Construction of a
General Cargo Vessel
PROJECT MANAGEMENT
TEAM TEN
● Project Charter
● Stakeholders
● Project Management Plan & Process
● Work Breakdown Structure
● Project schedule/Gantt chart
● Quality Check
● Post Project Review
INDEX
06-08-2022
POSITION INTERESTS INTERNAL/
EXTERNAL
Government
Taxation, VAT, Legislation, employment, truthful reporting, diversity,
legalities, externalities.
External
Employees Rates of pay, job security, compensation, respect, truthful communication. Internal
Customers Value, quality, customer care, ethical products. External
Suppliers
Providers of products and services used in the end product for the
customer, equitable business opportunities.
External
Creditors Credit score, new contracts, liquidity. External
Community
Jobs, involvement, environmental protection, shares, truthful
communication.
External
Trade Unions Quality, worker protection, jobs. Internal
Owners
Profitability, longevity, market share, market standing, succession planning,
raising capital, growth, social goals.
Internal
Investors Return on investment, income. External
STAKEHOLDERS
Project Management Plan
Production Management Plan
Budgets & Schedules
Work Orders and Time Charging
Material Control & Work Order
Pallets
Technical Packages for Production
Tests & Quality Assurance
Contract Management Plan
Project Management Team
Change Order Management
Progress Milestones & Payment
Management
Project Management Process
•
• Management of Persons Involved
• Management of EnquiriesEnquiry Stage
• Database of Past Work
• Material & Supply Estimates
• Vendor Database
• Estimates of Quotes
Bidding Stage
• Planning | Coordination | Execution | Monitoring
• Avoiding Conflict of Process & Department
Execution Stage
• Regulatory Approvals
• Test & Trials
• Delivery
• Invoicing
Delivery Stage
• Follow Up
• Feedback
• Documentation of Future Project
Post Delivery
Cost Estimating
Planning,Budgeting
& Scheduling
Labor & Manpower
Cost management
Earned Value
Management
Reporting
Purchasing &
Material Cost
Management
Cost Analysis
GANTT CHART
QUALITY CHECK
● Welding
● Cutting
● Electricity
● Wood works
● Plumbing
● Piping
● Auxiliary machinery
● Mooring Gear
● Safety Gear
● Accomodation
● Feeding System
● Fire systems
● Control system
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
Post Project Review
1. Performance review of every individual onboard for project.
2. Site Supervision & Reporting.
logistic Supply.
Proper surface preparation and coating application.
Safety and long-term maintenance.
3. Commissioning, Dock & Sea Trial Assistance
Monitoring.
Commissioning of machinery and system.
Equipment compliance as contracted.
4. Guarantee Claim Handling, Minimum vessel downtime
5. Equipment package review.
Serviceability.
Product suitability for intended type.
Load testing of all equipment.
6. Technical Specification Review.
Rulebook with all suppliers & makers list , with specification in central database.
7. Retrospection
TEAM
ABHINEK KUMAR
ABHISHEK SINGH
ARJUN REGHU
DHAIRYA SOLANKI
SRISHTI SINGH
TUSHAR BHAJIPALE
VED PRAKASH PAL
20191001
20191002
20191005
20191054
20191056
20191061
20191064

More Related Content

What's hot

Albany Medical Center Hospital PROJECT MANAGEMENT
Albany Medical Center Hospital PROJECT MANAGEMENTAlbany Medical Center Hospital PROJECT MANAGEMENT
Albany Medical Center Hospital PROJECT MANAGEMENTDouglas K. Axelson C.P.M.
 
Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...
Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...
Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...
Techshore Inspection Services
 
Voice Line Improvement Case Study
Voice Line Improvement Case StudyVoice Line Improvement Case Study
Voice Line Improvement Case StudyMarcin Malinowski
 
Aker Solutions resume
Aker Solutions resumeAker Solutions resume
Aker Solutions resumeMitchell Lee
 
Tooling Management Project
Tooling Management ProjectTooling Management Project
Tooling Management Projectchris stewart
 
Intergen energy ltd.
Intergen energy ltd.Intergen energy ltd.
Intergen energy ltd.
Intergen Energy Ltd.
 
Crow 2017
Crow 2017Crow 2017
Crow 2017
Gregory Crow
 
JAMES WRIGHT Resume
JAMES WRIGHT ResumeJAMES WRIGHT Resume
JAMES WRIGHT ResumeJames Wright
 
Electrical Assurance Presentation 2010
Electrical Assurance Presentation 2010Electrical Assurance Presentation 2010
Electrical Assurance Presentation 2010
mseaborn
 
Swayamacademicwriting
SwayamacademicwritingSwayamacademicwriting
Swayamacademicwriting
Sunil P Kumar
 
Peter Knowles Resume
Peter Knowles ResumePeter Knowles Resume
Peter Knowles ResumePeter Knowles
 
LRQA: EMBRAER Case Study - Carbon Disclosure Project Verification Strategy
LRQA: EMBRAER Case Study - Carbon Disclosure Project Verification StrategyLRQA: EMBRAER Case Study - Carbon Disclosure Project Verification Strategy
LRQA: EMBRAER Case Study - Carbon Disclosure Project Verification StrategyLloyd's Register - Management Systems
 

What's hot (19)

Ajay_CV_SQA
Ajay_CV_SQAAjay_CV_SQA
Ajay_CV_SQA
 
CV_Goh Yeu Shan, Aaron
CV_Goh Yeu Shan, AaronCV_Goh Yeu Shan, Aaron
CV_Goh Yeu Shan, Aaron
 
Albany Medical Center Hospital PROJECT MANAGEMENT
Albany Medical Center Hospital PROJECT MANAGEMENTAlbany Medical Center Hospital PROJECT MANAGEMENT
Albany Medical Center Hospital PROJECT MANAGEMENT
 
Electrical_Intern_Objectives r1
Electrical_Intern_Objectives r1Electrical_Intern_Objectives r1
Electrical_Intern_Objectives r1
 
Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...
Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...
Techshore Inspection Services in Kochi Kollam Calicut Thrissur Pathanamthitta...
 
Voice Line Improvement Case Study
Voice Line Improvement Case StudyVoice Line Improvement Case Study
Voice Line Improvement Case Study
 
Aker Solutions resume
Aker Solutions resumeAker Solutions resume
Aker Solutions resume
 
Tooling Management Project
Tooling Management ProjectTooling Management Project
Tooling Management Project
 
Intergen energy ltd.
Intergen energy ltd.Intergen energy ltd.
Intergen energy ltd.
 
MY JOB DESCRIPTION
MY JOB DESCRIPTIONMY JOB DESCRIPTION
MY JOB DESCRIPTION
 
Crow 2017
Crow 2017Crow 2017
Crow 2017
 
JAMES WRIGHT Resume
JAMES WRIGHT ResumeJAMES WRIGHT Resume
JAMES WRIGHT Resume
 
Value Stream Map
Value Stream MapValue Stream Map
Value Stream Map
 
Electrical Assurance Presentation 2010
Electrical Assurance Presentation 2010Electrical Assurance Presentation 2010
Electrical Assurance Presentation 2010
 
Swayamacademicwriting
SwayamacademicwritingSwayamacademicwriting
Swayamacademicwriting
 
Peter Knowles Resume
Peter Knowles ResumePeter Knowles Resume
Peter Knowles Resume
 
Resume
ResumeResume
Resume
 
ALameResume
ALameResumeALameResume
ALameResume
 
LRQA: EMBRAER Case Study - Carbon Disclosure Project Verification Strategy
LRQA: EMBRAER Case Study - Carbon Disclosure Project Verification StrategyLRQA: EMBRAER Case Study - Carbon Disclosure Project Verification Strategy
LRQA: EMBRAER Case Study - Carbon Disclosure Project Verification Strategy
 

Similar to Construction of a General Cargo Vessel

Sachin be mech_8_yrs_exp
Sachin be mech_8_yrs_expSachin be mech_8_yrs_exp
Sachin be mech_8_yrs_exp
sachin tagalpallewar
 
Resume
ResumeResume
BERR Industry / MAIN Presentation
BERR Industry / MAIN PresentationBERR Industry / MAIN Presentation
BERR Industry / MAIN Presentation
Murat Cengiz
 
GENERAL PRESENTATION FILE of THE BERR INDUSTRY
GENERAL PRESENTATION FILE of THE BERR INDUSTRYGENERAL PRESENTATION FILE of THE BERR INDUSTRY
GENERAL PRESENTATION FILE of THE BERR INDUSTRY
Berr Industry
 
INDUSTRIAL ENGINEERING SOLUTIONS
INDUSTRIAL ENGINEERING SOLUTIONSINDUSTRIAL ENGINEERING SOLUTIONS
INDUSTRIAL ENGINEERING SOLUTIONS
BERR Industrial engineering Services
 
Brushless dc motor
Brushless dc motorBrushless dc motor
Brushless dc motor
aroosa khan
 
Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3Sushil Kumar Jain
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
priyang2004
 
RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10Satyanarayana Raju
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
Malcolm Peart
 

Similar to Construction of a General Cargo Vessel (20)

Sachin be mech_8_yrs_exp
Sachin be mech_8_yrs_expSachin be mech_8_yrs_exp
Sachin be mech_8_yrs_exp
 
Resume
ResumeResume
Resume
 
BERR Industry / MAIN Presentation
BERR Industry / MAIN PresentationBERR Industry / MAIN Presentation
BERR Industry / MAIN Presentation
 
Husains CV
Husains CVHusains CV
Husains CV
 
Turnover Engineer
Turnover EngineerTurnover Engineer
Turnover Engineer
 
Resume New
Resume NewResume New
Resume New
 
Pranav.Varshney
Pranav.VarshneyPranav.Varshney
Pranav.Varshney
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 
SHAILESH MISHRA_ RESUME
SHAILESH MISHRA_ RESUMESHAILESH MISHRA_ RESUME
SHAILESH MISHRA_ RESUME
 
GENERAL PRESENTATION FILE of THE BERR INDUSTRY
GENERAL PRESENTATION FILE of THE BERR INDUSTRYGENERAL PRESENTATION FILE of THE BERR INDUSTRY
GENERAL PRESENTATION FILE of THE BERR INDUSTRY
 
INDUSTRIAL ENGINEERING SOLUTIONS
INDUSTRIAL ENGINEERING SOLUTIONSINDUSTRIAL ENGINEERING SOLUTIONS
INDUSTRIAL ENGINEERING SOLUTIONS
 
Brushless dc motor
Brushless dc motorBrushless dc motor
Brushless dc motor
 
Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3
 
Raghavendra Resume
Raghavendra ResumeRaghavendra Resume
Raghavendra Resume
 
Resume -UD
Resume -UDResume -UD
Resume -UD
 
Prashant Wani1
Prashant Wani1Prashant Wani1
Prashant Wani1
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10
 
Pradeep CV
Pradeep CV Pradeep CV
Pradeep CV
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
 

More from Arjun Reghu

ORGANIZATIONAL INNOVATION SLIDES MBA PDPU
ORGANIZATIONAL INNOVATION SLIDES MBA PDPUORGANIZATIONAL INNOVATION SLIDES MBA PDPU
ORGANIZATIONAL INNOVATION SLIDES MBA PDPU
Arjun Reghu
 
TYPES OF SOLAR ENERGY HARVESTING TECHNIQUES
TYPES OF SOLAR ENERGY HARVESTING TECHNIQUESTYPES OF SOLAR ENERGY HARVESTING TECHNIQUES
TYPES OF SOLAR ENERGY HARVESTING TECHNIQUES
Arjun Reghu
 
Learning transfer FULL PRESENTATION
Learning transfer FULL PRESENTATIONLearning transfer FULL PRESENTATION
Learning transfer FULL PRESENTATION
Arjun Reghu
 
A STUDY ON COMMERCIAL ASPECTS OF LNG
A STUDY ON COMMERCIAL ASPECTS OF LNGA STUDY ON COMMERCIAL ASPECTS OF LNG
A STUDY ON COMMERCIAL ASPECTS OF LNG
Arjun Reghu
 
GE BAKER HUGHES ACUSITION
GE BAKER HUGHES ACUSITION GE BAKER HUGHES ACUSITION
GE BAKER HUGHES ACUSITION
Arjun Reghu
 
IS THIS END OF CRUDE OIL INDUSTRY?
IS THIS END OF CRUDE OIL INDUSTRY?IS THIS END OF CRUDE OIL INDUSTRY?
IS THIS END OF CRUDE OIL INDUSTRY?
Arjun Reghu
 
A Presentation on Heat Exchangers
A Presentation on Heat ExchangersA Presentation on Heat Exchangers
A Presentation on Heat Exchangers
Arjun Reghu
 
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTORNEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
Arjun Reghu
 
Stop Climate Change by Removing CO2
Stop Climate Change by Removing CO2Stop Climate Change by Removing CO2
Stop Climate Change by Removing CO2
Arjun Reghu
 
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTORNEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
Arjun Reghu
 

More from Arjun Reghu (10)

ORGANIZATIONAL INNOVATION SLIDES MBA PDPU
ORGANIZATIONAL INNOVATION SLIDES MBA PDPUORGANIZATIONAL INNOVATION SLIDES MBA PDPU
ORGANIZATIONAL INNOVATION SLIDES MBA PDPU
 
TYPES OF SOLAR ENERGY HARVESTING TECHNIQUES
TYPES OF SOLAR ENERGY HARVESTING TECHNIQUESTYPES OF SOLAR ENERGY HARVESTING TECHNIQUES
TYPES OF SOLAR ENERGY HARVESTING TECHNIQUES
 
Learning transfer FULL PRESENTATION
Learning transfer FULL PRESENTATIONLearning transfer FULL PRESENTATION
Learning transfer FULL PRESENTATION
 
A STUDY ON COMMERCIAL ASPECTS OF LNG
A STUDY ON COMMERCIAL ASPECTS OF LNGA STUDY ON COMMERCIAL ASPECTS OF LNG
A STUDY ON COMMERCIAL ASPECTS OF LNG
 
GE BAKER HUGHES ACUSITION
GE BAKER HUGHES ACUSITION GE BAKER HUGHES ACUSITION
GE BAKER HUGHES ACUSITION
 
IS THIS END OF CRUDE OIL INDUSTRY?
IS THIS END OF CRUDE OIL INDUSTRY?IS THIS END OF CRUDE OIL INDUSTRY?
IS THIS END OF CRUDE OIL INDUSTRY?
 
A Presentation on Heat Exchangers
A Presentation on Heat ExchangersA Presentation on Heat Exchangers
A Presentation on Heat Exchangers
 
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTORNEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
 
Stop Climate Change by Removing CO2
Stop Climate Change by Removing CO2Stop Climate Change by Removing CO2
Stop Climate Change by Removing CO2
 
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTORNEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
NEW BUSINESS MODELS & DIGITALIZATION IN THE ENERGY SECTOR
 

Recently uploaded

Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
kimdan468
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
Mohammed Sikander
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 

Recently uploaded (20)

Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 

Construction of a General Cargo Vessel

  • 1. Construction of a General Cargo Vessel PROJECT MANAGEMENT TEAM TEN
  • 2. ● Project Charter ● Stakeholders ● Project Management Plan & Process ● Work Breakdown Structure ● Project schedule/Gantt chart ● Quality Check ● Post Project Review INDEX
  • 4. POSITION INTERESTS INTERNAL/ EXTERNAL Government Taxation, VAT, Legislation, employment, truthful reporting, diversity, legalities, externalities. External Employees Rates of pay, job security, compensation, respect, truthful communication. Internal Customers Value, quality, customer care, ethical products. External Suppliers Providers of products and services used in the end product for the customer, equitable business opportunities. External Creditors Credit score, new contracts, liquidity. External Community Jobs, involvement, environmental protection, shares, truthful communication. External Trade Unions Quality, worker protection, jobs. Internal Owners Profitability, longevity, market share, market standing, succession planning, raising capital, growth, social goals. Internal Investors Return on investment, income. External STAKEHOLDERS
  • 5. Project Management Plan Production Management Plan Budgets & Schedules Work Orders and Time Charging Material Control & Work Order Pallets Technical Packages for Production Tests & Quality Assurance Contract Management Plan Project Management Team Change Order Management Progress Milestones & Payment Management
  • 6. Project Management Process • • Management of Persons Involved • Management of EnquiriesEnquiry Stage • Database of Past Work • Material & Supply Estimates • Vendor Database • Estimates of Quotes Bidding Stage • Planning | Coordination | Execution | Monitoring • Avoiding Conflict of Process & Department Execution Stage • Regulatory Approvals • Test & Trials • Delivery • Invoicing Delivery Stage • Follow Up • Feedback • Documentation of Future Project Post Delivery
  • 7. Cost Estimating Planning,Budgeting & Scheduling Labor & Manpower Cost management Earned Value Management Reporting Purchasing & Material Cost Management Cost Analysis
  • 8.
  • 9.
  • 10.
  • 11.
  • 13. QUALITY CHECK ● Welding ● Cutting ● Electricity ● Wood works ● Plumbing ● Piping ● Auxiliary machinery ● Mooring Gear ● Safety Gear ● Accomodation ● Feeding System ● Fire systems ● Control system ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔
  • 14. Post Project Review 1. Performance review of every individual onboard for project. 2. Site Supervision & Reporting. logistic Supply. Proper surface preparation and coating application. Safety and long-term maintenance. 3. Commissioning, Dock & Sea Trial Assistance Monitoring. Commissioning of machinery and system. Equipment compliance as contracted. 4. Guarantee Claim Handling, Minimum vessel downtime 5. Equipment package review. Serviceability. Product suitability for intended type. Load testing of all equipment. 6. Technical Specification Review. Rulebook with all suppliers & makers list , with specification in central database. 7. Retrospection
  • 15. TEAM ABHINEK KUMAR ABHISHEK SINGH ARJUN REGHU DHAIRYA SOLANKI SRISHTI SINGH TUSHAR BHAJIPALE VED PRAKASH PAL 20191001 20191002 20191005 20191054 20191056 20191061 20191064