SlideShare a Scribd company logo
1 of 25
Download to read offline
Smooth Integration
of Modules On-Site
6TH ANNUAL MODULAR CONSTRUCTION &
PREFABRICATION SUMMIT
PRESENTER: SCOTT COOMBES
Introduction
Project Manager, having been a Project
Engineer and involved in the Coal Seam Gas
industry for the last 7.5 yeas.
Involved in a range of
projects (over the full
life-cycle):
• Large gas compression
and processing plants,
• Gas and water
gathering networks
including wellhead
surface facilities.
• Exploration pilots and
dam construction.
• Water treatment and
water / brine injection
test facilities.
Agenda
A. Introduction
B. Why modularise / pre-fabricate
C. Identification of opportunities and cost savings
D. Integration of modularisation strategy within project
E. Identifying whether detailing developed is in collaboration with the
design team, general contractor, fabricator and installer.
F. Designing the project so that work structured for what is done on-site
matches what has been manufactured in the factory
G. Efficient flow of site assembly works.
H. Hook-up / connection onsite
I. Closing summary
I believe the principals behind
successful modularisation apply
across all sectors.
I will also provide some specific
examples of what worked. This will
be based on process plants.
For the purpose of this
presentation:
• Pre-fabrication,
• Equipment skidding,
• Equipment modularisation
Can all be take as “modularisation”;
the principal discussed generally
apply to all of the above.
Why modularise / pre-
fabricate?
The drivers behind your modularisation strategy should be clear:
• What do you hope to achieve in taking this approach?
• What are the trade offs that have been made?
• What are the risk associated with the strategy being taken?
Delving deeper than a presumed and schedule saving or quality
improvement.
Being clear of the objectives and this feeding into each stage of work
and work planning is key.
Integration (or planning) of your modularisation strategy over the whole
of project lifecycle is key to the best results (or success as verse failure
in some cases).
This especially the case is this is different to you (as a company / team).
Benefits
Cost:
• Access to lower labour rates,
• Access to lower / no labour overheads,
• Improved labour efficiency,
Schedule:
• Early commencement long lead scope.
• Design interfaces (can be a decrease in
complexity or an increase in complexity).
• Elimination of trades / work sequences on
critical path site works.
• May be the only effective method for
concurrent work.
De-risking project
• Work outside of weather issues or site
access considerations.
• May be more able to remove scope poor
performing fabricators as vs site works.
• Typically shop or yard fabrication is able to
be executed in a manner lending itself to
safer methods as well as better / more
efficient QA / QC process.
Project Management:
• Typically a structured / effective
method for separation of scope and
packages to various parties (with
options for more competitive
bidding).
• Can simplify site installation scope,
and provide clear boundaries
between scopes.
• Fabrication management is typically
less intensive than site management
(onshore fabrication).
• Reduced site scope / time with the
associated stakeholder benefits.
• Decongested worksites / reduced site
manning pressures.
• Ability for extensive offsite testing
and control optimisation.
Identification of opportunities
and cost savings.
Suggestions for identification and
prioritisation:
• Break the project down and target the
high cost area’s first.
• Quantify the cost difference between
on and off site work (including
efficiency).
• Identify the associated benefits from
modularisation, benchmark and cost
these.
• Review what others are doing, out of
your sector / industry (good for idea’s
and contacts).
• Look at what’s putting the highest risk
and or management burden into your
project.
$-
$50.00
$100.00
$150.00
$200.00
$250.00
Brisbane Remote
Rate Comparison - Supervisor (2014)
($/h)
Base Rate (to client) Accomidation
Vehicle Costs Travel on and off shift costs
Daily paid travel time Remote site productivity impact
Why Modularise - A specific case on
specialised labour.
Equipment, plant and system complexity generally increasing over
time.
This leads to increased requirements for specialist labour onsite,
especially during start up and commissioning.
The overhead, lead time and resource utilisation on site is lower than
in most fabrication workshops or yards.
One example. Mobilisation of a specific PLC programmer from
Adelaide to central Queensland.
• 2+ days of induction,
• 1 week lead time, 2 days mobilisation and demobilisation each way.
• Increased rates,
• Decreased productivity onsite.
For less than a weeks work onsite. Do it before the equipment arrives
onsite.
Integration of modularisation
strategy within a project
As the portion of scope that is modularised or the module complexity
increase’s this integration (or consideration of impacts) increasingly
critical.
Key considerations in early project planning / feasibility are:
Logistics Estimating and Planning Design
Transport / route module size
/ weight limits, can these be
changed?
What are the cost savings
(and what drives the
realisation of those costs).
Does the system / project
lend itself (or parts of it) to
modularisation or pre
fabrication.
Receiving site size / weight
limits.
What are the cost increases. Are there any major
departures in design
requirements to the norm?
Transport options lead-time,
duration and time
constraints.
What are the schedule
changes.
What’s the best module
stagey considering available
information.
Design and Delivery
Design Fabrication Contracting
Are new skills required? Complexity of scope and risk to project may
be different. Are you using the right
contract’s (from both a management and risk
mitigation perspective).
How is the layout / high level design done
considerate of modularisation. Factoring
access, lifting, module connection /
interfaces.
Depending on strategy, there may be an
increased volume of work tendered /
procured / expedited.
How do the modules interface efficiently. Are you fabricators experienced delivering to
the required standards (more QA / QC or
documentation scope may be associated with
the increased module scope).
What are the O&M requirements relating to
access, congestion or packaging.
How are transport constraints to be
managed? Are there any constraints local to
the fabricator?
Design and Delivery - continued
Construction Others
Does the construction work planning and
execution hinge on module deliveries?
Do you have to build out from modules?
Is there enough scope outside of the modules
(or enough work force flexibility) to cope with
changed module delivery dates?
Are there any stakeholder impacts e.g.
• Concerns over local content
• Impacts to the community due to module
transport (can be very visible).
Is a change in the workforce or plant
equipment required for efficient delivery.
Maximisation of offsite testing and plant
optimisation.
Is there a risk of damage to modules during
installation.
Are there any new major risks to the project,
what’s the mitigation plan or contingency.
Should you be adopting a just in time deliver
and place strategy or stockpile / stage and
install?
It becomes clear that these are not typically one dimensional problems.
Module detailing
Who’s best place to complete layout and detail design?
• In-house design team?
• Engineering consultants?
• Fabricator?
• Installation Contractor?
• Collaboration?
Collaboration, not the simple recipe for success;
• Stronger design leaders are required to coalesce options and idea’s into direction.
• Have found non design phase personnel can struggle finding good input and visualising both the
design and issues. Good technical leads are required to ask the right questions. Maybe
requiring mock-up’s, preliminary design details or prototypes to get the right input from
stakeholders and non design personnel.
Module detailing - Experience
Experience (with modular design) maters:
a) Good “normal approach” designers may not adapt to the changed requirements as well as
expected. Often resulting in missed opportunities.
b) There may be new design challenges, where the lack of experience becomes apparent (e.g.
design for transport size and loads, increased detailed consideration of O&M access,
complexity in module interfaces and layout details, new constructability issues).
c) Experience aligned with your modularisation objectives (or the key project lifecycle phases)
may be critical.
d) The rework / change complexity is typically higher with modularisation (mistakes and late
design evolution or changes cost more and take longer).
Module detailing -
Recommendations
Recommendations:
a) In early design stages look at what changes may have occurred. May need increased
stakeholder consultation in design / detailing (end users / operations and maintenance).
b) The right choice for detailing depends on your project, but likely uses either fabricators /
packagers or experienced engineering firms for the detailing for more extensive projects and
may uses your own for smaller or less complicated scopes.
c) Setting out the objectives, constraints (e.g. size) and specific requirements needs to be done
(or closely facilitated) by the project “owner”. This will also include making sure there is the
right representation from non design team disciplines for collaboration.
d) If your doing more extensive modularisation, this experience matters from the early project
stages such as layout.
e) It may be wise to allocate specific resources, deliverables and time to management and
maximisation of your modularisation outcomes (likely a experienced cross discipline
resources).
Site-work alignment for
modularisation
Extensive modularisation changes site work scope and also commercial /
contractual risks.
Module delivery to site may become key, with little ability to mitigate delays
by moving work fronts.
Clear scope for module installation and connection becomes increasingly
important.
Consider:
a) Align module design and fabrication sequence with site “areas”, packages or separable portions
where the site works can be done with a degree of independence from other areas. Align work
planning and scoping with this breakdown.
b) Fabricator / equipment package documentation is likely to be come more complex and extensive as
well as more critical for successful site works. Early identification and management of this with
fabricators and vendors is key. Leading into site work scoping and planning.
c) Module interfaces become important. Ensure that specific work planning is given to the interface
area’s and installation sequence.
Efficient flow of site assembly
works
Connection details:
• Constructability considered at design and installation planning.
• Adequately detailed.
• Interfaces (e.g. HD bolts) checked against as-con module dimensions (with sufficient
accuracy).
Module fit out / installation:
• Options to streamline fit out such as KOP’s issued with modules.
• Adequate installation details (manuals, assembly drawings etc.). Early enough for
construction estimating and planning.
Module delivery strategy
• Do you need to go with deliver and place or can you stage in local laydown?
• If there are a large number of modules, without major lifting or transport issues staging on
site gives some options during construction management.
• Avoid surprises on delivery or start up from transport damage (ensure specific thought is
given to transport and lifting loads as well as vibration and fatigue during design).
Efficient flow of site assembly
works
Safety and productivity – reduced working at heights.
Modules can be assembled at ground level and lifted into place.
Hook-up / connection onsite
I believe this is one of the key areas where a marked improvement in
savings and efficiencies from Modularisation and pre-fabrication can
come from.
True in all disciplines.
Biggest opportunities in structural, mechanical / piping, electrical and
concrete (pre-cast founding, landings and so forth).
Key points:
• Set metrics for design, which reflect your project objectives (e.g. number of
site connected pipes, number of modules) and drive these down.
• One of the biggest area’s where constructability reviews or input can benefit
• Be mindful of fabrication / foundation tolerances and the risks of damage
during placement.
Hook-up / connection onsite –
Mechanical alignment
Hook-up / connection onsite –
Instrument, Control and Electrical
Approach:
• ICE modularised
• Local PLC control for
each major processing
system
• Segregated process
control
• Balance of plant IO
and scope outside of
major packages
collected in separate
field IO cabinet
Specific example: Injection Trial Plant
Hook-up / connection onsite –
Instrument, Control and Electrical
Outcome:
• Simple integration and
interfaces (no
contractual issues RE
interfaces).
• Independent start of
each module
(concurrent work
fronts).
• Independent re-use of
each process system.
• Reduction in skilled
labour onsite as well as
reduction in hours.
0
50
100
150
200
250
300
350
400
Instruments Modularised
97% Reduction in
field terminations
Insturments
Number Modualrised
0
5
10
15
20
25
30
35
40
45
50
Aux. Skid connections within
packages
100% Reduction in
field terminations
Insturments Number plugged
0
20
40
60
80
100
120
140
160
Remote IO
93% Reduction in
field terminations
Incoming terminations
No. Field terminations
Hook-up / connection onsite –
Instrument, Control and Electrical
End use
Module “MCC”
Power Supply in and supply
to each system / area
Main Plant
Switchboard
Primary
Module A
On module
loads
Aux. Modules
Primary
Module B
On module
loads
Balance of
Plant Switch
board
Site lighting
Non
modularised
scope
Hook-up / connection onsite –
Instrument, Control and Electrical
Plugs can be a big benefit come site installation.
Hook-up / connection onsite –
Interface tolerances
Allow sufficient degree’s of freedom
for interface connection.
Length may be used to minimise
angular deflection.
Precision alignment between modules may not be viable, cost
effective, or necessary. Plan for this in your design.
Closing summary
Much of the above has talked about, design, integration thought all
stages of the project and clear objectives.
That’s because they by and large come to fruition as smooth integration
onsite and better project outcomes.
Hopefully the ideas and examples provided help drive your successful
modularisation and pre-fabrication.
For further advice, assistance or engineering and design:
Scott.Coombes@outlook.com
au.linkedin.com/in/ScottCoombesPM

More Related Content

What's hot

Debottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantDebottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantGBX Summits
 
Supplier Management Service
Supplier Management ServiceSupplier Management Service
Supplier Management ServiceJorge Torres
 
QC_Supplier Management_ALL En
QC_Supplier Management_ALL EnQC_Supplier Management_ALL En
QC_Supplier Management_ALL EnJorge Torres
 
Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015Jerry Beste
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMnadeemovic
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydNitin Sethi
 
Brent_Strahan_resume
Brent_Strahan_resumeBrent_Strahan_resume
Brent_Strahan_resumeBrent Strahan
 
Chips.Daniel On Line 6 1 10
Chips.Daniel On Line 6 1 10Chips.Daniel On Line 6 1 10
Chips.Daniel On Line 6 1 10dchips
 
CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23Avinash Wadaskar
 
Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_PayrollBalaguru SP
 
Episode 28 : Project Management Contract
Episode 28 :  Project Management ContractEpisode 28 :  Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 

What's hot (18)

CV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMACV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMA
 
Debottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantDebottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plant
 
TEG(resume)
TEG(resume)TEG(resume)
TEG(resume)
 
Supplier Management Service
Supplier Management ServiceSupplier Management Service
Supplier Management Service
 
CV_Pooranpr
CV_PooranprCV_Pooranpr
CV_Pooranpr
 
QC_Supplier Management_ALL En
QC_Supplier Management_ALL EnQC_Supplier Management_ALL En
QC_Supplier Management_ALL En
 
dapski042116
dapski042116dapski042116
dapski042116
 
Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAM
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
Brent_Strahan_resume
Brent_Strahan_resumeBrent_Strahan_resume
Brent_Strahan_resume
 
Revised.SOOFI_2016.A
Revised.SOOFI_2016.ARevised.SOOFI_2016.A
Revised.SOOFI_2016.A
 
Cv linked in
Cv linked inCv linked in
Cv linked in
 
Chips.Daniel On Line 6 1 10
Chips.Daniel On Line 6 1 10Chips.Daniel On Line 6 1 10
Chips.Daniel On Line 6 1 10
 
CV_Pooranpr
CV_PooranprCV_Pooranpr
CV_Pooranpr
 
CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23
 
Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_Payroll
 
Episode 28 : Project Management Contract
Episode 28 :  Project Management ContractEpisode 28 :  Project Management Contract
Episode 28 : Project Management Contract
 

Viewers also liked

Supply chain operations (Making and Delivering)
Supply chain operations (Making and Delivering)Supply chain operations (Making and Delivering)
Supply chain operations (Making and Delivering)Mohamed Effat
 
Nick Flanagan - Advanced Modular Construction, an opportunity for sa
Nick Flanagan - Advanced Modular Construction, an opportunity for saNick Flanagan - Advanced Modular Construction, an opportunity for sa
Nick Flanagan - Advanced Modular Construction, an opportunity for saMelanie Innes
 
Good, Fast, and Cheap: How Modular Design Improves Our Projects
Good, Fast, and Cheap: How Modular Design Improves Our ProjectsGood, Fast, and Cheap: How Modular Design Improves Our Projects
Good, Fast, and Cheap: How Modular Design Improves Our ProjectsJeremy Ward
 
Idea generation
Idea generationIdea generation
Idea generationsofttekweb
 
Coordinated Product And Supply Chain Design
Coordinated Product And Supply Chain DesignCoordinated Product And Supply Chain Design
Coordinated Product And Supply Chain Designpirama2000
 
Modular design
Modular designModular design
Modular design3688cm
 
Modular Design
Modular DesignModular Design
Modular DesignBrad Lewis
 
The Automotive Modular Design - Volkswagen group platform strategy/policy
The Automotive Modular Design - Volkswagen group platform strategy/policyThe Automotive Modular Design - Volkswagen group platform strategy/policy
The Automotive Modular Design - Volkswagen group platform strategy/policyInovev
 
Supply Chain Strategy Or Design
Supply Chain Strategy Or DesignSupply Chain Strategy Or Design
Supply Chain Strategy Or DesignTanuj Poddar
 
Supply chain management ppt @ bec doms
Supply chain management ppt @ bec domsSupply chain management ppt @ bec doms
Supply chain management ppt @ bec domsBabasab Patil
 

Viewers also liked (12)

Supply chain operations (Making and Delivering)
Supply chain operations (Making and Delivering)Supply chain operations (Making and Delivering)
Supply chain operations (Making and Delivering)
 
Nick Flanagan - Advanced Modular Construction, an opportunity for sa
Nick Flanagan - Advanced Modular Construction, an opportunity for saNick Flanagan - Advanced Modular Construction, an opportunity for sa
Nick Flanagan - Advanced Modular Construction, an opportunity for sa
 
Good, Fast, and Cheap: How Modular Design Improves Our Projects
Good, Fast, and Cheap: How Modular Design Improves Our ProjectsGood, Fast, and Cheap: How Modular Design Improves Our Projects
Good, Fast, and Cheap: How Modular Design Improves Our Projects
 
Idea generation
Idea generationIdea generation
Idea generation
 
Top down design
Top down designTop down design
Top down design
 
Coordinated Product And Supply Chain Design
Coordinated Product And Supply Chain DesignCoordinated Product And Supply Chain Design
Coordinated Product And Supply Chain Design
 
Modular design
Modular designModular design
Modular design
 
Modular Design
Modular DesignModular Design
Modular Design
 
The Automotive Modular Design - Volkswagen group platform strategy/policy
The Automotive Modular Design - Volkswagen group platform strategy/policyThe Automotive Modular Design - Volkswagen group platform strategy/policy
The Automotive Modular Design - Volkswagen group platform strategy/policy
 
Supply Chain Strategy Or Design
Supply Chain Strategy Or DesignSupply Chain Strategy Or Design
Supply Chain Strategy Or Design
 
Supply chain management ppt @ bec doms
Supply chain management ppt @ bec domsSupply chain management ppt @ bec doms
Supply chain management ppt @ bec doms
 
Supply Chain Strategy
Supply Chain StrategySupply Chain Strategy
Supply Chain Strategy
 

Similar to Smooth On-Site Integration of Modular Construction

BIM to support DfMA and Lean Construction
BIM to support DfMA and Lean ConstructionBIM to support DfMA and Lean Construction
BIM to support DfMA and Lean ConstructionAkio Moriwaki
 
Decommissioning Project Management
Decommissioning Project ManagementDecommissioning Project Management
Decommissioning Project ManagementAlexandre Houdart
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityIRJET Journal
 
M1: Introduction to Design for Manufacture
M1: Introduction to Design for ManufactureM1: Introduction to Design for Manufacture
M1: Introduction to Design for Manufacturetaruian
 
Onshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewOnshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewMerrylyn Yeo
 
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...AVEVA Group plc
 
Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Ishan Parekh
 
Cut & bend rebars
Cut & bend rebarsCut & bend rebars
Cut & bend rebarsParam Saxena
 
Evan Gritman Lewis
Evan Gritman LewisEvan Gritman Lewis
Evan Gritman LewisEvan Lewis
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
A Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout PlanningA Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout PlanningIRJET Journal
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Difference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanationDifference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanationManiKandan214178
 
Prefabricated structures | Primexbuildings
Prefabricated structures | PrimexbuildingsPrefabricated structures | Primexbuildings
Prefabricated structures | PrimexbuildingsPrimexBuildingSystems
 

Similar to Smooth On-Site Integration of Modular Construction (20)

BIM to support DfMA and Lean Construction
BIM to support DfMA and Lean ConstructionBIM to support DfMA and Lean Construction
BIM to support DfMA and Lean Construction
 
Decommissioning Project Management
Decommissioning Project ManagementDecommissioning Project Management
Decommissioning Project Management
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
 
Thomson CV
Thomson CVThomson CV
Thomson CV
 
M1: Introduction to Design for Manufacture
M1: Introduction to Design for ManufactureM1: Introduction to Design for Manufacture
M1: Introduction to Design for Manufacture
 
Onshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewOnshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s view
 
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...
 
Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)
 
Cut & bend rebars
Cut & bend rebarsCut & bend rebars
Cut & bend rebars
 
Evan Gritman Lewis
Evan Gritman LewisEvan Gritman Lewis
Evan Gritman Lewis
 
CAD _ UNIT 1.pptx
CAD _ UNIT 1.pptxCAD _ UNIT 1.pptx
CAD _ UNIT 1.pptx
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
UNIT 1
UNIT 1UNIT 1
UNIT 1
 
project management
project managementproject management
project management
 
A Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout PlanningA Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout Planning
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Difference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanationDifference between DFM, DFA, DFMA with good explanation
Difference between DFM, DFA, DFMA with good explanation
 
GulfConst-Performance
GulfConst-PerformanceGulfConst-Performance
GulfConst-Performance
 
Prefabricated structures | Primexbuildings
Prefabricated structures | PrimexbuildingsPrefabricated structures | Primexbuildings
Prefabricated structures | Primexbuildings
 

Smooth On-Site Integration of Modular Construction

  • 1. Smooth Integration of Modules On-Site 6TH ANNUAL MODULAR CONSTRUCTION & PREFABRICATION SUMMIT PRESENTER: SCOTT COOMBES
  • 2. Introduction Project Manager, having been a Project Engineer and involved in the Coal Seam Gas industry for the last 7.5 yeas. Involved in a range of projects (over the full life-cycle): • Large gas compression and processing plants, • Gas and water gathering networks including wellhead surface facilities. • Exploration pilots and dam construction. • Water treatment and water / brine injection test facilities.
  • 3. Agenda A. Introduction B. Why modularise / pre-fabricate C. Identification of opportunities and cost savings D. Integration of modularisation strategy within project E. Identifying whether detailing developed is in collaboration with the design team, general contractor, fabricator and installer. F. Designing the project so that work structured for what is done on-site matches what has been manufactured in the factory G. Efficient flow of site assembly works. H. Hook-up / connection onsite I. Closing summary
  • 4. I believe the principals behind successful modularisation apply across all sectors. I will also provide some specific examples of what worked. This will be based on process plants. For the purpose of this presentation: • Pre-fabrication, • Equipment skidding, • Equipment modularisation Can all be take as “modularisation”; the principal discussed generally apply to all of the above.
  • 5. Why modularise / pre- fabricate? The drivers behind your modularisation strategy should be clear: • What do you hope to achieve in taking this approach? • What are the trade offs that have been made? • What are the risk associated with the strategy being taken? Delving deeper than a presumed and schedule saving or quality improvement. Being clear of the objectives and this feeding into each stage of work and work planning is key. Integration (or planning) of your modularisation strategy over the whole of project lifecycle is key to the best results (or success as verse failure in some cases). This especially the case is this is different to you (as a company / team).
  • 6. Benefits Cost: • Access to lower labour rates, • Access to lower / no labour overheads, • Improved labour efficiency, Schedule: • Early commencement long lead scope. • Design interfaces (can be a decrease in complexity or an increase in complexity). • Elimination of trades / work sequences on critical path site works. • May be the only effective method for concurrent work. De-risking project • Work outside of weather issues or site access considerations. • May be more able to remove scope poor performing fabricators as vs site works. • Typically shop or yard fabrication is able to be executed in a manner lending itself to safer methods as well as better / more efficient QA / QC process. Project Management: • Typically a structured / effective method for separation of scope and packages to various parties (with options for more competitive bidding). • Can simplify site installation scope, and provide clear boundaries between scopes. • Fabrication management is typically less intensive than site management (onshore fabrication). • Reduced site scope / time with the associated stakeholder benefits. • Decongested worksites / reduced site manning pressures. • Ability for extensive offsite testing and control optimisation.
  • 7. Identification of opportunities and cost savings. Suggestions for identification and prioritisation: • Break the project down and target the high cost area’s first. • Quantify the cost difference between on and off site work (including efficiency). • Identify the associated benefits from modularisation, benchmark and cost these. • Review what others are doing, out of your sector / industry (good for idea’s and contacts). • Look at what’s putting the highest risk and or management burden into your project. $- $50.00 $100.00 $150.00 $200.00 $250.00 Brisbane Remote Rate Comparison - Supervisor (2014) ($/h) Base Rate (to client) Accomidation Vehicle Costs Travel on and off shift costs Daily paid travel time Remote site productivity impact
  • 8. Why Modularise - A specific case on specialised labour. Equipment, plant and system complexity generally increasing over time. This leads to increased requirements for specialist labour onsite, especially during start up and commissioning. The overhead, lead time and resource utilisation on site is lower than in most fabrication workshops or yards. One example. Mobilisation of a specific PLC programmer from Adelaide to central Queensland. • 2+ days of induction, • 1 week lead time, 2 days mobilisation and demobilisation each way. • Increased rates, • Decreased productivity onsite. For less than a weeks work onsite. Do it before the equipment arrives onsite.
  • 9. Integration of modularisation strategy within a project As the portion of scope that is modularised or the module complexity increase’s this integration (or consideration of impacts) increasingly critical. Key considerations in early project planning / feasibility are: Logistics Estimating and Planning Design Transport / route module size / weight limits, can these be changed? What are the cost savings (and what drives the realisation of those costs). Does the system / project lend itself (or parts of it) to modularisation or pre fabrication. Receiving site size / weight limits. What are the cost increases. Are there any major departures in design requirements to the norm? Transport options lead-time, duration and time constraints. What are the schedule changes. What’s the best module stagey considering available information.
  • 10. Design and Delivery Design Fabrication Contracting Are new skills required? Complexity of scope and risk to project may be different. Are you using the right contract’s (from both a management and risk mitigation perspective). How is the layout / high level design done considerate of modularisation. Factoring access, lifting, module connection / interfaces. Depending on strategy, there may be an increased volume of work tendered / procured / expedited. How do the modules interface efficiently. Are you fabricators experienced delivering to the required standards (more QA / QC or documentation scope may be associated with the increased module scope). What are the O&M requirements relating to access, congestion or packaging. How are transport constraints to be managed? Are there any constraints local to the fabricator?
  • 11. Design and Delivery - continued Construction Others Does the construction work planning and execution hinge on module deliveries? Do you have to build out from modules? Is there enough scope outside of the modules (or enough work force flexibility) to cope with changed module delivery dates? Are there any stakeholder impacts e.g. • Concerns over local content • Impacts to the community due to module transport (can be very visible). Is a change in the workforce or plant equipment required for efficient delivery. Maximisation of offsite testing and plant optimisation. Is there a risk of damage to modules during installation. Are there any new major risks to the project, what’s the mitigation plan or contingency. Should you be adopting a just in time deliver and place strategy or stockpile / stage and install? It becomes clear that these are not typically one dimensional problems.
  • 12. Module detailing Who’s best place to complete layout and detail design? • In-house design team? • Engineering consultants? • Fabricator? • Installation Contractor? • Collaboration? Collaboration, not the simple recipe for success; • Stronger design leaders are required to coalesce options and idea’s into direction. • Have found non design phase personnel can struggle finding good input and visualising both the design and issues. Good technical leads are required to ask the right questions. Maybe requiring mock-up’s, preliminary design details or prototypes to get the right input from stakeholders and non design personnel.
  • 13. Module detailing - Experience Experience (with modular design) maters: a) Good “normal approach” designers may not adapt to the changed requirements as well as expected. Often resulting in missed opportunities. b) There may be new design challenges, where the lack of experience becomes apparent (e.g. design for transport size and loads, increased detailed consideration of O&M access, complexity in module interfaces and layout details, new constructability issues). c) Experience aligned with your modularisation objectives (or the key project lifecycle phases) may be critical. d) The rework / change complexity is typically higher with modularisation (mistakes and late design evolution or changes cost more and take longer).
  • 14. Module detailing - Recommendations Recommendations: a) In early design stages look at what changes may have occurred. May need increased stakeholder consultation in design / detailing (end users / operations and maintenance). b) The right choice for detailing depends on your project, but likely uses either fabricators / packagers or experienced engineering firms for the detailing for more extensive projects and may uses your own for smaller or less complicated scopes. c) Setting out the objectives, constraints (e.g. size) and specific requirements needs to be done (or closely facilitated) by the project “owner”. This will also include making sure there is the right representation from non design team disciplines for collaboration. d) If your doing more extensive modularisation, this experience matters from the early project stages such as layout. e) It may be wise to allocate specific resources, deliverables and time to management and maximisation of your modularisation outcomes (likely a experienced cross discipline resources).
  • 15. Site-work alignment for modularisation Extensive modularisation changes site work scope and also commercial / contractual risks. Module delivery to site may become key, with little ability to mitigate delays by moving work fronts. Clear scope for module installation and connection becomes increasingly important. Consider: a) Align module design and fabrication sequence with site “areas”, packages or separable portions where the site works can be done with a degree of independence from other areas. Align work planning and scoping with this breakdown. b) Fabricator / equipment package documentation is likely to be come more complex and extensive as well as more critical for successful site works. Early identification and management of this with fabricators and vendors is key. Leading into site work scoping and planning. c) Module interfaces become important. Ensure that specific work planning is given to the interface area’s and installation sequence.
  • 16. Efficient flow of site assembly works Connection details: • Constructability considered at design and installation planning. • Adequately detailed. • Interfaces (e.g. HD bolts) checked against as-con module dimensions (with sufficient accuracy). Module fit out / installation: • Options to streamline fit out such as KOP’s issued with modules. • Adequate installation details (manuals, assembly drawings etc.). Early enough for construction estimating and planning. Module delivery strategy • Do you need to go with deliver and place or can you stage in local laydown? • If there are a large number of modules, without major lifting or transport issues staging on site gives some options during construction management. • Avoid surprises on delivery or start up from transport damage (ensure specific thought is given to transport and lifting loads as well as vibration and fatigue during design).
  • 17. Efficient flow of site assembly works Safety and productivity – reduced working at heights. Modules can be assembled at ground level and lifted into place.
  • 18. Hook-up / connection onsite I believe this is one of the key areas where a marked improvement in savings and efficiencies from Modularisation and pre-fabrication can come from. True in all disciplines. Biggest opportunities in structural, mechanical / piping, electrical and concrete (pre-cast founding, landings and so forth). Key points: • Set metrics for design, which reflect your project objectives (e.g. number of site connected pipes, number of modules) and drive these down. • One of the biggest area’s where constructability reviews or input can benefit • Be mindful of fabrication / foundation tolerances and the risks of damage during placement.
  • 19. Hook-up / connection onsite – Mechanical alignment
  • 20. Hook-up / connection onsite – Instrument, Control and Electrical Approach: • ICE modularised • Local PLC control for each major processing system • Segregated process control • Balance of plant IO and scope outside of major packages collected in separate field IO cabinet Specific example: Injection Trial Plant
  • 21. Hook-up / connection onsite – Instrument, Control and Electrical Outcome: • Simple integration and interfaces (no contractual issues RE interfaces). • Independent start of each module (concurrent work fronts). • Independent re-use of each process system. • Reduction in skilled labour onsite as well as reduction in hours. 0 50 100 150 200 250 300 350 400 Instruments Modularised 97% Reduction in field terminations Insturments Number Modualrised 0 5 10 15 20 25 30 35 40 45 50 Aux. Skid connections within packages 100% Reduction in field terminations Insturments Number plugged 0 20 40 60 80 100 120 140 160 Remote IO 93% Reduction in field terminations Incoming terminations No. Field terminations
  • 22. Hook-up / connection onsite – Instrument, Control and Electrical End use Module “MCC” Power Supply in and supply to each system / area Main Plant Switchboard Primary Module A On module loads Aux. Modules Primary Module B On module loads Balance of Plant Switch board Site lighting Non modularised scope
  • 23. Hook-up / connection onsite – Instrument, Control and Electrical Plugs can be a big benefit come site installation.
  • 24. Hook-up / connection onsite – Interface tolerances Allow sufficient degree’s of freedom for interface connection. Length may be used to minimise angular deflection. Precision alignment between modules may not be viable, cost effective, or necessary. Plan for this in your design.
  • 25. Closing summary Much of the above has talked about, design, integration thought all stages of the project and clear objectives. That’s because they by and large come to fruition as smooth integration onsite and better project outcomes. Hopefully the ideas and examples provided help drive your successful modularisation and pre-fabrication. For further advice, assistance or engineering and design: Scott.Coombes@outlook.com au.linkedin.com/in/ScottCoombesPM