SlideShare a Scribd company logo
1 of 19
TEN BASIC CONCEPTS FOR OWNERS 
PRESENTER: 
CRAIG DIRRIM, PARTNER
TEN BASIC CONCEPTS FOR OWNERS 
1. Disclose known information to bidders 
2. Provide accurate plans 
3. Obtain permits and easements in a timely 
manner 
4. Coordinate access to the site and work of 
others 
5. Supply equipment and material as scheduled
TEN BASIC CONCEPTS FOR OWNERS 
6. Respond promptly to change order and time 
extension requests 
7. Review submittals in a timely manner 
8. Make timely, reasonable inspections 
9. Provide a safe site environment 
10.Deal with the contractor in good faith
DISCLOSE KNOWN INFORMATION TO 
BIDDERS 
An owner’s duty to disclose will start at the issuance of 
the RFP and continue through construction. 
Includes ground water levels, flood conditions, 
subsurface soil conditions, hazardous materials, etc. 
Document the method and manner of disclosure (i.e., 
studies, photos, video reports).
PROVIDE ACCURATE PLANS 
Under the Spearin Doctrine, an owner warrants that its 
plans and specifications are accurate, and if a 
contractor performs in accordance with the design 
documents provided, the contractor will not be 
responsible for any inadequacies in the completed 
work. 
Spearin will also allow a contractor to recover for any 
additional costs or extra work which result from defects 
or inadequacies in the plans specifications. 
See United States v. Spearin, 248 U.S. 132 (1918)
PROVIDE ACCURATE PLANS 
Defenses to Spearin 
 Obvious defect – would a reasonable contractor have 
been able to identify the design error during a pre-bid 
review. 
 The contractor must perform its work in accordance 
with the plans and specifications. 
 The warranty of design in Spearin does not apply to 
performance specifications. 
 In certain cases, specific disclaimer language can defeat 
the obligation in Spearin, but such language could 
increase the cost of the project.
PROVIDE ACCURATE PLANS 
Practical Tips 
 Know your contract terms with your owner. Is there 
a limitation of liability? 
 Be careful “reusing” design documents
OBTAIN EASEMENTS AND PERMITS IN A TIMELY 
MANNER 
An owner typically needs to have all approvals 
required for a contractor to proceed. Manage this 
process. 
Have all R.O.W.’s been obtained before the 
notice to proceed? 
Are there conflicts with utility or railroad 
easements? 
Failure to provide such easements or permits 
may be an exception to a “no damages for delay” 
clause.
PROVIDE ACCESS TO THE SITE AND COORDINATE 
THEWORK OF OTHERS 
An owner is required to provide uninterrupted 
access to the project throughout the course of 
construction. 
The owner’s duty includes adequate space to 
perform the work (cranes, laydown, etc.).
PROVIDE ACCESS TO THE SITE AND 
COORDINATE THEWORK OF OTHERS 
The owner will need to coordinate other work so 
it will not interfere with the contractor’s planned 
sequence or schedule, particularly in cases where 
there are multiple primes. 
The owner should adequately disclose or limit 
possible interferences from ongoing operations in 
existing facilities.
SUPPLY OWNER FURNISHED EQUIPMENT AND 
MATERIAL IN ACCORDANCE WITH THE SCHEDULE 
When an owner chooses to supply material or 
equipment, it warrants that the supplied 
materials are suitable for its intended purpose. 
An owner who chooses to furnish certain 
equipment or materials must do so in 
accordance with the project schedule. Failure to 
do so may result in liability for additional costs or 
delay.
SUPPLY OWNER FURNISHED EQUIPMENT AND 
MATERIAL IN ACCORDANCE WITH THE SCHEDULE 
Specification of certain proprietary material or 
equipment by an owner implies that the 
materials or equipment will be available and 
are suitable for the work.
RESPOND PROMPTLY TO CHANGE ORDER AND 
TIME EXTENSION REQUESTS 
An owner has a duty to fairly evaluate and 
promptly respond to time extension requests. 
 Failure to respond to a time extension request may 
result in the finding of “Constructive Acceleration.” 
An owner has a duty to fairly evaluate and 
promptly respond to change order requests. 
 Failure to respond to a change order request may result 
in a project stoppage or escalate the matter to a claim 
status.
REVIEW SUBMITTALS AND RFI’S IN A TIMELY 
FASHION 
When the contract requires the contractor to submit 
shop drawings or other information to the owner for its 
review, there is a corresponding duty on the owner to 
make such a review in a manner which supports the 
project schedule. 
 Failure to review submittals in a timely fashion may subject 
an owner to a claim of active interference and could render 
a “no damage for delay” clause void. 
 Failure to respond to RFI’s in a timely manner may provide 
a contractor with a basis for an extended duration or delay 
claim.
MAKE TIMELY, REASONABLE INSPECTIONS 
If the contract requires inspections after 
particular phases or portions of work, an owner 
will have a duty to have sufficient personnel 
available to perform such inspections in 
accordance with the project schedule. 
An owner may be responsible for inconsistent 
inspections or “over” inspections of the 
contractor’s work.
MAKE TIMELY, REASONABLE INSPECTIONS 
An owner who has an opportunity to make a 
reasonable inspection and fails to make such 
inspection or undertakes an inspection, but 
fails to notify the contractor of obvious non-conforming 
work, the owner may be barred 
from seeking damages from the contractor for 
such work.
PROVIDE A SAFE ENVIRONMENT 
Are there site specific conditions or operation 
issues that the owner has specific knowledge 
of? If so, those should be disclosed. 
If the owner is undertaking to manage a 
multiple-prime project, the owner may have a 
heightened responsibility to ensure the safety 
of the project site.
DEAL WITH THE CONTRACTOR IN GOOD FAITH 
Every contract 
contains an implied 
covenant of good faith 
and fair dealing. 
This covenant of 
good faith and fair 
dealing can cover 
numerous owner acts 
and/or omissions.
THANK YOU! 
CRAIG DIRRIM 
301 SOUTH 13TH STREET, SUITE 500 
LINCOLN, NE 68508 
(402) 437-8500 
CDIRRIM@WOODSAITKEN.COM

More Related Content

What's hot

Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractPavitrah Segaran
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...
2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...
2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...Anirban Chakraborty
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 

What's hot (20)

Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Contract Management
Contract Management Contract Management
Contract Management
 
CV@JOMY NEW
CV@JOMY NEWCV@JOMY NEW
CV@JOMY NEW
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
LastNew CV
LastNew CVLastNew CV
LastNew CV
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contract
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
shahul HVAC - new 1
shahul HVAC - new 1shahul HVAC - new 1
shahul HVAC - new 1
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
Totie Laurel CV
Totie Laurel CVTotie Laurel CV
Totie Laurel CV
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...
2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...
2010 11 pgp1-lab_group_presentation_section b_group 15_30th_november_2010_(un...
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 

Viewers also liked

Viewers also liked (13)

Erasmus alterado.ppt 2
Erasmus alterado.ppt   2Erasmus alterado.ppt   2
Erasmus alterado.ppt 2
 
1.2g
1.2g1.2g
1.2g
 
Rajahpecahan
RajahpecahanRajahpecahan
Rajahpecahan
 
4.7
4.74.7
4.7
 
Fabbriche intergenerazionali
Fabbriche intergenerazionaliFabbriche intergenerazionali
Fabbriche intergenerazionali
 
BUS 365 Term Paper
BUS 365 Term PaperBUS 365 Term Paper
BUS 365 Term Paper
 
Portugal
Portugal Portugal
Portugal
 
Urodinamica prima della chirurgia per prolasso
Urodinamica prima della chirurgia  per prolassoUrodinamica prima della chirurgia  per prolasso
Urodinamica prima della chirurgia per prolasso
 
Module 2
Module 2Module 2
Module 2
 
Globalinvacom
GlobalinvacomGlobalinvacom
Globalinvacom
 
Algoritmo con estructuras repetitivas
Algoritmo con estructuras repetitivasAlgoritmo con estructuras repetitivas
Algoritmo con estructuras repetitivas
 
Nove anni di SIS: Quali evidenze?
Nove anni di SIS: Quali evidenze?Nove anni di SIS: Quali evidenze?
Nove anni di SIS: Quali evidenze?
 
Richard Haller Resume 2015
Richard Haller Resume 2015Richard Haller Resume 2015
Richard Haller Resume 2015
 

Similar to Ten Basic Concepts for Owners

Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
Managing Contractors Effectively 2011
Managing Contractors Effectively 2011Managing Contractors Effectively 2011
Managing Contractors Effectively 2011Stephen Findlay
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsFrancis Ho
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article OneMy own
 
Mar Dedal Portfolio
Mar Dedal PortfolioMar Dedal Portfolio
Mar Dedal Portfolioeaglemhar
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
Single Proprietorship JD
Single Proprietorship JDSingle Proprietorship JD
Single Proprietorship JDDean Apao
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction ContractsMelissa Brumback
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Site Instruction Provision
Site Instruction ProvisionSite Instruction Provision
Site Instruction ProvisionRichard Retita
 
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...Vipin Bakiwala
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptNesrElhandasa1
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 RegulationsKhalida Suleymanova
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job DescriptionTrevor Rutter
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
HVAC Estimation engineer
HVAC Estimation engineerHVAC Estimation engineer
HVAC Estimation engineerAhamed Falil
 

Similar to Ten Basic Concepts for Owners (20)

Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Managing Contractors Effectively 2011
Managing Contractors Effectively 2011Managing Contractors Effectively 2011
Managing Contractors Effectively 2011
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party Rights
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article One
 
Mar Dedal Portfolio
Mar Dedal PortfolioMar Dedal Portfolio
Mar Dedal Portfolio
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Single Proprietorship JD
Single Proprietorship JDSingle Proprietorship JD
Single Proprietorship JD
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Site Instruction Provision
Site Instruction ProvisionSite Instruction Provision
Site Instruction Provision
 
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 Regulations
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job Description
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
HVAC Estimation engineer
HVAC Estimation engineerHVAC Estimation engineer
HVAC Estimation engineer
 

Recently uploaded

Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Dr. Oliver Massmann
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书Fir L
 
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一st Las
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》o8wvnojp
 
Rights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaRights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaAbheet Mangleek
 
Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionNilamPadekar1
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书Fir sss
 
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书SD DS
 
Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesHome Tax Saver
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书SD DS
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSDr. Oliver Massmann
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书Fir sss
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书Fir sss
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementShubhiSharma858417
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书SD DS
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书1k98h0e1
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaNafiaNazim
 

Recently uploaded (20)

Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
 
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
定制(BU文凭证书)美国波士顿大学毕业证成绩单原版一比一
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
 
Rights of under-trial Prisoners in India
Rights of under-trial Prisoners in IndiaRights of under-trial Prisoners in India
Rights of under-trial Prisoners in India
 
Trial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 seditionTrial Tilak t 1897,1909, and 1916 sedition
Trial Tilak t 1897,1909, and 1916 sedition
 
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 如何办理威斯康星大学密尔沃基分校毕业证学位证书 如何办理威斯康星大学密尔沃基分校毕业证学位证书
如何办理威斯康星大学密尔沃基分校毕业证学位证书
 
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
如何办理(GWU毕业证书)乔治华盛顿大学毕业证学位证书
 
Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax Rates
 
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
如何办理(uOttawa毕业证书)渥太华大学毕业证学位证书
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
Special Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreementSpecial Accounting Areas - Hire purchase agreement
Special Accounting Areas - Hire purchase agreement
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in India
 

Ten Basic Concepts for Owners

  • 1. TEN BASIC CONCEPTS FOR OWNERS PRESENTER: CRAIG DIRRIM, PARTNER
  • 2. TEN BASIC CONCEPTS FOR OWNERS 1. Disclose known information to bidders 2. Provide accurate plans 3. Obtain permits and easements in a timely manner 4. Coordinate access to the site and work of others 5. Supply equipment and material as scheduled
  • 3. TEN BASIC CONCEPTS FOR OWNERS 6. Respond promptly to change order and time extension requests 7. Review submittals in a timely manner 8. Make timely, reasonable inspections 9. Provide a safe site environment 10.Deal with the contractor in good faith
  • 4. DISCLOSE KNOWN INFORMATION TO BIDDERS An owner’s duty to disclose will start at the issuance of the RFP and continue through construction. Includes ground water levels, flood conditions, subsurface soil conditions, hazardous materials, etc. Document the method and manner of disclosure (i.e., studies, photos, video reports).
  • 5. PROVIDE ACCURATE PLANS Under the Spearin Doctrine, an owner warrants that its plans and specifications are accurate, and if a contractor performs in accordance with the design documents provided, the contractor will not be responsible for any inadequacies in the completed work. Spearin will also allow a contractor to recover for any additional costs or extra work which result from defects or inadequacies in the plans specifications. See United States v. Spearin, 248 U.S. 132 (1918)
  • 6. PROVIDE ACCURATE PLANS Defenses to Spearin  Obvious defect – would a reasonable contractor have been able to identify the design error during a pre-bid review.  The contractor must perform its work in accordance with the plans and specifications.  The warranty of design in Spearin does not apply to performance specifications.  In certain cases, specific disclaimer language can defeat the obligation in Spearin, but such language could increase the cost of the project.
  • 7. PROVIDE ACCURATE PLANS Practical Tips  Know your contract terms with your owner. Is there a limitation of liability?  Be careful “reusing” design documents
  • 8. OBTAIN EASEMENTS AND PERMITS IN A TIMELY MANNER An owner typically needs to have all approvals required for a contractor to proceed. Manage this process. Have all R.O.W.’s been obtained before the notice to proceed? Are there conflicts with utility or railroad easements? Failure to provide such easements or permits may be an exception to a “no damages for delay” clause.
  • 9. PROVIDE ACCESS TO THE SITE AND COORDINATE THEWORK OF OTHERS An owner is required to provide uninterrupted access to the project throughout the course of construction. The owner’s duty includes adequate space to perform the work (cranes, laydown, etc.).
  • 10. PROVIDE ACCESS TO THE SITE AND COORDINATE THEWORK OF OTHERS The owner will need to coordinate other work so it will not interfere with the contractor’s planned sequence or schedule, particularly in cases where there are multiple primes. The owner should adequately disclose or limit possible interferences from ongoing operations in existing facilities.
  • 11. SUPPLY OWNER FURNISHED EQUIPMENT AND MATERIAL IN ACCORDANCE WITH THE SCHEDULE When an owner chooses to supply material or equipment, it warrants that the supplied materials are suitable for its intended purpose. An owner who chooses to furnish certain equipment or materials must do so in accordance with the project schedule. Failure to do so may result in liability for additional costs or delay.
  • 12. SUPPLY OWNER FURNISHED EQUIPMENT AND MATERIAL IN ACCORDANCE WITH THE SCHEDULE Specification of certain proprietary material or equipment by an owner implies that the materials or equipment will be available and are suitable for the work.
  • 13. RESPOND PROMPTLY TO CHANGE ORDER AND TIME EXTENSION REQUESTS An owner has a duty to fairly evaluate and promptly respond to time extension requests.  Failure to respond to a time extension request may result in the finding of “Constructive Acceleration.” An owner has a duty to fairly evaluate and promptly respond to change order requests.  Failure to respond to a change order request may result in a project stoppage or escalate the matter to a claim status.
  • 14. REVIEW SUBMITTALS AND RFI’S IN A TIMELY FASHION When the contract requires the contractor to submit shop drawings or other information to the owner for its review, there is a corresponding duty on the owner to make such a review in a manner which supports the project schedule.  Failure to review submittals in a timely fashion may subject an owner to a claim of active interference and could render a “no damage for delay” clause void.  Failure to respond to RFI’s in a timely manner may provide a contractor with a basis for an extended duration or delay claim.
  • 15. MAKE TIMELY, REASONABLE INSPECTIONS If the contract requires inspections after particular phases or portions of work, an owner will have a duty to have sufficient personnel available to perform such inspections in accordance with the project schedule. An owner may be responsible for inconsistent inspections or “over” inspections of the contractor’s work.
  • 16. MAKE TIMELY, REASONABLE INSPECTIONS An owner who has an opportunity to make a reasonable inspection and fails to make such inspection or undertakes an inspection, but fails to notify the contractor of obvious non-conforming work, the owner may be barred from seeking damages from the contractor for such work.
  • 17. PROVIDE A SAFE ENVIRONMENT Are there site specific conditions or operation issues that the owner has specific knowledge of? If so, those should be disclosed. If the owner is undertaking to manage a multiple-prime project, the owner may have a heightened responsibility to ensure the safety of the project site.
  • 18. DEAL WITH THE CONTRACTOR IN GOOD FAITH Every contract contains an implied covenant of good faith and fair dealing. This covenant of good faith and fair dealing can cover numerous owner acts and/or omissions.
  • 19. THANK YOU! CRAIG DIRRIM 301 SOUTH 13TH STREET, SUITE 500 LINCOLN, NE 68508 (402) 437-8500 CDIRRIM@WOODSAITKEN.COM