SlideShare a Scribd company logo
SELA Region Q4-2013 Thru-tubing
Recompletion and Thru-tubing
Workover Program
Project Performance Report
Project Summary
• 5 TTRC & TTWO projects in Lake Washington Area
• 4/5 projects were economically successful
projects
• Total Cost was 855.1 M$
• Percentage of AFE Spent was 83.2%
• Cumulative Oil Production was 12,820 BO
• Cumulative Net Oil Sales were 1,026 M$
• Payout was achieved in 34 days
• Daily Net Income was 25 M$/day
Economic Performance for the Program
Well AFE Cost (M$) Actual Cost (M$) Max Oil Rate (BOPD) Cum. Oil (BO)
BDC #150 120.2 105.5 69 1,390
BLD
CM #15 117.7 45.2 516 9,400
CM #212 315.1 407.0 30 30
CM #313 349.6 210.0 52 1,000
CM #339 125.0 87.4 63 1,000
∑ Program 1,027.5 855.1 730 12,820
NOTE - All Cumulative values presented are as of 1/5/14.
Project Details – BDC #150
TTWO – Perf Addition; TT GPK Screen Hangoff
• Project Payout = 36 days
• Spent AFE = 87.8%
• 42 BOPD, 339 MCFPD, 524 BWPD, (current stabilized rate)
• Project Duration was 1 day over the AFE timeline estimate due to high winds and poor weather
conditions
• Np = 1,390 BO
• The first lesson learned from this project was to plan for weather contingency downtime days when
conducting workover operations in the fourth quarter of the year in the SELA area.
• The second lesson learned from this project was that a thru-tubing hang-off screen assembly
deployed in the end of tubing above the perfs was an effective sand control method based on the
production performance.
Project Details – BLD CM #15
TTRC – Natrural Completion: e-line TT preforator
• Project Payout = 3 days
• Spent AFE = 38.4%
• 219 BOPD, 67 MCFPD, 0 BWPD, (current stabilized rate)
• Project Duration was on schedule with the AFE timeline estimate
• Np = 9,400 BO
• The main lesson learned from this project was that we have an analog
that illustrates that we can produce a well from 6300’ as a natural
completion using controlled rate (small choke size ≈14/64”) for sustained
cumulative production value of over 60 producing days (Np = 9400 BO).
Project Details – CM #212
TTGPK RC – e-line/slickline & pump only operation
• The project will most likely never pay out since the well appears to be producing
from a slightly depleted water swept sand!
• Spent AFE = 129.2%
• 0 BOPD, 228 MCFPD, 20 BWPD, (current stabilized rate)
• Project Duration was 13 days over the AFE timeline estimate due to high winds and poor weather conditions and
Challenging well conditions.
• Np = 30 BO
• The team plans to further evaluate the reservoir performance of this project and to gain an understanding of why
this project failed to provide the production that was planned.
• The first lesson learned from this project was to plan for weather contingency downtime days when conducting
workover operations in the fourth quarter of the year in the SELA area.
• The second lesson learned from this project was that reservoir’s in the 3100’MD depth range are capable of
accepting a sand control treatment at 500 #/ft-perforation of sand being deployed in the formation without a
screen out in a slightly pressure depleted water swept reservoir.
Project Details – CM #212
TTGPK RC – project challenges
• High winds and poor weather conditions
• Gravel pack sand volume pumped was 25X job planned volume
• DW plug failed to set and function properly twice
• Umbrella plug setting issues requiring slickline fishing.
Project Details – CM #313
TTGPK RC – e-line/slickline & pump only operation
• Estimated Project Payout = 61 days
• Spent AFE = 60.1%
• 52 BOPD, 50 MCFPD, 9 BWPD (current stabilized rate)
• Project Duration was 2 days over the AFE timeline estimate due to high winds and poor weather
conditions
• Np = 1,000 BO
• The main lesson learned from this project was that the team was able to execute a thru-tubing
gravel-packed recompletion without using Coiled Tubing as a component of the recompletion
operation using only a pump spread and wireline spread to execute this job for 210 M$. This
operation represents about a 125 M$ savings as compared to the coiled tubing thru-tubing
gravel-packed method.
• The second lesson learned from this project was to plan for weather contingency downtime days
when conducting workover operations in the fourth quarter of the year in the SELA area.
Project Details – CM #339
TTRC – Natrural Completion: e-line TT preforator
• Estimated Project Payout = 30 days
• Spent AFE = 69.9%
• 44 BOPD, 100 MCFPD, 4 BWPD (current stabilized rate)
• Project Duration was 4 days over the AFE timeline estimate due to high winds and poor weather conditions and
tubing restrictions caused by scaling of tubulars.
• Np = 1,000 BO
• The first lesson learned from this project was to plan for additional slickline work days for the mitigation of scale on
the wall of the production tubing and completion hardware in the wellbore when working in the SELA area
• The second lesson learned from this project was that we have an analog that illustrates that we can produce a
well from 3000’ as a natural completion using a controlled rate for sustained cumulative production value of
over 60 producing days (Np = 1000 BO); furthermore the well is still producing without sand production issues.
• The third lesson learned from this project was to plan for weather contingency downtime days when conducting
workover operations in the fourth quarter of the year in the SELA area.

More Related Content

What's hot

Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Association for Project Management
 
rhe-use_haynesville_1
rhe-use_haynesville_1rhe-use_haynesville_1
rhe-use_haynesville_1Manu Tayal
 
Introducing Process Group
Introducing Process GroupIntroducing Process Group
Introducing Process Group
process group
 
ARB Midstream: Condensate from the Rockies Producing Region
ARB Midstream: Condensate from the Rockies Producing RegionARB Midstream: Condensate from the Rockies Producing Region
ARB Midstream: Condensate from the Rockies Producing Region
Adam Bedard
 
Applied reservoir eng
Applied reservoir engApplied reservoir eng
Applied reservoir eng
mohamad1286
 
Luis Romualdez_CRC_Oxy
Luis Romualdez_CRC_OxyLuis Romualdez_CRC_Oxy
Luis Romualdez_CRC_Oxyromualdez luis
 
Kivi graceful decommisioning rotterdam may 2018
Kivi graceful decommisioning rotterdam   may 2018Kivi graceful decommisioning rotterdam   may 2018
Kivi graceful decommisioning rotterdam may 2018
sterker
 
Premier Oil Investor Presentation 2017-February
Premier Oil Investor Presentation 2017-FebruaryPremier Oil Investor Presentation 2017-February
Premier Oil Investor Presentation 2017-February
OILWIRE
 
SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...
SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...
SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...
John Downs
 
Final SLB Project
Final SLB ProjectFinal SLB Project
Final SLB ProjectEbuka David
 
B4 - Theistareykir Geothermal Power Plant An update on successful project
B4 - Theistareykir Geothermal Power Plant An update on successful projectB4 - Theistareykir Geothermal Power Plant An update on successful project
B4 - Theistareykir Geothermal Power Plant An update on successful project
Iceland Geothermal
 
Sector Summary - Subsea
Sector Summary - SubseaSector Summary - Subsea
Sector Summary - SubseaThomas Burke
 
Moffett Base-Wide Groundwater Update, September 10, 2009
Moffett Base-Wide Groundwater Update, September 10, 2009Moffett Base-Wide Groundwater Update, September 10, 2009
Moffett Base-Wide Groundwater Update, September 10, 2009
Steve Williams
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportHonolulu Civil Beat
 
Six Sigma - SWV Drilling Program - Executive Summary - Project 9173
Six Sigma - SWV Drilling Program - Executive Summary - Project 9173Six Sigma - SWV Drilling Program - Executive Summary - Project 9173
Six Sigma - SWV Drilling Program - Executive Summary - Project 9173Michael Hines
 
Cidade De Itajai Factsheet
Cidade De Itajai Factsheet Cidade De Itajai Factsheet
Cidade De Itajai Factsheet
Altera Infrastructure
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTAled Long
 
Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)
Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)
Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)
The i-Capital Africa Institute
 
ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...
ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...
ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...
Stochastic Simulation
 

What's hot (20)

Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
rhe-use_haynesville_1
rhe-use_haynesville_1rhe-use_haynesville_1
rhe-use_haynesville_1
 
Introducing Process Group
Introducing Process GroupIntroducing Process Group
Introducing Process Group
 
ARB Midstream: Condensate from the Rockies Producing Region
ARB Midstream: Condensate from the Rockies Producing RegionARB Midstream: Condensate from the Rockies Producing Region
ARB Midstream: Condensate from the Rockies Producing Region
 
Applied reservoir eng
Applied reservoir engApplied reservoir eng
Applied reservoir eng
 
Luis Romualdez_CRC_Oxy
Luis Romualdez_CRC_OxyLuis Romualdez_CRC_Oxy
Luis Romualdez_CRC_Oxy
 
Kivi graceful decommisioning rotterdam may 2018
Kivi graceful decommisioning rotterdam   may 2018Kivi graceful decommisioning rotterdam   may 2018
Kivi graceful decommisioning rotterdam may 2018
 
Premier Oil Investor Presentation 2017-February
Premier Oil Investor Presentation 2017-FebruaryPremier Oil Investor Presentation 2017-February
Premier Oil Investor Presentation 2017-February
 
SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...
SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...
SPE 199286 - Profiling the Production Performance of Five HPHT Gas Condensate...
 
Final SLB Project
Final SLB ProjectFinal SLB Project
Final SLB Project
 
B4 - Theistareykir Geothermal Power Plant An update on successful project
B4 - Theistareykir Geothermal Power Plant An update on successful projectB4 - Theistareykir Geothermal Power Plant An update on successful project
B4 - Theistareykir Geothermal Power Plant An update on successful project
 
Sector Summary - Subsea
Sector Summary - SubseaSector Summary - Subsea
Sector Summary - Subsea
 
cgts_services
cgts_servicescgts_services
cgts_services
 
Moffett Base-Wide Groundwater Update, September 10, 2009
Moffett Base-Wide Groundwater Update, September 10, 2009Moffett Base-Wide Groundwater Update, September 10, 2009
Moffett Base-Wide Groundwater Update, September 10, 2009
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
 
Six Sigma - SWV Drilling Program - Executive Summary - Project 9173
Six Sigma - SWV Drilling Program - Executive Summary - Project 9173Six Sigma - SWV Drilling Program - Executive Summary - Project 9173
Six Sigma - SWV Drilling Program - Executive Summary - Project 9173
 
Cidade De Itajai Factsheet
Cidade De Itajai Factsheet Cidade De Itajai Factsheet
Cidade De Itajai Factsheet
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXT
 
Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)
Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)
Recycled Concrete Aggregate - Dr. Asregedew Woldesenbet (3rd EACCES)
 
ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...
ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...
ResAssure - The World’s Fastest Reservoir Simulator | A Revolution in Reserve...
 

Similar to SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover

POWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTION
POWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTIONPOWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTION
POWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTION
iQHub
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
RCREEE
 
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction CostsWhy 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
AVEVA Group plc
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
Comit Projects Ltd
 
INPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPINPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPD. Alan Day
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantabhishekthakur309
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleKook Dean
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-Portfolio
Syed Arafath, PMI-SP certified
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
UK Carbon Capture and Storage Research Centre
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM K
Pravin Bokil
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
MichaelUberti
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationAmeya Margaj
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
Mujahid Ali Akhtar
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniquesKrishna Deo Prasad
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
Bharatha Rathnayke
 

Similar to SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover (20)

POWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTION
POWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTIONPOWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTION
POWER FOR FRAC SAND MINES DURING CONSTRUCTION & EARLY PRODUCTION
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
 
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction CostsWhy 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
INPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRPINPO Presentation - Sequoyah SGRP
INPO Presentation - Sequoyah SGRP
 
Used fuel andrew sowder - epri
Used fuel   andrew sowder - epriUsed fuel   andrew sowder - epri
Used fuel andrew sowder - epri
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plant
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-Portfolio
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM K
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentation
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniques
 
MNC-14
MNC-14MNC-14
MNC-14
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 

SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover

  • 1. SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover Program Project Performance Report
  • 2. Project Summary • 5 TTRC & TTWO projects in Lake Washington Area • 4/5 projects were economically successful projects • Total Cost was 855.1 M$ • Percentage of AFE Spent was 83.2% • Cumulative Oil Production was 12,820 BO • Cumulative Net Oil Sales were 1,026 M$ • Payout was achieved in 34 days • Daily Net Income was 25 M$/day
  • 3. Economic Performance for the Program Well AFE Cost (M$) Actual Cost (M$) Max Oil Rate (BOPD) Cum. Oil (BO) BDC #150 120.2 105.5 69 1,390 BLD CM #15 117.7 45.2 516 9,400 CM #212 315.1 407.0 30 30 CM #313 349.6 210.0 52 1,000 CM #339 125.0 87.4 63 1,000 ∑ Program 1,027.5 855.1 730 12,820 NOTE - All Cumulative values presented are as of 1/5/14.
  • 4. Project Details – BDC #150 TTWO – Perf Addition; TT GPK Screen Hangoff • Project Payout = 36 days • Spent AFE = 87.8% • 42 BOPD, 339 MCFPD, 524 BWPD, (current stabilized rate) • Project Duration was 1 day over the AFE timeline estimate due to high winds and poor weather conditions • Np = 1,390 BO • The first lesson learned from this project was to plan for weather contingency downtime days when conducting workover operations in the fourth quarter of the year in the SELA area. • The second lesson learned from this project was that a thru-tubing hang-off screen assembly deployed in the end of tubing above the perfs was an effective sand control method based on the production performance.
  • 5. Project Details – BLD CM #15 TTRC – Natrural Completion: e-line TT preforator • Project Payout = 3 days • Spent AFE = 38.4% • 219 BOPD, 67 MCFPD, 0 BWPD, (current stabilized rate) • Project Duration was on schedule with the AFE timeline estimate • Np = 9,400 BO • The main lesson learned from this project was that we have an analog that illustrates that we can produce a well from 6300’ as a natural completion using controlled rate (small choke size ≈14/64”) for sustained cumulative production value of over 60 producing days (Np = 9400 BO).
  • 6. Project Details – CM #212 TTGPK RC – e-line/slickline & pump only operation • The project will most likely never pay out since the well appears to be producing from a slightly depleted water swept sand! • Spent AFE = 129.2% • 0 BOPD, 228 MCFPD, 20 BWPD, (current stabilized rate) • Project Duration was 13 days over the AFE timeline estimate due to high winds and poor weather conditions and Challenging well conditions. • Np = 30 BO • The team plans to further evaluate the reservoir performance of this project and to gain an understanding of why this project failed to provide the production that was planned. • The first lesson learned from this project was to plan for weather contingency downtime days when conducting workover operations in the fourth quarter of the year in the SELA area. • The second lesson learned from this project was that reservoir’s in the 3100’MD depth range are capable of accepting a sand control treatment at 500 #/ft-perforation of sand being deployed in the formation without a screen out in a slightly pressure depleted water swept reservoir.
  • 7. Project Details – CM #212 TTGPK RC – project challenges • High winds and poor weather conditions • Gravel pack sand volume pumped was 25X job planned volume • DW plug failed to set and function properly twice • Umbrella plug setting issues requiring slickline fishing.
  • 8. Project Details – CM #313 TTGPK RC – e-line/slickline & pump only operation • Estimated Project Payout = 61 days • Spent AFE = 60.1% • 52 BOPD, 50 MCFPD, 9 BWPD (current stabilized rate) • Project Duration was 2 days over the AFE timeline estimate due to high winds and poor weather conditions • Np = 1,000 BO • The main lesson learned from this project was that the team was able to execute a thru-tubing gravel-packed recompletion without using Coiled Tubing as a component of the recompletion operation using only a pump spread and wireline spread to execute this job for 210 M$. This operation represents about a 125 M$ savings as compared to the coiled tubing thru-tubing gravel-packed method. • The second lesson learned from this project was to plan for weather contingency downtime days when conducting workover operations in the fourth quarter of the year in the SELA area.
  • 9. Project Details – CM #339 TTRC – Natrural Completion: e-line TT preforator • Estimated Project Payout = 30 days • Spent AFE = 69.9% • 44 BOPD, 100 MCFPD, 4 BWPD (current stabilized rate) • Project Duration was 4 days over the AFE timeline estimate due to high winds and poor weather conditions and tubing restrictions caused by scaling of tubulars. • Np = 1,000 BO • The first lesson learned from this project was to plan for additional slickline work days for the mitigation of scale on the wall of the production tubing and completion hardware in the wellbore when working in the SELA area • The second lesson learned from this project was that we have an analog that illustrates that we can produce a well from 3000’ as a natural completion using a controlled rate for sustained cumulative production value of over 60 producing days (Np = 1000 BO); furthermore the well is still producing without sand production issues. • The third lesson learned from this project was to plan for weather contingency downtime days when conducting workover operations in the fourth quarter of the year in the SELA area.