According to Juran, for the average American manufacturer, the costs of not quality in some cases come to represent 30% of the sales price.
For the builder or client company, a non compliance of contract causes delays in the delivery date, affecting site operations, these delays can generate additional costs not covered: costs of Labor, equipment and penalties if it affect start up of the project. In Peru, in national projects, 75% of projects had delays of up to 60 days.
In this situation, Supplier Management should be an alternative that allows early identification of a delay in delivery date, decline in the quality requirements, the possibility to capture information relevant to decision-making, in order to prevent and mitigate its effects on the project progress.
Episode 28 : Project Management Contract
most important document for the execution of a project.
project management - know very well, includes all important issues regarding supply and services
Fulfillment of requirements, review the contractual situation, to claim the respective extra costs
project engineers :
mastered the fundamental aspects of the contractual arrangements for negotiated with subcontractor
depends on the relevant information of the team members.
actual contract arrangement - trained and experienced traders and lawyers
Fédération Internationale des Ing é-nieurs - Conseils ” (FIDIC)
take equally into account the interests of Conditions of Contract for Works of Civil Engineering and Construction Conditions of Contract for Electrical an Mechanical Works
jus strictum (binding law) and jus dispositivum (modifiable law).
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
A project promoter or developer has an option to give single contract on turnkey basis on single contractor or to source project packages/components from several suppliers. Advantages of an EPC single contract are highlighted in this presentation.
Engagement Coordinator Megan Hoye gave a presentation on CEE's research projects to the American Institute of Architects Minnesota's, Committee on the Environment.
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Shrikant Kate
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construction Management _ Final Year (BE) _ Department of Civil Engineering _ TAE _ SPPU _ by Shrikant R. Kate
Construction scheduling, work study and work measurement Construction scheduling.
Construction project scheduling – purpose, factors affecting scheduling, time as a control tool
Work Breakdown Structure, project work breakdown levels, line of balance technique
Repetitive project management Work study and work measurement
Definition, objectives, basic procedure of work study, symbols, activity charts, string diagrams, time and motion studies.
Come At Pet Friendly Hotel near Cartersville GA and enjoy our hospitality at affordable room Rates Guarantied. Book Your Hotel in Cartersville GA http://www.qualityinnacartersville.com/.
Episode 28 : Project Management Contract
most important document for the execution of a project.
project management - know very well, includes all important issues regarding supply and services
Fulfillment of requirements, review the contractual situation, to claim the respective extra costs
project engineers :
mastered the fundamental aspects of the contractual arrangements for negotiated with subcontractor
depends on the relevant information of the team members.
actual contract arrangement - trained and experienced traders and lawyers
Fédération Internationale des Ing é-nieurs - Conseils ” (FIDIC)
take equally into account the interests of Conditions of Contract for Works of Civil Engineering and Construction Conditions of Contract for Electrical an Mechanical Works
jus strictum (binding law) and jus dispositivum (modifiable law).
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
A project promoter or developer has an option to give single contract on turnkey basis on single contractor or to source project packages/components from several suppliers. Advantages of an EPC single contract are highlighted in this presentation.
Engagement Coordinator Megan Hoye gave a presentation on CEE's research projects to the American Institute of Architects Minnesota's, Committee on the Environment.
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Shrikant Kate
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construction Management _ Final Year (BE) _ Department of Civil Engineering _ TAE _ SPPU _ by Shrikant R. Kate
Construction scheduling, work study and work measurement Construction scheduling.
Construction project scheduling – purpose, factors affecting scheduling, time as a control tool
Work Breakdown Structure, project work breakdown levels, line of balance technique
Repetitive project management Work study and work measurement
Definition, objectives, basic procedure of work study, symbols, activity charts, string diagrams, time and motion studies.
Come At Pet Friendly Hotel near Cartersville GA and enjoy our hospitality at affordable room Rates Guarantied. Book Your Hotel in Cartersville GA http://www.qualityinnacartersville.com/.
Rehabilitation after LRTI surgery (Burton)Karin van Pelt
E-poster considering successful early mobilization following surgery of the base of the thumb, presented at the IFSSH & IFSHT Triennal Congress 2016 at Buenos Aires.
Social Business Workshop - Payap University - Yunus CenterAndres Parraguirre
If you need the file, just shoot me an email contact@parra.me
This Workshop covers the following objectives:
○ Gain a common understanding of the social business concept promoted by Muhammad Yunus, its similarities and differences with other current social enterprise models, within the particular context of Thailand and Payap University.
○ Articulate the rationale for setting up an SE Center at Payap University, identify relevant drivers and challenges for creating interest in social business within the discussion of enterprise-led sustainable development.
○ Derive viable action points for taking the SE Centre proposal forward, based on discussion and reflection during the peer workshop, and visualize tangible targets for the SE Centre in terms general outcomes.
The "Asset Life Cycle, Cost Estimating and the CCRG (Cost Construction Reporting Guide 2005)" was an educational seminar provided as a joint panel offered through the Alberta Assessors Association in their 2015 annual conference. This learning opportunity was organized with the sole objective to share with the audience the best practices when reporting construction projects for property tax rendition purposes. We delved into the legal framework, the segregation of included versus excluded costs and the challenges Owners face while executing industrial projects.
Nature- Need for Project Management – types of projects – Project Management Knowledge areas and processes – Project skills – The role of Project Manager – Project Management Processes – Impact of Delays in Project Completions – Essential of Project Management Philosophy – Project Management Principles
Artificial intelligence (AI) offers new opportunities to radically reinvent the way we do business. This study explores how CEOs and top decision makers around the world are responding to the transformative potential of AI.
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...CIOWomenMagazine
This person is none other than Oprah Winfrey, a highly influential figure whose impact extends beyond television. This article will delve into the remarkable life and lasting legacy of Oprah. Her story serves as a reminder of the importance of perseverance, compassion, and firm determination.
The case study discusses the potential of drone delivery and the challenges that need to be addressed before it becomes widespread.
Key takeaways:
Drone delivery is in its early stages: Amazon's trial in the UK demonstrates the potential for faster deliveries, but it's still limited by regulations and technology.
Regulations are a major hurdle: Safety concerns around drone collisions with airplanes and people have led to restrictions on flight height and location.
Other challenges exist: Who will use drone delivery the most? Is it cost-effective compared to traditional delivery trucks?
Discussion questions:
Managerial challenges: Integrating drones requires planning for new infrastructure, training staff, and navigating regulations. There are also marketing and recruitment considerations specific to this technology.
External forces vary by country: Regulations, consumer acceptance, and infrastructure all differ between countries.
Demographics matter: Younger generations might be more receptive to drone delivery, while older populations might have concerns.
Stakeholders for Amazon: Customers, regulators, aviation authorities, and competitors are all stakeholders. Regulators likely hold the greatest influence as they determine the feasibility of drone delivery.
The Team Member and Guest Experience - Lead and Take Care of your restaurant team. They are the people closest to and delivering Hospitality to your paying Guests!
Make the call, and we can assist you.
408-784-7371
Foodservice Consulting + Design
Senior Project and Engineering Leader Jim Smith.pdfJim Smith
I am a Project and Engineering Leader with extensive experience as a Business Operations Leader, Technical Project Manager, Engineering Manager and Operations Experience for Domestic and International companies such as Electrolux, Carrier, and Deutz. I have developed new products using Stage Gate development/MS Project/JIRA, for the pro-duction of Medical Equipment, Large Commercial Refrigeration Systems, Appliances, HVAC, and Diesel engines.
My experience includes:
Managed customized engineered refrigeration system projects with high voltage power panels from quote to ship, coordinating actions between electrical engineering, mechanical design and application engineering, purchasing, production, test, quality assurance and field installation. Managed projects $25k to $1M per project; 4-8 per month. (Hussmann refrigeration)
Successfully developed the $15-20M yearly corporate capital strategy for manufacturing, with the Executive Team and key stakeholders. Created project scope and specifications, business case, ROI, managed project plans with key personnel for nine consumer product manufacturing and distribution sites; to support the company’s strategic sales plan.
Over 15 years of experience managing and developing cost improvement projects with key Stakeholders, site Manufacturing Engineers, Mechanical Engineers, Maintenance, and facility support personnel to optimize pro-duction operations, safety, EHS, and new product development. (BioLab, Deutz, Caire)
Experience working as a Technical Manager developing new products with chemical engineers and packaging engineers to enhance and reduce the cost of retail products. I have led the activities of multiple engineering groups with diverse backgrounds.
Great experience managing the product development of products which utilize complex electrical controls, high voltage power panels, product testing, and commissioning.
Created project scope, business case, ROI for multiple capital projects to support electrotechnical assembly and CPG goods. Identified project cost, risk, success criteria, and performed equipment qualifications. (Carrier, Electrolux, Biolab, Price, Hussmann)
Created detailed projects plans using MS Project, Gant charts in excel, and updated new product development in Jira for stakeholders and project team members including critical path.
Great knowledge of ISO9001, NFPA, OSHA regulations.
User level knowledge of MRP/SAP, MS Project, Powerpoint, Visio, Mastercontrol, JIRA, Power BI and Tableau.
I appreciate your consideration, and look forward to discussing this role with you, and how I can lead your company’s growth and profitability. I can be contacted via LinkedIn via phone or E Mail.
Jim Smith
678-993-7195
jimsmith30024@gmail.com
1. SUPPLIER MANAGEMENT
A TOOL TO PREVENT THE DELAY AND NON-
COMPLIANCE WITH CONTRACTUAL
REQUIREMENTS IN HEAVY & MEDIUM
CONSTRUCTION PROJECT
QUALITY CULTURE SAC
Management to continuous improvement
2. Background
• Capital projects are capitalized investment in time. (T = $)
• Projects with overlapping activities (fast-track), and
construction requirements JIT (Just in Time)
• A delay in the previous activities have a multiplifier effect
in time and project's costs.
Id Nombre de tarea Duración
1 Adquisición de emplazamiento 30 días
2 Obra civil 20 días
3 Instalación 5 días
4 Configuración 2 días
5 Pruebas 2 días
11/04 11/11 11/18 11/25 12/02 12/09 12/16 12/23 12/30 01/06 01/13 01/20 01/27
iembre diciembre enero f
3. Background
• The construction are exposed to no meet the deadline.
These indice reach almost 75%
• 45% of this delay are due to management problems.
• According to Jurans, for american suppliers, the costs of
no Quality reach in some cases 30% of sales price.
• No investigation studies in supply management , in our
country.
4. Problem
• In Project Management is unavoidable to have new
suppliers that allow us to outsource new activities.
• The poor training in management of manufacturing
companies produce 80% of the errors.
• Culture of "don't report errors" within providers.
• Culture of unpunctuality: Little commitment to meeting
deadlines of manufacturing startups.
5. Three Cause - Effect
DELAYS FOR NON-
CUMPLIANCE OF
CONTRACT
REQUIREMENTS
Poor Evaluation of Supplier
Poor Quality Control
Poor Project Management
QMS No implemented
Poor Production Capacity
QMS No Executed
Personal without Competence
Supplier's PM without experience
Derating Capacity by lack of attention
Unknow of Quality Requirements
Desynchronized Administrative
Processes
Poor Finantial Capacity
6. Supplier Management Services seeks to minimize or
better yet avoid the consequences caused by :
• Delays in delivery date or promised date .
• Fail in compliance with contractual requirements, and
• Failure to meet changes or modifications to the
purchase order.
• Additional costs not covered: for claims (MO and
paralyzed Resources & others in site).
• Saving by penalties of opportunity cost for delays of
PROJECT start up.
Objetives
7. Objetives
General Objetive:
Analyze the management of metalworking, electrics, and
civil suppliers, so that would prevent cost overruns by a
delay and compliance with contractual specifications.
Specific Objetives
• Relation of supplier management with the delay or non-
delivery.
• Relation of supplier management with the fulfill of
contractual specifications.
8. IMPORTANCE
8
The benefits of this research are for both companies
Operators and suppliers, since this proposal is made
to increase the competitiveness of both
• For supplier improve the management, quality and
delivery time with consequent savings and economic
benefit, and
• For construction consolidating of its
supply chain and reducing the risks
inherent to sub-contracting or
purchasing equipment.
9. IMPORTANCE
9
The benefits of this research are for both companies
Operators and metalworking suppliers, since this
proposal is made to increase the competitiveness of
both
• Logistic
• Quality, &
• Sub-Contract management
10. Supplier Management
We make available this work Supplier Management that
will allow:
• Contro & Meet real delivery time
• Anticipate the consequences of non-compliance with
contractual requirements and take steps in advance.
• Anticipated construction cost overruns for claims.
• Establish Supplier Management indicators in their
contracts.
11. Supplier Management
We make available this Supplier Management Services which breaks
down into:
• Supplier Evaluation
• Quality Assurance
• Shop Expediting (Activation)