PROJECT PLAN
Purdys Demising & Renovation
Donny Olson
OPMT- 3520
November 24th
, 2016
S t r e a m l i n e F a c i l i t y P l a n n i n g
1
Table of Contents
Project Charter ………………………………………………………………………………………..2-6
Communication Management Plan ………………………………………………………7
Risk Management Plan ……………………………………………………………………………8-9
Work Breakdown Structure & Dictionary …………………………………………..10-11
Project Budget ………………………………………………………………………………………….12-13
Appendices
Budget Summary & Breakdown
Gantt Chart
S t r e a m l i n e F a c i l i t y P l a n n i n g
2
1.1 Project Charter
1.1.1 Background
Streamline has been hired to provide project management services for
Purdys Chocolatier, for upcoming tenant improvements and warehouse demising
project. This project is needed because; increased web page sales has led to a need
for a new larger packing line area and they are planning for future growth, with the
addition of an office use mezzanine. Furthermore, because of the increase in sales,
additional staff must be hired as well. This has led to the need for: new bathrooms,
main floor office space, and a gym to help provide for valued workforce. Finally, we
will be using under-utilized space at 8330 Chester Street to move new tenants into
the building, this will provide a new revenue stream for Purdys. To make this
possible; a demising wall will be built, with accompanying exit corridors, and
wheelchair -accessible ramp.
The current situation for Purdys is a warehouse pack line that cannot meet
up with increased demand. Furthermore, space that could be generating an income
is sitting vacant. We will review all existing operations, review and oversee the
planning, engineering, construction, and closeout process while providing expert
project management experience, coupled with strong communication processes.
1.1.2 Goals
● Work in the best interest of the client and represent them throughout the
project life cycle.
● To maximize work efficiency and utilize cost-saving methods whenever
possible.
● Work closely with the engineering consultants and the General Contractor to
ensure as little disruption to Purdys daily work activities as possible.
● Deliver a product that is of high quality and value-added, completed on time
and meet or exceeds all client expectations.
S t r e a m l i n e F a c i l i t y P l a n n i n g
3
1.1.3 Scope of Work & Deliverables
PHASE 1:
1. Prepare site for construction (signage, equipment set-up, safety meetings,
and introductions)
2. Removal of existing pallet racking and other fixtures
3. Geotechnical testing of load bearing soils below the existing floor slab.
4. Cutting and coring concrete and preparing site for building demising wall
5. Demise 8330 & 8380 Chester Street (See Appendix A1 for dimensions)
6. Building 2 new interior exit corridors for shared space north and south of
demising wall, and 1 main exit corridor (exterior) exiting onto Kent Street (See B2
for details)
7. Trades will be managed by site contractor, and trades will be responsible
for ALL miscellaneous work related to their tasks (See work breakdown structure)
PHASE 2:
1. Construct 5 female and 5 male washrooms (These will have wheelchair
accessible washrooms inside)
Specs. Washrooms will be 3’ - 5
Handicapped Washroomswill be 5’ -5’ (All fixtures will be of commercial grade)
2. Construct new office space, lunchroom and first aid room
3. Building wheelchair accessible ramp for the new tenancy.
PHASE 3:
1. Remove north warehouse pallet racking for floor space
2. Demolition of existing washrooms and change rooms
3. Build new washrooms 7 male 7 female and 1 universal accessible (Specs. Will
remain the same as phase 2 washrooms)
4. Build new gym space (Gym equipment will not be provided or ordered)
5. Supply and install new mezzanine deck and pack line with adjoining coolers
this includes: Foundation, steel & concrete structure, walls & ceilings, l, and
equipment needed (humidity control unit, HVAC unit, new lighting etc.
 The mezzanine deck WILL NOT be built-out at this time but will be
available and built so future operations can be expanded as needed. This
will future build is not be in existing contract.
S t r e a m l i n e F a c i l i t y P l a n n i n g
4
1.1.4 Key Stakeholders
Client Purdys Chocolates
Sponsor Duncan Johnson (CFO) Available on request
Project manager Earl Vance 604-988-2322
Project team
members
Jim Prichard 778-563-4456
(Operations Manager)
Jesse Sengura 604-988-4511
(Floor Supervisors)
Donny Olson 604-842-5125
(Project Coordinator)
General Contractor: George Stevens 604-921-3342
Bynett Construction
Electrical Engineer: Joshua Merkel 778-651-4456
SML Electrical Consultants
Plumbing/HVAC: Hamid Rekashi 604-567-8932
Bycar Engineering
Sprinklers: Curtis Hayden 604-765-2232
Phaser Fire
Architect:
Edwin Wong 778-451-2311
Structural Engineer:
Bianco Wong 778-988-5678
Geotechnical Engineer:
Sarah Parry 604-229-4356
S t r e a m l i n e F a c i l i t y P l a n n i n g
5
1.1.5 Codes & Regulations
● Vancouver Building By-Law 2014 (VBBL 2014)
● British Columbia Fire Code 2012
★ ALL trades will be responsible for making sure their work is up to code, and
follows all by-laws. Any re-work that must be done; due to not following
code, the trade responsible will cover the cost from their contract. Contractor
will also oversee all daily operations and keep StreamLine updated.
★ A weekly project review meeting will be schedule
1.1.6 Project Priorities
● Demising 8380 Chester Street as quickly as possible. This will allow the client
to collect monthly rental income from the under-utilized space.
● Having PHASE 2 washrooms built and ready for use before December 1st,
2016. That is when the seasonal workforce arrives.
● Having the project completed on time and on budget
● Minimizing disruption to current operations.
● Minimising dust contamination of existing finished product.
S t r e a m l i n e F a c i l i t y P l a n n i n g
6
1.1.7 Project Milestones
Start Date: February 9th, 2016
Milestone 1: March 10th, 2016 - Permit Application
Milestone 2: July 28th, 2016 - Construction Starts
Milestone 3: November 1, 2016 – Occupancy granted for tenant space
Milestone 4: April 13th, 2017 – Completion of project Handover
1.1.8 Approval Signatures
Jim Pritchard,
Project Client
Duncan Johnson,
Project Sponsor
Earl Vance, Project
Manager
S t r e a m l i n e F a c i l i t y P l a n n i n g
7
1.2 Communications Plan
Clear and concise communication is what we strive for at Streamline. We will
be responsible for facilitating daily communications between the general contractor
and the client. Any decision or pertinent information regarding the project
deliverables will be followed by an e-mail, formal request for information or a
change order document. All information related to the project will be cc’d to all
stakeholders.
★ All e-mails that contain Request for Information (RFI’s) must be
answered with 72 hours. Failure to do so could cause delay in project
deliverables and increased costs.
1.2.1 Communication Matrix
Project Title: Purdy’s Demising & Renovation
Project Manager: Earl Vance
Project Coordinator: Donny Olson
General Contractor: George Stevens
Project Sponsor: Duncan Johnson
Date: February 9th
, 2016
Communication
Type
Purpose Recipients Delivery
Method
Frequency Who is
Responsible?
Kick Off Meeting Introduce the
project team, and
the project.
Review project
objectives, and
management
approach
Project
Sponsor
Project team
members
Stakeholders
Trades
Face to Face Once Project
Manager
Project Status
(Progress Report)
Report the project
status to the client
Project Team
Project
Sponsor
e-mail
Conference
Call
Once a week Project
Manager
Project
Coordinator
Project Team
Meetings
Review status of
the project with
team
Project Team Face to Face
Conference
Call
E-mail
Weekly Project
Manager
“Tool Box” talks Safety talks, areas
for concern, daily
tasks
General
Contractor
Trades
Face to Face Daily General
Contractor
Trades
Project updates
Action item Status
Weekly meetings
to deliver project
information and
“Weekly action
items”
Project
Manager
Meeting Weekly Project Team
S t r e a m l i n e F a c i l i t y P l a n n i n g
8
1.3 Risk Management Plan
Identifying, controlling, and mitigating risk is a key factor for any project. We
will be looking at all possible risks that can occur throughout the renovation. To do
this as effectively and efficiently as possible, we will be looking at past projects,
expert judgement, and consulting with stakeholders. We will also develop strategies
to mitigate, transfer, or avoid risks that we deem may affect the deliverables.
1.3.1 Risk Identification
Risk identification will be developed by: expert judgement, past projects,
discussions with trades, and client observations. Streamline will be building,
monitoring, and mitigating risks throughout the project to ensure effective risk
control. Below, are some the risks we have currently identified:
 City requirements & potential delays for building permit approval
 Materials not arriving on time
 Lack of communication between trades
 Washroomsnot being completed for seasonal influx of workers
 Trades not having enough workers to complete deliverables on time
 Disruption of Purdy’s operations
 Key resources not available
1.3.2 Probability & Impact
Level of Risk Probability Impact
High (4-5) The risk will likely
happen throughout
the project
The risk will cause
major disruption to
the schedule or
budget
Medium (3-4) The risk has a
moderate chance of
occurring
The risk will impact
the project
moderately
Low (2 or lower) The risk is unlikely to
occur
The risk will have
little impact on the
budget or schedule
S t r e a m l i n e F a c i l i t y P l a n n i n g
9
1.3.3 Risk Prioritization and Management
Level of risk Action to be taken Management of risk
Critical (25) Requires urgent action
Notify all stakeholders and sponsor
Avoid at all cost
Serious (15-20) Monitored and review during
planning stage
To be dealt with as quickly as
possible
Notify affected stakeholders and
client
Transfer or mitigate risk
Moderate (6-
12)
Notify project sponsor
Identify risk during planning,
monitor, and handle accordingly
Transfer or mitigate risk
Low (1-5) Review and monitor Accept
1.3.4 Risk Matrix
Risk Description Probability Impact Risk
Score
Action Risk Response
Permits not being
approved
3 4 12 mitigate Out of our control, be
prepared and have
documentation ready
Materials not arriving on
time
3 5 15 mitigate Order all fixtures and
materials well ahead of
schedule
Lack of communication
between trades
3 4 12 mitigate Have “tool box talks”
and remind trades of
communication
Washrooms not
completed
2 2 4 accept Work within schedule, if
not completed. Rent
washroom trailer
Disruption of daily
operations
2 4 8 avoid Operations will be shut
down while we work
Workplace injury 3 5 15 Transfer
avoid
WBC coverage, and
have safety officer go
over orientation with
ALL personnel
S t r e a m l i n e F a c i l i t y P l a n n i n g
10
1.4 Work Breakdown Structure Dictionary
 Architectural Drawings - Complete and have architectural drawings
stamped and approved.
 Soil Coring & Testing - Have soil cored and tested to ensure soil is feasible
to build on.
 Engineered drawings - Complete and have engineering drawings stamped
and approved.
 Permit Application - Submit permits for approval.
 Steel shop drawing & delivery - Have structural steel drawing submitted,
then deliver product.
 Site Preparation – This includes: site reviews, demolition of existing
structures, cutting out concrete for rough-ins, putting up signage, fencing,
toilets, dismantling racking for construction, running any temporary lines
(water, electricity, etc.)
 Demising wall and Exit Corridors – Cutting out masonry and steel for new
exit corridor on west wall, installing structural steel header and frame, and
installing new door.
 Finishing - This includes tasks that are involved with deliverable that will not
be broken down due to cost. This will include painting, millwork, and related
finishes for deliverables. They will be broken down for the budget and scope.
For Phase 1 handicap accessible ramp, this includes railings, painting and
anti-slip plating installation.
 Doors And Windows – Task involves all windows and doors for the project.
This task also includes the delivery, installation, caulking, and weather-
stripping.
 Equipment Delivery & Set up – Having all components shipped delivered
and organized for new pack-line and cooler
 Moving/Fixturing/Commissioning - This task involves assembling,
fixturing, and testing new pack-line.
 Contingency – Going through all contingency items and making sure
nothing is missed.
 Occupancy and Operational - Getting clients moved in and operational.
S t r e a m l i n e F a c i l i t y P l a n n i n g
11
1.5 Budget
Soft Costs
Planning and design
drawings
$54,106 $54,106 Incl.
below
Project Management Fee $46,376 $46,376 $60,860
Structural Engineering $10,500 $10,500 $8,035
Mechanical Engineering $13,500 $13,500 $13,500
Electrical Engineering $11,990 $11,990 $11,990
Geotechnical Consulting $9,933 $9,933 $9,933
Permits fees &
Disbursements
$7,500 $7,500 $7,500
Plots, Copies, Couriers,
other misc. charges
Incl. Above Incl. Above Incl.
Above
Total
Soft Costs:
$153,905 $153,905 $111,881
Contingency (10%):
$169,978 $87,834 $159,691 Equals Contingency, Less
Change Orders (below)
Total Construction & Soft
Costs:
$2,023,668 $1,644,761 $676,604
(GST Not Incl.)
Change Orders
Approved Invoiced
CO#1 Additional T-Bar/tile (shipping office area and
old washroom area): RSY
$6,250 Pending site
instruction/
pricing
CO#2 Electrical Addendum 1: Tytan $1,980 $1,890
C0#3 Mechanical Addendum M-1: MMC $4,500
CO#4 Credit – Door Removal (3) – openings, doors,
frames, hardware: Allmar
($1,345)
CO#5 Credit – Change to water pipe sizing and
insulate: MMC
($9,800)
CO#6 Credit – Change to toilets to wall hang ($618)
CO#7 Mechanical Engineering: Add web sales & Pack
Line to scope
$6,000
CO#8 Electrical Engineering: Addendum 1 Web sales
& Pack Line
$2,621 $2,602
CO#9 Geotechnical Consulting: New soil parameters &
foundation solution
$1,890 $1,890
CO#10 Structural Steel Re-design $3,836
CO#11 New sewer connection $66,900
Contractor Profit/Overhead (2%) $230
Total Change Orders: $82,443 $6,382
S t r e a m l i n e F a c i l i t y P l a n n i n g
12
Bynett Construction June 16th
Approved
Budget
Anticipated
or Approved
to date
Invoiced to
date Comments
Site Preparation &
Ground work
$10,882 $10,882
Demolitions $45,568 $45,568 $8,025 AMEC cutting and coring
Asphalt Paving $3,000 $3,000
Concrete + Formwork +
Finishing
$45,082 $45,082 $4,398 Drake/Yaat
Concrete Reinforcing
steel
$31,978 $31,978
Structural steel & metal
deck
$80,404 $91,619 Continental Steel
Misc. Metals $16,000 Incl. Above Continental Steel
Rough carpentry &
Framing
$10,000 $10,000
Finishing Carpentry $2,000 $2,000
Millwork $13,000 $13,489
Exterior Cladding $9,000 $9,000
Roofing $21,000 $17,136 Roofix
Caulking $2,550 $2,550
Doors & Frames $32,850 $21,000 $19,655 Allmar
Windows, Entrances, and
Glazing
$10,506 $10,506
Drywall $133,236 $82,100 $80,613 RSY Contracting
Acoustic Ceilings $19,592 $15,750 Incl. Above RSY Contracting
Floor Finishes $41,043 $28,981
Painting $43,229 $37,780
Specialties $27,000 $27,000
Mechanical $381,868 $555,470 $101,676 Humidity control
machine, Added to
Budget, MCM McGregor
Electrical $349,897 $160,370 $70,659 Tytan Electric
Credit/adjustment T5
Warehouse Lighting
$0 -$30,556
Cash Allowance/Other $25,000 25,000
Misc. Bynett site charges Incl. Above Incl. Above $14,052 Also pulling from General
Conditions
Contractor Profit- On
Sub Trade costs and site
expenses/Materials (2%)
$27,094 $24,391 $6,342
Construction
Management Fee
($20,900, 6 months)
$125,400 $125,400 $83,600
General Conditions (PM,
Accounting, Insur., Tel.,
First Aid, Etc.
$38,700 $38,700 $16,074
Total Construction: $1,545,879 $1,408,060 $405,095 (9.2%)
S t r e a m l i n e F a c i l i t y P l a n n i n g
13
Total Project Cost: $1,726,906
GST Not Incl.

More Related Content

What's hot

Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014Michael Khalil
 
Mohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdfMohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdfmohammedattique
 
engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016Mohamed Gamal
 
Mazhar SheikhMECH ENGR-CV- 2016-Construction
Mazhar SheikhMECH ENGR-CV- 2016-ConstructionMazhar SheikhMECH ENGR-CV- 2016-Construction
Mazhar SheikhMECH ENGR-CV- 2016-ConstructionMazhar Sheikh
 
Beach house construction desktop 02 29
Beach house construction desktop 02 29Beach house construction desktop 02 29
Beach house construction desktop 02 29sheylaobm
 
Benoit Giroux - CV2015 English Linkedin no page 6
Benoit Giroux - CV2015 English Linkedin no page 6Benoit Giroux - CV2015 English Linkedin no page 6
Benoit Giroux - CV2015 English Linkedin no page 6Benoit Giroux
 
Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce Brown
 
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)Imteyaz Ahmad
 
neeraj kumar - resume (1)
neeraj kumar - resume (1)neeraj kumar - resume (1)
neeraj kumar - resume (1)Neeraj Kumar
 
Sample-Construction-Business-Proposal
Sample-Construction-Business-ProposalSample-Construction-Business-Proposal
Sample-Construction-Business-ProposalJennifer Riggins
 
Ibrahim_Abdelkhalig_Curriculum_vitae_(2)
Ibrahim_Abdelkhalig_Curriculum_vitae_(2) Ibrahim_Abdelkhalig_Curriculum_vitae_(2)
Ibrahim_Abdelkhalig_Curriculum_vitae_(2) Ibraim Mohamed
 
cv_Ariel A. Quisto - Copy
cv_Ariel A. Quisto - Copycv_Ariel A. Quisto - Copy
cv_Ariel A. Quisto - Copyariel quisto
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev ehesands2437
 

What's hot (20)

Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014
 
Mohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdfMohammed_Attique - CV.pdf
Mohammed_Attique - CV.pdf
 
engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016
 
Mazhar SheikhMECH ENGR-CV- 2016-Construction
Mazhar SheikhMECH ENGR-CV- 2016-ConstructionMazhar SheikhMECH ENGR-CV- 2016-Construction
Mazhar SheikhMECH ENGR-CV- 2016-Construction
 
Beach house construction desktop 02 29
Beach house construction desktop 02 29Beach house construction desktop 02 29
Beach house construction desktop 02 29
 
C V
C VC V
C V
 
CV1
CV1CV1
CV1
 
Benoit Giroux - CV2015 English Linkedin no page 6
Benoit Giroux - CV2015 English Linkedin no page 6Benoit Giroux - CV2015 English Linkedin no page 6
Benoit Giroux - CV2015 English Linkedin no page 6
 
DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
Royce_Brown Resume-82115
Royce_Brown Resume-82115Royce_Brown Resume-82115
Royce_Brown Resume-82115
 
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)Imteyaz ahmad   12 yrs exp in MEP (Site / Project Management)
Imteyaz ahmad 12 yrs exp in MEP (Site / Project Management)
 
neeraj kumar - resume (1)
neeraj kumar - resume (1)neeraj kumar - resume (1)
neeraj kumar - resume (1)
 
Sample-Construction-Business-Proposal
Sample-Construction-Business-ProposalSample-Construction-Business-Proposal
Sample-Construction-Business-Proposal
 
Ibrahim_Abdelkhalig_Curriculum_vitae_(2)
Ibrahim_Abdelkhalig_Curriculum_vitae_(2) Ibrahim_Abdelkhalig_Curriculum_vitae_(2)
Ibrahim_Abdelkhalig_Curriculum_vitae_(2)
 
cv_Ariel A. Quisto - Copy
cv_Ariel A. Quisto - Copycv_Ariel A. Quisto - Copy
cv_Ariel A. Quisto - Copy
 
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
Lead_Planner_Ashfaq_Hussain_Resume_Jul2015
 
Joe Harris' Resume 2016
Joe Harris' Resume 2016Joe Harris' Resume 2016
Joe Harris' Resume 2016
 
Monitoring Programme Review
Monitoring Programme ReviewMonitoring Programme Review
Monitoring Programme Review
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev eh
 

Viewers also liked

Cox Springfield MO ED Site Visit
Cox Springfield MO ED Site VisitCox Springfield MO ED Site Visit
Cox Springfield MO ED Site Visitkat0783
 
Panchmel dal-recipe-in-hindi
Panchmel dal-recipe-in-hindiPanchmel dal-recipe-in-hindi
Panchmel dal-recipe-in-hindizayka recipes
 
Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016
Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016
Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016Donny Olson
 
SHANKAR ANANTHARAMAN manager resume (1)
SHANKAR ANANTHARAMAN manager resume (1)SHANKAR ANANTHARAMAN manager resume (1)
SHANKAR ANANTHARAMAN manager resume (1)Shankar Anantharaman
 
Presentación internet
Presentación internetPresentación internet
Presentación internetcjaimes432
 
Dhokla idli-recipe-in-hindi
Dhokla idli-recipe-in-hindiDhokla idli-recipe-in-hindi
Dhokla idli-recipe-in-hindizayka recipes
 
research framwork chapter 6 quantitative business analysis
research framwork chapter 6 quantitative business analysisresearch framwork chapter 6 quantitative business analysis
research framwork chapter 6 quantitative business analysisMuzammil Malik
 

Viewers also liked (13)

Cox Springfield MO ED Site Visit
Cox Springfield MO ED Site VisitCox Springfield MO ED Site Visit
Cox Springfield MO ED Site Visit
 
Shailee_Rathod_CV
Shailee_Rathod_CVShailee_Rathod_CV
Shailee_Rathod_CV
 
Trabajo final aracelis
Trabajo final aracelisTrabajo final aracelis
Trabajo final aracelis
 
Panchmel dal-recipe-in-hindi
Panchmel dal-recipe-in-hindiPanchmel dal-recipe-in-hindi
Panchmel dal-recipe-in-hindi
 
Shailee_Rathod_CV
Shailee_Rathod_CVShailee_Rathod_CV
Shailee_Rathod_CV
 
Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016
Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016
Purdy's Chocolatier Renovation & Demise (Current Schedule) - 21 Oct 2016
 
SHANKAR ANANTHARAMAN manager resume (1)
SHANKAR ANANTHARAMAN manager resume (1)SHANKAR ANANTHARAMAN manager resume (1)
SHANKAR ANANTHARAMAN manager resume (1)
 
Prueba 2 maria cando ortega.
Prueba 2  maria cando ortega.Prueba 2  maria cando ortega.
Prueba 2 maria cando ortega.
 
Presentación internet
Presentación internetPresentación internet
Presentación internet
 
Dhokla idli-recipe-in-hindi
Dhokla idli-recipe-in-hindiDhokla idli-recipe-in-hindi
Dhokla idli-recipe-in-hindi
 
Animales vertebrados e invertebrados
Animales vertebrados e invertebradosAnimales vertebrados e invertebrados
Animales vertebrados e invertebrados
 
FAI - Formação e Assessoria Integral
FAI - Formação e Assessoria IntegralFAI - Formação e Assessoria Integral
FAI - Formação e Assessoria Integral
 
research framwork chapter 6 quantitative business analysis
research framwork chapter 6 quantitative business analysisresearch framwork chapter 6 quantitative business analysis
research framwork chapter 6 quantitative business analysis
 

Similar to Project management plan

Creek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxCreek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxZiyad Zaidi
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxRebeccaEdwards88
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxRUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxagnesdcarey33086
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management MethodologyMohammed Al-Taee
 
Bai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du anBai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du anDoan Tran Ngocvu
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxlesleyryder69361
 
Assignment Help Moodle Monkey
Assignment Help Moodle Monkey Assignment Help Moodle Monkey
Assignment Help Moodle Monkey ZomakSoluion
 
COVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCOVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCruzIbarra161
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1suzzanekan
 

Similar to Project management plan (20)

Creek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docxCreek Vista Marine FARAAZ KHAN WORK Report.docx
Creek Vista Marine FARAAZ KHAN WORK Report.docx
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
Project management
Project managementProject management
Project management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 
Group Presentation MSMS
Group Presentation MSMSGroup Presentation MSMS
Group Presentation MSMS
 
Running head PMPM .docx
Running head PMPM                                          .docxRunning head PMPM                                          .docx
Running head PMPM .docx
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project charter j
Project charter jProject charter j
Project charter j
 
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxRUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
 
APM_AEB_FINAL
APM_AEB_FINALAPM_AEB_FINAL
APM_AEB_FINAL
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
Bai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du anBai 3 giai doan hoach dinh du an
Bai 3 giai doan hoach dinh du an
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
 
Project mangment
Project mangmentProject mangment
Project mangment
 
Assignment Help Moodle Monkey
Assignment Help Moodle Monkey Assignment Help Moodle Monkey
Assignment Help Moodle Monkey
 
COVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated ProjecCOVERTITLE PAGE Table of ContentsI. Integrated Projec
COVERTITLE PAGE Table of ContentsI. Integrated Projec
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
 

Project management plan

  • 1. PROJECT PLAN Purdys Demising & Renovation Donny Olson OPMT- 3520 November 24th , 2016
  • 2. S t r e a m l i n e F a c i l i t y P l a n n i n g 1 Table of Contents Project Charter ………………………………………………………………………………………..2-6 Communication Management Plan ………………………………………………………7 Risk Management Plan ……………………………………………………………………………8-9 Work Breakdown Structure & Dictionary …………………………………………..10-11 Project Budget ………………………………………………………………………………………….12-13 Appendices Budget Summary & Breakdown Gantt Chart
  • 3. S t r e a m l i n e F a c i l i t y P l a n n i n g 2 1.1 Project Charter 1.1.1 Background Streamline has been hired to provide project management services for Purdys Chocolatier, for upcoming tenant improvements and warehouse demising project. This project is needed because; increased web page sales has led to a need for a new larger packing line area and they are planning for future growth, with the addition of an office use mezzanine. Furthermore, because of the increase in sales, additional staff must be hired as well. This has led to the need for: new bathrooms, main floor office space, and a gym to help provide for valued workforce. Finally, we will be using under-utilized space at 8330 Chester Street to move new tenants into the building, this will provide a new revenue stream for Purdys. To make this possible; a demising wall will be built, with accompanying exit corridors, and wheelchair -accessible ramp. The current situation for Purdys is a warehouse pack line that cannot meet up with increased demand. Furthermore, space that could be generating an income is sitting vacant. We will review all existing operations, review and oversee the planning, engineering, construction, and closeout process while providing expert project management experience, coupled with strong communication processes. 1.1.2 Goals ● Work in the best interest of the client and represent them throughout the project life cycle. ● To maximize work efficiency and utilize cost-saving methods whenever possible. ● Work closely with the engineering consultants and the General Contractor to ensure as little disruption to Purdys daily work activities as possible. ● Deliver a product that is of high quality and value-added, completed on time and meet or exceeds all client expectations.
  • 4. S t r e a m l i n e F a c i l i t y P l a n n i n g 3 1.1.3 Scope of Work & Deliverables PHASE 1: 1. Prepare site for construction (signage, equipment set-up, safety meetings, and introductions) 2. Removal of existing pallet racking and other fixtures 3. Geotechnical testing of load bearing soils below the existing floor slab. 4. Cutting and coring concrete and preparing site for building demising wall 5. Demise 8330 & 8380 Chester Street (See Appendix A1 for dimensions) 6. Building 2 new interior exit corridors for shared space north and south of demising wall, and 1 main exit corridor (exterior) exiting onto Kent Street (See B2 for details) 7. Trades will be managed by site contractor, and trades will be responsible for ALL miscellaneous work related to their tasks (See work breakdown structure) PHASE 2: 1. Construct 5 female and 5 male washrooms (These will have wheelchair accessible washrooms inside) Specs. Washrooms will be 3’ - 5 Handicapped Washroomswill be 5’ -5’ (All fixtures will be of commercial grade) 2. Construct new office space, lunchroom and first aid room 3. Building wheelchair accessible ramp for the new tenancy. PHASE 3: 1. Remove north warehouse pallet racking for floor space 2. Demolition of existing washrooms and change rooms 3. Build new washrooms 7 male 7 female and 1 universal accessible (Specs. Will remain the same as phase 2 washrooms) 4. Build new gym space (Gym equipment will not be provided or ordered) 5. Supply and install new mezzanine deck and pack line with adjoining coolers this includes: Foundation, steel & concrete structure, walls & ceilings, l, and equipment needed (humidity control unit, HVAC unit, new lighting etc.  The mezzanine deck WILL NOT be built-out at this time but will be available and built so future operations can be expanded as needed. This will future build is not be in existing contract.
  • 5. S t r e a m l i n e F a c i l i t y P l a n n i n g 4 1.1.4 Key Stakeholders Client Purdys Chocolates Sponsor Duncan Johnson (CFO) Available on request Project manager Earl Vance 604-988-2322 Project team members Jim Prichard 778-563-4456 (Operations Manager) Jesse Sengura 604-988-4511 (Floor Supervisors) Donny Olson 604-842-5125 (Project Coordinator) General Contractor: George Stevens 604-921-3342 Bynett Construction Electrical Engineer: Joshua Merkel 778-651-4456 SML Electrical Consultants Plumbing/HVAC: Hamid Rekashi 604-567-8932 Bycar Engineering Sprinklers: Curtis Hayden 604-765-2232 Phaser Fire Architect: Edwin Wong 778-451-2311 Structural Engineer: Bianco Wong 778-988-5678 Geotechnical Engineer: Sarah Parry 604-229-4356
  • 6. S t r e a m l i n e F a c i l i t y P l a n n i n g 5 1.1.5 Codes & Regulations ● Vancouver Building By-Law 2014 (VBBL 2014) ● British Columbia Fire Code 2012 ★ ALL trades will be responsible for making sure their work is up to code, and follows all by-laws. Any re-work that must be done; due to not following code, the trade responsible will cover the cost from their contract. Contractor will also oversee all daily operations and keep StreamLine updated. ★ A weekly project review meeting will be schedule 1.1.6 Project Priorities ● Demising 8380 Chester Street as quickly as possible. This will allow the client to collect monthly rental income from the under-utilized space. ● Having PHASE 2 washrooms built and ready for use before December 1st, 2016. That is when the seasonal workforce arrives. ● Having the project completed on time and on budget ● Minimizing disruption to current operations. ● Minimising dust contamination of existing finished product.
  • 7. S t r e a m l i n e F a c i l i t y P l a n n i n g 6 1.1.7 Project Milestones Start Date: February 9th, 2016 Milestone 1: March 10th, 2016 - Permit Application Milestone 2: July 28th, 2016 - Construction Starts Milestone 3: November 1, 2016 – Occupancy granted for tenant space Milestone 4: April 13th, 2017 – Completion of project Handover 1.1.8 Approval Signatures Jim Pritchard, Project Client Duncan Johnson, Project Sponsor Earl Vance, Project Manager
  • 8. S t r e a m l i n e F a c i l i t y P l a n n i n g 7 1.2 Communications Plan Clear and concise communication is what we strive for at Streamline. We will be responsible for facilitating daily communications between the general contractor and the client. Any decision or pertinent information regarding the project deliverables will be followed by an e-mail, formal request for information or a change order document. All information related to the project will be cc’d to all stakeholders. ★ All e-mails that contain Request for Information (RFI’s) must be answered with 72 hours. Failure to do so could cause delay in project deliverables and increased costs. 1.2.1 Communication Matrix Project Title: Purdy’s Demising & Renovation Project Manager: Earl Vance Project Coordinator: Donny Olson General Contractor: George Stevens Project Sponsor: Duncan Johnson Date: February 9th , 2016 Communication Type Purpose Recipients Delivery Method Frequency Who is Responsible? Kick Off Meeting Introduce the project team, and the project. Review project objectives, and management approach Project Sponsor Project team members Stakeholders Trades Face to Face Once Project Manager Project Status (Progress Report) Report the project status to the client Project Team Project Sponsor e-mail Conference Call Once a week Project Manager Project Coordinator Project Team Meetings Review status of the project with team Project Team Face to Face Conference Call E-mail Weekly Project Manager “Tool Box” talks Safety talks, areas for concern, daily tasks General Contractor Trades Face to Face Daily General Contractor Trades Project updates Action item Status Weekly meetings to deliver project information and “Weekly action items” Project Manager Meeting Weekly Project Team
  • 9. S t r e a m l i n e F a c i l i t y P l a n n i n g 8 1.3 Risk Management Plan Identifying, controlling, and mitigating risk is a key factor for any project. We will be looking at all possible risks that can occur throughout the renovation. To do this as effectively and efficiently as possible, we will be looking at past projects, expert judgement, and consulting with stakeholders. We will also develop strategies to mitigate, transfer, or avoid risks that we deem may affect the deliverables. 1.3.1 Risk Identification Risk identification will be developed by: expert judgement, past projects, discussions with trades, and client observations. Streamline will be building, monitoring, and mitigating risks throughout the project to ensure effective risk control. Below, are some the risks we have currently identified:  City requirements & potential delays for building permit approval  Materials not arriving on time  Lack of communication between trades  Washroomsnot being completed for seasonal influx of workers  Trades not having enough workers to complete deliverables on time  Disruption of Purdy’s operations  Key resources not available 1.3.2 Probability & Impact Level of Risk Probability Impact High (4-5) The risk will likely happen throughout the project The risk will cause major disruption to the schedule or budget Medium (3-4) The risk has a moderate chance of occurring The risk will impact the project moderately Low (2 or lower) The risk is unlikely to occur The risk will have little impact on the budget or schedule
  • 10. S t r e a m l i n e F a c i l i t y P l a n n i n g 9 1.3.3 Risk Prioritization and Management Level of risk Action to be taken Management of risk Critical (25) Requires urgent action Notify all stakeholders and sponsor Avoid at all cost Serious (15-20) Monitored and review during planning stage To be dealt with as quickly as possible Notify affected stakeholders and client Transfer or mitigate risk Moderate (6- 12) Notify project sponsor Identify risk during planning, monitor, and handle accordingly Transfer or mitigate risk Low (1-5) Review and monitor Accept 1.3.4 Risk Matrix Risk Description Probability Impact Risk Score Action Risk Response Permits not being approved 3 4 12 mitigate Out of our control, be prepared and have documentation ready Materials not arriving on time 3 5 15 mitigate Order all fixtures and materials well ahead of schedule Lack of communication between trades 3 4 12 mitigate Have “tool box talks” and remind trades of communication Washrooms not completed 2 2 4 accept Work within schedule, if not completed. Rent washroom trailer Disruption of daily operations 2 4 8 avoid Operations will be shut down while we work Workplace injury 3 5 15 Transfer avoid WBC coverage, and have safety officer go over orientation with ALL personnel
  • 11. S t r e a m l i n e F a c i l i t y P l a n n i n g 10 1.4 Work Breakdown Structure Dictionary  Architectural Drawings - Complete and have architectural drawings stamped and approved.  Soil Coring & Testing - Have soil cored and tested to ensure soil is feasible to build on.  Engineered drawings - Complete and have engineering drawings stamped and approved.  Permit Application - Submit permits for approval.  Steel shop drawing & delivery - Have structural steel drawing submitted, then deliver product.  Site Preparation – This includes: site reviews, demolition of existing structures, cutting out concrete for rough-ins, putting up signage, fencing, toilets, dismantling racking for construction, running any temporary lines (water, electricity, etc.)  Demising wall and Exit Corridors – Cutting out masonry and steel for new exit corridor on west wall, installing structural steel header and frame, and installing new door.  Finishing - This includes tasks that are involved with deliverable that will not be broken down due to cost. This will include painting, millwork, and related finishes for deliverables. They will be broken down for the budget and scope. For Phase 1 handicap accessible ramp, this includes railings, painting and anti-slip plating installation.  Doors And Windows – Task involves all windows and doors for the project. This task also includes the delivery, installation, caulking, and weather- stripping.  Equipment Delivery & Set up – Having all components shipped delivered and organized for new pack-line and cooler  Moving/Fixturing/Commissioning - This task involves assembling, fixturing, and testing new pack-line.  Contingency – Going through all contingency items and making sure nothing is missed.  Occupancy and Operational - Getting clients moved in and operational.
  • 12. S t r e a m l i n e F a c i l i t y P l a n n i n g 11 1.5 Budget Soft Costs Planning and design drawings $54,106 $54,106 Incl. below Project Management Fee $46,376 $46,376 $60,860 Structural Engineering $10,500 $10,500 $8,035 Mechanical Engineering $13,500 $13,500 $13,500 Electrical Engineering $11,990 $11,990 $11,990 Geotechnical Consulting $9,933 $9,933 $9,933 Permits fees & Disbursements $7,500 $7,500 $7,500 Plots, Copies, Couriers, other misc. charges Incl. Above Incl. Above Incl. Above Total Soft Costs: $153,905 $153,905 $111,881 Contingency (10%): $169,978 $87,834 $159,691 Equals Contingency, Less Change Orders (below) Total Construction & Soft Costs: $2,023,668 $1,644,761 $676,604 (GST Not Incl.) Change Orders Approved Invoiced CO#1 Additional T-Bar/tile (shipping office area and old washroom area): RSY $6,250 Pending site instruction/ pricing CO#2 Electrical Addendum 1: Tytan $1,980 $1,890 C0#3 Mechanical Addendum M-1: MMC $4,500 CO#4 Credit – Door Removal (3) – openings, doors, frames, hardware: Allmar ($1,345) CO#5 Credit – Change to water pipe sizing and insulate: MMC ($9,800) CO#6 Credit – Change to toilets to wall hang ($618) CO#7 Mechanical Engineering: Add web sales & Pack Line to scope $6,000 CO#8 Electrical Engineering: Addendum 1 Web sales & Pack Line $2,621 $2,602 CO#9 Geotechnical Consulting: New soil parameters & foundation solution $1,890 $1,890 CO#10 Structural Steel Re-design $3,836 CO#11 New sewer connection $66,900 Contractor Profit/Overhead (2%) $230 Total Change Orders: $82,443 $6,382
  • 13. S t r e a m l i n e F a c i l i t y P l a n n i n g 12 Bynett Construction June 16th Approved Budget Anticipated or Approved to date Invoiced to date Comments Site Preparation & Ground work $10,882 $10,882 Demolitions $45,568 $45,568 $8,025 AMEC cutting and coring Asphalt Paving $3,000 $3,000 Concrete + Formwork + Finishing $45,082 $45,082 $4,398 Drake/Yaat Concrete Reinforcing steel $31,978 $31,978 Structural steel & metal deck $80,404 $91,619 Continental Steel Misc. Metals $16,000 Incl. Above Continental Steel Rough carpentry & Framing $10,000 $10,000 Finishing Carpentry $2,000 $2,000 Millwork $13,000 $13,489 Exterior Cladding $9,000 $9,000 Roofing $21,000 $17,136 Roofix Caulking $2,550 $2,550 Doors & Frames $32,850 $21,000 $19,655 Allmar Windows, Entrances, and Glazing $10,506 $10,506 Drywall $133,236 $82,100 $80,613 RSY Contracting Acoustic Ceilings $19,592 $15,750 Incl. Above RSY Contracting Floor Finishes $41,043 $28,981 Painting $43,229 $37,780 Specialties $27,000 $27,000 Mechanical $381,868 $555,470 $101,676 Humidity control machine, Added to Budget, MCM McGregor Electrical $349,897 $160,370 $70,659 Tytan Electric Credit/adjustment T5 Warehouse Lighting $0 -$30,556 Cash Allowance/Other $25,000 25,000 Misc. Bynett site charges Incl. Above Incl. Above $14,052 Also pulling from General Conditions Contractor Profit- On Sub Trade costs and site expenses/Materials (2%) $27,094 $24,391 $6,342 Construction Management Fee ($20,900, 6 months) $125,400 $125,400 $83,600 General Conditions (PM, Accounting, Insur., Tel., First Aid, Etc. $38,700 $38,700 $16,074 Total Construction: $1,545,879 $1,408,060 $405,095 (9.2%)
  • 14. S t r e a m l i n e F a c i l i t y P l a n n i n g 13 Total Project Cost: $1,726,906 GST Not Incl.