SlideShare a Scribd company logo
Stephen Music
Work Experience
Kenny Construction
Area Construction Manager June 2016-Present
• Responsible for environmental and engineering walk downs and creating e@s plans and planning
profiles for structure types that will accommodate work to be done.
• Supporting Kenny and PPL team at whatever was needed to get plans together and execute full
scope of work.
• Advised on specialty contracts such as transmission foundations Helicopter work and all methods
of energized transmission work including but not limited to bare hand method, hotstick method,
robotic arms, and rubber glove methods.
• Helped monitor job milestones made sure contractor stayed on schedule followed safety rules
and built to spec as engineering called for?
Excelon (Comed) January2016- June
2016
Area Construction Manager
• Managing anywhere from 1 all the way up to 25 crews.
• Responsible to make sure crews follow Excelon/Comed safety rules.
• Maintaining schedule and budget on any types of jobs from secondary distribution voltage all the
way to transmission voltage underground and overhread.
• Supporting project team in planning, engineering, getting all plans and permits together and
fulfilling completions all the way from ground breaking to restoration.
Coastal Power and Electric April 2015 –
January 2016
Site Manager
• Managing a 60 man bid crew on day to day operations including but not limited to: setting up
equipment rentals, ordering tools, inspecting work done by foreman and craft labor for accuracy
to engineering drawings.
• Primary responsibilities are Quality Assurance and site safety
• Supporting Project Managers with setting up and maintaining the schedule and budget.
• Wet and dry Transmission line construction, 345KV
Blattner Energy September 2014 - March 2015
Site Manager
• Managing a 60 man bid crew focusing on: managing man power hours, total budget, and
material purchasing
• Managing and maintaining environmental health & safety methods and keeping the project
compliant
• Scheduling of day to day work included monthly outlook meetings with upper management and
owners of utility clients
• Mentoring foreman to move into superintendent roles
Cianbro corporation 2013 - August 2014
Site Manager
• Cianbro was responsible for a 115 kv line and 2 substations for a private company; one was a
switchyard to stepdown 230kv to 115 kv; the other was a switchyard for 115kv transfer to 34.5 kv
lines.
• Manage day to operations of crews including: scheduling sub-contractors, planning, and
executing work
• Manage budget and maintaining a safe work environment and environmental controls.
Air2 llc 2012 - 2013
Aerial Foreman
• Full helicopter support of construction of maintenance from distribution lines to 500 kv including
long line work board and skid work ladder work and bare hand work on energized transmission
lines.
Pike Electric 2011 - 2012
Site Manager
• I maintain the day to day operations of a 10 man transmission crew.
• Was responsible for overseeing the setting caissons, poles, pull out old wire, installing new wire
wreck out old structures and maintaining a safety conscious job site.
• I scheduled hot line tags and dead line clearances
• I managed material supply, time sheets, and ordering of materials needed.
Cianbro Corporation 2009 - 2011
Superintendent
• I manage a 12 to 15 man crew in day to day operations including but not limited to equipment
mobilization and spotting for a full transmission construction job.
• Primarily responsible for managing subcontractors including quality assurance of line work
• I also planned all safety actions put into place during the day and environmental cleanup at the
end of the job from day to day.
• I scheduled all sub-contractor work as well.
Notable Projects
• Capx2020 for xcel energy
• Mprp for Central Maine Power
• Sceg upgrade to transmission infrastructure from the addition of nuclear units which included
nearly 300 miles of double circuit bundle 230 kv with 115kv under build
OSHA 10 Certified

More Related Content

What's hot

Projects - consulting engineer
Projects - consulting engineerProjects - consulting engineer
Projects - consulting engineerChris Owen
 
Lead HRSG Commissioning TFA
Lead HRSG Commissioning TFALead HRSG Commissioning TFA
Lead HRSG Commissioning TFA
AhmedAttia136
 
Airservices
Airservices Airservices
Airservices
Od Solutions
 
DEMOBILIZATION PLAN.docx
DEMOBILIZATION PLAN.docxDEMOBILIZATION PLAN.docx
DEMOBILIZATION PLAN.docx
THEOPHILUSATOFLETCHE
 
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
Crosstown TO
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Crosstown TO
 
Stevan Hicks Short
Stevan Hicks ShortStevan Hicks Short
Stevan Hicks ShortStevan Hicks
 
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Crosstown TO
 
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Crosstown TO
 
Sandeep RESUME new
Sandeep RESUME newSandeep RESUME new
Sandeep RESUME newSandeep Kn
 

What's hot (20)

Resume
ResumeResume
Resume
 
Projects - consulting engineer
Projects - consulting engineerProjects - consulting engineer
Projects - consulting engineer
 
Lead HRSG Commissioning TFA
Lead HRSG Commissioning TFALead HRSG Commissioning TFA
Lead HRSG Commissioning TFA
 
Airservices
Airservices Airservices
Airservices
 
DEMOBILIZATION PLAN.docx
DEMOBILIZATION PLAN.docxDEMOBILIZATION PLAN.docx
DEMOBILIZATION PLAN.docx
 
ronald coventry cv n5
ronald coventry cv n5ronald coventry cv n5
ronald coventry cv n5
 
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
 
Glenn updated cv
Glenn updated cvGlenn updated cv
Glenn updated cv
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Resume with System 3
Resume with System 3Resume with System 3
Resume with System 3
 
Ben-Coleman II
Ben-Coleman IIBen-Coleman II
Ben-Coleman II
 
[Belle] Resume
[Belle] Resume[Belle] Resume
[Belle] Resume
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
Stevan Hicks Short
Stevan Hicks ShortStevan Hicks Short
Stevan Hicks Short
 
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
 
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
Sandeep RESUME new
Sandeep RESUME newSandeep RESUME new
Sandeep RESUME new
 

Similar to Stephen music resume seeking new opportunities

Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cvGeoff Chandler
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302Rhod Mayers
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams
 
Cv For Sitemanager
Cv For SitemanagerCv For Sitemanager
Cv For Sitemanagermathavan2008
 
TCF Resume UPDATED 05 APRIL, 2015
TCF Resume UPDATED 05 APRIL, 2015TCF Resume UPDATED 05 APRIL, 2015
TCF Resume UPDATED 05 APRIL, 2015Teddy Fernando
 
Wellington Shumba CV projects
Wellington Shumba CV projectsWellington Shumba CV projects
Wellington Shumba CV projectsweshumba
 
William Cooper Resume Rev
William Cooper Resume RevWilliam Cooper Resume Rev
William Cooper Resume RevWscooper
 
Current Public Resume
Current Public ResumeCurrent Public Resume
Current Public ResumeLee Riopel
 
Saqib Shahzad CV updated
Saqib Shahzad CV updatedSaqib Shahzad CV updated
Saqib Shahzad CV updatedSaqib Shahzad
 

Similar to Stephen music resume seeking new opportunities (20)

Christopher Kinnon Resume
Christopher Kinnon ResumeChristopher Kinnon Resume
Christopher Kinnon Resume
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cv
 
MATHAVAN LATEST CV ON AUG 2015
MATHAVAN LATEST CV ON AUG 2015MATHAVAN LATEST CV ON AUG 2015
MATHAVAN LATEST CV ON AUG 2015
 
Stephen Cordova Final CV
Stephen Cordova Final CVStephen Cordova Final CV
Stephen Cordova Final CV
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017
 
Project Experience
Project ExperienceProject Experience
Project Experience
 
Henrys Resume 2016 Q3
Henrys Resume 2016 Q3Henrys Resume 2016 Q3
Henrys Resume 2016 Q3
 
Cv For Sitemanager
Cv For SitemanagerCv For Sitemanager
Cv For Sitemanager
 
dean resume (1)
dean resume (1)dean resume (1)
dean resume (1)
 
RSRynkiewicz2015r
RSRynkiewicz2015rRSRynkiewicz2015r
RSRynkiewicz2015r
 
TCF Resume UPDATED 05 APRIL, 2015
TCF Resume UPDATED 05 APRIL, 2015TCF Resume UPDATED 05 APRIL, 2015
TCF Resume UPDATED 05 APRIL, 2015
 
Wellington Shumba CV projects
Wellington Shumba CV projectsWellington Shumba CV projects
Wellington Shumba CV projects
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
rcallueng resume
rcallueng resumercallueng resume
rcallueng resume
 
William Cooper Resume Rev
William Cooper Resume RevWilliam Cooper Resume Rev
William Cooper Resume Rev
 
Current Public Resume
Current Public ResumeCurrent Public Resume
Current Public Resume
 
Saqib Shahzad CV updated
Saqib Shahzad CV updatedSaqib Shahzad CV updated
Saqib Shahzad CV updated
 
CV -mosleh
CV -moslehCV -mosleh
CV -mosleh
 

Recently uploaded

Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...
Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...
Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...
SocialHRCamp
 
Periodical - Employee Spotlight Kathryn Hillenburg
Periodical - Employee Spotlight Kathryn HillenburgPeriodical - Employee Spotlight Kathryn Hillenburg
Periodical - Employee Spotlight Kathryn Hillenburg
marketing659039
 
原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样
原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样
原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样
4y5yl5qy
 
Rally Webinar Recruitment Marketing for High Volume Hiring.pdf
Rally Webinar Recruitment Marketing for High Volume Hiring.pdfRally Webinar Recruitment Marketing for High Volume Hiring.pdf
Rally Webinar Recruitment Marketing for High Volume Hiring.pdf
Rally Recruitment Marketing
 
Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...
Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...
Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...
SocialHRCamp
 
一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样
一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样
一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样
6budtn3l
 
1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样
1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样
1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样
4y5yl5qy
 
CI or FS Poly Cleared Job Fair Handbook | June 6
CI or FS Poly Cleared Job Fair Handbook | June 6CI or FS Poly Cleared Job Fair Handbook | June 6
CI or FS Poly Cleared Job Fair Handbook | June 6
ClearedJobs.Net
 

Recently uploaded (8)

Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...
Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...
Becoming Relentlessly Human-Centred in an AI World - Erin Patchell - SocialHR...
 
Periodical - Employee Spotlight Kathryn Hillenburg
Periodical - Employee Spotlight Kathryn HillenburgPeriodical - Employee Spotlight Kathryn Hillenburg
Periodical - Employee Spotlight Kathryn Hillenburg
 
原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样
原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样
原版定制(ucdavis毕业证书)加州大学戴维斯分校毕业证学位证书电子版原版一模一样
 
Rally Webinar Recruitment Marketing for High Volume Hiring.pdf
Rally Webinar Recruitment Marketing for High Volume Hiring.pdfRally Webinar Recruitment Marketing for High Volume Hiring.pdf
Rally Webinar Recruitment Marketing for High Volume Hiring.pdf
 
Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...
Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...
Accelerating AI Integration with Collaborative Learning - Kinga Petrovai - So...
 
一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样
一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样
一模一样(unh毕业证书)美国新罕布什尔大学毕业证学位证书案例原版一模一样
 
1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样
1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样
1比1仿制(csun毕业证书)加州州立大学北岭分校毕业证硕士文凭原版一模一样
 
CI or FS Poly Cleared Job Fair Handbook | June 6
CI or FS Poly Cleared Job Fair Handbook | June 6CI or FS Poly Cleared Job Fair Handbook | June 6
CI or FS Poly Cleared Job Fair Handbook | June 6
 

Stephen music resume seeking new opportunities

  • 1. Stephen Music Work Experience Kenny Construction Area Construction Manager June 2016-Present • Responsible for environmental and engineering walk downs and creating e@s plans and planning profiles for structure types that will accommodate work to be done. • Supporting Kenny and PPL team at whatever was needed to get plans together and execute full scope of work. • Advised on specialty contracts such as transmission foundations Helicopter work and all methods of energized transmission work including but not limited to bare hand method, hotstick method, robotic arms, and rubber glove methods. • Helped monitor job milestones made sure contractor stayed on schedule followed safety rules and built to spec as engineering called for? Excelon (Comed) January2016- June 2016 Area Construction Manager • Managing anywhere from 1 all the way up to 25 crews. • Responsible to make sure crews follow Excelon/Comed safety rules. • Maintaining schedule and budget on any types of jobs from secondary distribution voltage all the way to transmission voltage underground and overhread. • Supporting project team in planning, engineering, getting all plans and permits together and fulfilling completions all the way from ground breaking to restoration. Coastal Power and Electric April 2015 – January 2016 Site Manager • Managing a 60 man bid crew on day to day operations including but not limited to: setting up equipment rentals, ordering tools, inspecting work done by foreman and craft labor for accuracy to engineering drawings. • Primary responsibilities are Quality Assurance and site safety • Supporting Project Managers with setting up and maintaining the schedule and budget. • Wet and dry Transmission line construction, 345KV Blattner Energy September 2014 - March 2015 Site Manager • Managing a 60 man bid crew focusing on: managing man power hours, total budget, and material purchasing • Managing and maintaining environmental health & safety methods and keeping the project compliant • Scheduling of day to day work included monthly outlook meetings with upper management and owners of utility clients • Mentoring foreman to move into superintendent roles Cianbro corporation 2013 - August 2014 Site Manager • Cianbro was responsible for a 115 kv line and 2 substations for a private company; one was a switchyard to stepdown 230kv to 115 kv; the other was a switchyard for 115kv transfer to 34.5 kv lines.
  • 2. • Manage day to operations of crews including: scheduling sub-contractors, planning, and executing work • Manage budget and maintaining a safe work environment and environmental controls. Air2 llc 2012 - 2013 Aerial Foreman • Full helicopter support of construction of maintenance from distribution lines to 500 kv including long line work board and skid work ladder work and bare hand work on energized transmission lines. Pike Electric 2011 - 2012 Site Manager • I maintain the day to day operations of a 10 man transmission crew. • Was responsible for overseeing the setting caissons, poles, pull out old wire, installing new wire wreck out old structures and maintaining a safety conscious job site. • I scheduled hot line tags and dead line clearances • I managed material supply, time sheets, and ordering of materials needed. Cianbro Corporation 2009 - 2011 Superintendent • I manage a 12 to 15 man crew in day to day operations including but not limited to equipment mobilization and spotting for a full transmission construction job. • Primarily responsible for managing subcontractors including quality assurance of line work • I also planned all safety actions put into place during the day and environmental cleanup at the end of the job from day to day. • I scheduled all sub-contractor work as well. Notable Projects • Capx2020 for xcel energy • Mprp for Central Maine Power • Sceg upgrade to transmission infrastructure from the addition of nuclear units which included nearly 300 miles of double circuit bundle 230 kv with 115kv under build OSHA 10 Certified