Jebel Ali Terminal 4, Phase 1
Project Introduction
1
BAM International
URS
Delta Marine Consultants
1. Introduction - Project Location
JA T4 Project Introduction 2
Located in the Jebel Ali Free
Zone just south of Dubai, UAE.
The project site is across from
the Container Terminal 2
2. Project Overview
JA T4 Project Introduction 3
N/KOM
fabricator
Berth 4
RAS LAFFAN
Bridge
Southern
Causeway
Northern
Causeway
Island Road
Quay Wall
and Yard
Area
3.Scope Description
SCOPE OF WORKS
The works include design, procure, construct, testing and commissioning of the
following:
• Demolishing existing structures.
• Dredging the quay basin to -18.00m CD
• 400m Quay wall
• Reclamation and Soil Improvement – Yard and Causeway
• General Cargo Yard with lighting, fencing, paving and services.
• Causeway construction
o Northern Causeway 1800 m
o Southern Causeway with approach 650 m
• 420m Bridge
• 5 km Road works
• Various Administration and Security buildings
JA T4 Project Introduction 4
Quay Wall
JA T4 Project Introduction 5
• 400 m Pre-cast Block Wall
• 2660 units
• Dredging of Foundation & Navigation
Basin
• Rock Backfill
• In situ coping beam
• Quay Wall Furniture
Quay Wall
JA T4 Project Introduction 6
Marine Bridge
• 40m Spans
• 420m long
• Gravity Piers based
on rock foundation
• The Pier will be a
precast reinforced
footings with steel
pile column
• Cast in situ pile
plugs
• AASHTO Girders
• In situ concrete
deck
• ICE required
• Seismic parameters
considered
Marine Bridge
JA T4 Project Introduction 7
Causeway
• North & South
Causeway
• North Causeway
1870 m
• South Causeway
650m
• Causeway width
35m
• Different Armour
types for different
sections
• Soil Replacement &
Soil Improvement
required for
compaction
Causeway
Roadway
JA T4 Project Introduction 8
Roadway
• 5.08 km of roads to be constructed
various
• Single Carriageway for whole
project
• Different zones identified to which
the design parameters are applied.
• Surface build up optimised as per
zone requirements
General Cargo Yard Pavement
JA T4 Project Introduction 9
• Maximum axle load for yard
pavement - Reach Stacker.
• 100mm Concrete pavers for
surfacing
• Drainage requirement – Gullies with
grids to manholes and pipe line. Oil
separators at discharge
General Cargo Yard Pavements
Yard Utilities
JA T4 Project Introduction 10
• Utilities include yard lighting, ducting,
fencing & road markings.
• Lighting by subcontractor – 8 mast
50 lux - 20 lux
• Road markings as per storage bays
• Ducts included for future data
services
Yard Utilities
Buildings
JA T4 Project Introduction 11
• Building Works include
• Administration building (8m X 8m)
• Entrance building (4.5m X 2.5m)
• Security Post
• Toilet block (5.3m X 5.3m)
• Substation building (DEWA
requirements)
Buildings
JA T4 Project Introduction 12
Power Supply
• Max power allowable
200 kW
• Calculated load 164
kW
• Road lighting, yard
lighting, buildings,
miscellaneous
• HV Cable route from CT2
to new substation on island
• LV just for lighting of
southern causeway directly
from CT2 SS
HV & LV Power Supply
4. Overall Work Schedule
13
2014 2015
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Design ( ~8 months)
Precast Operations (8.5 months)
Mobilisation
Yard Area (~10 months)
Buildings (~8 months)
Quay Wall (~13 months)
Revetments (~4 months)
Causeway Works (~11 months)sd
Approach Bridge (~12.5 months)
Road Works (~7 months)
Construction (13 months)
Notice to Commence
Project Completion
Preliminary Works
Marine Works
completion
Dredging (2.5 months)
• Entire Programme 18½months
• Entire Programme based on a 6 day work week with Fridays as rest days
• Dredging Activities are based on a 7 day work week with 24 hours working
• Programme assumes 24 hour working for certain key works / activities
• Design Programme is developed based on Milestone Deliverables
• Since this is a fast track project, a collaborative design review process
needs to be adopted through all the stages
• Overall Design Period is 8 months including approvals
JA T4 Project Introduction 14
4. Overall Programme
5. EIA & Monitoring
JA T4 Project Introduction 15
• EIA Report
The EIA is developed to determine the
impact of the project development to the
surrounding environment
• EIA Process
BAM International appointed DOME
International, an expert in the field to
perform the assessment
This included a survey of the
environmental baseline and provides a
projection of the project’s impact on the
environment
From this assessment a CEMP will be
developed to ensure that the works will
not adversely affect the environment
15

More Related Content

What's hot

Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
RAMS Boards - performance
RAMS Boards - performance RAMS Boards - performance
RAMS Boards - performance RAMS Boards
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Crosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Wael Nafad
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Selected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge CabacoSelected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge CabacoJorge Cabaco
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck finalCrosstown TO
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15VDOT Northern Virginia
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.vragabata
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 

What's hot (20)

Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
RAMS Boards - performance
RAMS Boards - performance RAMS Boards - performance
RAMS Boards - performance
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Selected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge CabacoSelected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge Cabaco
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck final
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 

Viewers also liked

Farmprojectslideshow
FarmprojectslideshowFarmprojectslideshow
Farmprojectslideshowtmlolsen
 
VjayLad_Data_book_online
VjayLad_Data_book_onlineVjayLad_Data_book_online
VjayLad_Data_book_onlineVjay Lad
 
Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?
Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?
Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?kalaidos-gesundheit
 
CAS Management in der Gesundheitswirtschaft – Mentoringprogramm
CAS Management in der Gesundheitswirtschaft – MentoringprogrammCAS Management in der Gesundheitswirtschaft – Mentoringprogramm
CAS Management in der Gesundheitswirtschaft – Mentoringprogrammkalaidos-gesundheit
 
Modern Graphic Design
Modern Graphic DesignModern Graphic Design
Modern Graphic DesignYekaterina22
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanDavid H Moloney
 

Viewers also liked (12)

SBC Triptico 2014_
SBC Triptico 2014_SBC Triptico 2014_
SBC Triptico 2014_
 
Presentation16
Presentation16Presentation16
Presentation16
 
Cross Currents
Cross CurrentsCross Currents
Cross Currents
 
Farmprojectslideshow
FarmprojectslideshowFarmprojectslideshow
Farmprojectslideshow
 
VjayLad_Data_book_online
VjayLad_Data_book_onlineVjayLad_Data_book_online
VjayLad_Data_book_online
 
Anstruther Pier
Anstruther PierAnstruther Pier
Anstruther Pier
 
KG _
KG _KG _
KG _
 
Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?
Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?
Interprofessionelles Ausbilden in Schweden: Zukunft oder Utopie?
 
Dev Ops at Hatena
Dev Ops at HatenaDev Ops at Hatena
Dev Ops at Hatena
 
CAS Management in der Gesundheitswirtschaft – Mentoringprogramm
CAS Management in der Gesundheitswirtschaft – MentoringprogrammCAS Management in der Gesundheitswirtschaft – Mentoringprogramm
CAS Management in der Gesundheitswirtschaft – Mentoringprogramm
 
Modern Graphic Design
Modern Graphic DesignModern Graphic Design
Modern Graphic Design
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 

Similar to JAT4 Kick off Introduction - UAE Navy

Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentationZiad el-Balbisi
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITEDWater Birds (Ali)
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
K.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionK.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionascemiami-dade
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaStephen McKnight
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdfRaviNobleseas
 
KEY NOTE HILLSTA EXTERNAL v2
KEY NOTE HILLSTA EXTERNAL v2KEY NOTE HILLSTA EXTERNAL v2
KEY NOTE HILLSTA EXTERNAL v2Fan Hao
 
Mohamad Taleb updated cv 2016
Mohamad Taleb updated cv 2016Mohamad Taleb updated cv 2016
Mohamad Taleb updated cv 2016Mohamad Taleb
 
David Goodwin Resume 2015 LP
David Goodwin Resume 2015 LPDavid Goodwin Resume 2015 LP
David Goodwin Resume 2015 LPDavid Goodwin
 
Doing more with less - Duncan Whitfield, Smart desalination
Doing more with less - Duncan Whitfield, Smart desalinationDoing more with less - Duncan Whitfield, Smart desalination
Doing more with less - Duncan Whitfield, Smart desalinationWater Industry Alliance
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyThorne & Derrick International
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Copy of Abcede Solidanio (1)
Copy of Abcede Solidanio (1)Copy of Abcede Solidanio (1)
Copy of Abcede Solidanio (1)Abcede Solidanio
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2David Matthew
 
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...Invest Northern Ireland
 
Marina barrage (09/10s2)
Marina barrage (09/10s2)Marina barrage (09/10s2)
Marina barrage (09/10s2)gn022010sem1
 

Similar to JAT4 Kick off Introduction - UAE Navy (20)

Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentation
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Burj khalifa Dubai
Burj khalifa DubaiBurj khalifa Dubai
Burj khalifa Dubai
 
K.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progressionK.2 vogtle units 3 and 4 nuclear development early site construction progression
K.2 vogtle units 3 and 4 nuclear development early site construction progression
 
Mohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oilMohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oil
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf
 
KEY NOTE HILLSTA EXTERNAL v2
KEY NOTE HILLSTA EXTERNAL v2KEY NOTE HILLSTA EXTERNAL v2
KEY NOTE HILLSTA EXTERNAL v2
 
Mohamad Taleb updated cv 2016
Mohamad Taleb updated cv 2016Mohamad Taleb updated cv 2016
Mohamad Taleb updated cv 2016
 
David Goodwin Resume 2015 LP
David Goodwin Resume 2015 LPDavid Goodwin Resume 2015 LP
David Goodwin Resume 2015 LP
 
Doing more with less - Duncan Whitfield, Smart desalination
Doing more with less - Duncan Whitfield, Smart desalinationDoing more with less - Duncan Whitfield, Smart desalination
Doing more with less - Duncan Whitfield, Smart desalination
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Copy of Abcede Solidanio (1)
Copy of Abcede Solidanio (1)Copy of Abcede Solidanio (1)
Copy of Abcede Solidanio (1)
 
David Matthew Resume2
David Matthew Resume2David Matthew Resume2
David Matthew Resume2
 
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
 
slides
slidesslides
slides
 
Marina barrage (09/10s2)
Marina barrage (09/10s2)Marina barrage (09/10s2)
Marina barrage (09/10s2)
 

JAT4 Kick off Introduction - UAE Navy

  • 1. Jebel Ali Terminal 4, Phase 1 Project Introduction 1 BAM International URS Delta Marine Consultants
  • 2. 1. Introduction - Project Location JA T4 Project Introduction 2 Located in the Jebel Ali Free Zone just south of Dubai, UAE. The project site is across from the Container Terminal 2
  • 3. 2. Project Overview JA T4 Project Introduction 3 N/KOM fabricator Berth 4 RAS LAFFAN Bridge Southern Causeway Northern Causeway Island Road Quay Wall and Yard Area
  • 4. 3.Scope Description SCOPE OF WORKS The works include design, procure, construct, testing and commissioning of the following: • Demolishing existing structures. • Dredging the quay basin to -18.00m CD • 400m Quay wall • Reclamation and Soil Improvement – Yard and Causeway • General Cargo Yard with lighting, fencing, paving and services. • Causeway construction o Northern Causeway 1800 m o Southern Causeway with approach 650 m • 420m Bridge • 5 km Road works • Various Administration and Security buildings JA T4 Project Introduction 4
  • 5. Quay Wall JA T4 Project Introduction 5 • 400 m Pre-cast Block Wall • 2660 units • Dredging of Foundation & Navigation Basin • Rock Backfill • In situ coping beam • Quay Wall Furniture Quay Wall
  • 6. JA T4 Project Introduction 6 Marine Bridge • 40m Spans • 420m long • Gravity Piers based on rock foundation • The Pier will be a precast reinforced footings with steel pile column • Cast in situ pile plugs • AASHTO Girders • In situ concrete deck • ICE required • Seismic parameters considered Marine Bridge
  • 7. JA T4 Project Introduction 7 Causeway • North & South Causeway • North Causeway 1870 m • South Causeway 650m • Causeway width 35m • Different Armour types for different sections • Soil Replacement & Soil Improvement required for compaction Causeway
  • 8. Roadway JA T4 Project Introduction 8 Roadway • 5.08 km of roads to be constructed various • Single Carriageway for whole project • Different zones identified to which the design parameters are applied. • Surface build up optimised as per zone requirements
  • 9. General Cargo Yard Pavement JA T4 Project Introduction 9 • Maximum axle load for yard pavement - Reach Stacker. • 100mm Concrete pavers for surfacing • Drainage requirement – Gullies with grids to manholes and pipe line. Oil separators at discharge General Cargo Yard Pavements
  • 10. Yard Utilities JA T4 Project Introduction 10 • Utilities include yard lighting, ducting, fencing & road markings. • Lighting by subcontractor – 8 mast 50 lux - 20 lux • Road markings as per storage bays • Ducts included for future data services Yard Utilities
  • 11. Buildings JA T4 Project Introduction 11 • Building Works include • Administration building (8m X 8m) • Entrance building (4.5m X 2.5m) • Security Post • Toilet block (5.3m X 5.3m) • Substation building (DEWA requirements) Buildings
  • 12. JA T4 Project Introduction 12 Power Supply • Max power allowable 200 kW • Calculated load 164 kW • Road lighting, yard lighting, buildings, miscellaneous • HV Cable route from CT2 to new substation on island • LV just for lighting of southern causeway directly from CT2 SS HV & LV Power Supply
  • 13. 4. Overall Work Schedule 13 2014 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Design ( ~8 months) Precast Operations (8.5 months) Mobilisation Yard Area (~10 months) Buildings (~8 months) Quay Wall (~13 months) Revetments (~4 months) Causeway Works (~11 months)sd Approach Bridge (~12.5 months) Road Works (~7 months) Construction (13 months) Notice to Commence Project Completion Preliminary Works Marine Works completion Dredging (2.5 months)
  • 14. • Entire Programme 18½months • Entire Programme based on a 6 day work week with Fridays as rest days • Dredging Activities are based on a 7 day work week with 24 hours working • Programme assumes 24 hour working for certain key works / activities • Design Programme is developed based on Milestone Deliverables • Since this is a fast track project, a collaborative design review process needs to be adopted through all the stages • Overall Design Period is 8 months including approvals JA T4 Project Introduction 14 4. Overall Programme
  • 15. 5. EIA & Monitoring JA T4 Project Introduction 15 • EIA Report The EIA is developed to determine the impact of the project development to the surrounding environment • EIA Process BAM International appointed DOME International, an expert in the field to perform the assessment This included a survey of the environmental baseline and provides a projection of the project’s impact on the environment From this assessment a CEMP will be developed to ensure that the works will not adversely affect the environment 15