SlideShare a Scribd company logo
TOPIC: CHANGE ORDER MANAGEMENT TO PROJECT SUCCESS:
ABSTRACT
It can be argued that the successful management of change is crucial to any organization in order to
survive and succeed in the present highly competitive and continuously evolving business environment.
The purpose of this paper is, to provide an industrial views / Action to Reduce / Minimize the changes
(either it is an Engineering change or a Commercial change) at post award of Contracts or Purchase
Orders. Supply Chain Team plays important role towards constructing a new framework for managing
changes.
1. Introduction:
Change Order Management is the backbone of the Project. Project Team need to handle it very
strategically to achieve the Project Success. In Oil & Gas, Power, Petrochemical Industrial, We generally
build Large Refineries, Chemical Plants. It is a huge Investment by the Government / Private Investors.
Governments / Private Investors do the feasibility studies in critical areas concerning to the project For
example cost & schedule, Site Environmental condition, Design, Process, Safety, logistic, cultural
differences and political & social interference etc. with the help of Engineering Consultants / Financial
planners / Project Planners / Equipment Cost estimation / Construction Cost Estimation etc. Based on the
inputs from these consultants, Investor will take a decision to Kick-start the project, if find it feasible or
profitable (will able to complete within the desired schedule & Cost). Here in this paper we will focus
How Change Order Management plays critical Rolls in project success / failure. Cost & Schedule is the
only key components shall be impacting due to changes.
2. Definitions:
Change Order Management: A change order Management is a component of the change management
process whereby changes in the Scope of Work agreed to by the Owner, Contractor and
Architect/Engineer are implemented or executed.
Project Cost: The project cost is the total project cost which includes engineering fees, material costs,
and construction costs, permit fees, land, furnishings, financing and all other costs that were incurred in
completion of the project.
Project Schedule: The Project Schedule that communicates what work needs to be performed, which
resources of the organization will perform the work and the timeframes in which that work needs to be
performed. It is a part of Contact documents.
3. Basics:
We define Project Cost in 2 major heads, Material Cost and Construction Cost (Appx. 90%), balance 10%
is the miscellaneous costs. You will surprise to hear that Material Cost, specially the Project Long Lead
Materials comprising 35-40% of total project cost.
For example in building a Petrochemical plant, we need Boiler, Waste water Treatment plant, Cooling
Tower, Transformers, DG Sets, Pumps, Electrical Cables, piping bulks, Electrical bulks,
Instrumentation’s bulks and many other small items / Equipments.
The Equipment Purchasing Cost & manufacturing / fabrication process must be closely monitored with
respect to allotted budget and Project Baseline schedule respectively.
4. Change Order Management:
When we think about Change Order Management following questions start running around us:
A. Who initiate the Change Order & Why we need Change Order after placing the Purchase Order?
B. Who approve the Change Order?
C. Who negotiate & release the change orders to the Supplier?
D. How Change orders impacting the Project overall Cost & Schedule completion date?
E. What actions should be taken to minimize the Change Orders?
Answering these questions create a firm foundation about the understanding on Change Order
Management.
A. Change order could be initiated by Equipment Responsible Engineer / Buyer.
a. Change order initiated by the Engineer is termed as Technical / Engineering Change Order,
mostly due to the any one or more of the reasons listed below.
Size/ capacity of Equipment Change
Process Change
Client Inputs
Construction Inputs
HAZOP (Hazard and operability study)
Change in quantities (Increase / Decrease) /substitution of one item for another
b. Change order initiated by the Buyer is termed as Commercial Change Order , mostly due the
following reasons
Inadvertently omission of supplier’s commercial offers few pricings.
Inadvertently follow the wrong Technical Bid Evaluation Sheet.
Price Calculation Error /change in price for an ordered item
Delivery Extension
B. In general Technical Change order will be approved by the Engineering Manager / Client (if
applicable). Commercial Change orders will be approved by the Project authorised signature matrix
listed approval Authorities or by the clients (as agreed in Client Contract).
C. Buyer will negotiate & release the Change Order to the Supplier.
D. Change orders impact the Project in terms of Cost & schedule, it can be positive cost impact (means
reduction to the PO value) or Negative cost impact (means increase in the PO value). In terms of
schedule, if material delivery delayed from the agreed PO contractual delivery date than it will extend
the overall project completion date. If we get early delivery of material than we can save the
construction cost or overall project cost with respect to the budget by early completing the project.
E. We can minimize or optimize the change order counts, but not touch the zero count. For example, in
large Project, Material Requirement / Requisition were generated by the Engineering disciplines such
as, Civil, Structural, Mechanical, Electrical, Control System, Piping, and Safety etc. Mostly the lack
of close coordination or communication gap between engineering departments will leads to origin of
Change Orders on the projects.
Following action must be taken to optimize the change order counts.
a) Conducting Weekly / Bi-weekly meetings among engineering disciplines before release of
technical RFQ to the Procurement Department.
b) Peer review of engineering documents by discipline colleagues.
c) Early involvement of Procurement, Quality department in reviewing the technical RFQs.
d) Client review of Engineering RFQ
e) Buyer must review & crosscheck the commercial offers pricing in detailed manner to
eliminate the wrong prices errors.
f) Buyer must read the Engineer’s issued final Purchase Requisition OR Technical Bid
evaluation.
g) Price calculation error must reach to the zero count; it can be archived by re-checking and
getting the peer review of prices.
h) Delivery extension Request always comes from the Supplier, buyer to issue the change
order based on the facts presented by the supplier.
5. Conclusion:
All projects, even the best planned projects, will experience change, and there will be costs, impacts, and
disruptions associated with implementing the changes. So we need to minimize or try to remove the root
cause of Change Orders. This paper will help you more in achieving the organization goals of best change
order management in terms of minimizing the change order counts.

More Related Content

What's hot

Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1
Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1
Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1
Khalid Mustafa
 
Tarif pengujian uptb bpmsk
Tarif pengujian uptb bpmskTarif pengujian uptb bpmsk
Tarif pengujian uptb bpmsk
Santsaja
 
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Claudius Herry
 
ppt kurva s wahyu.pdf
ppt kurva s wahyu.pdfppt kurva s wahyu.pdf
ppt kurva s wahyu.pdf
wahyuhermawan18
 
The 2015 Millennial Majority Workforce: Study Results
The 2015 Millennial Majority Workforce: Study ResultsThe 2015 Millennial Majority Workforce: Study Results
The 2015 Millennial Majority Workforce: Study Results
Elance-oDesk
 
Ta3211 6 rancangan peledakan jenjang
Ta3211 6 rancangan peledakan jenjangTa3211 6 rancangan peledakan jenjang
Ta3211 6 rancangan peledakan jenjangNovrina Annisaa
 
ניהול ומדידת ביצועים
ניהול ומדידת ביצועיםניהול ומדידת ביצועים
ניהול ומדידת ביצועים
ESP
 
01. Kebijakan dan Landasan DB.pdf
01. Kebijakan dan Landasan DB.pdf01. Kebijakan dan Landasan DB.pdf
01. Kebijakan dan Landasan DB.pdf
GunturYanP
 
Penyesuaian Harga
Penyesuaian HargaPenyesuaian Harga
Penyesuaian Harga
ssusera0c4fc
 
MOHD JAMAL AKTAR QA/QC
MOHD JAMAL AKTAR QA/QCMOHD JAMAL AKTAR QA/QC
MOHD JAMAL AKTAR QA/QC
MOHAMMAD JAMAL AKTAR
 
Metode pelaksanaan proyek
Metode pelaksanaan proyekMetode pelaksanaan proyek
Metode pelaksanaan proyek
Wesly Simarmata
 
Dlh Perling dan Pertek
Dlh   Perling dan PertekDlh   Perling dan Pertek
Dlh Perling dan Pertek
Era Wibowo
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf
08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf
08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf
ssuser91ceb01
 
Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan ...
Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan  ...Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan  ...
Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan ...
Khalid Mustafa
 
SOP Pekerjaan Konstruksi
SOP Pekerjaan KonstruksiSOP Pekerjaan Konstruksi
SOP Pekerjaan Konstruksi
Jocky Nahor
 

What's hot (16)

Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1
Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1
Persiapan Pengadaan Barang/Jasa Pemerintah - Bagian 1
 
Tarif pengujian uptb bpmsk
Tarif pengujian uptb bpmskTarif pengujian uptb bpmsk
Tarif pengujian uptb bpmsk
 
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
Prosedur pelaporan (laporan harian, mingguan, bulanan) kon-19
 
ppt kurva s wahyu.pdf
ppt kurva s wahyu.pdfppt kurva s wahyu.pdf
ppt kurva s wahyu.pdf
 
The 2015 Millennial Majority Workforce: Study Results
The 2015 Millennial Majority Workforce: Study ResultsThe 2015 Millennial Majority Workforce: Study Results
The 2015 Millennial Majority Workforce: Study Results
 
Ta3211 6 rancangan peledakan jenjang
Ta3211 6 rancangan peledakan jenjangTa3211 6 rancangan peledakan jenjang
Ta3211 6 rancangan peledakan jenjang
 
ניהול ומדידת ביצועים
ניהול ומדידת ביצועיםניהול ומדידת ביצועים
ניהול ומדידת ביצועים
 
01. Kebijakan dan Landasan DB.pdf
01. Kebijakan dan Landasan DB.pdf01. Kebijakan dan Landasan DB.pdf
01. Kebijakan dan Landasan DB.pdf
 
Penyesuaian Harga
Penyesuaian HargaPenyesuaian Harga
Penyesuaian Harga
 
MOHD JAMAL AKTAR QA/QC
MOHD JAMAL AKTAR QA/QCMOHD JAMAL AKTAR QA/QC
MOHD JAMAL AKTAR QA/QC
 
Metode pelaksanaan proyek
Metode pelaksanaan proyekMetode pelaksanaan proyek
Metode pelaksanaan proyek
 
Dlh Perling dan Pertek
Dlh   Perling dan PertekDlh   Perling dan Pertek
Dlh Perling dan Pertek
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf
08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf
08-HO-Pengendalian Biaya, Mutu dan Waktu.pdf
 
Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan ...
Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan  ...Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan  ...
Paparan Sosialisasi SE PUPR Nomor 19 Tahun 2021 tentang Pedoman Pelaksanaan ...
 
SOP Pekerjaan Konstruksi
SOP Pekerjaan KonstruksiSOP Pekerjaan Konstruksi
SOP Pekerjaan Konstruksi
 

Similar to CHANGE ORDER MANAGEMENT TO PROJECT SUCCESS

Manufacturing equipment new vs. remanufacturing
Manufacturing equipment  new vs. remanufacturingManufacturing equipment  new vs. remanufacturing
Manufacturing equipment new vs. remanufacturing
Antonio Reis
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1reddvise
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
Gregoire Lesecq
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
AprilRosal1
 
purchasing and contracting for projects
 purchasing and contracting for projects purchasing and contracting for projects
purchasing and contracting for projects
Somashekar S.M
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Mb0049 project management
Mb0049 project managementMb0049 project management
Mb0049 project management
Devendra Kachhi
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projectsD.Pawan Kumar
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
DrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
Dr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
Dr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
drdej19
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
Dr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
DrFereydounDejahang
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
HASMANIRA
 
glossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfglossary-of-construction-terms.pdf
glossary-of-construction-terms.pdf
CarlStevenAtencio
 
Project change request template v2.0
Project change request template v2.0Project change request template v2.0
Project change request template v2.0
Aditya Pandey
 
Changes in construction projects
Changes in construction projectsChanges in construction projects
Changes in construction projects
Mohamed Abdalla
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
Mohamed Abdalla
 

Similar to CHANGE ORDER MANAGEMENT TO PROJECT SUCCESS (20)

Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
Manufacturing equipment new vs. remanufacturing
Manufacturing equipment  new vs. remanufacturingManufacturing equipment  new vs. remanufacturing
Manufacturing equipment new vs. remanufacturing
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
purchasing and contracting for projects
 purchasing and contracting for projects purchasing and contracting for projects
purchasing and contracting for projects
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Mb0049 project management
Mb0049 project managementMb0049 project management
Mb0049 project management
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
glossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfglossary-of-construction-terms.pdf
glossary-of-construction-terms.pdf
 
Project change request template v2.0
Project change request template v2.0Project change request template v2.0
Project change request template v2.0
 
Changes in construction projects
Changes in construction projectsChanges in construction projects
Changes in construction projects
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 

Recently uploaded

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 

CHANGE ORDER MANAGEMENT TO PROJECT SUCCESS

  • 1. TOPIC: CHANGE ORDER MANAGEMENT TO PROJECT SUCCESS: ABSTRACT It can be argued that the successful management of change is crucial to any organization in order to survive and succeed in the present highly competitive and continuously evolving business environment. The purpose of this paper is, to provide an industrial views / Action to Reduce / Minimize the changes (either it is an Engineering change or a Commercial change) at post award of Contracts or Purchase Orders. Supply Chain Team plays important role towards constructing a new framework for managing changes. 1. Introduction: Change Order Management is the backbone of the Project. Project Team need to handle it very strategically to achieve the Project Success. In Oil & Gas, Power, Petrochemical Industrial, We generally build Large Refineries, Chemical Plants. It is a huge Investment by the Government / Private Investors. Governments / Private Investors do the feasibility studies in critical areas concerning to the project For example cost & schedule, Site Environmental condition, Design, Process, Safety, logistic, cultural differences and political & social interference etc. with the help of Engineering Consultants / Financial planners / Project Planners / Equipment Cost estimation / Construction Cost Estimation etc. Based on the inputs from these consultants, Investor will take a decision to Kick-start the project, if find it feasible or profitable (will able to complete within the desired schedule & Cost). Here in this paper we will focus How Change Order Management plays critical Rolls in project success / failure. Cost & Schedule is the only key components shall be impacting due to changes. 2. Definitions: Change Order Management: A change order Management is a component of the change management process whereby changes in the Scope of Work agreed to by the Owner, Contractor and Architect/Engineer are implemented or executed. Project Cost: The project cost is the total project cost which includes engineering fees, material costs, and construction costs, permit fees, land, furnishings, financing and all other costs that were incurred in completion of the project. Project Schedule: The Project Schedule that communicates what work needs to be performed, which resources of the organization will perform the work and the timeframes in which that work needs to be performed. It is a part of Contact documents.
  • 2. 3. Basics: We define Project Cost in 2 major heads, Material Cost and Construction Cost (Appx. 90%), balance 10% is the miscellaneous costs. You will surprise to hear that Material Cost, specially the Project Long Lead Materials comprising 35-40% of total project cost. For example in building a Petrochemical plant, we need Boiler, Waste water Treatment plant, Cooling Tower, Transformers, DG Sets, Pumps, Electrical Cables, piping bulks, Electrical bulks, Instrumentation’s bulks and many other small items / Equipments. The Equipment Purchasing Cost & manufacturing / fabrication process must be closely monitored with respect to allotted budget and Project Baseline schedule respectively. 4. Change Order Management: When we think about Change Order Management following questions start running around us: A. Who initiate the Change Order & Why we need Change Order after placing the Purchase Order? B. Who approve the Change Order? C. Who negotiate & release the change orders to the Supplier? D. How Change orders impacting the Project overall Cost & Schedule completion date? E. What actions should be taken to minimize the Change Orders? Answering these questions create a firm foundation about the understanding on Change Order Management. A. Change order could be initiated by Equipment Responsible Engineer / Buyer. a. Change order initiated by the Engineer is termed as Technical / Engineering Change Order, mostly due to the any one or more of the reasons listed below. Size/ capacity of Equipment Change Process Change Client Inputs Construction Inputs HAZOP (Hazard and operability study) Change in quantities (Increase / Decrease) /substitution of one item for another b. Change order initiated by the Buyer is termed as Commercial Change Order , mostly due the following reasons Inadvertently omission of supplier’s commercial offers few pricings. Inadvertently follow the wrong Technical Bid Evaluation Sheet. Price Calculation Error /change in price for an ordered item Delivery Extension
  • 3. B. In general Technical Change order will be approved by the Engineering Manager / Client (if applicable). Commercial Change orders will be approved by the Project authorised signature matrix listed approval Authorities or by the clients (as agreed in Client Contract). C. Buyer will negotiate & release the Change Order to the Supplier. D. Change orders impact the Project in terms of Cost & schedule, it can be positive cost impact (means reduction to the PO value) or Negative cost impact (means increase in the PO value). In terms of schedule, if material delivery delayed from the agreed PO contractual delivery date than it will extend the overall project completion date. If we get early delivery of material than we can save the construction cost or overall project cost with respect to the budget by early completing the project. E. We can minimize or optimize the change order counts, but not touch the zero count. For example, in large Project, Material Requirement / Requisition were generated by the Engineering disciplines such as, Civil, Structural, Mechanical, Electrical, Control System, Piping, and Safety etc. Mostly the lack of close coordination or communication gap between engineering departments will leads to origin of Change Orders on the projects. Following action must be taken to optimize the change order counts. a) Conducting Weekly / Bi-weekly meetings among engineering disciplines before release of technical RFQ to the Procurement Department. b) Peer review of engineering documents by discipline colleagues. c) Early involvement of Procurement, Quality department in reviewing the technical RFQs. d) Client review of Engineering RFQ e) Buyer must review & crosscheck the commercial offers pricing in detailed manner to eliminate the wrong prices errors. f) Buyer must read the Engineer’s issued final Purchase Requisition OR Technical Bid evaluation. g) Price calculation error must reach to the zero count; it can be archived by re-checking and getting the peer review of prices. h) Delivery extension Request always comes from the Supplier, buyer to issue the change order based on the facts presented by the supplier. 5. Conclusion: All projects, even the best planned projects, will experience change, and there will be costs, impacts, and disruptions associated with implementing the changes. So we need to minimize or try to remove the root cause of Change Orders. This paper will help you more in achieving the organization goals of best change order management in terms of minimizing the change order counts.