley, LEED AP
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
teohwooisin
 
Business of anaerobic digestion project delivery basics
Business of anaerobic digestion project delivery basicsBusiness of anaerobic digestion project delivery basics
Business of anaerobic digestion project delivery basics
eisenmannusa
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
Pang Khai Shuen
 
Introduction to soft landings 2
Introduction to soft landings 2Introduction to soft landings 2
Introduction to soft landings 2
Marie Orritt
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
Allan Berry
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract management
raymond_wan2005
 
VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)
habibfathi
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
Charles S. Maggio
 
Sandip Mukherjee Profile
Sandip Mukherjee ProfileSandip Mukherjee Profile
Sandip Mukherjee Profile
sandipm
 
Scott Bunce 4+ Years Of Innovation
Scott Bunce 4+ Years Of InnovationScott Bunce 4+ Years Of Innovation
Scott Bunce 4+ Years Of Innovation
Scott Bunce
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
resume-.PDF (2)
resume-.PDF (2)resume-.PDF (2)
resume-.PDF (2)
nishit dalal
 
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Energy Network marcus evans
 
A g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier pptA g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier ppt
p6academy
 
A g cs perspective on primavera unifier - Oracle Primavera P6 Collaborate 14
A g cs perspective on primavera unifier  - Oracle Primavera P6 Collaborate 14A g cs perspective on primavera unifier  - Oracle Primavera P6 Collaborate 14
A g cs perspective on primavera unifier - Oracle Primavera P6 Collaborate 14
p6academy
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
Flobz Caloy
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
shillier38
 

What's hot (20)

Ohio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New RealityOhio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New Reality
 
Design Build Intro
Design Build IntroDesign Build Intro
Design Build Intro
 
2013 Federal D-B Downsized
2013 Federal D-B Downsized2013 Federal D-B Downsized
2013 Federal D-B Downsized
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 
Business of anaerobic digestion project delivery basics
Business of anaerobic digestion project delivery basicsBusiness of anaerobic digestion project delivery basics
Business of anaerobic digestion project delivery basics
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Introduction to soft landings 2
Introduction to soft landings 2Introduction to soft landings 2
Introduction to soft landings 2
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract management
 
VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
 
Sandip Mukherjee Profile
Sandip Mukherjee ProfileSandip Mukherjee Profile
Sandip Mukherjee Profile
 
Scott Bunce 4+ Years Of Innovation
Scott Bunce 4+ Years Of InnovationScott Bunce 4+ Years Of Innovation
Scott Bunce 4+ Years Of Innovation
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
resume-.PDF (2)
resume-.PDF (2)resume-.PDF (2)
resume-.PDF (2)
 
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
 
A g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier pptA g cs persepective on primavera unifier ppt
A g cs persepective on primavera unifier ppt
 
A g cs perspective on primavera unifier - Oracle Primavera P6 Collaborate 14
A g cs perspective on primavera unifier  - Oracle Primavera P6 Collaborate 14A g cs perspective on primavera unifier  - Oracle Primavera P6 Collaborate 14
A g cs perspective on primavera unifier - Oracle Primavera P6 Collaborate 14
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 

Similar to Team Structures and Project Performance in the Design-Build Marketplace

Taking the Creep Out of Scope Creep
Taking the Creep Out of Scope CreepTaking the Creep Out of Scope Creep
Taking the Creep Out of Scope Creep
Computer Aid, Inc
 
Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10
friscozephyr
 
Using Agile Approach with Fixed Budget Projects
Using Agile Approach with Fixed Budget ProjectsUsing Agile Approach with Fixed Budget Projects
Using Agile Approach with Fixed Budget Projects
Synerzip
 
Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...
mike benedetto
 
project management
project managementproject management
project management
Sanchita Siromoni
 
UNIT 1
UNIT 1UNIT 1
Offshore product development - a case study
Offshore product development - a case studyOffshore product development - a case study
Offshore product development - a case study
Check Business
 
Shapiro Solo Sheet 2009 09 21 Linked In
Shapiro Solo Sheet 2009 09 21 Linked InShapiro Solo Sheet 2009 09 21 Linked In
Shapiro Solo Sheet 2009 09 21 Linked In
ShapiroCara
 
Pe ch 1
Pe ch   1Pe ch   1
Pe ch 1
tumhara
 
Dtp Intro 061811
Dtp Intro 061811Dtp Intro 061811
Dtp Intro 061811
Non-dilutive.com
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
Salvador Carlos Hernandez Ramirez
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
Salvador Carlos Hernandez Ramirez
 
Agile fixed-price-slide share
Agile fixed-price-slide shareAgile fixed-price-slide share
Agile fixed-price-slide share
Kurush Wadia
 
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Lviv Startup Club
 
57086 10 business_case
57086 10 business_case57086 10 business_case
57086 10 business_case
Engineering Department
 
Creating high performance project teams 2013
Creating high performance project teams   2013Creating high performance project teams   2013
Creating high performance project teams 2013
Edward Byers, PMP, SSGB
 
The SPH EPC Way
The SPH EPC WayThe SPH EPC Way
The SPH EPC Way
SapPresents1
 
Risk on complex_projects_project_auditors
Risk on complex_projects_project_auditorsRisk on complex_projects_project_auditors
Risk on complex_projects_project_auditors
Joy Gumz
 
Navbuild
NavbuildNavbuild
Construction Add On for Navision
Construction Add On for NavisionConstruction Add On for Navision
Construction Add On for Navision
Cetas Information Technology Pvt Ltd
 

Similar to Team Structures and Project Performance in the Design-Build Marketplace (20)

Taking the Creep Out of Scope Creep
Taking the Creep Out of Scope CreepTaking the Creep Out of Scope Creep
Taking the Creep Out of Scope Creep
 
Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10
 
Using Agile Approach with Fixed Budget Projects
Using Agile Approach with Fixed Budget ProjectsUsing Agile Approach with Fixed Budget Projects
Using Agile Approach with Fixed Budget Projects
 
Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...Business Case Strategies For Integrating Comissioning With Construction And P...
Business Case Strategies For Integrating Comissioning With Construction And P...
 
project management
project managementproject management
project management
 
UNIT 1
UNIT 1UNIT 1
UNIT 1
 
Offshore product development - a case study
Offshore product development - a case studyOffshore product development - a case study
Offshore product development - a case study
 
Shapiro Solo Sheet 2009 09 21 Linked In
Shapiro Solo Sheet 2009 09 21 Linked InShapiro Solo Sheet 2009 09 21 Linked In
Shapiro Solo Sheet 2009 09 21 Linked In
 
Pe ch 1
Pe ch   1Pe ch   1
Pe ch 1
 
Dtp Intro 061811
Dtp Intro 061811Dtp Intro 061811
Dtp Intro 061811
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
 
Agile fixed-price-slide share
Agile fixed-price-slide shareAgile fixed-price-slide share
Agile fixed-price-slide share
 
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...Андрій Просов  “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
 
57086 10 business_case
57086 10 business_case57086 10 business_case
57086 10 business_case
 
Creating high performance project teams 2013
Creating high performance project teams   2013Creating high performance project teams   2013
Creating high performance project teams 2013
 
The SPH EPC Way
The SPH EPC WayThe SPH EPC Way
The SPH EPC Way
 
Risk on complex_projects_project_auditors
Risk on complex_projects_project_auditorsRisk on complex_projects_project_auditors
Risk on complex_projects_project_auditors
 
Navbuild
NavbuildNavbuild
Navbuild
 
Construction Add On for Navision
Construction Add On for NavisionConstruction Add On for Navision
Construction Add On for Navision
 

Recently uploaded

2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
aragme
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
MJ Global
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
LuanWise
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
ecamare2
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
NZSG
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Lviv Startup Club
 
Recruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media MasterclassRecruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media Masterclass
LuanWise
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
Chandresh Chudasama
 
buy old yahoo accounts buy yahoo accounts
buy old yahoo accounts buy yahoo accountsbuy old yahoo accounts buy yahoo accounts
buy old yahoo accounts buy yahoo accounts
Susan Laney
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 

Recently uploaded (20)

2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
 
Building Your Employer Brand with Social Media
Building Your Employer Brand with Social MediaBuilding Your Employer Brand with Social Media
Building Your Employer Brand with Social Media
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
 
Recruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media MasterclassRecruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media Masterclass
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
 
buy old yahoo accounts buy yahoo accounts
buy old yahoo accounts buy yahoo accountsbuy old yahoo accounts buy yahoo accounts
buy old yahoo accounts buy yahoo accounts
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 

Team Structures and Project Performance in the Design-Build Marketplace

  • 1. Team Structures and Project Performance in the Design-Build / Integrated Project Delivery Marketplace Mark E. Alpert, P.E., DBIA CH2M HILL
  • 2. • Introduction Agenda • Team Structure – Engineer-lead – Integrated design-build without self-performance – Integrated design-build with self-performance – Constructor-led – Other markets • Owners’ Team Structure Preferences • Implications for Companies Going Forward
  • 3. Introduction: teams must have a design-build mindset Engineer Constructor Engineer Engineer + Constructor + Constructor + Design-Build Mindset ≠ DESIGN-BUILD = DESIGN-BUILD 3
  • 5. Typical Design-Build Team Structures • Engineer-lead • Contractor-lead • Integrated design-build without self-performance • Integrated design-build with self-performance 5
  • 6. Engineer-Lead • Will require clear division of responsibility between engineer and contractor • Technical complexity – New/unproven/cutting edge technology • Stringent project requirements – Increased effluent quality, consent decree mandate • David L. TippincommercialFacility, Tampa. FL Unique Water Treatment requirements 2002 DBIA Water Systems Quality Award • Owner preference of approach in team structure 6
  • 7. Contractor-led • Will require clear division of responsibility between contractor and engineer • Normal structure for transportation market • Project risk is lower than a complex processing facility • Greater site constraints/challenges • Past experience with project owner • Larger projectWater Treatment Plant and Southern Delivery System bonding requirements? Finished Water Pump Station • Legislation mandating self-performance Colorado Springs, Colorado
  • 8. Integrated design-build without self-performance • Single firm with full project responsibility • May or may not be schedule-driven • Owner wants input into subcontractor/vendor selection • Greater involvement from local market • Legislation may not allow self-performance • Simple team structure with single point of accountability Bonita Springs East Water Reclamation Facility, Bonita Springs, FL. • MustDBIA Excellence Awardfor Projects over $15 Million 2008 meet security for performance requirements
  • 9. Integrated design-build with self-performance • Technical and procurement expertise required • Local or state legislation or policy mandates self- performance • Self-performance potentially cheaper than subcontracted work • Must be able to manage all project risks successfully • Project cost is critical • Must meetDBIA National Water/Wastewater Award Spokane County Regional Water Reclamation Facility, Spokane, WA 2012 security for performance requirements
  • 10. Planning Market Deliver Implications for Practioners • Decide what structure fits • Define what risk is best for your firm acceptable to your firm • Identify personnel who • Inform insurance can be effective with companies and banks of selected structure and different business project requirements approach • Define what’s a “good • What additional business deal” for your firm and infrastructure is needed how much are you willing to be successful to invest to win 10
  • 11. Planning Market Deliver Get Smart on What Clients Expect • Performance guarantees • Transparency in pricing • Cost of work • Design for design-build • Financial risk and margin • Project management – expectations add the right talent 11
  • 12. Planning Market Deliver Deliver Work and Refine from Lessons Learned • Choose experienced Design- • Accountability will be key in Build Manager to lead firm’s performance team • Commit core experienced resources to projects • Establish pricing criteria that is market based and meets firm’s business goals • Standardized systems and tools to control, cost, scope, and schedule 12
  • 13. Significant Opportunities for Design-Build Delivery
  • 14. Tailor your business to the market and mandated delivery structures that match clients and opportunities. The future is bright for those firms that adapt to the changing marketplace.

Editor's Notes

  1. Prime/Sub or Joint VentureUsually single firm with team subcontractorsUsually single firm without team subcontractorsEngineer subconsultant to contractor
  2. David L. Tippin Water Treatment Facility, Tampa. FL2002 DBIA Water Systems Quality Award
  3. Bonita Springs East Water Reclamation Facility, Bonita Springs, FL. 2008 DBIA Excellence Award for Projects over $15 Million
  4. Spokane County Regional Water Reclamation Facility, Spokane, WA2012 DBIA National Water/Wastewater Award