STUDENT/FACULTY ENTRANCE IMPROVEMENT
[Insert appropriate disclaimer(s)]
STUDENT/FACULTYENTRANCE
IMPROVEMENT
PROJECTMANAGEMENTPLAN
Version 1.4
03/14/2016
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 1 of 10
VERSION HISTORY
Version
#
Implemented
By
Revision
Date
Approved
By
Approval
Date
Reason
1.0 Robin Teller 02/02/2016 James Bayliff 02/02/2016 Plan Approval
1.1 Robin Teller 02/29/2016 James Bayliff 02/29/2016 Revision 1
1.2 Robin Teller 03/07/2016 James Bayliff 03/09/2016 Revision 2
1.3 Robin Teller 3/11/2016 James Bayliff 03/14/2016 Revision 3
1.4 Robin Teller 03/14/2016 James Bayliff 03/14/2016 Revision 4
UP Template Version: 11/30/06
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 2 of 10
TABLE OF CONTENTS
1: INTRODUCTION……………………………………………………………………...........3
1.2 PURPOSE OF PROJECT MANAGEMENT PLAN………………………….....3
2: EXECUTIVE SUMMARY OF PROJECT CHARTER………………………………….3
2.1 ASSUMPTIONS/CONSTRAINTS……………………………………………......3
2.2 ASSUMPTIONS……………………………………………………………………3
2.3 CONSTRAINTS……………………………………………………………………4
3: SCOPE MANAGEMENT………………………………………………………………......4
3.1 WORK BREAKDOWN STRUCTURE………………………………………......5
3.2 DEPLOYMENT PLAN……………………………………………………………5
3.3 CHANGE CONTROL MANAGEMENT………………………………………...6
4: SCHEDULE/TIME MANAGEMENT…………………………………………………......6
4.1 MILESTONES...…………………………………………………………………….6
4.2 PROJECT SCHEDULE……………………………………………………………6
5: COST/BUDGET MANAGEMENT………………………………………………………...7
6: QUAILTY MANAGEMENT……………………………………………………………….7
7: COMMUNICATION MANAGEMENT…………………………………………………...7
7.1 COMMUNICATION MATRIX…………………………………………………...7
8: RISK MANAGEMENT……………………………………………………………………..7
8.1 RISK LOG…………………………………………………………………………..8
9: ISSUE MANAGEMENT…………………………………………………………………....8
9.1 ISSUE LOG…………………………………………………………………………8
10: PROCUREMENT MANAGEMENT……………………………………………………..9
11: COMPLIANCE RELATED PLANNING………………………………………………...9
APPENDIX A: PROJECT MANAGEMENT PLAN APPROVAL…………………………9
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 3 of 10
1 INTRODUCTION
1.1 PURPOSE OF PROJECT MANAGEMENT PLAN
The purpose of this project is to replace the current awning with a longer and wider awning
in an effort to mitigate water intrusion into the building in an effort to help prevent falls and
possible injuries to anyone using that entrance, to protect the swipe pad and other electrical
systems from damage, and to provide a covered are for people to stand while waiting to
enter the building or waiting after classes.
2 EXECUTIVE SUMMARY OF PROJECT CHARTER
The background to this improvement plan is that the current awning over the student/faculty
entrance is not adequate enough to prevent water intrusion during inclement weather, which
could lead to falls and/or injuries, the electrical systems are subject to water damage, which
could cause a short in the systems and does not provides an area that allows people to stand
while waiting to gain access to or when leaving the building.
The purpose of the student/faculty entrance improvement idea is to mitigate water intrusion
during inclement weather, thus lessening the chances of falls and/or injuries. A larger
awning will protect the electronic entry pad and lighting system, while providing protection
for persons using the entrance.
The project management plan will be used to keep Vince Femia, campus president, Jim
Mancini, maintenance supervisor, as well as the owner of the building informed of the
project scope, design, budget, time frame and of any issues and/or constraints that may arise
regarding any phase of the project.
2.1 ASSUMPTIONS/CONSTRAINTS
2.2 ASSUMPTIONS
This section identifies the statements believed to be true and from which a
conclusion was drawn to define this project charter.
1. The week of demolition, construction and installation will be sunny and clear.
2. All the materials and workers will show up on the correct days and times.
3. The project will meet all codes and pass all inspections
4. Project will be completed under budget
5. Project will be completed on time
6. The final outcome will meet with the campus president and building owner
approval.
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 4 of 10
2.3 CONSTRAINTS
This section identifies any limitation that must be taken into consideration prior to
the initiation of the project.
1. Inclement weather
2. Contractor unable to begin as intended due to unforeseen circumstances
3. Issues that do not meet code requirements.
4. Additional work which was not budgeted arising during project.
5. Project not completed will not be completed on time due to unforeseen
circumstances.
6. Final outcome does not meet with sponsor approval
3 SCOPE MANAGEMENT
The processes needed are planning, design, plan approval, budget, timeframe, project
quote, sponsor approval, funding approval, permission to award contract to approved
contractor, initial deposit for work, cordoning off interior and exterior work area,
demolition of existing awning, debris removal, area prep for new installation, installation
of new awning, inspections, final sign off and final payment. Any deviation from initial
scope will need to provide a change management request.
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 5 of 10
3.1 WORK BREAKDOWN STRUCTURE
STUDENT/FACULTY ENTRANCE IMPROVEMENT
INITIATION PLANNING EXECUTION CONTROL CLOSEOUT
Current awing
is not
adequate
Layout of what
is needed for
project.
Hold follow-up
meeting with all
involved and obtain
needed signatures
Status of project
progress will take
place daily between
contractor and
maintenance
supervisory
Final meeting with
all involved for
project signoff
Replace
existing
awning
Hold initial
meeting all
involved
Give go ahead for
project
commencement
All materials will
meet or exceed
codes
Final payments
made
Create and
submit
project
charter
Develop and
submit project
plan along with
documentation
Notify staff and
students of entrance
closure
Will be aware of
risks that could
happen
Student/Faculty
Entrance reopened
Gain charter
approval
Gain project
approval
Prep work area in
regards with regards
to safety
Project will not
exceed budget or
time frame
Demolition
Installation of new
awning
Final inspections
Final approvals
Cleaning up work
area
3.2 DEPLOYMENT PLAN
An initial meeting will be held will all involved to go over and approve project plan. A
follow up meeting will take place just before project commencement. Once work
commences, the contractor will have project completed within set time frame.
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 6 of 10
3.3 CHANGE CONTROL MANAGEMENT
Any changes to initial scope of work must be submitted in writing to project manager for
sponsor approval.
4 SCHEDULE/TIME MANAGEMENT
The time frame given for project completion is one week. The dates are March 30, 2016
thru April 5, 2016. This is the period when the least number of students will be on
campus. No more than one day should be set for each step of the project to be completed in
this given time. If more time is needed, the project manager and sponsor must informed as
soon possible to make the provisions necessary.
4.1 MILESTONES
The table below lists the milestones for this project, along with their estimated completion
timeframe.
Milestones Estimated Completion Timeframe
Plan presentation 02/02/2016
Plan approval 02/02/2016
Contract awarded 03/16/2016
Contractor commences pre construction process 03/23/2016
Staff and Students notified of construction and
area closure
03/24/2016
Kick off to project 03/28/2016
Work area prep 03/30/2016
Demolition 03/30/2016
Delivery and Inventory of Materials 03/31/2016
Assembly and Installation 04/01/2016
Clean up and necessary repairs 04/01/2016
Final Inspection 04/04/2016
Final Sign off 04/04/2016
Project Completion 04/04/2016
Entrance reopened 04/05/2016
4.2 PROJECT SCHEDULE
Project kick off meeting 03/28/2016
Site Prep including closing off
hallway section
03/30/2016
Demolition 03/30/2016
Assembly and installation 04/01/2016
Clean up 04/01/2016
Final inspections and approval 04/04/2016
Reopen entrance 04/05/2016
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 7 of 10
5 COST/BUDGET MANAGEMENT
A budget was set at $3000 to allow for any issues that may arise. Project was quoted at
$1175 for instillation and materials, and additional $350 was quoted for permits. Total
quote $1525. An additional $1475 was added to the quote as a contingency.
6 QUALITY MANAGEMENT
Project will meet or exceed all city codes. All materials needed to complete this project
will meet or exceed wind load compliance regulations. Project will be completed within
the allotted time frame or sooner. Project will meet or exceed client expectations.
7 COMMUNICATIONS MANAGEMENT
Daily communication must to take place between the contractor and project manager as to
the status of the project. This needs to be done in person, phone or email.
7.1 COMMUNICATION MATRIX
Stakeholder Messages Vehicles Frequency Communicators Feedback
Mechanisms
Vince Femia
Jim Mancini
East Coast
Aluminum
8 RISK MANAGEMENT
There are certain risks associated with this project as listed in 8.1
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 8 of 10
8.1 RISK LOG
RISK LOG
ID# RISKS PROBABILITY IMPACTCATEGORY RISK RANK
1 Inclement weather
2
Delay in arrival of
materials
3 Delay in start of project
4 Project going over budget
5 Inspection delayed
6 Worker injury
7 Damage to building
8
Project not completed in
allotted time frame
9
Contractor not able to
begin on time
9 ISSUE MANAGEMENT
There are certain issues that may arise in the course of this project as listed in 9.1
9.1 ISSUE LOG
ISSUE LOG
ID
# DATE ISSUE PROSPECT STATUS COMMENTS
1
2
3
4
5
6
7
8
9
STUDENT/FACULTY ENTRANCE IMPROVEMENT
Page 9 of 10
10 PROCUREMENTMANAGEMENT
East Coast Aluminum will be responsible for all materials needed to complete awning.
11 COMPLIANCE RELATED PLANNING
Project will be within or exceeding all compliance requirements.
Appendix A: Project Management Plan Approval
The undersigned acknowledge they have reviewed the student/faculty entrance
improvement Project Management Plan and agree with the approach it presents. Changes
to this Project Management Plan will be coordinated with and approved by the undersigned
or their designated representatives.
Signature: Date:
Print Name:
Title:
Role:
Signature: Date:
Print Name:
Title:
Role:
Signature: Date:
Print Name:
Title:
Role:

More Related Content

What's hot

FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
20080129024931.contract checklists
20080129024931.contract checklists20080129024931.contract checklists
20080129024931.contract checklistsAshraf Javed
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Antonio Coladarce
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
Iffat Al Gharbi
 
Ten Basic Concepts for Owners
Ten Basic Concepts for OwnersTen Basic Concepts for Owners
Ten Basic Concepts for Owners
Woods & Aitken LLP
 
Project Management
Project ManagementProject Management
Project ManagementAnton Orlov
 
Critical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجةCritical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجة
Eng.Ahmed Said Mohamed Refaei
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013Weero Koster
 

What's hot (10)

Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
20080129024931.contract checklists
20080129024931.contract checklists20080129024931.contract checklists
20080129024931.contract checklists
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
 
Short termim workplan_20100602_part3
Short termim workplan_20100602_part3Short termim workplan_20100602_part3
Short termim workplan_20100602_part3
 
Ten Basic Concepts for Owners
Ten Basic Concepts for OwnersTen Basic Concepts for Owners
Ten Basic Concepts for Owners
 
Project Management
Project ManagementProject Management
Project Management
 
Critical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجةCritical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجة
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013
 

Viewers also liked

QNBFS Daily Technical Trader - Qatar November 02, 2016
QNBFS Daily Technical Trader - Qatar November 02, 2016QNBFS Daily Technical Trader - Qatar November 02, 2016
QNBFS Daily Technical Trader - Qatar November 02, 2016
QNB Group
 
В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...
В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...
В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...
Vasikinbox
 
Pintemos nuestra escuela
Pintemos nuestra escuelaPintemos nuestra escuela
Pintemos nuestra escueladec-admin
 
Aprovechamiento de la basura
Aprovechamiento de la basuraAprovechamiento de la basura
Aprovechamiento de la basuradec-admin
 
El cambio climático
El cambio climáticoEl cambio climático
El cambio climáticodec-admin
 
Описание протокола PayPal для благотворительных организаций
Описание протокола PayPal для благотворительных организацийОписание протокола PayPal для благотворительных организаций
Описание протокола PayPal для благотворительных организаций
PayPalMoscow
 
Industrial revolution
Industrial revolutionIndustrial revolution
Industrial revolution
Yumonomics
 
Furia ambiental
Furia ambientalFuria ambiental
Furia ambientaldec-admin
 
Tudósok
TudósokTudósok
Tudósok
merczne
 
Escuela segura
Escuela seguraEscuela segura
Escuela seguradec-admin
 
500. platiquemos sin pelearnos
500. platiquemos sin pelearnos500. platiquemos sin pelearnos
500. platiquemos sin pelearnosdec-admin
 
Que el sol no nos lastime
Que el sol no nos lastimeQue el sol no nos lastime
Que el sol no nos lastimedec-admin
 

Viewers also liked (14)

QNBFS Daily Technical Trader - Qatar November 02, 2016
QNBFS Daily Technical Trader - Qatar November 02, 2016QNBFS Daily Technical Trader - Qatar November 02, 2016
QNBFS Daily Technical Trader - Qatar November 02, 2016
 
В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...
В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...
В мечтах о "голубых океанах" или поиск рыночного пространства, в котором нет ...
 
Pintemos nuestra escuela
Pintemos nuestra escuelaPintemos nuestra escuela
Pintemos nuestra escuela
 
Aprovechamiento de la basura
Aprovechamiento de la basuraAprovechamiento de la basura
Aprovechamiento de la basura
 
El cambio climático
El cambio climáticoEl cambio climático
El cambio climático
 
Описание протокола PayPal для благотворительных организаций
Описание протокола PayPal для благотворительных организацийОписание протокола PayPal для благотворительных организаций
Описание протокола PayPal для благотворительных организаций
 
Industrial revolution
Industrial revolutionIndustrial revolution
Industrial revolution
 
Oral presentatıon . apsr. 2017
Oral presentatıon . apsr. 2017Oral presentatıon . apsr. 2017
Oral presentatıon . apsr. 2017
 
Svetsen_gjutjärn
Svetsen_gjutjärnSvetsen_gjutjärn
Svetsen_gjutjärn
 
Furia ambiental
Furia ambientalFuria ambiental
Furia ambiental
 
Tudósok
TudósokTudósok
Tudósok
 
Escuela segura
Escuela seguraEscuela segura
Escuela segura
 
500. platiquemos sin pelearnos
500. platiquemos sin pelearnos500. platiquemos sin pelearnos
500. platiquemos sin pelearnos
 
Que el sol no nos lastime
Que el sol no nos lastimeQue el sol no nos lastime
Que el sol no nos lastime
 

Similar to Student Project

CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
RebeccaEdwards88
 
Project brief
Project briefProject brief
Project briefkerneng
 
Project brief
Project brief Project brief
Project brief Haziq1511
 
project plan document(ppd)
project plan document(ppd)project plan document(ppd)
project plan document(ppd)
maamir farooq
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
PM3110 Project Part 1 Kapricia Morris
PM3110 Project Part 1 Kapricia MorrisPM3110 Project Part 1 Kapricia Morris
PM3110 Project Part 1 Kapricia MorrisKapricia Morris
 
Project brief
Project brief Project brief
Project brief PK146
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
hyacinthshackley2629
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
Aditi Garg
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)JamesMoy7
 
Project management plan
Project management planProject management plan
Project management planDonny Olson
 
Project management (1)
Project management (1)Project management (1)
Project management (1)Hetal Visaria
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)Pinky Chan
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1JamesMoy7
 
76 s201905
76 s20190576 s201905
76 s201905
IJRAT
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
suzzanekan
 

Similar to Student Project (20)

CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 
Project brief
Project briefProject brief
Project brief
 
Project brief
Project brief Project brief
Project brief
 
project plan document(ppd)
project plan document(ppd)project plan document(ppd)
project plan document(ppd)
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
PM3110 Project Part 1 Kapricia Morris
PM3110 Project Part 1 Kapricia MorrisPM3110 Project Part 1 Kapricia Morris
PM3110 Project Part 1 Kapricia Morris
 
Project background
Project backgroundProject background
Project background
 
Project brief
Project brief Project brief
Project brief
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)
 
Project management plan
Project management planProject management plan
Project management plan
 
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)
 
ICIP2G
ICIP2GICIP2G
ICIP2G
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1
 
Project brief
Project briefProject brief
Project brief
 
76 s201905
76 s20190576 s201905
76 s201905
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
 

More from Robin S Teller (12)

president fall 2016
president fall 2016president fall 2016
president fall 2016
 
Hair show
Hair showHair show
Hair show
 
president summer 2016
president summer 2016president summer 2016
president summer 2016
 
deans spring2016
deans spring2016deans spring2016
deans spring2016
 
president winter2016
president winter2016president winter2016
president winter2016
 
president summer2015
president summer2015president summer2015
president summer2015
 
Letter monica
Letter monicaLetter monica
Letter monica
 
letter bayliff
letter bayliffletter bayliff
letter bayliff
 
letter scott
letter scottletter scott
letter scott
 
email response.pdf
email response.pdfemail response.pdf
email response.pdf
 
enron
enronenron
enron
 
ENTRANCE PP
ENTRANCE PPENTRANCE PP
ENTRANCE PP
 

Student Project

  • 1. STUDENT/FACULTY ENTRANCE IMPROVEMENT [Insert appropriate disclaimer(s)] STUDENT/FACULTYENTRANCE IMPROVEMENT PROJECTMANAGEMENTPLAN Version 1.4 03/14/2016
  • 2. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 1 of 10 VERSION HISTORY Version # Implemented By Revision Date Approved By Approval Date Reason 1.0 Robin Teller 02/02/2016 James Bayliff 02/02/2016 Plan Approval 1.1 Robin Teller 02/29/2016 James Bayliff 02/29/2016 Revision 1 1.2 Robin Teller 03/07/2016 James Bayliff 03/09/2016 Revision 2 1.3 Robin Teller 3/11/2016 James Bayliff 03/14/2016 Revision 3 1.4 Robin Teller 03/14/2016 James Bayliff 03/14/2016 Revision 4 UP Template Version: 11/30/06
  • 3. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 2 of 10 TABLE OF CONTENTS 1: INTRODUCTION……………………………………………………………………...........3 1.2 PURPOSE OF PROJECT MANAGEMENT PLAN………………………….....3 2: EXECUTIVE SUMMARY OF PROJECT CHARTER………………………………….3 2.1 ASSUMPTIONS/CONSTRAINTS……………………………………………......3 2.2 ASSUMPTIONS……………………………………………………………………3 2.3 CONSTRAINTS……………………………………………………………………4 3: SCOPE MANAGEMENT………………………………………………………………......4 3.1 WORK BREAKDOWN STRUCTURE………………………………………......5 3.2 DEPLOYMENT PLAN……………………………………………………………5 3.3 CHANGE CONTROL MANAGEMENT………………………………………...6 4: SCHEDULE/TIME MANAGEMENT…………………………………………………......6 4.1 MILESTONES...…………………………………………………………………….6 4.2 PROJECT SCHEDULE……………………………………………………………6 5: COST/BUDGET MANAGEMENT………………………………………………………...7 6: QUAILTY MANAGEMENT……………………………………………………………….7 7: COMMUNICATION MANAGEMENT…………………………………………………...7 7.1 COMMUNICATION MATRIX…………………………………………………...7 8: RISK MANAGEMENT……………………………………………………………………..7 8.1 RISK LOG…………………………………………………………………………..8 9: ISSUE MANAGEMENT…………………………………………………………………....8 9.1 ISSUE LOG…………………………………………………………………………8 10: PROCUREMENT MANAGEMENT……………………………………………………..9 11: COMPLIANCE RELATED PLANNING………………………………………………...9 APPENDIX A: PROJECT MANAGEMENT PLAN APPROVAL…………………………9
  • 4. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 3 of 10 1 INTRODUCTION 1.1 PURPOSE OF PROJECT MANAGEMENT PLAN The purpose of this project is to replace the current awning with a longer and wider awning in an effort to mitigate water intrusion into the building in an effort to help prevent falls and possible injuries to anyone using that entrance, to protect the swipe pad and other electrical systems from damage, and to provide a covered are for people to stand while waiting to enter the building or waiting after classes. 2 EXECUTIVE SUMMARY OF PROJECT CHARTER The background to this improvement plan is that the current awning over the student/faculty entrance is not adequate enough to prevent water intrusion during inclement weather, which could lead to falls and/or injuries, the electrical systems are subject to water damage, which could cause a short in the systems and does not provides an area that allows people to stand while waiting to gain access to or when leaving the building. The purpose of the student/faculty entrance improvement idea is to mitigate water intrusion during inclement weather, thus lessening the chances of falls and/or injuries. A larger awning will protect the electronic entry pad and lighting system, while providing protection for persons using the entrance. The project management plan will be used to keep Vince Femia, campus president, Jim Mancini, maintenance supervisor, as well as the owner of the building informed of the project scope, design, budget, time frame and of any issues and/or constraints that may arise regarding any phase of the project. 2.1 ASSUMPTIONS/CONSTRAINTS 2.2 ASSUMPTIONS This section identifies the statements believed to be true and from which a conclusion was drawn to define this project charter. 1. The week of demolition, construction and installation will be sunny and clear. 2. All the materials and workers will show up on the correct days and times. 3. The project will meet all codes and pass all inspections 4. Project will be completed under budget 5. Project will be completed on time 6. The final outcome will meet with the campus president and building owner approval.
  • 5. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 4 of 10 2.3 CONSTRAINTS This section identifies any limitation that must be taken into consideration prior to the initiation of the project. 1. Inclement weather 2. Contractor unable to begin as intended due to unforeseen circumstances 3. Issues that do not meet code requirements. 4. Additional work which was not budgeted arising during project. 5. Project not completed will not be completed on time due to unforeseen circumstances. 6. Final outcome does not meet with sponsor approval 3 SCOPE MANAGEMENT The processes needed are planning, design, plan approval, budget, timeframe, project quote, sponsor approval, funding approval, permission to award contract to approved contractor, initial deposit for work, cordoning off interior and exterior work area, demolition of existing awning, debris removal, area prep for new installation, installation of new awning, inspections, final sign off and final payment. Any deviation from initial scope will need to provide a change management request.
  • 6. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 5 of 10 3.1 WORK BREAKDOWN STRUCTURE STUDENT/FACULTY ENTRANCE IMPROVEMENT INITIATION PLANNING EXECUTION CONTROL CLOSEOUT Current awing is not adequate Layout of what is needed for project. Hold follow-up meeting with all involved and obtain needed signatures Status of project progress will take place daily between contractor and maintenance supervisory Final meeting with all involved for project signoff Replace existing awning Hold initial meeting all involved Give go ahead for project commencement All materials will meet or exceed codes Final payments made Create and submit project charter Develop and submit project plan along with documentation Notify staff and students of entrance closure Will be aware of risks that could happen Student/Faculty Entrance reopened Gain charter approval Gain project approval Prep work area in regards with regards to safety Project will not exceed budget or time frame Demolition Installation of new awning Final inspections Final approvals Cleaning up work area 3.2 DEPLOYMENT PLAN An initial meeting will be held will all involved to go over and approve project plan. A follow up meeting will take place just before project commencement. Once work commences, the contractor will have project completed within set time frame.
  • 7. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 6 of 10 3.3 CHANGE CONTROL MANAGEMENT Any changes to initial scope of work must be submitted in writing to project manager for sponsor approval. 4 SCHEDULE/TIME MANAGEMENT The time frame given for project completion is one week. The dates are March 30, 2016 thru April 5, 2016. This is the period when the least number of students will be on campus. No more than one day should be set for each step of the project to be completed in this given time. If more time is needed, the project manager and sponsor must informed as soon possible to make the provisions necessary. 4.1 MILESTONES The table below lists the milestones for this project, along with their estimated completion timeframe. Milestones Estimated Completion Timeframe Plan presentation 02/02/2016 Plan approval 02/02/2016 Contract awarded 03/16/2016 Contractor commences pre construction process 03/23/2016 Staff and Students notified of construction and area closure 03/24/2016 Kick off to project 03/28/2016 Work area prep 03/30/2016 Demolition 03/30/2016 Delivery and Inventory of Materials 03/31/2016 Assembly and Installation 04/01/2016 Clean up and necessary repairs 04/01/2016 Final Inspection 04/04/2016 Final Sign off 04/04/2016 Project Completion 04/04/2016 Entrance reopened 04/05/2016 4.2 PROJECT SCHEDULE Project kick off meeting 03/28/2016 Site Prep including closing off hallway section 03/30/2016 Demolition 03/30/2016 Assembly and installation 04/01/2016 Clean up 04/01/2016 Final inspections and approval 04/04/2016 Reopen entrance 04/05/2016
  • 8. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 7 of 10 5 COST/BUDGET MANAGEMENT A budget was set at $3000 to allow for any issues that may arise. Project was quoted at $1175 for instillation and materials, and additional $350 was quoted for permits. Total quote $1525. An additional $1475 was added to the quote as a contingency. 6 QUALITY MANAGEMENT Project will meet or exceed all city codes. All materials needed to complete this project will meet or exceed wind load compliance regulations. Project will be completed within the allotted time frame or sooner. Project will meet or exceed client expectations. 7 COMMUNICATIONS MANAGEMENT Daily communication must to take place between the contractor and project manager as to the status of the project. This needs to be done in person, phone or email. 7.1 COMMUNICATION MATRIX Stakeholder Messages Vehicles Frequency Communicators Feedback Mechanisms Vince Femia Jim Mancini East Coast Aluminum 8 RISK MANAGEMENT There are certain risks associated with this project as listed in 8.1
  • 9. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 8 of 10 8.1 RISK LOG RISK LOG ID# RISKS PROBABILITY IMPACTCATEGORY RISK RANK 1 Inclement weather 2 Delay in arrival of materials 3 Delay in start of project 4 Project going over budget 5 Inspection delayed 6 Worker injury 7 Damage to building 8 Project not completed in allotted time frame 9 Contractor not able to begin on time 9 ISSUE MANAGEMENT There are certain issues that may arise in the course of this project as listed in 9.1 9.1 ISSUE LOG ISSUE LOG ID # DATE ISSUE PROSPECT STATUS COMMENTS 1 2 3 4 5 6 7 8 9
  • 10. STUDENT/FACULTY ENTRANCE IMPROVEMENT Page 9 of 10 10 PROCUREMENTMANAGEMENT East Coast Aluminum will be responsible for all materials needed to complete awning. 11 COMPLIANCE RELATED PLANNING Project will be within or exceeding all compliance requirements. Appendix A: Project Management Plan Approval The undersigned acknowledge they have reviewed the student/faculty entrance improvement Project Management Plan and agree with the approach it presents. Changes to this Project Management Plan will be coordinated with and approved by the undersigned or their designated representatives. Signature: Date: Print Name: Title: Role: Signature: Date: Print Name: Title: Role: Signature: Date: Print Name: Title: Role: