SlideShare a Scribd company logo
Steps for planning,
layout, design,
construction and
operation of barrages
The successful working of a barrage depends on a proper selection of the
location, alignment, layout, design and operation of the structure. Hence, the
following aspects have to be carefully looked in Barrage working
•Site investigation and data collection ;
This consists of :-
1- Study of availablemaps and satelliteimageries,
2- Regional and site geology ,
3- Study of foundation strata ,
4- Study of available hydrological data ,
5- Assessment of water needed for diversion ,
6- Effect of the barrageon environment ,
7- Limitationson water withdrawal ,
8- Availability of construction material ,
9- Communication to thesite of work ,
10- Detailed topographical survey ,
11- Hydro-meteorological data ,
12- Sediment concentration data ,
13-Pond survey ,
14- Study of navigation and fish ,
15- Study for power generation , and
16- Study for provision of a rail or a road bridgeacross the barrage.
•Location and alignment selection of the barrage axis ;
The location for a barrageshould be decided on considerationsof suitability for
the
main structure(barrage) and itsappurtenant works, likesilt removing devices
and
intakefor canals(also called canal head regulators). An ideal location would
be that which satisfies the requirementsof all these three components. Some of
the pointsthat have to be kept in mind in selecting an appropriatelocation for a
barrageare as follows:
1- The canal head regulators(or head-works, as they are called) must planned to
be suitableto divert water to a canal for irrigation , by achievea barrageof
reasonableheight. The combined cost of construction of head-worksand that of
the canal fromthe barrageup to thepoint where the water is first used for
irrigation should besmall.
2- The favorablelocation for fixing thesitefor a barrageand canal head- works
may have to be selected due to largequantitiesof rock excavation required.
3- The river reach at theproposed location should be straight, asfar as possible,
so that velocitiesmay be uniformand thesectional area of theriver fairly
constant.
•Planning, layout of the barrage and its
appurtenant structures ;
The location and alignment of thebarrageaxis and that of thecanal head works
may be decided but the other details, likethe width of the barrageand
regulator,
levels crests, lengthsof floors, river training works, pond level , etc. have to be
finalized based on the hydraulic conditionsand geologic characteristicsof the
river
bed and banks of the site. The major
planning aspects are as follows:
1- Design flood ;
The diversion structurehasto be designed in such a way that it
may be able to pass a high flood of sufficient magnitude(called thedesign
flood) safely. It is assumed that when the design flood passes the structureall
the gates of thestructurearefully open and it acts like a weir across the river
with only the obstruction of thepiers between the abutments.
2- Afflux ;
The structurewould cause a rise in the water level on the upstream
compared to level in the downstreamat the timeof passage of a high flood
(equal to or morethan thedesign flood) with all thegates open. This risein
water level on theupstream is called afflux.
3- Free Board ;
When the permissibleafflux is decided, the necessary upstream,
sufficient FreeBoard has to be provided so that there is no overtopping of the
water over the barrageand banks . The Free Board to be provided depends on
the importanceof the structuregenerally, 1.5 to 2 m Free Board abovethe
afflux water level on theupstream is provided.
4- Pond Level ;
Pond level is the level of water, immediately upstreamof the
barrage, which is required to divert a water into the main irrigation canal with
its full supply. The pond level is measured by adding the energy losses
through thehead regulator of canal to the full supply level of thecanal at its
starting point just downstreamof the head regulator .
5- Waterway ;
The waterway, is the clear opening of a barrageto allowflood
flowto pass has a bearing on the afflux. Hence, a maximumlimit placed on
the afflux also limitstheminimumwaterway. Many a times, theLacey’s
stable perimeter for the highest flood dischargeis taken as the basis of
calculating thewaterway , where :-
P = 4.83 Q1/2
Q is the design flood dischargein m3/s for the 50 year frequency flood.
6- River training works ;
This works needs to , guide the river to flow axially
through thebarrage, Proper alignment of guidebunds is essential to ensure
satisfactory flowconditionsin thevicinity of thebarrage. In case of wide
alluvial banks, the length and curvatureat the head of theguide bunds should
be kept such that the worst meander loop is kept away from either the canal
embankment or the approach embankment.
7- Crest levels of spillway ;
The bays of a barragearein the shape of weirs or
spillwaysand the crest levels of these have to be decided correctly. Someof
the bays towardsthe canal end of thebarrageare provided with lower crest
(Figure12) in order to:
• Maintain a clear and well defined river channel towardsthe canal head
regulator .
• Enablethe canal to drawsilt free water from surface only as much as
possible .
• Scour thesilt deposited in front of the head regulator .
8- Spillway bays ;
This is the main body of the barragefor controlling the
dischargesand to raisethe water level to the desired valueto feed the canals.
It is a reinforced concretestructuredesigned as a raft foundation supporting
the weight of thegates, piers and the bridgeaboveto prevent sinking into the
sandy river bed foundation. The Figuresbelowillustratea typical featureand
section of a spillway bay .
9- Cut-off ;
Cut-offs are barriers provided below the floor of the
barrage both at
the upstream and the downstream ends. They may be in
the form of concrete
lungs or steel sheet-piles, The purpose of providing
cutoff is to increases the
flow path and reduces the uplift pressure, that resulting
due to the differential
pressurehead between upstream and downstream
which cause uplift of river
bed particles against the barrage floor , thus the cut-off
ensuring stability to the structure .
10- Silt excluding devices ;
The silt excluding tunnelscarry heavy silt down
the river belowthe under sluices. It is a thin, vertical, curved parallel walled
structuresconstructed of plain or reinforced concrete, it is provided as a
part of the under sluice bays of thebarragefloor in the river pocket adjacent to
the head regulator to minimizesediment entry into thecanal through thehead
regulator. Assuch, theexcludershave to deal with alluvial materialssuch as
boulders, gravel, and sand or silt depending upon theparent bed material and
that which is being transported by theriver.
11- Canal Head Regulator ;
The water that enters acanal is regulated
through a HeadRegulator. A typical cross sectionthrougharegulator is
shown in Figure below. As it is desirable toexclude silt as muchas possible
from the head regulator, the axis of the head regulator is laidat an angle from
90oto 110otothe barrage axis

More Related Content

What's hot

Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
Rajkumar G
 
Canal Fall
Canal FallCanal Fall
Canal Fall
GAURAV. H .TANDON
 
Canal structures
Canal structuresCanal structures
Canal structures
MANJUNATH BORAKANAVAR
 
Bridge components
Bridge componentsBridge components
Bridge components
AratiSavant
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
Divya Vishnoi
 
Canal of design
Canal of designCanal of design
Canal of design
PREMKUMAR
 
Intze tank design
Intze tank designIntze tank design
Intze tank design
Koppolu Abishek
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
sarhad university peshawer
 
Synthetic unit hydrograph
Synthetic unit hydrographSynthetic unit hydrograph
Synthetic unit hydrograph
Satish Taji
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
Animesh Verma
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
SAGAR RAUT
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
Raj Daxini
 
theory of seepage
theory of seepagetheory of seepage
theory of seepage
SANJEEV Wazir
 
Box culvert
Box culvertBox culvert
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
sarojkhadka059
 
Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
JYOTIRANJAN43
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
Aditya Mistry
 
design of weirs
design of weirsdesign of weirs
design of weirs
SANJEEV Wazir
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
Divya Vishnoi
 
Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit Kumar
AmitKumar7069
 

What's hot (20)

Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
Canal structures
Canal structuresCanal structures
Canal structures
 
Bridge components
Bridge componentsBridge components
Bridge components
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
 
Canal of design
Canal of designCanal of design
Canal of design
 
Intze tank design
Intze tank designIntze tank design
Intze tank design
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
 
Synthetic unit hydrograph
Synthetic unit hydrographSynthetic unit hydrograph
Synthetic unit hydrograph
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
theory of seepage
theory of seepagetheory of seepage
theory of seepage
 
Box culvert
Box culvertBox culvert
Box culvert
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
 
Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
 
Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit Kumar
 

Similar to Steps for planning_layout_design_constru

Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Venkataraju Badanapuri
 
Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report
vikas rahangdale
 
Hydraulic structures pdf
Hydraulic structures pdfHydraulic structures pdf
Hydraulic structures pdf
Saqib Imran
 
Diversion Works_Part4_Civil_Engineering.pdf
Diversion Works_Part4_Civil_Engineering.pdfDiversion Works_Part4_Civil_Engineering.pdf
Diversion Works_Part4_Civil_Engineering.pdf
adityajarwal2004
 
Presentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptxPresentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptx
TameneAdugna2
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
Shubham Gautam
 
Lecture 0 design of spilways an overview
Lecture 0 design of spilways an overviewLecture 0 design of spilways an overview
Lecture 0 design of spilways an overview
Addis Ababa Science and Technology University
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
Abdul Sahid
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
dhruvalsu
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
Saqib Imran
 
Ch-3.pptx
Ch-3.pptxCh-3.pptx
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
abdqadeer
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
brijlata sharma
 
Geological factor for canal alignment
Geological factor for canal alignmentGeological factor for canal alignment
Geological factor for canal alignment
Pramoda Raj
 
Ijciet 10 02_037
Ijciet 10 02_037Ijciet 10 02_037
Ijciet 10 02_037
IAEME Publication
 
UNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptxUNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptx
Divs97
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
KhawarSakhani
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork
Jay Khoradiya
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
Damalla Rams
 

Similar to Steps for planning_layout_design_constru (20)

Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
 
Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report Barrage Gate Operation Rules and Silt Control Devices Report
Barrage Gate Operation Rules and Silt Control Devices Report
 
Hydraulic structures pdf
Hydraulic structures pdfHydraulic structures pdf
Hydraulic structures pdf
 
Diversion Works_Part4_Civil_Engineering.pdf
Diversion Works_Part4_Civil_Engineering.pdfDiversion Works_Part4_Civil_Engineering.pdf
Diversion Works_Part4_Civil_Engineering.pdf
 
Dams
DamsDams
Dams
 
Presentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptxPresentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptx
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Lecture 0 design of spilways an overview
Lecture 0 design of spilways an overviewLecture 0 design of spilways an overview
Lecture 0 design of spilways an overview
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
 
Ch-3.pptx
Ch-3.pptxCh-3.pptx
Ch-3.pptx
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Geological factor for canal alignment
Geological factor for canal alignmentGeological factor for canal alignment
Geological factor for canal alignment
 
Ijciet 10 02_037
Ijciet 10 02_037Ijciet 10 02_037
Ijciet 10 02_037
 
UNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptxUNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptx
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 

Recently uploaded

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 

Recently uploaded (20)

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 

Steps for planning_layout_design_constru

  • 1. Steps for planning, layout, design, construction and operation of barrages The successful working of a barrage depends on a proper selection of the location, alignment, layout, design and operation of the structure. Hence, the following aspects have to be carefully looked in Barrage working •Site investigation and data collection ; This consists of :- 1- Study of availablemaps and satelliteimageries, 2- Regional and site geology , 3- Study of foundation strata , 4- Study of available hydrological data , 5- Assessment of water needed for diversion , 6- Effect of the barrageon environment ,
  • 2. 7- Limitationson water withdrawal , 8- Availability of construction material , 9- Communication to thesite of work , 10- Detailed topographical survey , 11- Hydro-meteorological data , 12- Sediment concentration data , 13-Pond survey , 14- Study of navigation and fish , 15- Study for power generation , and 16- Study for provision of a rail or a road bridgeacross the barrage. •Location and alignment selection of the barrage axis ; The location for a barrageshould be decided on considerationsof suitability for the main structure(barrage) and itsappurtenant works, likesilt removing devices and intakefor canals(also called canal head regulators). An ideal location would be that which satisfies the requirementsof all these three components. Some of the pointsthat have to be kept in mind in selecting an appropriatelocation for a barrageare as follows: 1- The canal head regulators(or head-works, as they are called) must planned to
  • 3. be suitableto divert water to a canal for irrigation , by achievea barrageof reasonableheight. The combined cost of construction of head-worksand that of the canal fromthe barrageup to thepoint where the water is first used for irrigation should besmall. 2- The favorablelocation for fixing thesitefor a barrageand canal head- works may have to be selected due to largequantitiesof rock excavation required. 3- The river reach at theproposed location should be straight, asfar as possible, so that velocitiesmay be uniformand thesectional area of theriver fairly constant. •Planning, layout of the barrage and its appurtenant structures ; The location and alignment of thebarrageaxis and that of thecanal head works may be decided but the other details, likethe width of the barrageand regulator, levels crests, lengthsof floors, river training works, pond level , etc. have to be finalized based on the hydraulic conditionsand geologic characteristicsof the river
  • 4. bed and banks of the site. The major planning aspects are as follows: 1- Design flood ; The diversion structurehasto be designed in such a way that it may be able to pass a high flood of sufficient magnitude(called thedesign flood) safely. It is assumed that when the design flood passes the structureall the gates of thestructurearefully open and it acts like a weir across the river with only the obstruction of thepiers between the abutments.
  • 5. 2- Afflux ; The structurewould cause a rise in the water level on the upstream compared to level in the downstreamat the timeof passage of a high flood (equal to or morethan thedesign flood) with all thegates open. This risein water level on theupstream is called afflux. 3- Free Board ; When the permissibleafflux is decided, the necessary upstream, sufficient FreeBoard has to be provided so that there is no overtopping of the water over the barrageand banks . The Free Board to be provided depends on the importanceof the structuregenerally, 1.5 to 2 m Free Board abovethe
  • 6. afflux water level on theupstream is provided. 4- Pond Level ; Pond level is the level of water, immediately upstreamof the barrage, which is required to divert a water into the main irrigation canal with its full supply. The pond level is measured by adding the energy losses through thehead regulator of canal to the full supply level of thecanal at its starting point just downstreamof the head regulator . 5- Waterway ; The waterway, is the clear opening of a barrageto allowflood flowto pass has a bearing on the afflux. Hence, a maximumlimit placed on the afflux also limitstheminimumwaterway. Many a times, theLacey’s stable perimeter for the highest flood dischargeis taken as the basis of
  • 7. calculating thewaterway , where :- P = 4.83 Q1/2 Q is the design flood dischargein m3/s for the 50 year frequency flood. 6- River training works ; This works needs to , guide the river to flow axially through thebarrage, Proper alignment of guidebunds is essential to ensure satisfactory flowconditionsin thevicinity of thebarrage. In case of wide alluvial banks, the length and curvatureat the head of theguide bunds should be kept such that the worst meander loop is kept away from either the canal embankment or the approach embankment.
  • 8. 7- Crest levels of spillway ; The bays of a barragearein the shape of weirs or spillwaysand the crest levels of these have to be decided correctly. Someof the bays towardsthe canal end of thebarrageare provided with lower crest (Figure12) in order to: • Maintain a clear and well defined river channel towardsthe canal head regulator .
  • 9. • Enablethe canal to drawsilt free water from surface only as much as possible . • Scour thesilt deposited in front of the head regulator . 8- Spillway bays ; This is the main body of the barragefor controlling the dischargesand to raisethe water level to the desired valueto feed the canals. It is a reinforced concretestructuredesigned as a raft foundation supporting the weight of thegates, piers and the bridgeaboveto prevent sinking into the sandy river bed foundation. The Figuresbelowillustratea typical featureand
  • 10. section of a spillway bay .
  • 11. 9- Cut-off ; Cut-offs are barriers provided below the floor of the barrage both at the upstream and the downstream ends. They may be in the form of concrete lungs or steel sheet-piles, The purpose of providing cutoff is to increases the flow path and reduces the uplift pressure, that resulting due to the differential pressurehead between upstream and downstream which cause uplift of river bed particles against the barrage floor , thus the cut-off ensuring stability to the structure .
  • 12. 10- Silt excluding devices ; The silt excluding tunnelscarry heavy silt down the river belowthe under sluices. It is a thin, vertical, curved parallel walled structuresconstructed of plain or reinforced concrete, it is provided as a part of the under sluice bays of thebarragefloor in the river pocket adjacent to the head regulator to minimizesediment entry into thecanal through thehead regulator. Assuch, theexcludershave to deal with alluvial materialssuch as boulders, gravel, and sand or silt depending upon theparent bed material and that which is being transported by theriver.
  • 13. 11- Canal Head Regulator ; The water that enters acanal is regulated through a HeadRegulator. A typical cross sectionthrougharegulator is shown in Figure below. As it is desirable toexclude silt as muchas possible from the head regulator, the axis of the head regulator is laidat an angle from