SlideShare a Scribd company logo
1 of 17
A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Oak Marr Pump Station Rehabilitation – Construction Project
Wastewater Project – Virtual Community Meeting
Microsoft Teams – December 7, 2021, at 6:30 p.m.
Fairfax County Project Manager: Christopher Mata, P.E.
Project Engineer: HDR & RK&K
December 2021
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Agenda
2
1. Project Team Introductions & Attendee Virtual Sign-In
2. Project Location
3. Project Background & Need
4. Study Phase
5. Design Phase
6. Construction Phase
7. Project Schedule
8. Questions and Answers
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Project Team Introductions & Attendee Virtual Sign-In
3
• Fairfax County Project Manager:
– Christopher Mata, P.E. – Senior Engineer III
• Department of Public Works and Environmental Services (DPWES) – Capital Facilities –
Wastewater Design and Construction Division – Wastewater Collection Branch
• HDR Project Team:
– Fady Afif, P.E. – Project Manager
– Badana Mohamadi – Project Engineer
• RK&K Project Team
– Mike Klevenz, P.E. – QA/QC
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Virtual Meeting Administrative Items
4
• Attendee Virtual Sign-In (2 options)
1. Private Message me on MS Teams – Name, Property Address, Email,
Phone Number
2. Email me @ cmata0@fairfaxcounty.gov - Name, Property Address,
Email, Phone Number
• To reduce feedback, please remain on mute until the end of the
presentation during the Q&A
• The chat board on the right-side of your screen is available
throughout the presentation
Oak Marr Pump Station Rehabilitate – Construction Project
Project Location
Capital Facilities – Wastewater Design and Construction Division – Collections Branch 5
Project
Location
Flow Direction
Sewer service area
and project area
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Project Background & Need
6
• Neighborhood was built in the 1980s,
and the sewer infrastructure has been in
operation since.
• Aged pump station equipment – pumps,
valves, fans, concrete, etc.
• This aging equipment has the potential
of causing:
– Sanitary Sewer Overflows (SSO)
– Sewer back-ups into homes
– Environmental damages
– Maintenance problems
Oak Marr Pump Station Rehabilitate – Construction Project
Existing Conditions
Capital Facilities – Wastewater Design and Construction Division – Collections Branch 7
Incoming Flows
Outgoing Flows
Pump
Station
Site
Oak Marr Pump Station Rehabilitate – Construction Project
Existing Conditions
Capital Facilities – Wastewater Design and Construction Division – Collections Branch 8
Incoming Flows
Outgoing Flows
Pump
Station
Site
EXISTING
ACCESS
ROAD/ TRAIL
EXISTING
FENCE
EXISTING
BUILDING
EXISTING
MANHOLES
EXISTING
FUEL TANK
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Study Phase
9
• Fall 2020 study:
– Evaluated existing conditions – flow analysis, hydraulic
assessment, site & equipment assessment.
– Alternative analysis and recommendation to rehabilitate the
pump stations.
• Criteria: Community impacts, schedule, cost, constructability,
maintainability, operability, reliability
• Recommended Alternative:
– Construct a parallel pump station on the same parcel
– Repurposing 4 existing below-ground structures & installing 2
new below-ground structures
– Pump station building will remain & new generator to be
installed outside
– Sewer services will not be impacted
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Design Phase
10
• Includes Designing:
– Pumps and wet-well
– Permanent by-pass & meter vault
– New enclosed standby generator
– Re-routing of sewer force main
– Station fence (w/ slats) realignment
– Access road repaving and widening in
front of the pump station
– Adding another gate
– Miscellaneous concrete work
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Design Phase
11
EXPANDED ACCESS
ROAD
EXTENDED
FENCE
TEMPORARY
CONSTRUCTION
EASEMENT
STANDBY
GENERATOR
NEW
UNDERGROUND
STRUCTURES
TREE
REMOVAL
Repurposed below-
ground structures (x4)
Oak Marr Pump Station Rehabilitate – Construction Project
Proposed Changes
Capital Facilities – Wastewater Design and Construction Division – Collections Branch 12
Proposed Tree Removal
These
trees to
remain
Proposed trimming of
branches
Pond
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Construction Phase - What to expect
13
• Construction Activity:
– Construction entrance off of Elmesmeade
Ct. cul-de-sac.
– Some construction activity to take place
along trail pathway.
– Excavation for the new wet well and valve
vault
– Dewatering until excavation is complete and
new structures have been placed
– Installing precast structures for wet well and
valve vault
– Installing emergency generator
– Bypass pumping within project site.
Oak Marr Pump Station Rehabilitate – Construction Project
Construction Phase – Access Through the Community
Capital Facilities – Wastewater Design and Construction Division – Collections Branch 14
Oak Marr Pump Station Rehabilitate – Construction Project
Project Schedule
15
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
December 2019
Study Began
October
2020
Study
Complete
January 2022
Anticipate
Acquiring all
Land Rights
Summer 2022*
Construction
Beginning
December 2021
Public Meeting
Summer 2023*
Construction
Completion
March 2021
Design Began
*This was updated as of March 2022
Oak Marr Pump Station Rehabilitate – Construction Project
Capital Facilities – Wastewater Design and Construction Division – Collection Branch
Questions & Answers
16
Capital Facilities – Wastewater Design and Construction Division – Collections Branch
Additional Information
For additional information, please contact
www.fairfaxcounty.gov/publicworks
Oak Marr Pump Station Rehabilitate – Construction Project
Christopher Mata, P.E.
703-324-5111, TTY 711
cmata0@fairfaxcounty.gov
Capital Facilities – Wastewater Design and Construction Division – Collections Branch 17
Questions & Answers

More Related Content

What's hot

Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampReston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road WalkwayFairfax County
 
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerOld Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerFairfax County
 
Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018Fairfax County
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Fairfax County
 
Gallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsGallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsFairfax County
 
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
 
Graham Park Plaza Emergency Repair
Graham Park Plaza Emergency RepairGraham Park Plaza Emergency Repair
Graham Park Plaza Emergency RepairFairfax County
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationFairfax County
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main ProjectFairfax County
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof ReplacementFairfax County
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairFairfax County
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County
 
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
 
Jefferson Fire Station #18
Jefferson Fire Station #18Jefferson Fire Station #18
Jefferson Fire Station #18Fairfax County
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Fairfax County
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond ImprovementFairfax County
 

What's hot (20)

Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampReston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerOld Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity Sewer
 
Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1
 
Gallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsGallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue Improvements
 
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)
 
Crisis Care Facility
Crisis Care FacilityCrisis Care Facility
Crisis Care Facility
 
Graham Park Plaza Emergency Repair
Graham Park Plaza Emergency RepairGraham Park Plaza Emergency Repair
Graham Park Plaza Emergency Repair
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main Project
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof Replacement
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016
 
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
 
Jefferson Fire Station #18
Jefferson Fire Station #18Jefferson Fire Station #18
Jefferson Fire Station #18
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond Improvement
 

Similar to Oak Marr Pump Station Rehabilitation – Construction Project

Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Fairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020Fairfax County
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
 
Colfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation ProjectColfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation ProjectFairfax County
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting Fairfax County
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Fairfax County
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveFairfax County
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Fairfax County
 
2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKSTimothy Antos
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park NorthFairfax County
 
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingLakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingFairfax County
 

Similar to Oak Marr Pump Station Rehabilitation – Construction Project (20)

Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
 
Colfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation ProjectColfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation Project
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting
 
Display boards
Display boardsDisplay boards
Display boards
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
 
2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park North
 
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingLakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community Meeting
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 
Reston Fire Station #25
Reston Fire Station #25Reston Fire Station #25
Reston Fire Station #25Fairfax County
 
Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Fairfax County
 
Lakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community MeetingLakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community MeetingFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 
Reston Fire Station #25
Reston Fire Station #25Reston Fire Station #25
Reston Fire Station #25
 
Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22
 
Lakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community MeetingLakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community Meeting
 

Recently uploaded

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

Oak Marr Pump Station Rehabilitation – Construction Project

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Oak Marr Pump Station Rehabilitation – Construction Project Wastewater Project – Virtual Community Meeting Microsoft Teams – December 7, 2021, at 6:30 p.m. Fairfax County Project Manager: Christopher Mata, P.E. Project Engineer: HDR & RK&K December 2021
  • 2. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Agenda 2 1. Project Team Introductions & Attendee Virtual Sign-In 2. Project Location 3. Project Background & Need 4. Study Phase 5. Design Phase 6. Construction Phase 7. Project Schedule 8. Questions and Answers
  • 3. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Project Team Introductions & Attendee Virtual Sign-In 3 • Fairfax County Project Manager: – Christopher Mata, P.E. – Senior Engineer III • Department of Public Works and Environmental Services (DPWES) – Capital Facilities – Wastewater Design and Construction Division – Wastewater Collection Branch • HDR Project Team: – Fady Afif, P.E. – Project Manager – Badana Mohamadi – Project Engineer • RK&K Project Team – Mike Klevenz, P.E. – QA/QC
  • 4. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Virtual Meeting Administrative Items 4 • Attendee Virtual Sign-In (2 options) 1. Private Message me on MS Teams – Name, Property Address, Email, Phone Number 2. Email me @ cmata0@fairfaxcounty.gov - Name, Property Address, Email, Phone Number • To reduce feedback, please remain on mute until the end of the presentation during the Q&A • The chat board on the right-side of your screen is available throughout the presentation
  • 5. Oak Marr Pump Station Rehabilitate – Construction Project Project Location Capital Facilities – Wastewater Design and Construction Division – Collections Branch 5 Project Location Flow Direction Sewer service area and project area
  • 6. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Project Background & Need 6 • Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since. • Aged pump station equipment – pumps, valves, fans, concrete, etc. • This aging equipment has the potential of causing: – Sanitary Sewer Overflows (SSO) – Sewer back-ups into homes – Environmental damages – Maintenance problems
  • 7. Oak Marr Pump Station Rehabilitate – Construction Project Existing Conditions Capital Facilities – Wastewater Design and Construction Division – Collections Branch 7 Incoming Flows Outgoing Flows Pump Station Site
  • 8. Oak Marr Pump Station Rehabilitate – Construction Project Existing Conditions Capital Facilities – Wastewater Design and Construction Division – Collections Branch 8 Incoming Flows Outgoing Flows Pump Station Site EXISTING ACCESS ROAD/ TRAIL EXISTING FENCE EXISTING BUILDING EXISTING MANHOLES EXISTING FUEL TANK
  • 9. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Study Phase 9 • Fall 2020 study: – Evaluated existing conditions – flow analysis, hydraulic assessment, site & equipment assessment. – Alternative analysis and recommendation to rehabilitate the pump stations. • Criteria: Community impacts, schedule, cost, constructability, maintainability, operability, reliability • Recommended Alternative: – Construct a parallel pump station on the same parcel – Repurposing 4 existing below-ground structures & installing 2 new below-ground structures – Pump station building will remain & new generator to be installed outside – Sewer services will not be impacted
  • 10. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Design Phase 10 • Includes Designing: – Pumps and wet-well – Permanent by-pass & meter vault – New enclosed standby generator – Re-routing of sewer force main – Station fence (w/ slats) realignment – Access road repaving and widening in front of the pump station – Adding another gate – Miscellaneous concrete work
  • 11. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Design Phase 11 EXPANDED ACCESS ROAD EXTENDED FENCE TEMPORARY CONSTRUCTION EASEMENT STANDBY GENERATOR NEW UNDERGROUND STRUCTURES TREE REMOVAL Repurposed below- ground structures (x4)
  • 12. Oak Marr Pump Station Rehabilitate – Construction Project Proposed Changes Capital Facilities – Wastewater Design and Construction Division – Collections Branch 12 Proposed Tree Removal These trees to remain Proposed trimming of branches Pond
  • 13. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collections Branch Construction Phase - What to expect 13 • Construction Activity: – Construction entrance off of Elmesmeade Ct. cul-de-sac. – Some construction activity to take place along trail pathway. – Excavation for the new wet well and valve vault – Dewatering until excavation is complete and new structures have been placed – Installing precast structures for wet well and valve vault – Installing emergency generator – Bypass pumping within project site.
  • 14. Oak Marr Pump Station Rehabilitate – Construction Project Construction Phase – Access Through the Community Capital Facilities – Wastewater Design and Construction Division – Collections Branch 14
  • 15. Oak Marr Pump Station Rehabilitate – Construction Project Project Schedule 15 Capital Facilities – Wastewater Design and Construction Division – Collections Branch December 2019 Study Began October 2020 Study Complete January 2022 Anticipate Acquiring all Land Rights Summer 2022* Construction Beginning December 2021 Public Meeting Summer 2023* Construction Completion March 2021 Design Began *This was updated as of March 2022
  • 16. Oak Marr Pump Station Rehabilitate – Construction Project Capital Facilities – Wastewater Design and Construction Division – Collection Branch Questions & Answers 16 Capital Facilities – Wastewater Design and Construction Division – Collections Branch
  • 17. Additional Information For additional information, please contact www.fairfaxcounty.gov/publicworks Oak Marr Pump Station Rehabilitate – Construction Project Christopher Mata, P.E. 703-324-5111, TTY 711 cmata0@fairfaxcounty.gov Capital Facilities – Wastewater Design and Construction Division – Collections Branch 17 Questions & Answers