SlideShare a Scribd company logo
1 of 25
The Design, Construction, Testing &
Commissioning of Strategic Reservoirs
(Phase III)
Faisaliah - Jeddah
Letter of Award: 8/1/2014
Site Hand Over Date : 22/06/2014
Completion Date: 23/04/2016
Contract Period: 18 month
Time Extension : 9 months
Contract Value: 451,800,000 SR
Project location: Jeddah City -
Reservoirs area of FAISALAH
Project location:
• Finish the soil improvement work for both tanks 1&3
• Finish of installation and commissioning for the batch plant by the
attendance of the Consultant and receive approval for the submitted
calibration report.
• Finish the design for the tower crane location, casting 1 crane foundation
and finish reinforcement for 3 other cranes foundation and ready to cast ,
finish assembly for 2 tower crane and ready for installation.
• Delivery for 4 tower cranes to the site.
• Excavation is running in area of tank #1 and finish about
50%.
• Submit the recovery time schedule by the new dates after notice of
proceeding the work of the project.
• Delivery for the formwork for the wall, Post tensioning material, pipes
material.
• Finish 95 % of site mobilization.
• Finish the first path of rerouting the fiber optic and delivered the Lab to
NWC, Working is running to finish the second path to delivered the
training center.
Work Situation:
Construction ..1:
Excavation is running in
area of tank #1
Complete removal for
the existing pipe in
area of tank #4
Construction ..2:
Start
assembly
for the
wall
formwork
Internal
External
Construction ..3:
Finish assembly
for 2 tower
cranes
Tower crane #1
Tower crane #2
Construction ..4:
Start dewatering activity
Construction ..5:
Finish the soil improvement work for
tank #3
Construction ..6:
After approval for the soil
improvement for tanks 2 & 4 to be
“Stone Column” technique – as
shown in the photos below
(1)(2)(3)
Construction ..7:
Finish of
installation and
commissioning for
the batch plant by
the attendance of
the Consultant
Construction ..8:
Implementation for
protection trench
Construction ..9:
Start rebar & formwork
forming
Construction ..10:
Finish new
offices for DNGO
site engineers
and main
subcontractors
Construction ..11:
Material
delivery
for
formwork
and post
tension
material
Material Delivery ..1:
Delivery for
pipes 8”
Material Delivery ..2:
Soil improvement work:
• Receive approval for the design report for tank #1.
• Pressure meter test is running to submit the final report for tank #3.
• Receive APPROVAL FOR THE NEW SOIL IMPROVEMENT TECHNIQUE
“Stone Column” for tanks 2 & 4.
Foundation design:
• Submit the foundation design (under revision)
Wall design:
• Receive approval for the wall design.
Piping design:
• Receive approval for the “GRP PIPING SPECIFICATIONS UNDER TANK”
• Receive approval for the submitted method statement for pipe
installation and hydro test.
• Receive approval for the method statement for the dewatering system.
• Received some information for the hydraulic and electrical
design, still some minor information is missing to complete
the required design.
‫التصميم‬ ‫أعمال‬ ‫موقف‬:
• In hand 394 manpower, 76
equipment.
• Manpower are available under the
sponsorship of the company to
complete the work on the project.
ِ‫ب‬ ‫ا‬‫َّل‬ِ‫إ‬ ‫ي‬ِ‫ق‬‫ي‬ِ‫ف‬ ْ‫و‬َ‫ت‬ ‫ا‬َ‫م‬َ‫و‬ْ‫ي‬َ‫ل‬َ‫ع‬ ۚ ِ ‫ا‬‫اَّلل‬ِ‫ه‬
ُ‫أ‬ ِ‫ه‬ْ‫ي‬َ‫ل‬ِ‫إ‬َ‫و‬ ُ‫ت‬ْ‫ل‬‫ا‬‫ك‬َ‫و‬َ‫ت‬ُُ ‫ي‬ِ‫ِن‬
‫العظيم‬ ُ ‫ه‬‫اَّلل‬ ‫صدق‬

More Related Content

What's hot

Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Presentation Sample KAAU
Presentation Sample KAAUPresentation Sample KAAU
Presentation Sample KAAUAbdullah Bakhsh
 
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)amr mahrous
 
D_Chiu senior project draft
D_Chiu senior project draftD_Chiu senior project draft
D_Chiu senior project draftDavid Chiu
 
DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2Ian Kelly
 
Resume - RAVI PRAKASH
Resume - RAVI PRAKASHResume - RAVI PRAKASH
Resume - RAVI PRAKASHRavi Prakash
 
50 MW METRO WIND POWER PROJECT
50 MW METRO WIND POWER PROJECT50 MW METRO WIND POWER PROJECT
50 MW METRO WIND POWER PROJECTTilal Ahmed
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Crosstown TO
 
Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Crosstown TO
 

What's hot (20)

CV - Ahmed Mounir
CV - Ahmed MounirCV - Ahmed Mounir
CV - Ahmed Mounir
 
Montrose BLP
Montrose BLPMontrose BLP
Montrose BLP
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Rashid C_Synopsis_R6
Rashid C_Synopsis_R6Rashid C_Synopsis_R6
Rashid C_Synopsis_R6
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
 
Vedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas ShipsVedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas Ships
 
Vedam Design:- BWTS - Retrofits Services
Vedam Design:-  BWTS - Retrofits Services Vedam Design:-  BWTS - Retrofits Services
Vedam Design:- BWTS - Retrofits Services
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Presentation Sample KAAU
Presentation Sample KAAUPresentation Sample KAAU
Presentation Sample KAAU
 
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
 
D_Chiu senior project draft
D_Chiu senior project draftD_Chiu senior project draft
D_Chiu senior project draft
 
Vedam Design: Dredging Solutions
Vedam Design: Dredging Solutions Vedam Design: Dredging Solutions
Vedam Design: Dredging Solutions
 
DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2
 
Resume - RAVI PRAKASH
Resume - RAVI PRAKASHResume - RAVI PRAKASH
Resume - RAVI PRAKASH
 
50 MW METRO WIND POWER PROJECT
50 MW METRO WIND POWER PROJECT50 MW METRO WIND POWER PROJECT
50 MW METRO WIND POWER PROJECT
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017
 

Viewers also liked

Vogt, Nicholas - Behavioral Analysis of Elite CFB Recruits
Vogt, Nicholas - Behavioral Analysis of Elite CFB RecruitsVogt, Nicholas - Behavioral Analysis of Elite CFB Recruits
Vogt, Nicholas - Behavioral Analysis of Elite CFB RecruitsNicholas Vogt
 
BOB_20arbotreknew_20edit0316
BOB_20arbotreknew_20edit0316BOB_20arbotreknew_20edit0316
BOB_20arbotreknew_20edit0316Scott Walters
 
Medical Imaging of Pneumothorax (PNO)-Walif Chbeir
Medical Imaging of Pneumothorax (PNO)-Walif ChbeirMedical Imaging of Pneumothorax (PNO)-Walif Chbeir
Medical Imaging of Pneumothorax (PNO)-Walif ChbeirWalif Chbeir
 
New aspects of treatment of the breast cancer
New aspects of treatment of the breast cancerNew aspects of treatment of the breast cancer
New aspects of treatment of the breast cancerTetiana Ivanets
 
Normal Labral Variants - Walif Chbeir
Normal Labral Variants - Walif ChbeirNormal Labral Variants - Walif Chbeir
Normal Labral Variants - Walif ChbeirWalif Chbeir
 
Endoscopic methods of treatment of the "early" stomach and esophagus cancer
Endoscopic methods of treatment of the "early" stomach and esophagus cancer Endoscopic methods of treatment of the "early" stomach and esophagus cancer
Endoscopic methods of treatment of the "early" stomach and esophagus cancer Tetiana Ivanets
 

Viewers also liked (12)

Jabir CV
Jabir CVJabir CV
Jabir CV
 
Vogt, Nicholas - Behavioral Analysis of Elite CFB Recruits
Vogt, Nicholas - Behavioral Analysis of Elite CFB RecruitsVogt, Nicholas - Behavioral Analysis of Elite CFB Recruits
Vogt, Nicholas - Behavioral Analysis of Elite CFB Recruits
 
Hanover 300 Community Visioning Recap
Hanover 300 Community Visioning RecapHanover 300 Community Visioning Recap
Hanover 300 Community Visioning Recap
 
01buses
01buses01buses
01buses
 
Membership Report
Membership ReportMembership Report
Membership Report
 
Imagine West Roxbury August 2016
Imagine West Roxbury August 2016Imagine West Roxbury August 2016
Imagine West Roxbury August 2016
 
BOB_20arbotreknew_20edit0316
BOB_20arbotreknew_20edit0316BOB_20arbotreknew_20edit0316
BOB_20arbotreknew_20edit0316
 
Medical Imaging of Pneumothorax (PNO)-Walif Chbeir
Medical Imaging of Pneumothorax (PNO)-Walif ChbeirMedical Imaging of Pneumothorax (PNO)-Walif Chbeir
Medical Imaging of Pneumothorax (PNO)-Walif Chbeir
 
silway-agricultrial silicone surfactant
silway-agricultrial silicone surfactantsilway-agricultrial silicone surfactant
silway-agricultrial silicone surfactant
 
New aspects of treatment of the breast cancer
New aspects of treatment of the breast cancerNew aspects of treatment of the breast cancer
New aspects of treatment of the breast cancer
 
Normal Labral Variants - Walif Chbeir
Normal Labral Variants - Walif ChbeirNormal Labral Variants - Walif Chbeir
Normal Labral Variants - Walif Chbeir
 
Endoscopic methods of treatment of the "early" stomach and esophagus cancer
Endoscopic methods of treatment of the "early" stomach and esophagus cancer Endoscopic methods of treatment of the "early" stomach and esophagus cancer
Endoscopic methods of treatment of the "early" stomach and esophagus cancer
 

Similar to Design, Construction & Commissioning of Strategic Reservoirs in Jeddah

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportDivyesh Mungara
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Boiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailingBoiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailingGaurav Kumar
 
Cv.eslam elsnosy.update
Cv.eslam elsnosy.updateCv.eslam elsnosy.update
Cv.eslam elsnosy.updateEslam Elsnosy
 
CV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.updateCV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.updateEslam Elsnosy
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cvGeoff Chandler
 
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Fairfax County
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsNirav Mistry
 
Husin Asran_Nov'16
Husin Asran_Nov'16Husin Asran_Nov'16
Husin Asran_Nov'16Husin Asran
 

Similar to Design, Construction & Commissioning of Strategic Reservoirs in Jeddah (20)

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
CV Updated
CV UpdatedCV Updated
CV Updated
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
CV
CVCV
CV
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Boiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailingBoiler Supporting structure-Steel detailing
Boiler Supporting structure-Steel detailing
 
AH15019
AH15019AH15019
AH15019
 
Resume -Amarnath
Resume -AmarnathResume -Amarnath
Resume -Amarnath
 
Resume -Amarnath
Resume -AmarnathResume -Amarnath
Resume -Amarnath
 
Cv.eslam elsnosy.update
Cv.eslam elsnosy.updateCv.eslam elsnosy.update
Cv.eslam elsnosy.update
 
CV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.updateCV.Eslam-ELSNOSY.update
CV.Eslam-ELSNOSY.update
 
9C404.5.ppt
9C404.5.ppt9C404.5.ppt
9C404.5.ppt
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cv
 
Muhammad_Aslam_CV
Muhammad_Aslam_CVMuhammad_Aslam_CV
Muhammad_Aslam_CV
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
 
Husin Asran_Nov'16
Husin Asran_Nov'16Husin Asran_Nov'16
Husin Asran_Nov'16
 

Design, Construction & Commissioning of Strategic Reservoirs in Jeddah

  • 1.
  • 2. The Design, Construction, Testing & Commissioning of Strategic Reservoirs (Phase III) Faisaliah - Jeddah
  • 3. Letter of Award: 8/1/2014 Site Hand Over Date : 22/06/2014 Completion Date: 23/04/2016 Contract Period: 18 month Time Extension : 9 months Contract Value: 451,800,000 SR Project location: Jeddah City - Reservoirs area of FAISALAH
  • 5.
  • 6. • Finish the soil improvement work for both tanks 1&3 • Finish of installation and commissioning for the batch plant by the attendance of the Consultant and receive approval for the submitted calibration report. • Finish the design for the tower crane location, casting 1 crane foundation and finish reinforcement for 3 other cranes foundation and ready to cast , finish assembly for 2 tower crane and ready for installation. • Delivery for 4 tower cranes to the site. • Excavation is running in area of tank #1 and finish about 50%. • Submit the recovery time schedule by the new dates after notice of proceeding the work of the project. • Delivery for the formwork for the wall, Post tensioning material, pipes material. • Finish 95 % of site mobilization. • Finish the first path of rerouting the fiber optic and delivered the Lab to NWC, Working is running to finish the second path to delivered the training center. Work Situation:
  • 7. Construction ..1: Excavation is running in area of tank #1
  • 8. Complete removal for the existing pipe in area of tank #4 Construction ..2:
  • 10. Finish assembly for 2 tower cranes Tower crane #1 Tower crane #2 Construction ..4:
  • 12. Finish the soil improvement work for tank #3 Construction ..6:
  • 13. After approval for the soil improvement for tanks 2 & 4 to be “Stone Column” technique – as shown in the photos below (1)(2)(3) Construction ..7:
  • 14. Finish of installation and commissioning for the batch plant by the attendance of the Consultant Construction ..8:
  • 16. Start rebar & formwork forming Construction ..10:
  • 17. Finish new offices for DNGO site engineers and main subcontractors Construction ..11:
  • 18.
  • 21.
  • 22. Soil improvement work: • Receive approval for the design report for tank #1. • Pressure meter test is running to submit the final report for tank #3. • Receive APPROVAL FOR THE NEW SOIL IMPROVEMENT TECHNIQUE “Stone Column” for tanks 2 & 4. Foundation design: • Submit the foundation design (under revision) Wall design: • Receive approval for the wall design. Piping design: • Receive approval for the “GRP PIPING SPECIFICATIONS UNDER TANK” • Receive approval for the submitted method statement for pipe installation and hydro test. • Receive approval for the method statement for the dewatering system. • Received some information for the hydraulic and electrical design, still some minor information is missing to complete the required design. ‫التصميم‬ ‫أعمال‬ ‫موقف‬:
  • 23.
  • 24. • In hand 394 manpower, 76 equipment. • Manpower are available under the sponsorship of the company to complete the work on the project.
  • 25. ِ‫ب‬ ‫ا‬‫َّل‬ِ‫إ‬ ‫ي‬ِ‫ق‬‫ي‬ِ‫ف‬ ْ‫و‬َ‫ت‬ ‫ا‬َ‫م‬َ‫و‬ْ‫ي‬َ‫ل‬َ‫ع‬ ۚ ِ ‫ا‬‫اَّلل‬ِ‫ه‬ ُ‫أ‬ ِ‫ه‬ْ‫ي‬َ‫ل‬ِ‫إ‬َ‫و‬ ُ‫ت‬ْ‫ل‬‫ا‬‫ك‬َ‫و‬َ‫ت‬ُُ ‫ي‬ِ‫ِن‬ ‫العظيم‬ ُ ‫ه‬‫اَّلل‬ ‫صدق‬