Hunter Mill District Community Outreach Meeting: Nov. 4, 2015Fairfax County
This document summarizes a community outreach meeting that was held on November 4, 2015 to discuss the redevelopment of Reston Town Center North. The meeting covered Phase 1 and Phase 2 development plans, including proposed components such as a replacement library, homeless shelter, affordable housing units, retail/commercial space, and potential future uses. Feedback from a prior September 19th meeting was also acknowledged. Details were provided on timelines, public participation opportunities, and tentative development plans and components for the library, shelter, housing, and other elements.
Reston Town Center North Community Update May 31, 2017Fairfax County
On May 31, 2017, at the Lake Anne Elementary School, Hunter Mill District Supervisor Cathy Hudgins hosted a community meeting to provide an update on the Reston Town Center North Development Project. For more information on this project, visit www.fairfaxcounty.gov/dpwes/restontowncenternorth
The document summarizes a community meeting about the design of the Huntington Levee project. It discusses the project background and completed tasks like surveys and conceptual design. It also describes the interior drainage analysis that was conducted to understand water flow behind the levee and size pumps and storage areas. Upcoming steps include permit submissions and a pump station design session. The schedule forecasts completing design in 2017 and construction from 2017-2019. Future community outreach plans are also outlined.
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
The document summarizes a community meeting about the Huntington Levee project. It provides an overview of the project background and history, updates on the design including renderings of key features, details about planned community amenities and construction access, the results of flood modeling, and the project schedule and outreach efforts. The levee system is intended to protect homes in the area from a 100-year flood. The design incorporates earthen levees, I-walls, a pump station, trails, and native landscaping. Construction is planned to begin in early 2017 upon completing permitting.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
Fairfax County Commercial and Industrial Property Tax for TransportationFairfax County
The Fairfax County Board of Supervisors approved an ordinance establishing the commercial and industrial property tax for transportation in September 2007. Collection of this revenue source began in 2008 (FY 2009). This revenue is just one source of many revenue sources that are needed to fund transportation improvements.
Hunter Mill District Community Outreach Meeting: Nov. 4, 2015Fairfax County
This document summarizes a community outreach meeting that was held on November 4, 2015 to discuss the redevelopment of Reston Town Center North. The meeting covered Phase 1 and Phase 2 development plans, including proposed components such as a replacement library, homeless shelter, affordable housing units, retail/commercial space, and potential future uses. Feedback from a prior September 19th meeting was also acknowledged. Details were provided on timelines, public participation opportunities, and tentative development plans and components for the library, shelter, housing, and other elements.
Reston Town Center North Community Update May 31, 2017Fairfax County
On May 31, 2017, at the Lake Anne Elementary School, Hunter Mill District Supervisor Cathy Hudgins hosted a community meeting to provide an update on the Reston Town Center North Development Project. For more information on this project, visit www.fairfaxcounty.gov/dpwes/restontowncenternorth
The document summarizes a community meeting about the design of the Huntington Levee project. It discusses the project background and completed tasks like surveys and conceptual design. It also describes the interior drainage analysis that was conducted to understand water flow behind the levee and size pumps and storage areas. Upcoming steps include permit submissions and a pump station design session. The schedule forecasts completing design in 2017 and construction from 2017-2019. Future community outreach plans are also outlined.
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
The document summarizes a community meeting about the Huntington Levee project. It provides an overview of the project background and history, updates on the design including renderings of key features, details about planned community amenities and construction access, the results of flood modeling, and the project schedule and outreach efforts. The levee system is intended to protect homes in the area from a 100-year flood. The design incorporates earthen levees, I-walls, a pump station, trails, and native landscaping. Construction is planned to begin in early 2017 upon completing permitting.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
Fairfax County Commercial and Industrial Property Tax for TransportationFairfax County
The Fairfax County Board of Supervisors approved an ordinance establishing the commercial and industrial property tax for transportation in September 2007. Collection of this revenue source began in 2008 (FY 2009). This revenue is just one source of many revenue sources that are needed to fund transportation improvements.
This document provides information about an upcoming stream restoration project along Dead Run in Fairfax County, Virginia. The project will restore 2,800 linear feet of Dead Run and its tributaries through McLean Central Park and Dead Run Stream Valley Park from February 2018 to early 2020. It will involve natural channel design, repairing a tributary headcut, replacing a pedestrian bridge, invasive plant removal, and replanting the riparian corridor. The work will be conducted in three phases by Meadville Land Services to minimize disturbances. Residents are asked to stay outside construction limits for their safety.
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectFairfax County
The Dead Run at Dominican Retreat - Segment 1 Stream Restoration project restored approximately 2,000 linear feet of Dead Run in Fairfax County, Virginia. The project used natural channel design principles to restore stream morphology, replace bridges and culverts, control invasive species, and add in-stream structures to reduce erosion. It was completed ahead of schedule and on budget in June 2017. The restoration aims to improve water quality and habitat in the tributary of Dead Run that flows into the Potomac River.
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
This document summarizes a citizens information meeting about a proposed sidewalk project along Kirby Road between Chesterbrook Road and Mori Street in Fairfax County, Virginia. The project is estimated to cost $2 million and would construct a new 5-foot wide sidewalk with curb ramps and drainage improvements to meet accessibility standards. It may require relocating utilities, removing trees, and acquiring additional right-of-way or easements. The project schedule estimates intermediate design in spring 2019, pre-final design in late 2019, beginning construction in late 2021, and completing construction in summer 2022. Attendees were invited to provide comments.
The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Fairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding plans to complete missing segments of the Potomac Heritage National Scenic Trail between Richmond Highway and Southwood Drive in Mount Vernon, Virginia. The meeting covered the project purpose and description, existing conditions, conceptual design plans featuring a pedestrian bridge over Dogue Creek and potential impacts. Next steps include accepting public feedback until April 8th and further design and environmental review before a follow-up public meeting.
Crook at Mantua Elementary School Stream RestorationFairfax County
3,700 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
2,986 lbs/total phosphorus
6,483 lbs/total nitrogren
514.6 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Turkey Run at Truro Subdivision Stream RestorationFairfax County
The Turkey Run @ Truro Subdivision Stream Restoration project in Fairfax County, VA restored 3,850 linear feet of stream channel and tributaries. The project improved stream morphology, removed an existing pedestrian bridge and replaced it along with six others, removed an existing trail and part of a parking lot, added materials to stabilize the stream bed and banks, controlled invasive species, and added structures to reduce erosion and improve habitat. The project is estimated to reduce phosphorus and nitrogen pollution and sediment entering Accotink Creek and the Potomac River annually.
Fairfax County Land Conservation Awards 2016Fairfax County
This document provides information about the Fairfax County Land Conservation Awards 2016 event. It recognizes outstanding projects, individuals, and organizations in several categories related to land conservation and environmental protection efforts in Fairfax County, Virginia. The categories include large single family residential, large commercial, small commercial, special project, and infill lot. Several projects are highlighted for each category, and individuals are recognized for their contributions in engineering, construction oversight, development, and conservation work.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
The document summarizes a stream restoration project along Paul Spring Branch in Fairfax County, Virginia. The project restored 550 feet of degraded stream channel using natural design techniques, reconnected the channel to its floodplain, stabilized the stream bed and banks with structures, and restored the site with native plants. The project is estimated to reduce nitrogen, phosphorus, and sediment loads to the stream.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
The document provides an annual review of initiatives related to College Station's Comprehensive Plan, including updates to various master plans covering topics such as neighborhoods, transportation, parks, utilities, and economic development. Key accomplishments in 2018 involved advancing projects identified in the plans, such as expanding trails and sidewalks, rehabilitating infrastructure in older areas, and extending utilities to serve future growth.
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement ProjectFairfax County
The Fairfax County Department of Public Works and Environmental Services upgraded over 3000 linear feet of stormwater infrastructure in the Franklin Park and Chesterbrook neighborhoods to reduce flooding, improve stormwater flow and water quality. The project was completed on time and on budget in December 2016 through the construction of swales, infiltration trenches, underground storage chambers and permeable surfaces. The project is estimated to reduce nitrogen, phosphorus and sediment runoff into local waterways.
This document provides details about the Autumnwood Park Pond Retrofit Project in Hunter Mill District. The purpose of the project was to retrofit an existing stormwater management pond to provide improved water quality and storage capacity. Key aspects of the retrofit included excavating areas for a forebay, wetlands, and seven cascade steps connected by three new micropools. Native plantings and trees were installed to restore the disturbed areas. The retrofit is projected to remove 7.7 pounds/year of phosphorus, 63.4 pounds/year of nitrogen, and 2,720 pounds/year of total suspended solids from surrounding runoff.
Dead Run Stream Restoration Public Meeting May 19, 2015Fairfax County
This document summarizes a public meeting for a stream restoration project on Dead Run in Fairfax County, VA. It discusses the project scope and status, concept plans to widen and stabilize the stream channel, address flooding concerns, efforts to preserve trees, and next steps. Alternative access options were presented to minimize tree removal, and buffer restoration efforts along the stream were discussed to improve habitat and water quality. Feedback from residents was addressed, and the project aims to have minimal impact on the floodplain.
This document provides information about an upcoming stream restoration project along Dead Run in Fairfax County, Virginia. The project will restore 2,800 linear feet of Dead Run and its tributaries through McLean Central Park and Dead Run Stream Valley Park from February 2018 to early 2020. It will involve natural channel design, repairing a tributary headcut, replacing a pedestrian bridge, invasive plant removal, and replanting the riparian corridor. The work will be conducted in three phases by Meadville Land Services to minimize disturbances. Residents are asked to stay outside construction limits for their safety.
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectFairfax County
The Dead Run at Dominican Retreat - Segment 1 Stream Restoration project restored approximately 2,000 linear feet of Dead Run in Fairfax County, Virginia. The project used natural channel design principles to restore stream morphology, replace bridges and culverts, control invasive species, and add in-stream structures to reduce erosion. It was completed ahead of schedule and on budget in June 2017. The restoration aims to improve water quality and habitat in the tributary of Dead Run that flows into the Potomac River.
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
This document summarizes a citizens information meeting about a proposed sidewalk project along Kirby Road between Chesterbrook Road and Mori Street in Fairfax County, Virginia. The project is estimated to cost $2 million and would construct a new 5-foot wide sidewalk with curb ramps and drainage improvements to meet accessibility standards. It may require relocating utilities, removing trees, and acquiring additional right-of-way or easements. The project schedule estimates intermediate design in spring 2019, pre-final design in late 2019, beginning construction in late 2021, and completing construction in summer 2022. Attendees were invited to provide comments.
The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Fairfax County
This document summarizes a public information meeting held by the Fairfax County Department of Transportation regarding plans to complete missing segments of the Potomac Heritage National Scenic Trail between Richmond Highway and Southwood Drive in Mount Vernon, Virginia. The meeting covered the project purpose and description, existing conditions, conceptual design plans featuring a pedestrian bridge over Dogue Creek and potential impacts. Next steps include accepting public feedback until April 8th and further design and environmental review before a follow-up public meeting.
Crook at Mantua Elementary School Stream RestorationFairfax County
3,700 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
2,986 lbs/total phosphorus
6,483 lbs/total nitrogren
514.6 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Turkey Run at Truro Subdivision Stream RestorationFairfax County
The Turkey Run @ Truro Subdivision Stream Restoration project in Fairfax County, VA restored 3,850 linear feet of stream channel and tributaries. The project improved stream morphology, removed an existing pedestrian bridge and replaced it along with six others, removed an existing trail and part of a parking lot, added materials to stabilize the stream bed and banks, controlled invasive species, and added structures to reduce erosion and improve habitat. The project is estimated to reduce phosphorus and nitrogen pollution and sediment entering Accotink Creek and the Potomac River annually.
Fairfax County Land Conservation Awards 2016Fairfax County
This document provides information about the Fairfax County Land Conservation Awards 2016 event. It recognizes outstanding projects, individuals, and organizations in several categories related to land conservation and environmental protection efforts in Fairfax County, Virginia. The categories include large single family residential, large commercial, small commercial, special project, and infill lot. Several projects are highlighted for each category, and individuals are recognized for their contributions in engineering, construction oversight, development, and conservation work.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
The document summarizes a stream restoration project along Paul Spring Branch in Fairfax County, Virginia. The project restored 550 feet of degraded stream channel using natural design techniques, reconnected the channel to its floodplain, stabilized the stream bed and banks with structures, and restored the site with native plants. The project is estimated to reduce nitrogen, phosphorus, and sediment loads to the stream.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
The document provides an annual review of initiatives related to College Station's Comprehensive Plan, including updates to various master plans covering topics such as neighborhoods, transportation, parks, utilities, and economic development. Key accomplishments in 2018 involved advancing projects identified in the plans, such as expanding trails and sidewalks, rehabilitating infrastructure in older areas, and extending utilities to serve future growth.
Franklin Park and Chesterbrook Neighborhood Stormwater Improvement ProjectFairfax County
The Fairfax County Department of Public Works and Environmental Services upgraded over 3000 linear feet of stormwater infrastructure in the Franklin Park and Chesterbrook neighborhoods to reduce flooding, improve stormwater flow and water quality. The project was completed on time and on budget in December 2016 through the construction of swales, infiltration trenches, underground storage chambers and permeable surfaces. The project is estimated to reduce nitrogen, phosphorus and sediment runoff into local waterways.
This document provides details about the Autumnwood Park Pond Retrofit Project in Hunter Mill District. The purpose of the project was to retrofit an existing stormwater management pond to provide improved water quality and storage capacity. Key aspects of the retrofit included excavating areas for a forebay, wetlands, and seven cascade steps connected by three new micropools. Native plantings and trees were installed to restore the disturbed areas. The retrofit is projected to remove 7.7 pounds/year of phosphorus, 63.4 pounds/year of nitrogen, and 2,720 pounds/year of total suspended solids from surrounding runoff.
Dead Run Stream Restoration Public Meeting May 19, 2015Fairfax County
This document summarizes a public meeting for a stream restoration project on Dead Run in Fairfax County, VA. It discusses the project scope and status, concept plans to widen and stabilize the stream channel, address flooding concerns, efforts to preserve trees, and next steps. Alternative access options were presented to minimize tree removal, and buffer restoration efforts along the stream were discussed to improve habitat and water quality. Feedback from residents was addressed, and the project aims to have minimal impact on the floodplain.
Banks Property Stream Restoration (DC9218)Fairfax County
The Banks Property Stream Restoration project restored 1,150 linear feet of degraded stream tributary. The project established a stable channel geometry, reconnected the stream to its floodplain, stabilized the stream bed and banks with structures like rock sills and cross-vanes, daylighted piped sections, and replanted the site with native vegetation. The restoration is estimated to reduce nitrogen, phosphorus, and sediment loads to the stream. The project involved several Fairfax County departments and private organizations and was substantially completed in November 2014.
The Springfield Forest Schupps Add. 1115DP Summerton Way Pond project retrofitted an existing dry pond in Fairfax County, VA to improve stormwater quality and detention. The retrofit removed the existing concrete trickle ditch, regraded the facility to lengthen the flow path and maximize pond volume, excavated three micro-pools, installed an endwall, concrete apron, and trash rack at the riser, constructed an access road, and restored the site with seed and plantings. The project aims to remove phosphorus, nitrogen, and suspended solids from stormwater runoff.
The document describes the Sequoia Park Pond (0705DP) Retrofit Project in Fairfax County, VA, which retrofitted an existing stormwater pond to provide improved water quality benefits through the construction of micro-pools, rock weirs, and other features; it provides details on the project overview, team members, and pre-existing and new conditions of the pond and surrounding area; additional information can be found by contacting the Fairfax County Department of Public Works and Environmental Services.
This document from Fairfax County discusses the gypsy moth, an invasive pest that defoliates trees. It notes that gypsy moths lay egg masses that can be found on tree trunks and other surfaces from July to April. The county monitors for egg masses annually and encourages residents to search their properties and report any findings, to help detect and control local gypsy moth populations. Residents are advised to scrape detected egg masses into soapy water or bleach to help control the pest on their properties.
Approximately 1,000 cubic yards of sediment was dredged from an existing pond and the stream channel was restored. Two detention ponds were retrofitted to improve water quality and establish a functioning biological system. Dredging services were donated by Wetland Studies and Solutions, Inc.
Land Development Update-NAIOP/NVBIA Joint Meeting: Dec. 10, 2015Fairfax County
This document provides information from a joint meeting between NAIOP and NVBIA on December 10, 2015. It includes an update on land development projects in Fairfax County. Several county agencies provided information in the document. The Department of Public Works and Environmental Services reported on average site plan timelines, which have decreased from previous periods. The Fire Marshal's Office outlined their plan review inventory and backlog. Planning and Zoning also provided an update. Finally, the document announced a new webpage for the NVBIA/NAIOP Fairfax committee to share information.
This document provides updates from various county agencies on land development and construction projects. It discusses staffing changes and current hiring within departments like LDS, DPZ, and Fire Marshal. Timelines for development plan reviews are presented. The document also outlines several cross-agency initiatives to improve processes like inspections, proffers, and restaurants. LDS shares their top priorities such as combining initial inspections. E-plans and performance metrics are discussed as areas of focus. The Fire Marshal provides statistics on their building plan inventory and review times.
The Overly Drive Flood Mitigation Project was completed on time and under budget on June 28, 2013. The project provided an overland relief channel to convey water from an overflowing 54" pipe to an existing junction box and culvert, preventing flooding of five homes. Key elements included constructing a natural stream channel with rock steps, walls, and vegetation to direct water away from homes and toward an outlet under I-495. The project was led by Ratna S Pottumuthu and Mannan Qureshi and addressed a longstanding flooding issue in the area.
This document provides details about a pond retrofit project in Fairfax County, VA called Towlston Meadows Sec 3 Pond 1. The purpose of the project was to increase water quality and add an access road for maintenance. Work included regrading the pond, adding micro pools, increasing storage volume, and constructing an all-weather access road. Native plants were also installed to restore the landscape. The project was completed on time and on budget in April 2014.
Dead Run Stream Restoration Public Meeting June 9, 2015Fairfax County
This document summarizes a public meeting held on June 9, 2015 to discuss the Dead Run Segments 2/3 Stream Restoration Project in Fairfax County, VA. The project aims to restore 1,800 linear feet of Dead Run stream through McLean Central Park and Dead Run Stream Valley Park. Key topics discussed include the project timeline and extent, responses to community issues raised, next steps including forming a citizen task force, and potential design refinements to minimize tree and canopy loss while improving water quality and habitat.
Draft Chesapeake Bay TMDL Action Plan Public MeetingFairfax County
This document provides a summary of Fairfax County, VA's draft action plan to meet pollutant reduction requirements under the Chesapeake Bay Total Maximum Daily Load (TMDL). It outlines the county's two-pronged approach to meet MS4 permit requirements and statewide watershed implementation plan milestones. Key components discussed include addressing increases from new development since 2009, utilizing existing watershed plans, and employing various stormwater retrofit and stream restoration projects to achieve the necessary nitrogen, phosphorus, and sediment reductions. Uncertainties and challenges completing the remaining reductions are also noted.
Fall Cankerworm Sticky Banding: A Community Working TogetherFairfax County
This document discusses the biology and life cycle of fall cankerworms, how Fairfax County monitors for them using sticky banding around tree trunks, and the impacts of defoliation. It provides instructions for assembling and using sticky banding kits to trap female cankerworms crawling up tree trunks, which allows for monitoring of populations and recommendations for treatment if high numbers are caught. The goal is to help reduce defoliation that can weaken and kill trees with repeated heavy infestations.
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Fairfax County
This document summarizes a public meeting to discuss a stream restoration project on Bull Neck Run at the Spring Hill Recreation Center. The meeting outlined Fairfax County's watershed planning efforts, presented the project objectives and existing conditions, and proposed improvements and example projects. Attendees were invited to ask questions. The project aims to provide water quality controls and protect channel capacity as required for a recreation center expansion. Next steps include design, permitting, public feedback, construction, and long-term maintenance.
This document summarizes a stormwater management project in Fairfax Station, Virginia. The project retrofitted an existing stormwater pond to provide improved water quality and additional storage. Work included regrading the pond, excavating micropools, extending riprap, installing a rock weir, replacing a trail, and restoring plantings. Upon completion, the project is estimated to remove over 10 pounds of phosphorus, 2 pounds of nitrogen, and 470 pounds of suspended solids from stormwater each year.
Columbia Road/Randolph Court Stream Restoration July 2015Fairfax County
This document summarizes a proposed stream restoration project in Fairfax County, VA. It describes the existing failing gabion walls and eroding stream banks. The proposed project would replace the gabion walls with more natural stream restoration structures like cross vanes, root wads, and boulder toes to stabilize the banks. It would also add planted buffer zones and benches along the stream. The project requires designing temporary construction access given the steep slopes, and coordinating with other planned restoration work. It outlines the conceptual design, approval, and construction schedule.
Contractor Awareness Training Below Ground Facilities 2016Fairfax County
This document provides an overview of a stormwater maintenance awareness training held by the Department of Public Works and Environmental Services in Fairfax County, VA. The training covered the history of stormwater regulations, types of stormwater management facilities like underground detention, sand filters, and manufactured BMPs. It discussed common maintenance issues for these facilities like debris and sediment accumulation, damage to components, and remedial actions required. The document included pictures of different facility components and deficiencies to illustrate key points.
The document summarizes a community meeting to discuss the conceptual design for the Huntington Levee project. The meeting covered the project background and flooding issues facing the community. It then reviewed the conceptual design features being considered, including the use of collection drains versus a cutoff wall, different locations for a pump station, options for stormwater diversion, and use of an earthen levee alone or in combination with an I-wall. The design aims to meet FEMA accreditation standards to reduce flooding and received feedback from the community.
Miller Heights Outfall Rehabilitation Project 2014Fairfax County
The Miller Heights Outfall Rehabilitation Project was completed on time and within budget. The project involved stabilizing over 250 feet of eroded channel near Miller Road and Miller Heights Road. Natural stream channel design was used, including rock cross vanes, weirs, and plantings to reduce erosion and improve water quality. The project addressed safety concerns and stabilized the channel while providing environmental benefits.
South Orange Valley and Third Street Redevelopment PlanAlex Torpey
This document summarizes the redevelopment plans for a 2.7 acre property located in the Village. A mixed-use development is proposed that would include approximately 521 space parking facility, 215 residential rental units (including affordable units), and 3,000 square feet of retail space. The development would be constructed by Jonathan Rose Companies and involves relocating the local rescue squad facility. Key aspects of the financial agreement, redevelopment plan, and anticipated development timetable are outlined.
The city commission workshop will discuss potentially acquiring the Post Office property adjacent to Central Park to expand the park. Acquiring the property has long been part of the city's plans and policies to enhance Central Park, which has received strong community support. Prior attempts to purchase the property from the USPS were unsuccessful. The workshop will explore the project objectives, costs, funding sources, and commission decisions needed to potentially reengage the USPS in negotiations.
OCR: Fairfax County Revitalization ProgramFairfax County
The Fairfax County Office of Community Revitalization (OCR) facilitates redevelopment within targeted commercial areas to improve economic vitality, appearance, and function. OCR established 5 Commercial Revitalization Districts and 2 Commercial Revitalization Areas to support revitalization. OCR uses strategies like community visioning, placemaking, public-private partnerships, and public policy to address challenges and guide growth in a sustainable manner through mixed-use development and investment in transit areas.
Update on Reston Development and Transportation ProjectsFairfax County
The document provides an update on development and transportation projects in Reston, Virginia from the Fairfax County Department of Transportation. It discusses major construction deliveries and current development activity, including thousands of residential units and millions of square feet of commercial space approved or under construction. It also provides status updates on numerous transportation projects to support this growth, such as the Silver Line Metro expansion, new roads, and intersection improvements.
This presentation summarized plans for redevelopment of the Ephesus Church-Fordham Boulevard area, including:
1) Increasing connectivity, creating greenspace and mixed-use nodes, and encouraging multi-family and transit-oriented development;
2) Conceptual plans showing over 1,000 residential units, 300,000 square feet of office and retail space, and a 280,000 square foot hotel;
3) Proposed transportation improvements including new road connections and intersections; and
4) Plans to implement the redevelopment through zoning changes, development agreements, and public-private partnerships to fund $8.8 million in infrastructure through financing methods like tax-increment financing.
This document summarizes a quarterly meeting of the Lee's Summit 360° Implementation Committee. It outlines progress and next steps on several city strategic plan goals, including pursuing highest and best uses of underutilized properties, awarding an energy efficiency grant, solid waste collection and curbside recycling, cultural arts projects like the Arnold Hall redevelopment, and an airport business plan. It also discusses potential bond projects and tracking progress online.
Reston Transportation Funding Plan: July 15, 2016Fairfax County
This document summarizes a stakeholder meeting about developing a funding plan for transportation improvements in Reston, Virginia. The plan would fund projects like road widenings and intersections recommended in Reston's comprehensive plan to support new development. Public and private funding sources would be used. Private sources could include developer proffers, contributions to a road fund, tax districts, and tax increment financing. The county presented a tentative framework allocating costs 53% to public funds and 47% to private. Road projects would be fully public while intersections and a new grid network would be mostly privately funded. Feedback was sought on different road fund scenarios to generate private funds, with rates based on Tysons or proportional to Reston development.
Reston Transportation Funding Plan: Community Meeting June 27, 2016Fairfax County
This document provides an overview and summary of a county transportation funding plan meeting for Reston, Virginia. The following key points were discussed:
- The purpose is to develop a funding plan to pay for transportation improvements approved in the Reston Master Plan to support new development.
- Improvements include road, intersection, and grid projects totaling $2.276 billion. Public funds would pay for road projects while private funds would pay for intersections and most of the grid.
- Private funding sources may include proffers, contributions to a road fund, tax districts, and service districts. Road fund contribution rates were discussed.
- Some funding scenarios could leave a shortfall that may be addressed through a
This ordinance amends the City of DuPont's comprehensive plan, land use regulations, and zoning map regarding three areas: the civic center area, the mineral resource overlay, and the Fort Lake Business and Technology Park. It rezones 4.86 acres in the civic center area from residential to mixed use. It also amends elements and maps relating to the mineral resource overlay and the Fort Lake area to be consistent with requirements of the Washington State Growth Management Act. The ordinance was adopted after public hearings and consideration of exhibits outlining the amendments.
This ordinance amends the City of DuPont comprehensive plan, land use regulations, and zoning map regarding three areas: 1) The Civic Center Area, redesignating 4.86 acres from residential to mixed use. 2) The Mineral Resource Overlay. 3) The Fort Lake Business and Technology Park. The amendments went through public processes including workshops and hearings. The city council approved the amendments based on findings that they are consistent with goals of the comprehensive plan and state growth management laws.
This ordinance amends the City of DuPont comprehensive plan, land use regulations, and zoning map regarding three areas: 1) The Civic Center Area, redesignating 4.86 acres from residential to mixed use. 2) The Mineral Resource Overlay. 3) The Fort Lake Business and Technology Park. The amendments went through public processes including workshops and hearings. The city council approved the amendments based on findings that they are consistent with goals of the comprehensive plan and state growth management laws.
The document is a 5-page agenda for the May 14, 2013 City Council meeting in San Angelo, Texas. The agenda includes 16 items to be discussed, with several items involving proposed changes to zoning ordinances and amendments to the city's comprehensive plan. Public hearings and presentations from city staff are scheduled on issues relating to land use and development in various areas around San Angelo.
The document summarizes a community planning process for the Forest Hills area of Boston. Over the course of 10 meetings between 2006 and 2008, hundreds of community residents provided feedback. This input was used to develop a community vision for the Forest Hills station area with goals of promoting residential and business growth while preserving open space. The vision included elements like a vibrant mixed-use district, improved traffic, community orientation, green and sustainable development, and enhanced green spaces.
The document is the agenda for the Silicon Valley Rapid Transit Program Working Committee meeting on October 6, 2014. The agenda includes items such as approving previous meeting minutes, discussing Phase 2 of the VTA BART Silicon Valley extension project, receiving updates on the Berryessa extension project and SVRT program, and announcements. Under item 4, the committee will discuss defining the Phase 2 project for entry into the New Starts federal funding program by the end of 2014. Item 5 involves status updates on the Berryessa extension project's schedule, budget, property acquisition, and construction progress.
The letter provides a detailed objection to a planning application to develop land in Westcott, Surrey. It argues that approving the development would be premature for several reasons: 1) The site is designated as a reserve housing site and should not be developed until other suitable sites are exhausted; 2) There is no current housing deficit based on existing targets; 3) New housing targets set by the local council may be lower; 4) The location is less sustainable than other sites. It also argues the proposed density of housing is too high given site constraints.
The document is the agenda for a City Council meeting to take place on October 1, 2013. The agenda includes items such as opening procedures, consent agenda items like approving meeting minutes and awarding contracts, a regular agenda with public hearings and ordinances on zoning changes, and closing procedures like future agenda items and adjournment. Key issues to be discussed are zoning changes, awarding of contracts, and reports on fire prevention and the energy industry. The meeting will take place at the McNease Convention Center and is open to the public.
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
The document summarizes a presentation given to the Reston community on a proposed transportation funding plan for Reston, Virginia. The presentation covered background on the need for a funding plan, proposed projects and costs, coordination with an advisory group, potential public and private revenue sources, and different funding scenarios. The goal of the funding plan is to allocate costs fairly between public and private sources to pay for $2.265 billion in road, intersection, and grid network improvements over 40 years to support the Reston Phase I Comprehensive Plan. Feedback was sought from the community on the preliminary proposals.
The document summarizes the history and vision for improving the Bridge Road corridor in Hobe Sound, Florida. It details how plans for enhancing Bridge Road as a "Main Street" setting date back to 1994. Community meetings and studies were held from 1998-2010 to develop a conceptual plan. This included evaluating parking, utilities, sidewalks and traffic. The plan was accepted in 2011 and right-of-way acquisitions were approved in 2012. Additional coordination with property owners and utilities occurred in 2013-2014. While 90% design plans were received in 2014, funding issues prevented completion and the project was cancelled.
Similar to Hunter Mill District Community Outreach Meeting (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
This document summarizes a pedestrian access improvement project along Clarks Crossing Road in Fairfax County, Virginia. The project improved pedestrian and bicycle access by constructing a missing link of sidewalk between Brookside Lane and an existing sidewalk further along Clarks Crossing Road. Work included installing sidewalk, curb ramps, drainage improvements, and milling and overlaying asphalt. The project was substantially completed in March 2022 and provides approximately 200 feet of new pedestrian access along Clarks Crossing Road.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Sully Community Center Construction ProgressFairfax County
This document provides construction progress photos of the Sully Community Center in Fairfax County, Virginia. The photos show the ongoing construction of the building's exterior, interior spaces like the lobby, corridors, multi-purpose rooms, game room, gym, exercise room, and healthcare suite. The document was published by the Fairfax County Department of Public Works and Environmental Services to share updates on the construction of the new community center, which is scheduled to open in summer 2022.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This document summarizes a meeting about a proposed arts center in Reston, Virginia that would result from a proffer from Boston Properties for development of an area known as Block J. The meeting covered the background and objectives of community outreach efforts to understand needs for the arts venue. Feedback was shared from previous focus group meetings on performing arts, visual arts, and other topics. Key spaces discussed included a 500-seat theater, art studios, galleries, and support spaces. Next steps include further programming, cost estimating, and community input before potential design and construction.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
This document summarizes a focus group meeting to discuss needs and ideas for a proposed new arts center in Reston, Virginia. The meeting covered background on the proposed project, which would result from a development proffer. Attendees provided input through polls and discussion on desired visual arts programming, spaces, and amenities. Key priorities identified included studio space, galleries, classrooms, digital media facilities, and ensuring the center is diverse, equitable and accessible. The project team will take this community feedback into account as they continue planning.
18062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
केरल उच्च न्यायालय ने 11 जून, 2024 को मंडला पूजा में भाग लेने की अनुमति मांगने वाली 10 वर्षीय लड़की की रिट याचिका को खारिज कर दिया, जिसमें सर्वोच्च न्यायालय की एक बड़ी पीठ के समक्ष इस मुद्दे की लंबित प्रकृति पर जोर दिया गया। यह आदेश न्यायमूर्ति अनिल के. नरेंद्रन और न्यायमूर्ति हरिशंकर वी. मेनन की खंडपीठ द्वारा पारित किया गया
16062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...The Lifesciences Magazine
Federal authorities have advised the public to remain vigilant but calm in response to the ongoing bird flu outbreak of highly pathogenic avian influenza, commonly known as bird flu.
13062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
ग्रेटर मुंबई के नगर आयुक्त को एक खुले पत्र में याचिका दायर कर 540 से अधिक मुंबईकरों ने सभी अवैध और अस्थिर होर्डिंग्स, साइनबोर्ड और इलेक्ट्रिक साइनेज को तत्काल हटाने और 13 मई, 2024 की शाम को घाटकोपर में अवैध होर्डिंग के गिरने की विनाशकारी घटना के बाद अपराधियों के खिलाफ सख्त कार्रवाई की मांग की है, जिसमें 17 लोगों की जान चली गई और कई निर्दोष लोग गंभीर रूप से घायल हो गए।
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...rittaajmal71
Since fleeing to the United States in 2014, Guo Wengui has founded a number of projects in the United States, such as GTV Media Group, GTV private equity, farm loan project, G Club Operations Co., LTD., and Himalaya Exchange.
19 जून को बॉम्बे हाई कोर्ट ने विवादित फिल्म ‘हमारे बारह’ को 21 जून को थिएटर में रिलीज करने का रास्ता साफ कर दिया, हालांकि यह सुनिश्चित करने के बाद कि फिल्म निर्माता कुछ आपत्तिजनक अंशों को हटा दें।
17062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
Recent years have seen a disturbing rise in violence, discrimination, and intolerance against Christian communities in various Islamic countries. This multifaceted challenge, deeply rooted in historical, social, and political animosities, demands urgent attention. Despite the escalating persecution, substantial support from the Western world remains lacking.
Why We Chose ScyllaDB over DynamoDB for "User Watch Status"ScyllaDB
Yichen Wei and Adam Drennan share the architecture and technical requirements behind "user watch status" for a major global media streaming service, what that meant for their database, the pros and cons of the many options they considered for replacing DynamoDB, why they ultimately chose ScyllaDB, and their lessons learned so far.
15062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
projet de traité négocié à Istanbul (anglais).pdfEdouardHusson
Ceci est le projet de traité qui avait été négocié entre Russes et Ukrainiens à Istanbul en mars 2022, avant que les Etats-Unis et la Grande-Bretagne ne détournent Kiev de signer.
1. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
1
Hunter Mill District
Community Outreach Meeting
September 19, 2015
2. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
2
North County Services
3. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
3
North County Services
Reston Town
Center North
4. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
4
Aerial View of Properties
5. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
5
• Public Works – Redevelopment of County Property
Implement the vision outlined in the Comprehensive Plan Amendment adopted in
2014, which received extensive community participation and guidance
Partner with Inova to perform a 1:1 land swap, and submit an overall rezoning of
the combined properties, to create a grid of streets and developable blocks in
conformance with the Comprehensive Plan Amendment
Create mixed-use development, integrate public uses in an urban form, create
places where people want to be, diversify the tax base, and invest in infrastructure
Collaborate with Health and Human Services for opportunities to deliver services,
consistent with their North County regional recommendations
Goals
6. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
6
Current Property Ownership
7. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
7
Comprehensive Plan Amendment Layout
Figure 31: Concept for Town Center North Mixed Use Area (p. 98 of 116)
8. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
8
Ownership: Before and After
9. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
9
Existing Facilities
10. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
10
Partnership with Inova
• Interim Real Estate Exchange Agreement (IREEA)
Goal: Resubdivide and rezone County and Inova properties in compliance with the adopted
Comprehensive Plan Amendment, to create a grid of streets with developable blocks
Seek rezoning using existing densities of 0.90 FAR and 50 dwelling units per acre
Fairfax County Park Authority (FCPA) contributes 5 acres, in exchange for development rights
to 90,000 square feet (in future Phase 2)
Fairfax County Redevelopment and Housing Authority (FCRHA) owns Block 9, and would
rezone separately
Board of Supervisors (BOS) authorization on July 28, 2015, to advertise a Public Hearing on
September 22, 2015, regarding the County-Inova IREEA
BOS item on September 22, 2015, for BOS to act on behalf of FCPA for property exchange
BOS Public Hearing on September 22, 2015, regarding the County-Inova IREEA
Rezoning of the overall property would commence after the Public Hearing process
conclusion and BOS approval (should it so act)
Separate rezonings would be required later for development of individual blocks
11. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
11
Development Phases - County
12. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
12
Phase 1 Development - County
• Phase 1: Blocks 7 and 8
The three parcels comprising Blocks 7 and 8 are south of Bowman Towne Drive, are already owned
by the County and are not subject to the land swap with Inova, so the County can begin the process
of finding a development partner using PPEA procurement rules. An RFP will be issued in two parts.
Part 1 of the RFP is a request for qualifications, without offering specific scope. Respondents
submitted information about their financial strength and their prior development experience.
June 30, 2015: Advertisement
August 20, 2015: Submission of qualifications received
Part 2 of the RFP will be a request for public-private development proposals from the pre-qualified
development teams.
The County will review and select a development proposal, and negotiate a development
agreement, per PPEA guidelines.
A rezoning application specific to Blocks 7 and 8 will be submitted by the County subsequent to the
successful conclusion of the overall rezoning.
The community will have further input opportunities during the overall rezoning and during the
Blocks 7 and 8 rezoning.
13. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
13
Phase 1 Development Components
• Phase 1 (Blocks 7 and 8):
Replacement Library
Replacement Shelter
Affordable Housing
Potential County residential units for transition out of the Shelter
Potential County residential units for other Human Services programs
Potential “village” space/rooms adjacent to the Library
Potential space adjacent to the Shelter, for use by public service groups under contract to Fairfax County
Other uses as recommended by the Comprehensive Plan
14. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
14
Phase 2 Development - County
• Future Phase 2: Blocks 1, 3, 5 and 9
The Phase 2 blocks are north of Bowman Town Drive, and would be created through the County-
Inova rezoning and land swap
Public-private development opportunities will be considered in the future for Phase 2
Phase 2 contains the existing North County Human Services Building, a facility in need of
renovations or redevelopment to meet the evolving needs of the community
The western portion of Block 5 contains the new North County Governmental Center and Reston
Police Station, but the eastern portion of Block 5 has room for development
The Fairfax County Park Authority has development rights for 90,000 square feet that would be
utilized in Phase 2
Other uses will be considered for Phase 2
Block 9 is owned by the Fairfax County Redevelopment and Housing Authority (FCRHA), and
would be rezoned and redeveloped separately at a future time
15. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
15
Phase 2 Development Components
• Phase 2 (Blocks 1, 3, 5 and 9):
North County Governmental Center and Reston Police Station
Replacement North County Human Services Building
Affordable Housing
90,000 square feet of development rights by the Fairfax County Park Authority
Separate Block 9 rezoning by the Redevelopment and Housing Authority
Potential indoor recreation/aquatics center
Potential performing arts center
Potential fire station
Potential County residential units for transition out of the Shelter
Potential County residential units for other Human Services programs
Potential community meeting rooms
Other uses as recommended by the Comprehensive Plan
16. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
16
Public Participation and Outreach
• Public Participation during Land Planning
Phase I - Amendment to the Comprehensive Plan, Item ST09-III-UP1(A)
Community Land Use College - Fall 2009
Reston Master Plan Task Force – 2010- 2014
Facilitated Community Meetings 2010 (3) & 2013 (1)
Other Participation Forums – (Staff Meetings, Website, ListServe & Social Media)
Planning Commission Public Hearing – November 13, 2013
Planning Commission Recommends Adoption by the Board of Supervisors – January 9, 2014
Board of Supervisors Public Hearing – January 28, 2014
Adoption by Board of Supervisors – February 11, 2014
• Public Outreach
January 9, 2015: Redevelopment project presented to the Reston Community Center (RCC) Board
February 28, 2015: Redevelopment project presented at the “Hunter Mill Community Summit”
July 29, 2015: Redevelopment project presented at a community meeting
17. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
17
Public Participation and Outreach
• Future Opportunities for Public Involvement
Public Hearing regarding the County-Inova “Interim Real Estate Exchange Agreement” (IREEA), otherwise
known as the land swap (September 22, 2015)
Public Hearing process during the overall rezoning to create the grid of streets and blocks
Public Hearing process during the County’s Phase 1 rezoning for development of Blocks 7 and 8
Public Hearing processes during the County’s future Phase 2 rezoning for development of Blocks 1, 3 and 5
Additional recurring “non-regulatory” public interface opportunities to be scheduled throughout the
development process
18. Fairfax County DPWES
Building Design & Construction DivisionSeptember 19, 2015
Reston Town Center North
18
• Additional Information:
Fairfax County Web Page
http://www.fairfaxcounty.gov/dpwes/restontowncenternorth/
Questions via Email
restontowncenternorth@fairfaxcounty.gov