SlideShare a Scribd company logo
1 of 15
Download to read offline
Landsvirkjun
Theistareykir Geothermal Power Plant
An update on successful project
Valur Knútsson, Chief project manager
Presentation on IGC, April 26, 2018
Content of presentation
• Theistareykir Geothermal
Power Plant
• HSE matters
• The scope
• The Construction history
• Challenges and success
• Northern Sustainability Project
HSE – zero accident policy
Registration of all incidents
▪ Accidents with or without absense from work
▪ Almost accidents, near misses
▪ Dangerous behaviour
▪ Critical circumstances
▪ Dangerous equipment
Logged incidents
▪ Approx. 1.096.143 working hours
▪ 6 accidents with absense from work
(H-200 = 1,09) – lost working hours 1052
▪ 29 accidents without absense from work
MT Bæjarfjall
Drilling Area A
Transformers
Service building
and Work Shop
Moist eliminators
Cooling
towers
Steam valve station
and Silencers
Main Steam supply pipelines Steam separators
Re-injection wells
Picture showing the main parts of the project
The powerhouse is built for two 45 MWe units
Great emphasis is placed on environmental issues and a good surface finish of construction area
Steam gathering pipeline 5
Steam gathering pipeline 2
Engineering: Theistareykir Geothermal Power Plant
Approaching with care
Decades of reservoir researhes
▪ Planned utilization 90 MWe
▪ Steam power of 58 MWe confirmed prior to
construction start
▪ Reservoir capacity tests
Environment monitoring and reclamation
▪ Monitoring of flora and fauna during construction
▪ Replacement of vegetation
▪ CO2 countermeasures by planting of trees
▪ Reclamation of grazing land
Aflprófun
Replacement of vegetation
Aflprófun
Monitoring
Wells
Power estimate
Mwe Remark
ÞG-01 6,9 Confirmed / In use
ÞG-03 7,0 Confirmed / In use
ÞG-04 21,3 Confirmed / In use
ÞG-05B 8,4 Confirmed / In use
ÞG-06 7,3 Confirmed / In use
ÞG-07 4,7 Confirmed / In use
ÞG-09 3,6 Confirmed / Not in use
ÞG-11 14,4 Confirmed / In use
ÞG-12 5,7 Confirmed / In use
ÞG-13 7,3 Confirmed / In use
ÞG-14 - To be tested for re-injection?
ÞG-15 2,0 Estimated / Not in use
ÞG-16 1,9 Confirmed / Not in use
ÞG-17 14,8 Confirmed / Not in use
ÞG-18 2 Estimated / Not connected
Estimated power capacity equals 105,3 + 2 MWe
Engineering: Steam wells for 90 MWe
Re-injection area
Separator station
Power house area
Drilling area
Well path
Steam wells
Clarification:
7
Theistareykir
Power Plant
Mission
accomplished with-
in time schedule and
budget
The Construction
Hisrory
8
9
Technical data per Turbine,
Generator and Cold End:
Turbine rotor desing:
Single flow multi stage reaction type
Rated/max. output: 45/47,25 MW
Inlet steam pressure: 9,0 bara
Temperature: 175,4 °C
Gas content: 0,60% by weight
Turbine rated speed: 3000 rpm
Rotating blade rows: 12
Last stage blade length: 798 mm
Total steam consumption: 77,2 kg/s
Generator output: 50 MVA
Generator voltage: 11 kV, 50 Hz
Excitation system: Brushless
Condenser type:
Surface, shell and tube type
Condenser pressure: 0,08 bara
Gas extraction system: Hybrid
Cooling tower type:
Mechanical induced draught wet type
Transmission system
Landsnet 2018
SOG
HRA
SIG
BUR
PRB
SUL
VAF
HAM
BRE
KOR
GEH
SVA
FIT
NES
BLA
KRA
RAN
LAV
LAX
VAR
TEH
HOL
HRY
GED
220 kV
132 kV
66 kV
Lines & cables
33 kV
HRU
GLE
MJO
VAT
VEG
AND
AKR
SAU
DAL
KOP
HUS
KEL
BRD
BOL
ISA
VOG
GRUOLA
SEL
TOR
HVE
FLU
HEL
HVO
RIM
VES
STU
ESK
NSK
SEY
EYV
LAG
VOP
FASFLJ
REY
RAU
LIN
KOL
HNO
OLD
A12
KLA
BUD
THR
KS1BV2BV1
IF1
BD1
TA1
MJ1
GL1
HT1
VS1
OL1
GF1
LV1
BL1
BL2
RA1
DA1
SA1
HU1
KR1
LA1
KR2
TR1
VP1
LF1 SF1
ES1EY1FL2
FL3
FL4
SR1
SR2
FA1
NK1
TE1
HO1
PB1
SI4
HA1
VF1
SI3
HV1
HR1
SI2
BH1
HE2
RI1
HE1
BU2
BU3 BU1
SE1
HG1
TO1
SE2
VM1,2,3
SN1
BR1
SO3
NE1
NE2
SO2
HN1,2
SU3
SU1
GE1
VE1
STA
SE3
HOF
KR4
KS1
BAK
Þeistareykir (THR) is connected to
a very week transmission grid
Main challenges for the plant´s
operation is the unit´s performance in
the week grid:
• Active frequency – and voltage
regulation is mandatory function.
• Set objectives accived in good co-
operation with Landsnet (grid
operator) and the contractor (Fuji).
Northern Sustainability Project
Geothermal Sustainability Assessment Protocol (GSAP)
Theistareykir – GSAP results
Preparation phase
▪ 18 Topics assessed
▪ 10 Proven Best Practice (5)
▪ 6 One gap against PB Practice
▪ 2 Basic Good Practice (3)
Encouragement for all
participants
▪ Sustainable approach from
the very beginning
▪ Motivation througout the
project´s execution
https://www.landsvirkjun.is/Media/gsap-
theistareykir-assessment-reportfinal-3-
may-2017-4.pdf
12
Northern Sustainability Project
Objectives
▪ Capture expectations and concerns of
stakeholders regarding proposed constructions
and operations.
▪ Monitor the social, environmental and
economical indicators.
▪ Build up knowledge and data that will improve
decision making
Sustainability indicators
▪ Developed by project owners and stakeholders
▪ First measurements / results expected to be
accessible in the first half of 2018
http://www.gaumur.is from end of May 2018
The Project
… to prepare and construct
a 90 MW Geothermal
Power Station utilizing
natural resources in a
sustainable way.
The Product
… hoped to be a testament
to the positive impact of
Landsvirkjun in Iceland
… and the conclusion
All photographs by
Mr. Hreinn Hjartarson
Thank you

More Related Content

What's hot

Technology development in Statoil
Technology development in Statoil Technology development in Statoil
Technology development in Statoil Statoil
 
Process Optimization for Small-Scale LNG Plants
Process Optimization for Small-Scale LNG PlantsProcess Optimization for Small-Scale LNG Plants
Process Optimization for Small-Scale LNG PlantsShilpa Dubey
 
Reduce your o2 to zero in your gas stream with eco vapor 9 3-18
Reduce your o2 to zero in your gas stream with eco vapor 9 3-18Reduce your o2 to zero in your gas stream with eco vapor 9 3-18
Reduce your o2 to zero in your gas stream with eco vapor 9 3-18EcoVapor Recovery Systems, Inc.
 
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...Neil Woodward
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
Cold weather performance of heat pumps in Irish homes – Do we really need to ...
Cold weather performance of heat pumps in Irish homes – Do we really need to ...Cold weather performance of heat pumps in Irish homes – Do we really need to ...
Cold weather performance of heat pumps in Irish homes – Do we really need to ...Heather Morrissey
 
Caldera inteligente: optimización de la combustión y reducción de emisiones
Caldera inteligente: optimización de la combustión y reducción de emisionesCaldera inteligente: optimización de la combustión y reducción de emisiones
Caldera inteligente: optimización de la combustión y reducción de emisionesAVEBIOM
 
Longer, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiersLonger, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiersStatoil
 
Conceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redusedConceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redusedThomas Stalin
 
Partial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trendsPartial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trendsAlex Byrne
 
Field Study of an Intelligent, Networked, Retrofittable Water Heater Controller
Field Study of an Intelligent, Networked, Retrofittable Water Heater ControllerField Study of an Intelligent, Networked, Retrofittable Water Heater Controller
Field Study of an Intelligent, Networked, Retrofittable Water Heater ControllerCenter for Energy and Environment
 
Windpower Engineering Webinar - Vortex Generators on Wind Turbines
Windpower Engineering Webinar - Vortex Generators on Wind TurbinesWindpower Engineering Webinar - Vortex Generators on Wind Turbines
Windpower Engineering Webinar - Vortex Generators on Wind TurbinesUpWind Solutions
 
Optimized Air/Water Heat Pump selection
Optimized Air/Water Heat Pump selectionOptimized Air/Water Heat Pump selection
Optimized Air/Water Heat Pump selectionLuca Zordan
 
Highest meteorological station in Canada designed for cold climate and comple...
Highest meteorological station in Canada designed for cold climate and comple...Highest meteorological station in Canada designed for cold climate and comple...
Highest meteorological station in Canada designed for cold climate and comple...Winterwind
 
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...GSE Systems, Inc.
 
Introduction to Small Scale LNG Opportunities
Introduction to Small Scale LNG OpportunitiesIntroduction to Small Scale LNG Opportunities
Introduction to Small Scale LNG OpportunitiesEPCM Holdings
 
GE ADGT Application iGas
GE ADGT Application iGasGE ADGT Application iGas
GE ADGT Application iGasGE코리아
 

What's hot (20)

Technology development in Statoil
Technology development in Statoil Technology development in Statoil
Technology development in Statoil
 
Process Optimization for Small-Scale LNG Plants
Process Optimization for Small-Scale LNG PlantsProcess Optimization for Small-Scale LNG Plants
Process Optimization for Small-Scale LNG Plants
 
Reduce your o2 to zero in your gas stream with eco vapor 9 3-18
Reduce your o2 to zero in your gas stream with eco vapor 9 3-18Reduce your o2 to zero in your gas stream with eco vapor 9 3-18
Reduce your o2 to zero in your gas stream with eco vapor 9 3-18
 
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Cold weather performance of heat pumps in Irish homes – Do we really need to ...
Cold weather performance of heat pumps in Irish homes – Do we really need to ...Cold weather performance of heat pumps in Irish homes – Do we really need to ...
Cold weather performance of heat pumps in Irish homes – Do we really need to ...
 
Caldera inteligente: optimización de la combustión y reducción de emisiones
Caldera inteligente: optimización de la combustión y reducción de emisionesCaldera inteligente: optimización de la combustión y reducción de emisiones
Caldera inteligente: optimización de la combustión y reducción de emisiones
 
Longer, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiersLonger, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiers
 
Conceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redusedConceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redused
 
Wind in Forest
Wind in ForestWind in Forest
Wind in Forest
 
Partial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trendsPartial Repowering of Wind Turbines: technical risks, opportunities and trends
Partial Repowering of Wind Turbines: technical risks, opportunities and trends
 
Field Study of an Intelligent, Networked, Retrofittable Water Heater Controller
Field Study of an Intelligent, Networked, Retrofittable Water Heater ControllerField Study of an Intelligent, Networked, Retrofittable Water Heater Controller
Field Study of an Intelligent, Networked, Retrofittable Water Heater Controller
 
Windpower Engineering Webinar - Vortex Generators on Wind Turbines
Windpower Engineering Webinar - Vortex Generators on Wind TurbinesWindpower Engineering Webinar - Vortex Generators on Wind Turbines
Windpower Engineering Webinar - Vortex Generators on Wind Turbines
 
Optimized Air/Water Heat Pump selection
Optimized Air/Water Heat Pump selectionOptimized Air/Water Heat Pump selection
Optimized Air/Water Heat Pump selection
 
Highest meteorological station in Canada designed for cold climate and comple...
Highest meteorological station in Canada designed for cold climate and comple...Highest meteorological station in Canada designed for cold climate and comple...
Highest meteorological station in Canada designed for cold climate and comple...
 
JE Final Presentation
JE Final PresentationJE Final Presentation
JE Final Presentation
 
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
 
Introduction to Small Scale LNG Opportunities
Introduction to Small Scale LNG OpportunitiesIntroduction to Small Scale LNG Opportunities
Introduction to Small Scale LNG Opportunities
 
GE ADGT Application iGas
GE ADGT Application iGasGE ADGT Application iGas
GE ADGT Application iGas
 
CEN/TC 312 Thermal solar systems and components
CEN/TC 312 Thermal solar systems and componentsCEN/TC 312 Thermal solar systems and components
CEN/TC 312 Thermal solar systems and components
 

Similar to B4 - Theistareykir Geothermal Power Plant An update on successful project

Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...Ajay Singhal
 
P&U Operations Review Presentation_14032019.pptx
P&U Operations Review Presentation_14032019.pptxP&U Operations Review Presentation_14032019.pptx
P&U Operations Review Presentation_14032019.pptxAastharaj16
 
d2_400_318_Alzuabi.pdf
d2_400_318_Alzuabi.pdfd2_400_318_Alzuabi.pdf
d2_400_318_Alzuabi.pdfSathiaShekar1
 
CTE WIND CIVIL ENGINEERING (brochure)
CTE WIND CIVIL ENGINEERING (brochure)CTE WIND CIVIL ENGINEERING (brochure)
CTE WIND CIVIL ENGINEERING (brochure)Jean-bernard Casanove
 
BPSCL Vocational Training report
BPSCL Vocational Training report BPSCL Vocational Training report
BPSCL Vocational Training report Rahul Raj
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house pptEr Sagar
 
COMPASS SWING.pptx
COMPASS SWING.pptxCOMPASS SWING.pptx
COMPASS SWING.pptxFendiKaze
 
Concerntatini solar plant ppt
Concerntatini solar plant pptConcerntatini solar plant ppt
Concerntatini solar plant pptkarmbir saini
 
White - LNG Processing Presentation.ppt
White - LNG Processing Presentation.pptWhite - LNG Processing Presentation.ppt
White - LNG Processing Presentation.pptLemuelGulliver
 
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.pptJiji118054
 
Training presentation
Training presentation Training presentation
Training presentation Keyur Patel
 
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_ceaCea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_ceaProbodh Mallick
 

Similar to B4 - Theistareykir Geothermal Power Plant An update on successful project (20)

CESC-TGS REPORT
CESC-TGS REPORTCESC-TGS REPORT
CESC-TGS REPORT
 
Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...
 
Air cooled condensers
Air cooled condensersAir cooled condensers
Air cooled condensers
 
P&U Operations Review Presentation_14032019.pptx
P&U Operations Review Presentation_14032019.pptxP&U Operations Review Presentation_14032019.pptx
P&U Operations Review Presentation_14032019.pptx
 
d2_400_318_Alzuabi.pdf
d2_400_318_Alzuabi.pdfd2_400_318_Alzuabi.pdf
d2_400_318_Alzuabi.pdf
 
CTE WIND CIVIL ENGINEERING (brochure)
CTE WIND CIVIL ENGINEERING (brochure)CTE WIND CIVIL ENGINEERING (brochure)
CTE WIND CIVIL ENGINEERING (brochure)
 
BPSCL Vocational Training report
BPSCL Vocational Training report BPSCL Vocational Training report
BPSCL Vocational Training report
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house ppt
 
COMPASS SWING.pptx
COMPASS SWING.pptxCOMPASS SWING.pptx
COMPASS SWING.pptx
 
Company profile MAPS TG
Company profile MAPS TGCompany profile MAPS TG
Company profile MAPS TG
 
Hindalco Mahan CPP.pdf
Hindalco Mahan CPP.pdfHindalco Mahan CPP.pdf
Hindalco Mahan CPP.pdf
 
OSX1 FPSO Buyers Rev2
OSX1 FPSO Buyers Rev2OSX1 FPSO Buyers Rev2
OSX1 FPSO Buyers Rev2
 
Concerntatini solar plant ppt
Concerntatini solar plant pptConcerntatini solar plant ppt
Concerntatini solar plant ppt
 
White - LNG Processing Presentation.ppt
White - LNG Processing Presentation.pptWhite - LNG Processing Presentation.ppt
White - LNG Processing Presentation.ppt
 
MAPS TG
MAPS TGMAPS TG
MAPS TG
 
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
 
Training presentation
Training presentation Training presentation
Training presentation
 
Sunoryx sizing tool
Sunoryx sizing toolSunoryx sizing tool
Sunoryx sizing tool
 
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_ceaCea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
Cea’s perspective on_energy_efficiency_in_thermal_power_generation_cea
 

More from Iceland Geothermal

Geothermal Landscape study final
Geothermal Landscape study finalGeothermal Landscape study final
Geothermal Landscape study finalIceland Geothermal
 
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...Iceland Geothermal
 
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...Iceland Geothermal
 
C4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from airC4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from airIceland Geothermal
 
C4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in MexicoC4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in MexicoIceland Geothermal
 
C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.Iceland Geothermal
 
C4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial productC4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial productIceland Geothermal
 
C3 - Production Modelling for Sustainability
C3 - Production Modelling for SustainabilityC3 - Production Modelling for Sustainability
C3 - Production Modelling for SustainabilityIceland Geothermal
 
C3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approachC3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approachIceland Geothermal
 
C3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable useC3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable useIceland Geothermal
 
C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...Iceland Geothermal
 
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...Iceland Geothermal
 
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONC2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONIceland Geothermal
 
C2 - ENGINEERING THE ENERGY TRANSITION
C2 - ENGINEERING THE  ENERGY TRANSITIONC2 - ENGINEERING THE  ENERGY TRANSITION
C2 - ENGINEERING THE ENERGY TRANSITIONIceland Geothermal
 
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...Iceland Geothermal
 
C1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its EffectsC1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its EffectsIceland Geothermal
 
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTSC1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTSIceland Geothermal
 
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...Iceland Geothermal
 
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyIceland Geothermal
 

More from Iceland Geothermal (20)

Geothermal Landscape study final
Geothermal Landscape study finalGeothermal Landscape study final
Geothermal Landscape study final
 
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
 
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...
 
C4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from airC4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from air
 
C4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in MexicoC4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in Mexico
 
C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.
 
C4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial productC4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial product
 
C3 - Production Modelling for Sustainability
C3 - Production Modelling for SustainabilityC3 - Production Modelling for Sustainability
C3 - Production Modelling for Sustainability
 
C3 - IDDP2 A better tomorrow
C3 - IDDP2 A better tomorrowC3 - IDDP2 A better tomorrow
C3 - IDDP2 A better tomorrow
 
C3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approachC3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approach
 
C3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable useC3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable use
 
C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...
 
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
 
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONC2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
 
C2 - ENGINEERING THE ENERGY TRANSITION
C2 - ENGINEERING THE  ENERGY TRANSITIONC2 - ENGINEERING THE  ENERGY TRANSITION
C2 - ENGINEERING THE ENERGY TRANSITION
 
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
 
C1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its EffectsC1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its Effects
 
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTSC1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
 
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
 
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
 

Recently uploaded

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 

Recently uploaded (20)

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 

B4 - Theistareykir Geothermal Power Plant An update on successful project

  • 1. Landsvirkjun Theistareykir Geothermal Power Plant An update on successful project Valur Knútsson, Chief project manager Presentation on IGC, April 26, 2018
  • 2. Content of presentation • Theistareykir Geothermal Power Plant • HSE matters • The scope • The Construction history • Challenges and success • Northern Sustainability Project
  • 3. HSE – zero accident policy Registration of all incidents ▪ Accidents with or without absense from work ▪ Almost accidents, near misses ▪ Dangerous behaviour ▪ Critical circumstances ▪ Dangerous equipment Logged incidents ▪ Approx. 1.096.143 working hours ▪ 6 accidents with absense from work (H-200 = 1,09) – lost working hours 1052 ▪ 29 accidents without absense from work
  • 4. MT Bæjarfjall Drilling Area A Transformers Service building and Work Shop Moist eliminators Cooling towers Steam valve station and Silencers Main Steam supply pipelines Steam separators Re-injection wells Picture showing the main parts of the project The powerhouse is built for two 45 MWe units Great emphasis is placed on environmental issues and a good surface finish of construction area Steam gathering pipeline 5 Steam gathering pipeline 2 Engineering: Theistareykir Geothermal Power Plant
  • 5. Approaching with care Decades of reservoir researhes ▪ Planned utilization 90 MWe ▪ Steam power of 58 MWe confirmed prior to construction start ▪ Reservoir capacity tests Environment monitoring and reclamation ▪ Monitoring of flora and fauna during construction ▪ Replacement of vegetation ▪ CO2 countermeasures by planting of trees ▪ Reclamation of grazing land Aflprófun Replacement of vegetation Aflprófun Monitoring
  • 6. Wells Power estimate Mwe Remark ÞG-01 6,9 Confirmed / In use ÞG-03 7,0 Confirmed / In use ÞG-04 21,3 Confirmed / In use ÞG-05B 8,4 Confirmed / In use ÞG-06 7,3 Confirmed / In use ÞG-07 4,7 Confirmed / In use ÞG-09 3,6 Confirmed / Not in use ÞG-11 14,4 Confirmed / In use ÞG-12 5,7 Confirmed / In use ÞG-13 7,3 Confirmed / In use ÞG-14 - To be tested for re-injection? ÞG-15 2,0 Estimated / Not in use ÞG-16 1,9 Confirmed / Not in use ÞG-17 14,8 Confirmed / Not in use ÞG-18 2 Estimated / Not connected Estimated power capacity equals 105,3 + 2 MWe Engineering: Steam wells for 90 MWe Re-injection area Separator station Power house area Drilling area Well path Steam wells Clarification:
  • 7. 7 Theistareykir Power Plant Mission accomplished with- in time schedule and budget The Construction Hisrory
  • 8. 8
  • 9. 9 Technical data per Turbine, Generator and Cold End: Turbine rotor desing: Single flow multi stage reaction type Rated/max. output: 45/47,25 MW Inlet steam pressure: 9,0 bara Temperature: 175,4 °C Gas content: 0,60% by weight Turbine rated speed: 3000 rpm Rotating blade rows: 12 Last stage blade length: 798 mm Total steam consumption: 77,2 kg/s Generator output: 50 MVA Generator voltage: 11 kV, 50 Hz Excitation system: Brushless Condenser type: Surface, shell and tube type Condenser pressure: 0,08 bara Gas extraction system: Hybrid Cooling tower type: Mechanical induced draught wet type
  • 10. Transmission system Landsnet 2018 SOG HRA SIG BUR PRB SUL VAF HAM BRE KOR GEH SVA FIT NES BLA KRA RAN LAV LAX VAR TEH HOL HRY GED 220 kV 132 kV 66 kV Lines & cables 33 kV HRU GLE MJO VAT VEG AND AKR SAU DAL KOP HUS KEL BRD BOL ISA VOG GRUOLA SEL TOR HVE FLU HEL HVO RIM VES STU ESK NSK SEY EYV LAG VOP FASFLJ REY RAU LIN KOL HNO OLD A12 KLA BUD THR KS1BV2BV1 IF1 BD1 TA1 MJ1 GL1 HT1 VS1 OL1 GF1 LV1 BL1 BL2 RA1 DA1 SA1 HU1 KR1 LA1 KR2 TR1 VP1 LF1 SF1 ES1EY1FL2 FL3 FL4 SR1 SR2 FA1 NK1 TE1 HO1 PB1 SI4 HA1 VF1 SI3 HV1 HR1 SI2 BH1 HE2 RI1 HE1 BU2 BU3 BU1 SE1 HG1 TO1 SE2 VM1,2,3 SN1 BR1 SO3 NE1 NE2 SO2 HN1,2 SU3 SU1 GE1 VE1 STA SE3 HOF KR4 KS1 BAK Þeistareykir (THR) is connected to a very week transmission grid Main challenges for the plant´s operation is the unit´s performance in the week grid: • Active frequency – and voltage regulation is mandatory function. • Set objectives accived in good co- operation with Landsnet (grid operator) and the contractor (Fuji).
  • 11. Northern Sustainability Project Geothermal Sustainability Assessment Protocol (GSAP)
  • 12. Theistareykir – GSAP results Preparation phase ▪ 18 Topics assessed ▪ 10 Proven Best Practice (5) ▪ 6 One gap against PB Practice ▪ 2 Basic Good Practice (3) Encouragement for all participants ▪ Sustainable approach from the very beginning ▪ Motivation througout the project´s execution https://www.landsvirkjun.is/Media/gsap- theistareykir-assessment-reportfinal-3- may-2017-4.pdf 12
  • 13. Northern Sustainability Project Objectives ▪ Capture expectations and concerns of stakeholders regarding proposed constructions and operations. ▪ Monitor the social, environmental and economical indicators. ▪ Build up knowledge and data that will improve decision making Sustainability indicators ▪ Developed by project owners and stakeholders ▪ First measurements / results expected to be accessible in the first half of 2018 http://www.gaumur.is from end of May 2018
  • 14. The Project … to prepare and construct a 90 MW Geothermal Power Station utilizing natural resources in a sustainable way. The Product … hoped to be a testament to the positive impact of Landsvirkjun in Iceland … and the conclusion
  • 15. All photographs by Mr. Hreinn Hjartarson Thank you