SlideShare a Scribd company logo
CURRENT
SCENARIO
Current scenario
India expects to add 300 million new urban residents by 2050.
Under the 100 Smart Cities Mission, the government has approved INR480.0 billion.
To rehabilitate the slums, construct 20.0 million affordable housing units will be
constructed across the country by 2022.
AMRUT in 500 towns and cities to provide basic infrastructure services such as water
supply, sewerage connection, green spaces, parks and transportation facilities.
Bharatmala: 35,000km highways across 16 states.
Sagarmala: Connecting 12 major ports and 185 minor ports along the entire 7,500km
coastline.
Delhi Mumbai Industrial Corridor (DMIC): A six-lane expressway stretching 1,500km
connecting the industrial cities of Delhi and Mumbai
Major issues in construction industry
time overrun
cost overrun
construction waste
27.49%
75.00%
Building construction
projects
Infrastructure projects
Projects with time overrun
727 projects
782 projects
1-261 months delay
Major issues in construction industry
time overrun
cost overrun
construction waste
projects with cost overrun
projects without cost overrun
57%43%
Major issues in construction industry
FINANCING & PAYMENT ISSUES
ADDITIONAL WORK/EXTRA ITEMS
POOR CONSTRUCTION MGMT.
DELAY IN PLANNED ACTIVITY
o Delay in the settlement of contractor
claims by the owner
o Financial difficulties
o Delay in payment for extra
work/variations by owner
o Late payment to subcontractor or
suppliers
cost overruntime overrun &
Major issues in construction industry
FINANCING & PAYMENT ISSUES
ADDITIONAL WORK/EXTRA ITEMS
POOR CONSTRUCTION MGMT.
DELAY IN PLANNED ACTIVITY
o Lack of co-ordination between client
& contractor
o Scope change
o Ambiguous or incomplete tender
document
o Quality issues / mistakes
o Fraudulent practices
cost overruntime overrun &
Major issues in construction industry
FINANCING & PAYMENT ISSUES
ADDITIONAL WORK/EXTRA ITEMS
POOR CONSTRUCTION MGMT.
DELAY IN PLANNED ACTIVITY
o Infrequent quality assessment.
o Unavailability of modern machineries
& equipment.
o Unavailability of skilled labour.
o Improper coordination between client
& contractor.
o Lack of proper planning technologies
o Incompetent organizational
structure.
cost overruntime overrun &
Major issues in construction industry
FINANCING & PAYMENT ISSUES
ADDITIONAL WORK/EXTRA ITEMS
POOR CONSTRUCTION MGMT.
DELAY IN PLANNED ACTIVITY
o Scope change by client
o Design changes by client during
construction
o Unavailability of machineries &
equipment
o Delay in revising and approving
design documents by owner
o Shortage of labours
o Incompetent client
cost overruntime overrun &
Major issues in construction industry
45.6
48
67
270
12.8
14.7
22.1
110.7
0 50 100 150 200 250 300
1997
2001
2011
2021
2031
2041
2047
Construction waste Solid waste
time overrun
cost overrun
construction waste
million tonnes/year
Major issues in construction industry
construction waste
Construction industry is responsible
for 25-40% of the carbon emissions
on a global scale
30-40% of the total MSW is
generated by construction industry.
o Frequent Design Changes
o Poor Quality Of Materials
o Scope & design change
o Poor Planning
o Poor Site Management
Remedies Use of appropriate modern technologies
Modern materials which reduce waste
Proper planning & scheduling
Through proper collaboration between
contractor & client
Labour training program
Frequent quality assessment
Project Delivery Methods
• A system used for organizing and financing design, construction, operations, and
maintenance services for a structure or facility by entering into legal agreements with one or
more entities or parties. There are two key variables which account for the bulk of the
variation between delivery methods
• The extent of the integration of the various service providers.
• The extent to which the owner is directly financing the project
• DBB,DB,DBOM,BOT,PPP
In India the model which has
been used is DBB and now the trends
are shifting towards EPC,PPP DB .
Horizontal axis - the degree to which the design,
construction, and long term operations and maintenance
of an infrastructure facility are segmented into multiple
contracts or combined in a single contract.
Vertical axis- the degree to which funds to pay for capital
and operating cost are direct or indirect.
Project Delivery Methods
• Can impact allocation of risk, caps and liabilities
under the contract
• Can impact remedies available to Owner for default,
particularly Owner’s ability to obtain access to the
design documents required to complete the project
• Impacts contingencies and contract price
• Internal Self-Finance:
• Equity, Debentures and Bonds:
• Public Deposits:
• Loans from Banks:
• The Managing Agency System:
• Indigenous Bankers:
• Development Finance Institutions:
• Foreign Capital:
Project Funding
Advantages and Disadvantages
• Single point responsibility
• Opportunity for innovation and faster project
delivery
• Efficiency (design & construction expertise
together)
• Fitness for purpose
• No real alternative for proprietary technology
• Fewer changes and implementation simplified
• reduction of claims
• Increased flexibility Reduced administrative
burden for owner
• Cost savings and more certainty of final price
• Improved risk management for owner
• Greater ability to evaluate contractors on factors
other than cost
• Loss of control and reduced owner
involvement in design
• Cost of tendering (to all parties)
• Difficulty/time comparing different designs
• Cost of risks and contingencies
• Danger of Design-Build becoming Build-
Design
• Environmental/regulatory processes
• Limited pool of qualified Design-Builders
• QA/QC largely in contractor’s hands
• Disputes tend to be larger and more complex
• Management of long term risks
• Some lack of project definition prior to
contract award
• Consequences of default more drastic than for
D-B-B
Innovation in Project Management
Using new management techniques
1. Building information and Modelling (BIM): BIM involves all project stakeholders working collaboratively
on a detailed 3D model that includes all the functional systems of a building, such as heating, ventilation and
air conditioning (HVAC) and electrical installations, as well as the aesthetics of walls, windows, and roofs.
Because BIM is a collaborative process from beginning to end, it allows all parties working on a project to
visualize and analyze design decisions, and pinpoint interferences and other errors, before work begins on
site.
2. Agile methodology: Agile is an iterative, team-based approach to development. This
approach emphasizes the rapid delivery of an application in complete functional
components. Rather than creating tasks and schedules, all time is “time-boxed” into phases
called “sprints.” Each sprint has a defined duration (usually in weeks) with a running list of
deliverables, planned at the start of the sprint.
Innovation in Quality Management
Various methods:
1. Six Sigma
2. TQM – Total Quality Management
3. Deming cycle (PDCA)
4. DMAIC
5. EFQM Excellence Model
6. Kaizen
7. Lean
8. Poka yoke
9. Quality circles
Various tools:
1. Procore
2. Finalcad
3. Build7
4. Field wire
Innovation in Quality Management
Six Sigma Management:
Six Sigma is a complex method of management and, like Lean it is known more as a philosophy that the
organization (enterprise) must take. It is focused on continuous improvement (innovation) of the organizational by
understanding customer needs, using the process analysis and methods standardization in the measurement. It is
a comprehensive, flexible management system that is based on understanding customer needs and expectations,
on disciplined use of information and data to management and decision making.
Total Quality management:
TQM is a very complex management method that puts emphasis on the quality management in all dimensions of
the organizational life. It goes beyond quality management and it is also a method of strategic management and it
is a management philosophy for all of the organization activities. It is process oriented rather than result oriented
prioritizing quality, flexibility and services rather than cost and technical efficiency.
Use of Innovative Materials in Construction Industry can
help to -
 Increase Productivity of work
 Increase Performance & Durability of the Structure
 Increase Quality of work
 Reduce the Time
 Make the Building Environment Friendly
Use of Innovative Materials
There are some Innovative Materials which aren’t
using frequently in Indian Construction Industry
but use of those materials can enhance the
efficiency of the Projects .
Some of the Materials are like-
 Insulated Concrete
 Topmix Permeable Concrete
 MMFx Bars
 Bendable Concrete
Innovative Materials
INSULATED CONCRETE
 Stackable foam-concrete sandwich blocks, reinforced with
steel bars and filled with concrete.
 provide an excellent sound and heat insulation.
 Minimize the environmental impact of the building
TOPMIX PERMEABLE CONCRETE
 It has a high void content of 20-35%
 Allows surface water to drain through and dissipate
naturally.
 It is capable of letting through around 36,000 mm
of water/hour.
Innovative Materials
MMFx MICROCOMPOSITE BARS
 Corrosion Resistant
 Over 100-year Service Life
 Quantity Saving – 18 to 20% w.r.t. Fe500.
BENDABLE CONCRETE
 Also known as “Engineered cementitious composite”
(ECC).
 High Durability w.r.t. Conventional Concrete.
 It consumes 40% less energy as compared to conventional
concrete.
 Has an expected service life of 100 years.
Use of Innovative Materials
Innovation in Time, Cost and Quality
Time Reducing Technology
Cost Reducing Technology
Communication Technology
Innovative Technology have brought improvement in
Construction projects as follows:
• Save time
• Reducing cost
• Increase quality
• Reduce risk
• Increase Productivity
• Tracking the project progress
Productivity increasing Technology
Time Reducing Technology
1. Model Printing Technology or Brick Laying tech.
• Reduce Construction time
• Reduce material wastage
• Improve Worker Security
• Improve Work Quality
• Control the Delaying of the Projects.
2. Prefabrication technology
• Use for the fast construction
• Time reducing technology
• Use for high quality construction
• Highly engineering used in this construction
Use:
• All innovative technology reduced construction time.
• improved construction quality
Cost Reducing Technology
3. Slip Form Construction
• Use for the vertical pouring of concrete
• Continuous moving form Work
• Reducing time to stacking of Scaffolding while working
on construction site.
• Use for Tall structures ( Such as Bridges, Towers, Buildings
and Dams) as well as horizontal structures ( Such as
Roadways)
4. Self climbing or Crane Climbing Form work
• Special type of form work for the vertical Concrete.
• This type formwork use high rise story building more than
5 Story.
• The formwork move after the concrete set.
Use:
• Reducing time of shuttering and DE shuttering.
• Cost Reducing techniques of Scaffolding
• Single Time Capital Cost Investment.
Mechanization in Construction
• To reduce the amount of heavy manual work,
• Large output can be maintained if there is shortage of labour and manpower.
• to decrease the complexity of the projects involving high grade materials.
• Use of better equipment eliminates human error and thus ensure the superior quality of
work consistency.
• Optimum use of material, man and finance.
• Speedy construction avoid time and cost over-runs
• To control on the duration and cost implications by using mechanized equipment over
• The Conventional method, which can be used in the planning of construction project.
Mechanization in Construction
1. Telescopic handler
• Machine use for the multipurpose (Loading, Digging, Material
handling etc.)
• Machine is use only high scale projects only.
• Better heaping and very efficient in stacking of material storage.
• Reducing material carriage and handling time.
• Maximum productivity and economy through constant innovation
2. Screed Paving Machine
• Employed with screeding and leveling
• Use for high scale project, like airport, industrial flooring and road
paving
• Reducing time 400 Percentage than manual work
• Improved better quality of working floor
• Perfect in leveling, better quality production
• The machine is laser guided, automatic control system.
• Less manual effort
• Reduce labour cost
• Production high strength. Dense durable floor
Mechanization in Construction
3. Universal Plastering Machine
• Machine use for spray plastering on the interior as well as exterior
wall of the building.
• Provide best quality of finishing and Time Reducing.
• Saving more than 20% raw material (Cement & Sand)
• Reducing construction time
• It is very safe in construction sites.
• 330 sqm. Plastering done in one day
4. Wall Groove Chasing Machine
• Machine is used for brick and Block wall grove cut (chase) in vertical
surface.
• These machines can be used widely in the construction industry.
• Perfect use in flat plane
• It saving time than the manual work.
• Increasing productivity in wall chasing.
Innovation in Health and Safety
ConstructConnect
ISO BS8800
NBC Facility management
Safety is free from risk and danger.
Accidents is defined as an unexpected event resulting in damage.
Hazards is an unsafe condition or activity, which lead to accident.
Typology:
Chemical Hazards Physical Hazards
Biological Hazards Ergonomic Hazards
Cost of Acidents:
Direct cost
Indirect cost
Impact:
---Time----Budget----Accident statistics----Absenteeism---Low morale
Available Standards:
Innovation in Health and Safety
Designing for Construction Safety(DfCS): Application of Prevention through Design concepts to
construction worker safety.
Conceptual Design
Detailed Engineering
Procurement
Construction
Start-up
Ability to
Influence
Safety
Project Schedule
Construction Hazard Assessment and Implication Review
(CHAIR) process:
Commence
Construction
Begin
Concept
Design
CHAIR-2
CHAIR-3
Project Phase
CHAIR-1
Review of Concept
Design
Review of
Detailed
Design
Training and Safety Alert System:
• All worker attend training courses for:
Construction site safety
Designing inherently safe buildings
• Safety Alert System (SAS):
Safety reviews during document preparation
Safety symbols placed on drawings at locations
of potential hazards
Design
Kickoff Design
Internal
Review
Issue for
Construction
External
Review
Trade contractor
involvement
• QA/QC
• Cross-
discipline
• review
• Focused safety
review
• Owner review
• India's infrastructure is in critical need -We need sustained growth trajectory
and unleash the potential of human capital.
• Infrastructure financing lags way behind what's necessary to sustain growth
• Major Risks industry is facing-Delay in Land Acquisition Delay in Licenses,
Permits and Consents; Suspension of the Works, Variations
• Finance Document Default-
Sponsor Support ?
Lender Step-In ?
• Contractor Default
Parent Company Guarantee
Performance Bank Guarantee
Advance Payment Bond?
• Change in Law
• Force Majeure
Risks and Challenges
The Need of the Hour
• For India to sustain medium to long-term economic growth, the project financing market
has to grow at substantially higher levels
• Government would need to explore ways of keeping the sector moving.
• Government has made some progress on key issuesmixed reactions to Land Acquisition
Bill
RERA &GST- Consumer sentiment is finding its way back; ensures transparency
and efficiency in the market and safeguards the rights of home buyer
• Private sector developers and lenders need to be assured that the bottlenecks to project
implementation are adequately addressed by government and the recycling of capital
locked up in distressed projects is demonstrably achievable in a relatively short time-
frame.
• Well-structured projects require an understanding of the nuances of what can go wrong
over the term of the concession and the consequences that flow from that.
• Risks that are known can be mitigated, or at the very least, be taken after factoring them
into the commercials of the project.
. Reduction of regulatory uncertainty and delays
• Appropriate Structuring of projects –
• Developing financing mechanisms to suit the sector’s needs
• Efficient project management (from bid to execution)
Ultimately, how the parties to the project deal with the possibility of paralysis and the
speed that it can be resolved determine the likely successful outcome of any project.
The Need of the Hour
THANK YOU

More Related Content

What's hot

Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
cynfang Fong
 
BIM Introduction
BIM IntroductionBIM Introduction
BIM Introduction
Mohamed Mohsen Kamel
 
Application of BIM
Application of BIMApplication of BIM
Application of BIM
anojan kanagarathnam
 
Civil engineering disciplines and building classification
Civil engineering disciplines and building classificationCivil engineering disciplines and building classification
Civil engineering disciplines and building classification
Anjana R Menon
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
SLIIT, Sri Lanka
 
BIM
BIM BIM
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
hiewliming
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
Sultan M Muzahir
 
BIM BIM.pdf
BIM BIM.pdfBIM BIM.pdf
BIM BIM.pdf
Toe Myint Naing
 
Note on tunnel form construction
Note on tunnel form constructionNote on tunnel form construction
Note on tunnel form construction
RohanBuildersIndia
 
Building Information Model
Building Information ModelBuilding Information Model
Building Information Model
Manisha Shrivastava
 
Modular Construction
Modular ConstructionModular Construction
Modular Construction
Jeelkumar Patel
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Bim adoptation to sri lanka
Bim adoptation to sri lanka Bim adoptation to sri lanka
Bim adoptation to sri lanka
Dasun Kanishka Fernando
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
Gaurav Verma
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
ssuser32da691
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveyinggeddolan
 
Bim
BimBim
Structure & Infrastructure Planning
Structure & Infrastructure PlanningStructure & Infrastructure Planning
Structure & Infrastructure PlanningIr. Abdul Aziz Abas
 

What's hot (20)

Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
BIM Introduction
BIM IntroductionBIM Introduction
BIM Introduction
 
Application of BIM
Application of BIMApplication of BIM
Application of BIM
 
Civil engineering disciplines and building classification
Civil engineering disciplines and building classificationCivil engineering disciplines and building classification
Civil engineering disciplines and building classification
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
BIM
BIM BIM
BIM
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
 
BIM BIM.pdf
BIM BIM.pdfBIM BIM.pdf
BIM BIM.pdf
 
Note on tunnel form construction
Note on tunnel form constructionNote on tunnel form construction
Note on tunnel form construction
 
Building Information Model
Building Information ModelBuilding Information Model
Building Information Model
 
Modular Construction
Modular ConstructionModular Construction
Modular Construction
 
Construction process
Construction processConstruction process
Construction process
 
Bim adoptation to sri lanka
Bim adoptation to sri lanka Bim adoptation to sri lanka
Bim adoptation to sri lanka
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveying
 
Bim
BimBim
Bim
 
Structure & Infrastructure Planning
Structure & Infrastructure PlanningStructure & Infrastructure Planning
Structure & Infrastructure Planning
 

Similar to Innovation technique in construction

Application of BIM in civil industry
Application of BIM in civil industryApplication of BIM in civil industry
Application of BIM in civil industry
Sandya Devarajan
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Er.Sonali Nasikkar
 
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 20165 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
Aconex
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
Aconex
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
ssuser5fc1e7
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
IRJET Journal
 
Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15
British Institute of Facilities Management
 
Prefabrication structures in construction
Prefabrication structures in constructionPrefabrication structures in construction
Prefabrication structures in construction
RajalekshmiSivaram
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
Omar Selim
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
Omar Selim
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and construction
Ankit Singhai
 
Giving construction a new face with enhanced project quality and reduced rewo...
Giving construction a new face with enhanced project quality and reduced rewo...Giving construction a new face with enhanced project quality and reduced rewo...
Giving construction a new face with enhanced project quality and reduced rewo...
BIMEngus1
 
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
Aconex
 
Construction mirror oct2014
Construction mirror oct2014Construction mirror oct2014
Construction mirror oct2014Param Saxena
 
14.15 andrew killander, aconex for distribution
14.15 andrew killander, aconex   for distribution14.15 andrew killander, aconex   for distribution
14.15 andrew killander, aconex for distribution
Ibrahim Al-Hudhaif
 
Construction project management
Construction project managementConstruction project management
Construction project management
saif hasan
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of construction
ANNA REBECCA PRASAD
 

Similar to Innovation technique in construction (20)

Application of BIM in civil industry
Application of BIM in civil industryApplication of BIM in civil industry
Application of BIM in civil industry
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 20165 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
5 Reasons Owners Specify Project-Wide Data Management - Webinar, March 2016
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
5 methods session 1 webinar slideshare colorado hpte_siemensgamesa
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15
 
Prefabrication structures in construction
Prefabrication structures in constructionPrefabrication structures in construction
Prefabrication structures in construction
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
 
Bim
BimBim
Bim
 
Bim
BimBim
Bim
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and construction
 
Giving construction a new face with enhanced project quality and reduced rewo...
Giving construction a new face with enhanced project quality and reduced rewo...Giving construction a new face with enhanced project quality and reduced rewo...
Giving construction a new face with enhanced project quality and reduced rewo...
 
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
How BIM Can Improve Decisions and Reduce Errors - Webinar, December 2, 2015
 
Construction mirror oct2014
Construction mirror oct2014Construction mirror oct2014
Construction mirror oct2014
 
14.15 andrew killander, aconex for distribution
14.15 andrew killander, aconex   for distribution14.15 andrew killander, aconex   for distribution
14.15 andrew killander, aconex for distribution
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of construction
 

Recently uploaded

Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
khadija278284
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
OWASP Beja
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
Vladimir Samoylov
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
Sebastiano Panichella
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
Faculty of Medicine And Health Sciences
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
OECD Directorate for Financial and Enterprise Affairs
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
eCommerce Institute
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Sebastiano Panichella
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Orkestra
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
IP ServerOne
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Matjaž Lipuš
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Sebastiano Panichella
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
Access Innovations, Inc.
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
Howard Spence
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
faizulhassanfaiz1670
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Access Innovations, Inc.
 

Recently uploaded (16)

Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
 

Innovation technique in construction

  • 1.
  • 3. Current scenario India expects to add 300 million new urban residents by 2050. Under the 100 Smart Cities Mission, the government has approved INR480.0 billion. To rehabilitate the slums, construct 20.0 million affordable housing units will be constructed across the country by 2022. AMRUT in 500 towns and cities to provide basic infrastructure services such as water supply, sewerage connection, green spaces, parks and transportation facilities. Bharatmala: 35,000km highways across 16 states. Sagarmala: Connecting 12 major ports and 185 minor ports along the entire 7,500km coastline. Delhi Mumbai Industrial Corridor (DMIC): A six-lane expressway stretching 1,500km connecting the industrial cities of Delhi and Mumbai
  • 4. Major issues in construction industry time overrun cost overrun construction waste 27.49% 75.00% Building construction projects Infrastructure projects Projects with time overrun 727 projects 782 projects 1-261 months delay
  • 5. Major issues in construction industry time overrun cost overrun construction waste projects with cost overrun projects without cost overrun 57%43%
  • 6. Major issues in construction industry FINANCING & PAYMENT ISSUES ADDITIONAL WORK/EXTRA ITEMS POOR CONSTRUCTION MGMT. DELAY IN PLANNED ACTIVITY o Delay in the settlement of contractor claims by the owner o Financial difficulties o Delay in payment for extra work/variations by owner o Late payment to subcontractor or suppliers cost overruntime overrun &
  • 7. Major issues in construction industry FINANCING & PAYMENT ISSUES ADDITIONAL WORK/EXTRA ITEMS POOR CONSTRUCTION MGMT. DELAY IN PLANNED ACTIVITY o Lack of co-ordination between client & contractor o Scope change o Ambiguous or incomplete tender document o Quality issues / mistakes o Fraudulent practices cost overruntime overrun &
  • 8. Major issues in construction industry FINANCING & PAYMENT ISSUES ADDITIONAL WORK/EXTRA ITEMS POOR CONSTRUCTION MGMT. DELAY IN PLANNED ACTIVITY o Infrequent quality assessment. o Unavailability of modern machineries & equipment. o Unavailability of skilled labour. o Improper coordination between client & contractor. o Lack of proper planning technologies o Incompetent organizational structure. cost overruntime overrun &
  • 9. Major issues in construction industry FINANCING & PAYMENT ISSUES ADDITIONAL WORK/EXTRA ITEMS POOR CONSTRUCTION MGMT. DELAY IN PLANNED ACTIVITY o Scope change by client o Design changes by client during construction o Unavailability of machineries & equipment o Delay in revising and approving design documents by owner o Shortage of labours o Incompetent client cost overruntime overrun &
  • 10. Major issues in construction industry 45.6 48 67 270 12.8 14.7 22.1 110.7 0 50 100 150 200 250 300 1997 2001 2011 2021 2031 2041 2047 Construction waste Solid waste time overrun cost overrun construction waste million tonnes/year
  • 11. Major issues in construction industry construction waste Construction industry is responsible for 25-40% of the carbon emissions on a global scale 30-40% of the total MSW is generated by construction industry. o Frequent Design Changes o Poor Quality Of Materials o Scope & design change o Poor Planning o Poor Site Management
  • 12. Remedies Use of appropriate modern technologies Modern materials which reduce waste Proper planning & scheduling Through proper collaboration between contractor & client Labour training program Frequent quality assessment
  • 13.
  • 14. Project Delivery Methods • A system used for organizing and financing design, construction, operations, and maintenance services for a structure or facility by entering into legal agreements with one or more entities or parties. There are two key variables which account for the bulk of the variation between delivery methods • The extent of the integration of the various service providers. • The extent to which the owner is directly financing the project • DBB,DB,DBOM,BOT,PPP In India the model which has been used is DBB and now the trends are shifting towards EPC,PPP DB .
  • 15. Horizontal axis - the degree to which the design, construction, and long term operations and maintenance of an infrastructure facility are segmented into multiple contracts or combined in a single contract. Vertical axis- the degree to which funds to pay for capital and operating cost are direct or indirect. Project Delivery Methods • Can impact allocation of risk, caps and liabilities under the contract • Can impact remedies available to Owner for default, particularly Owner’s ability to obtain access to the design documents required to complete the project • Impacts contingencies and contract price
  • 16. • Internal Self-Finance: • Equity, Debentures and Bonds: • Public Deposits: • Loans from Banks: • The Managing Agency System: • Indigenous Bankers: • Development Finance Institutions: • Foreign Capital: Project Funding
  • 17. Advantages and Disadvantages • Single point responsibility • Opportunity for innovation and faster project delivery • Efficiency (design & construction expertise together) • Fitness for purpose • No real alternative for proprietary technology • Fewer changes and implementation simplified • reduction of claims • Increased flexibility Reduced administrative burden for owner • Cost savings and more certainty of final price • Improved risk management for owner • Greater ability to evaluate contractors on factors other than cost • Loss of control and reduced owner involvement in design • Cost of tendering (to all parties) • Difficulty/time comparing different designs • Cost of risks and contingencies • Danger of Design-Build becoming Build- Design • Environmental/regulatory processes • Limited pool of qualified Design-Builders • QA/QC largely in contractor’s hands • Disputes tend to be larger and more complex • Management of long term risks • Some lack of project definition prior to contract award • Consequences of default more drastic than for D-B-B
  • 18.
  • 19. Innovation in Project Management Using new management techniques 1. Building information and Modelling (BIM): BIM involves all project stakeholders working collaboratively on a detailed 3D model that includes all the functional systems of a building, such as heating, ventilation and air conditioning (HVAC) and electrical installations, as well as the aesthetics of walls, windows, and roofs. Because BIM is a collaborative process from beginning to end, it allows all parties working on a project to visualize and analyze design decisions, and pinpoint interferences and other errors, before work begins on site. 2. Agile methodology: Agile is an iterative, team-based approach to development. This approach emphasizes the rapid delivery of an application in complete functional components. Rather than creating tasks and schedules, all time is “time-boxed” into phases called “sprints.” Each sprint has a defined duration (usually in weeks) with a running list of deliverables, planned at the start of the sprint.
  • 20.
  • 21. Innovation in Quality Management Various methods: 1. Six Sigma 2. TQM – Total Quality Management 3. Deming cycle (PDCA) 4. DMAIC 5. EFQM Excellence Model 6. Kaizen 7. Lean 8. Poka yoke 9. Quality circles Various tools: 1. Procore 2. Finalcad 3. Build7 4. Field wire
  • 22. Innovation in Quality Management Six Sigma Management: Six Sigma is a complex method of management and, like Lean it is known more as a philosophy that the organization (enterprise) must take. It is focused on continuous improvement (innovation) of the organizational by understanding customer needs, using the process analysis and methods standardization in the measurement. It is a comprehensive, flexible management system that is based on understanding customer needs and expectations, on disciplined use of information and data to management and decision making. Total Quality management: TQM is a very complex management method that puts emphasis on the quality management in all dimensions of the organizational life. It goes beyond quality management and it is also a method of strategic management and it is a management philosophy for all of the organization activities. It is process oriented rather than result oriented prioritizing quality, flexibility and services rather than cost and technical efficiency.
  • 23.
  • 24. Use of Innovative Materials in Construction Industry can help to -  Increase Productivity of work  Increase Performance & Durability of the Structure  Increase Quality of work  Reduce the Time  Make the Building Environment Friendly Use of Innovative Materials
  • 25. There are some Innovative Materials which aren’t using frequently in Indian Construction Industry but use of those materials can enhance the efficiency of the Projects . Some of the Materials are like-  Insulated Concrete  Topmix Permeable Concrete  MMFx Bars  Bendable Concrete Innovative Materials
  • 26. INSULATED CONCRETE  Stackable foam-concrete sandwich blocks, reinforced with steel bars and filled with concrete.  provide an excellent sound and heat insulation.  Minimize the environmental impact of the building TOPMIX PERMEABLE CONCRETE  It has a high void content of 20-35%  Allows surface water to drain through and dissipate naturally.  It is capable of letting through around 36,000 mm of water/hour. Innovative Materials
  • 27. MMFx MICROCOMPOSITE BARS  Corrosion Resistant  Over 100-year Service Life  Quantity Saving – 18 to 20% w.r.t. Fe500. BENDABLE CONCRETE  Also known as “Engineered cementitious composite” (ECC).  High Durability w.r.t. Conventional Concrete.  It consumes 40% less energy as compared to conventional concrete.  Has an expected service life of 100 years. Use of Innovative Materials
  • 28.
  • 29. Innovation in Time, Cost and Quality Time Reducing Technology Cost Reducing Technology Communication Technology Innovative Technology have brought improvement in Construction projects as follows: • Save time • Reducing cost • Increase quality • Reduce risk • Increase Productivity • Tracking the project progress Productivity increasing Technology
  • 30. Time Reducing Technology 1. Model Printing Technology or Brick Laying tech. • Reduce Construction time • Reduce material wastage • Improve Worker Security • Improve Work Quality • Control the Delaying of the Projects. 2. Prefabrication technology • Use for the fast construction • Time reducing technology • Use for high quality construction • Highly engineering used in this construction Use: • All innovative technology reduced construction time. • improved construction quality
  • 31. Cost Reducing Technology 3. Slip Form Construction • Use for the vertical pouring of concrete • Continuous moving form Work • Reducing time to stacking of Scaffolding while working on construction site. • Use for Tall structures ( Such as Bridges, Towers, Buildings and Dams) as well as horizontal structures ( Such as Roadways) 4. Self climbing or Crane Climbing Form work • Special type of form work for the vertical Concrete. • This type formwork use high rise story building more than 5 Story. • The formwork move after the concrete set. Use: • Reducing time of shuttering and DE shuttering. • Cost Reducing techniques of Scaffolding • Single Time Capital Cost Investment.
  • 32.
  • 33. Mechanization in Construction • To reduce the amount of heavy manual work, • Large output can be maintained if there is shortage of labour and manpower. • to decrease the complexity of the projects involving high grade materials. • Use of better equipment eliminates human error and thus ensure the superior quality of work consistency. • Optimum use of material, man and finance. • Speedy construction avoid time and cost over-runs • To control on the duration and cost implications by using mechanized equipment over • The Conventional method, which can be used in the planning of construction project.
  • 34. Mechanization in Construction 1. Telescopic handler • Machine use for the multipurpose (Loading, Digging, Material handling etc.) • Machine is use only high scale projects only. • Better heaping and very efficient in stacking of material storage. • Reducing material carriage and handling time. • Maximum productivity and economy through constant innovation 2. Screed Paving Machine • Employed with screeding and leveling • Use for high scale project, like airport, industrial flooring and road paving • Reducing time 400 Percentage than manual work • Improved better quality of working floor • Perfect in leveling, better quality production • The machine is laser guided, automatic control system. • Less manual effort • Reduce labour cost • Production high strength. Dense durable floor
  • 35. Mechanization in Construction 3. Universal Plastering Machine • Machine use for spray plastering on the interior as well as exterior wall of the building. • Provide best quality of finishing and Time Reducing. • Saving more than 20% raw material (Cement & Sand) • Reducing construction time • It is very safe in construction sites. • 330 sqm. Plastering done in one day 4. Wall Groove Chasing Machine • Machine is used for brick and Block wall grove cut (chase) in vertical surface. • These machines can be used widely in the construction industry. • Perfect use in flat plane • It saving time than the manual work. • Increasing productivity in wall chasing.
  • 36.
  • 37. Innovation in Health and Safety ConstructConnect ISO BS8800 NBC Facility management Safety is free from risk and danger. Accidents is defined as an unexpected event resulting in damage. Hazards is an unsafe condition or activity, which lead to accident. Typology: Chemical Hazards Physical Hazards Biological Hazards Ergonomic Hazards Cost of Acidents: Direct cost Indirect cost Impact: ---Time----Budget----Accident statistics----Absenteeism---Low morale Available Standards:
  • 38. Innovation in Health and Safety Designing for Construction Safety(DfCS): Application of Prevention through Design concepts to construction worker safety. Conceptual Design Detailed Engineering Procurement Construction Start-up Ability to Influence Safety Project Schedule Construction Hazard Assessment and Implication Review (CHAIR) process: Commence Construction Begin Concept Design CHAIR-2 CHAIR-3 Project Phase CHAIR-1 Review of Concept Design Review of Detailed Design Training and Safety Alert System: • All worker attend training courses for: Construction site safety Designing inherently safe buildings • Safety Alert System (SAS): Safety reviews during document preparation Safety symbols placed on drawings at locations of potential hazards Design Kickoff Design Internal Review Issue for Construction External Review Trade contractor involvement • QA/QC • Cross- discipline • review • Focused safety review • Owner review
  • 39.
  • 40. • India's infrastructure is in critical need -We need sustained growth trajectory and unleash the potential of human capital. • Infrastructure financing lags way behind what's necessary to sustain growth • Major Risks industry is facing-Delay in Land Acquisition Delay in Licenses, Permits and Consents; Suspension of the Works, Variations • Finance Document Default- Sponsor Support ? Lender Step-In ? • Contractor Default Parent Company Guarantee Performance Bank Guarantee Advance Payment Bond? • Change in Law • Force Majeure Risks and Challenges
  • 41. The Need of the Hour • For India to sustain medium to long-term economic growth, the project financing market has to grow at substantially higher levels • Government would need to explore ways of keeping the sector moving. • Government has made some progress on key issuesmixed reactions to Land Acquisition Bill RERA &GST- Consumer sentiment is finding its way back; ensures transparency and efficiency in the market and safeguards the rights of home buyer • Private sector developers and lenders need to be assured that the bottlenecks to project implementation are adequately addressed by government and the recycling of capital locked up in distressed projects is demonstrably achievable in a relatively short time- frame. • Well-structured projects require an understanding of the nuances of what can go wrong over the term of the concession and the consequences that flow from that. • Risks that are known can be mitigated, or at the very least, be taken after factoring them into the commercials of the project.
  • 42. . Reduction of regulatory uncertainty and delays • Appropriate Structuring of projects – • Developing financing mechanisms to suit the sector’s needs • Efficient project management (from bid to execution) Ultimately, how the parties to the project deal with the possibility of paralysis and the speed that it can be resolved determine the likely successful outcome of any project. The Need of the Hour