SlideShare a Scribd company logo
PROJECTS: CONSULTING ENGINEER
Transco compression station environmental impact survey (2003)
Objective: Deliver surveys of four of Transco’s 80 bar.g compression stations, within manhour
budget and to client satisfaction. Identify main environmental impacts, and design
cost-effective mitigation measures.
Achieved: Surveys delivered on time, and with novel (yet practical) impact reduction
solutions.
Role: Lead engineer.
Power station fuel compressor station (2002 – 2003)
Objective: Deliver a natural gas compression station, to extremely demanding client
specifications, for GE’s first Frame 9H gas turbine installation.
Achieved: Station built to budget and on time. Demonstrated, by site test that the
installation met all the specifications: 10-second response time, +/-0.5% pressure
stability, <65dBA noise, and much else.
Role: Leading mechanical, process, instrumentation, and civils design team. Procure
compressors, from specification through vendor coordination and to final on-site
testing.
Power station cooling tower rectification (2002)
Objective: Find a minimum-cost method to rectify a mal-performing cooling tower, nominally
80MW capacity.
Achieved: Successfully diagnosed the cause of the performance shortfall by site survey and
detailed measurement. Process design and detailed design of rectification
measures, including fluid flow analysis both with and without rectification.
Subsequent tests in the rectified condition showed performance to specification.
Role: Lead mechanical engineer.
Hospital clinical waste incinerator (2002)
Objective: Meet client’s need to bring existing, but not commissioned, waste incinerator to a
safe-to-operate condition, and meet client’s contractual obligations. Minimise cost
and schedule. Close client’s contract as speedily and as economically as possible.
Achieved: Satisfied client, very content with the support they got at the end of an extremely
difficult contract. Extensive survey of existing installation, including HAZOP and
detailed sizing calculations. Rectifications designed and costed, contractors
identified, and works initiated.
Role: Project leader. Principal consultant and site representative.
Offshore substructure (1999 – 2000)
Objective: Deliver mechanical design for a concrete gravity substructure for Shell.
Achieved: Successful installation of the substructure, within 2m of required position.
Excellent revenue for employer, 2% under budget and on time.
Role: Lead mechanical engineer, for a team of up to three engineers. Representative for
the design team in the client’s offices, spearheading technical and commercial
negotiations.
Expert witness report for the collapse of a steam boiler (1999)
Objective: Improve client’s position in the negotiation of damages claim following equipment
failure.
Achieved: Identified cause and assigned fault, delivered expert witness report, provided
technical input to “without prejudice” negotiations. Client’s position very
materially improved, by being able to dismiss other party’s technical investigation.
Role: Mechanical engineer.
Dry dock mechanical services design and implementation (1999)
Objective: Refurbish the mechanical services to Nigg dry dock, to enable construction of large-
scale concrete gravity sub-structures (“CGS’s”) in this previously dis-used facility.
Achieved: Full site survey of existing installations, upon which to base lowest-cost
recommendations and design of the refurbishment. Procurement, installation, and
testing of the refurbishment, including 2MW of de-watering pump capacity.
Leading to satisfied client, and later use for the successful construction of two
CGS’s.
Role: Lead mechanical engineer.
Test of Siemens oil-fuelled gas turbine installation (1998)
Objective: Protect the client’s interests by full test and acceptance of a combined cycle power
station at Shenzen, China.
Achieved: Audited and approved the test protocol, witnessed vendor tests, carried out
normalisation and error assessment of results, provided recommendation for
acceptance following an agreed re-statement of the facility’s performance.
Role: Mechanical engineer.
Brewery, China (1997 – 1998)
Objective: Deliver the design for a coal-fired steam system to a 100,000hl/year brewery, at
minimum cost and to an extremely tight schedule.
Achieved: Optioneering and design of a system based on locally-sourced equipment, over-
coming the challenges of highly variable demand on a coal-fired boiler. System
subsequently implemented and successfully commissioned, within schedule and
8% under budget.
Role: Lead mechanical engineer.
Clinical waste incinerator delivery (1993 – 1994)
Objective: Deliver a 1T/hr clinical waste incinerator, with waste heat recovery and integrated
power generation – a UK-first.
Achieved: Delivery of this complex system, within an extremely tight site (footprint >80% of
site area), and to strict noise abatement requirements. Demonstrated compliance
with all regulatory and client requirements by n-site test.
Role: Followed the project from inception to final commissioning, in various roles. Site
identification, concept design, contractor selection, detailed design, site
supervision, commissioning.
Energy surveys (1993 – 2000)
Objective: Find opportunities to reduce the client’s energy consumption, by detailed site
survey.
Achieved: Too many surveys carried out to list them individually. Invariably found
opportunities to improve the client’s bottom line. My special contribution was the
use of fundamental engineering principles, plus a sense of what is practical, to offer
solutions that delight the client by their low capital cost.
Role: Energy specialist. Facilities surveyed include breweries, a chocolate factory, clinical
waste incineration facilities, high-rise commercial buildings, the National Physics
Laboratory, and district heating schemes.

More Related Content

What's hot

Resume - RAVI PRAKASH
Resume - RAVI PRAKASHResume - RAVI PRAKASH
Resume - RAVI PRAKASHRavi Prakash
 
Stephen music resume seeking new opportunities
Stephen music resume seeking new opportunitiesStephen music resume seeking new opportunities
Stephen music resume seeking new opportunities
Stephen Music
 
Roger Beck resume
Roger Beck resumeRoger Beck resume
Roger Beck resume
Roger Beck
 
Sajesh CV
Sajesh CVSajesh CV
Sajesh CV
Sajesh Kumar
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
Hosam Salah
 
guptapranay20072016
guptapranay20072016guptapranay20072016
guptapranay20072016Pranay Gupta
 
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015Partha Gorain
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
Mohamad Safarudin
 
Richard Heggen - 1 Page CV
Richard Heggen - 1 Page CVRichard Heggen - 1 Page CV
Richard Heggen - 1 Page CVRichard Heggen
 
CV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKURCV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKURshashi thakur
 
M.s. resume 290817
M.s. resume 290817M.s. resume 290817
M.s. resume 290817
Mohamad Safarudin
 
D Snyder Resume Power Point Presentation
D Snyder Resume Power Point PresentationD Snyder Resume Power Point Presentation
D Snyder Resume Power Point Presentation
dennissnyder54
 
G.N Engineering
G.N EngineeringG.N Engineering
G.N Engineering
guest90ce1a3
 

What's hot (19)

Abhishek Resume
Abhishek ResumeAbhishek Resume
Abhishek Resume
 
Resume - RAVI PRAKASH
Resume - RAVI PRAKASHResume - RAVI PRAKASH
Resume - RAVI PRAKASH
 
Stephen music resume seeking new opportunities
Stephen music resume seeking new opportunitiesStephen music resume seeking new opportunities
Stephen music resume seeking new opportunities
 
5. Brochure JPMC
5. Brochure JPMC5. Brochure JPMC
5. Brochure JPMC
 
Roger Beck resume
Roger Beck resumeRoger Beck resume
Roger Beck resume
 
Sajesh CV
Sajesh CVSajesh CV
Sajesh CV
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
 
guptapranay20072016
guptapranay20072016guptapranay20072016
guptapranay20072016
 
paramasivam resume
paramasivam resume paramasivam resume
paramasivam resume
 
jahangir
jahangirjahangir
jahangir
 
Yasser Hatem CV
Yasser Hatem CVYasser Hatem CV
Yasser Hatem CV
 
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
 
Mechanical Hvac INMA 3117
Mechanical Hvac INMA 3117Mechanical Hvac INMA 3117
Mechanical Hvac INMA 3117
 
Richard Heggen - 1 Page CV
Richard Heggen - 1 Page CVRichard Heggen - 1 Page CV
Richard Heggen - 1 Page CV
 
CV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKURCV- SHASHI KANT THAKUR
CV- SHASHI KANT THAKUR
 
M.s. resume 290817
M.s. resume 290817M.s. resume 290817
M.s. resume 290817
 
D Snyder Resume Power Point Presentation
D Snyder Resume Power Point PresentationD Snyder Resume Power Point Presentation
D Snyder Resume Power Point Presentation
 
G.N Engineering
G.N EngineeringG.N Engineering
G.N Engineering
 

Viewers also liked

DV Biologics Product Menu
DV Biologics Product MenuDV Biologics Product Menu
DV Biologics Product Menu
◂ Justin (M) Gaines ▸
 
The Grail Message - Volume 1, Lecture 4 - Morality
The Grail Message - Volume 1, Lecture 4 - Morality The Grail Message - Volume 1, Lecture 4 - Morality
The Grail Message - Volume 1, Lecture 4 - Morality
The Grail Movement
 
Instalacion de sistemas operativos windows y linux
Instalacion de sistemas operativos windows y linuxInstalacion de sistemas operativos windows y linux
Instalacion de sistemas operativos windows y linux
supernova2015
 
The Transformation and Future of Health Care | Mary Tolan
The Transformation and Future of Health Care  |  Mary TolanThe Transformation and Future of Health Care  |  Mary Tolan
The Transformation and Future of Health Care | Mary TolanMary Tolan
 
Matt cirriculum vitae
Matt cirriculum vitaeMatt cirriculum vitae
Matt cirriculum vitaeMATTHEW QUINN
 
Notification main june2015
Notification main june2015Notification main june2015
Notification main june2015
Dharminder Chahal
 
Malta 15 min presentation final.ppt
Malta 15 min presentation   final.pptMalta 15 min presentation   final.ppt
Malta 15 min presentation final.ppt
InboundMuse
 
Egyptian mummy part 2
Egyptian mummy part 2Egyptian mummy part 2
Egyptian mummy part 2
mebarbour
 
00 aprenda a dibujar
00 aprenda a dibujar00 aprenda a dibujar
00 aprenda a dibujar
Tommy Pain
 
Environmental responsibility
Environmental responsibilityEnvironmental responsibility
Environmental responsibility
Mike Strachan
 

Viewers also liked (14)

DV Biologics Product Menu
DV Biologics Product MenuDV Biologics Product Menu
DV Biologics Product Menu
 
The Grail Message - Volume 1, Lecture 4 - Morality
The Grail Message - Volume 1, Lecture 4 - Morality The Grail Message - Volume 1, Lecture 4 - Morality
The Grail Message - Volume 1, Lecture 4 - Morality
 
res- electrical instrumentation16
res- electrical instrumentation16res- electrical instrumentation16
res- electrical instrumentation16
 
Instalacion de sistemas operativos windows y linux
Instalacion de sistemas operativos windows y linuxInstalacion de sistemas operativos windows y linux
Instalacion de sistemas operativos windows y linux
 
The Transformation and Future of Health Care | Mary Tolan
The Transformation and Future of Health Care  |  Mary TolanThe Transformation and Future of Health Care  |  Mary Tolan
The Transformation and Future of Health Care | Mary Tolan
 
TIP_FINAL_-_Web_Version
TIP_FINAL_-_Web_VersionTIP_FINAL_-_Web_Version
TIP_FINAL_-_Web_Version
 
pcl cv
pcl cvpcl cv
pcl cv
 
Matt cirriculum vitae
Matt cirriculum vitaeMatt cirriculum vitae
Matt cirriculum vitae
 
Notification main june2015
Notification main june2015Notification main june2015
Notification main june2015
 
Malta 15 min presentation final.ppt
Malta 15 min presentation   final.pptMalta 15 min presentation   final.ppt
Malta 15 min presentation final.ppt
 
Egyptian mummy part 2
Egyptian mummy part 2Egyptian mummy part 2
Egyptian mummy part 2
 
00 aprenda a dibujar
00 aprenda a dibujar00 aprenda a dibujar
00 aprenda a dibujar
 
Environmental responsibility
Environmental responsibilityEnvironmental responsibility
Environmental responsibility
 
Final Draft Aug 29 2014
Final Draft Aug 29 2014Final Draft Aug 29 2014
Final Draft Aug 29 2014
 

Similar to Projects - consulting engineer

JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02Jamal Jamil
 
C V ALAA AMMAR 2
C V   ALAA AMMAR 2 C V   ALAA AMMAR 2
C V ALAA AMMAR 2 Alaa Ammar
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering ResumeStephen Davidson
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R S Rajaram
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R S Rajaram
 
Resume_Krishna Kumar_Btech_EL
Resume_Krishna Kumar_Btech_ELResume_Krishna Kumar_Btech_EL
Resume_Krishna Kumar_Btech_ELkrishna kumar
 
Resume-Pravin_Ghatge _EA1
Resume-Pravin_Ghatge _EA1Resume-Pravin_Ghatge _EA1
Resume-Pravin_Ghatge _EA1Pravin Ghatage
 
Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)Anand Dhawan
 

Similar to Projects - consulting engineer (20)

JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02JNJ CV _OilAndGas rev02
JNJ CV _OilAndGas rev02
 
C V ALAA AMMAR 2
C V   ALAA AMMAR 2 C V   ALAA AMMAR 2
C V ALAA AMMAR 2
 
CV-Project Manager
CV-Project ManagerCV-Project Manager
CV-Project Manager
 
MohammadShafique (1)
MohammadShafique (1)MohammadShafique (1)
MohammadShafique (1)
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering Resume
 
Nitin_Technical
Nitin_TechnicalNitin_Technical
Nitin_Technical
 
madhankumar new CV 2016 june...
madhankumar new CV 2016 june...madhankumar new CV 2016 june...
madhankumar new CV 2016 june...
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project Engineer
 
Anil Pachpande-CV2016
Anil Pachpande-CV2016Anil Pachpande-CV2016
Anil Pachpande-CV2016
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
PMC 1.1- 22jul16
PMC 1.1- 22jul16PMC 1.1- 22jul16
PMC 1.1- 22jul16
 
projects
projectsprojects
projects
 
Resume_Krishna Kumar_Btech_EL
Resume_Krishna Kumar_Btech_ELResume_Krishna Kumar_Btech_EL
Resume_Krishna Kumar_Btech_EL
 
Resume-Pravin_Ghatge _EA1
Resume-Pravin_Ghatge _EA1Resume-Pravin_Ghatge _EA1
Resume-Pravin_Ghatge _EA1
 
khalid mowafy CV
khalid mowafy CVkhalid mowafy CV
khalid mowafy CV
 
Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)
 
CV Aug16
CV Aug16CV Aug16
CV Aug16
 
Resume Acc
Resume AccResume Acc
Resume Acc
 
vinoth-projects
vinoth-projectsvinoth-projects
vinoth-projects
 

Projects - consulting engineer

  • 1. PROJECTS: CONSULTING ENGINEER Transco compression station environmental impact survey (2003) Objective: Deliver surveys of four of Transco’s 80 bar.g compression stations, within manhour budget and to client satisfaction. Identify main environmental impacts, and design cost-effective mitigation measures. Achieved: Surveys delivered on time, and with novel (yet practical) impact reduction solutions. Role: Lead engineer. Power station fuel compressor station (2002 – 2003) Objective: Deliver a natural gas compression station, to extremely demanding client specifications, for GE’s first Frame 9H gas turbine installation. Achieved: Station built to budget and on time. Demonstrated, by site test that the installation met all the specifications: 10-second response time, +/-0.5% pressure stability, <65dBA noise, and much else. Role: Leading mechanical, process, instrumentation, and civils design team. Procure compressors, from specification through vendor coordination and to final on-site testing. Power station cooling tower rectification (2002) Objective: Find a minimum-cost method to rectify a mal-performing cooling tower, nominally 80MW capacity. Achieved: Successfully diagnosed the cause of the performance shortfall by site survey and detailed measurement. Process design and detailed design of rectification measures, including fluid flow analysis both with and without rectification. Subsequent tests in the rectified condition showed performance to specification. Role: Lead mechanical engineer. Hospital clinical waste incinerator (2002) Objective: Meet client’s need to bring existing, but not commissioned, waste incinerator to a safe-to-operate condition, and meet client’s contractual obligations. Minimise cost and schedule. Close client’s contract as speedily and as economically as possible. Achieved: Satisfied client, very content with the support they got at the end of an extremely difficult contract. Extensive survey of existing installation, including HAZOP and detailed sizing calculations. Rectifications designed and costed, contractors identified, and works initiated.
  • 2. Role: Project leader. Principal consultant and site representative. Offshore substructure (1999 – 2000) Objective: Deliver mechanical design for a concrete gravity substructure for Shell. Achieved: Successful installation of the substructure, within 2m of required position. Excellent revenue for employer, 2% under budget and on time. Role: Lead mechanical engineer, for a team of up to three engineers. Representative for the design team in the client’s offices, spearheading technical and commercial negotiations. Expert witness report for the collapse of a steam boiler (1999) Objective: Improve client’s position in the negotiation of damages claim following equipment failure. Achieved: Identified cause and assigned fault, delivered expert witness report, provided technical input to “without prejudice” negotiations. Client’s position very materially improved, by being able to dismiss other party’s technical investigation. Role: Mechanical engineer. Dry dock mechanical services design and implementation (1999) Objective: Refurbish the mechanical services to Nigg dry dock, to enable construction of large- scale concrete gravity sub-structures (“CGS’s”) in this previously dis-used facility. Achieved: Full site survey of existing installations, upon which to base lowest-cost recommendations and design of the refurbishment. Procurement, installation, and testing of the refurbishment, including 2MW of de-watering pump capacity. Leading to satisfied client, and later use for the successful construction of two CGS’s. Role: Lead mechanical engineer. Test of Siemens oil-fuelled gas turbine installation (1998) Objective: Protect the client’s interests by full test and acceptance of a combined cycle power station at Shenzen, China. Achieved: Audited and approved the test protocol, witnessed vendor tests, carried out normalisation and error assessment of results, provided recommendation for acceptance following an agreed re-statement of the facility’s performance. Role: Mechanical engineer. Brewery, China (1997 – 1998)
  • 3. Objective: Deliver the design for a coal-fired steam system to a 100,000hl/year brewery, at minimum cost and to an extremely tight schedule. Achieved: Optioneering and design of a system based on locally-sourced equipment, over- coming the challenges of highly variable demand on a coal-fired boiler. System subsequently implemented and successfully commissioned, within schedule and 8% under budget. Role: Lead mechanical engineer. Clinical waste incinerator delivery (1993 – 1994) Objective: Deliver a 1T/hr clinical waste incinerator, with waste heat recovery and integrated power generation – a UK-first. Achieved: Delivery of this complex system, within an extremely tight site (footprint >80% of site area), and to strict noise abatement requirements. Demonstrated compliance with all regulatory and client requirements by n-site test. Role: Followed the project from inception to final commissioning, in various roles. Site identification, concept design, contractor selection, detailed design, site supervision, commissioning. Energy surveys (1993 – 2000) Objective: Find opportunities to reduce the client’s energy consumption, by detailed site survey. Achieved: Too many surveys carried out to list them individually. Invariably found opportunities to improve the client’s bottom line. My special contribution was the use of fundamental engineering principles, plus a sense of what is practical, to offer solutions that delight the client by their low capital cost. Role: Energy specialist. Facilities surveyed include breweries, a chocolate factory, clinical waste incineration facilities, high-rise commercial buildings, the National Physics Laboratory, and district heating schemes.