preparing
contracts
01
terms conditions
standard set of boiler plate
terms to be included in contract
03
tech specs & annex
additional information and
arrangement to be conveyed
02
delivery terms
standard terms of delivery
accepted across the globe
terms & conditions
basic
clauses
scope
‘statement of work’ or ‘scope of supply’
price and payment terms
‘the price’ and how it will be paid over what period and portions
milestones
defining the different stages of concerned procurement
delivery
conditions
timeline of deliveries
timeline for different batches or quantity of delivery
incentives and fines
bonus for early delivery and damages for delay
timeframe of contract
duration of the contract or date till expiry of the arrangement
delivery
conditions
no later than
due date is the last acceptable
date of delivery
on or before
can be delivered early but latest
should be by the due date
no earlier than
should not be delivered earlier
than the mentioned date
on or after
to be delivered on the mentioned
date or later but not earlier
deliverable
the concerned product or the service outcome
delivery
conditions
limitation of liability
transfer of ownership of materials as per incoterms
insurance
type of insurance, compulsion and scope of buyer or seller
product
support
warranty
scope and extent of warranty
installation and service
services pertaining to set-up, installation and trial of product
after sales
commitment of after sales services and spares support
quality
criteria
inspection and acceptance
arrangement for inspection and deliverable acceptance criteria
performance bonds
unconditional financial bonds for performance guarantee
performance reporting
types of reports, items covered in each and frequency
quality
criteria
sub contractor qualification & approval
qualification criteria for sub contractor & approving authority
change handling
spectrum of changes and procedure for handling
troubleshooting
arrangement
termination arrangement
procedure to follow and arrangement applicable upon termination
dispute resolution
procedures, preferred dispute resolution & applicable jurisdiction
delivery terms
incoterms
transfer of liability
at what point is the ownership transferred to buyer
globally accepted
incoterms is globally accepted to regulate trade activities
current version: 2020
versions are updated every four years
common
incoterms
EXW
ex-works – loaded on carriage
CIF
carriage up to destination port
with cargo insurance
DPU
unloaded at destination excluding
destination customs
FOB
on board shipping vessel
DAP
carriage up to destination
excluding destination customs
DDP
carriage up to destination including
destination customs
technical
specifications
material grade
specific grade or quality of raw
material to be used
drawings
designs or detailed drawings to
be provided for manufacturing
procedure requirements
any pre-requisites or mandatory
procedures to be followed
built
specifications / features regarding
the product-built quality
confirming standards
established standards for product
design or quality
other
provisions
progress reporting
items covered and frequency of
progress reporting
site inspection
authority of client to visit supplier
site during the process
third party validation
participation and scope of third
parties in the process
periodic review
joint review of the status with
client and supplier reps
client representative
point of contact for the supplier
for coordinating the process
new
courses
business essentials
all fundamentals that you need to know about business along with
an interesting section on evolution of business.
product costing and pricing
calculating product cost with fundamental understanding of business
and various pricing strategies!
procurement management
ultimate guide to managing procurement by understanding the
fundamentals, selection criteria, risk management, contracts & more

Section 05 Preparing Contracts

  • 1.
    preparing contracts 01 terms conditions standard setof boiler plate terms to be included in contract 03 tech specs & annex additional information and arrangement to be conveyed 02 delivery terms standard terms of delivery accepted across the globe
  • 2.
  • 3.
    basic clauses scope ‘statement of work’or ‘scope of supply’ price and payment terms ‘the price’ and how it will be paid over what period and portions milestones defining the different stages of concerned procurement
  • 4.
    delivery conditions timeline of deliveries timelinefor different batches or quantity of delivery incentives and fines bonus for early delivery and damages for delay timeframe of contract duration of the contract or date till expiry of the arrangement
  • 5.
    delivery conditions no later than duedate is the last acceptable date of delivery on or before can be delivered early but latest should be by the due date no earlier than should not be delivered earlier than the mentioned date on or after to be delivered on the mentioned date or later but not earlier deliverable the concerned product or the service outcome
  • 6.
    delivery conditions limitation of liability transferof ownership of materials as per incoterms insurance type of insurance, compulsion and scope of buyer or seller
  • 7.
    product support warranty scope and extentof warranty installation and service services pertaining to set-up, installation and trial of product after sales commitment of after sales services and spares support
  • 8.
    quality criteria inspection and acceptance arrangementfor inspection and deliverable acceptance criteria performance bonds unconditional financial bonds for performance guarantee performance reporting types of reports, items covered in each and frequency
  • 9.
    quality criteria sub contractor qualification& approval qualification criteria for sub contractor & approving authority change handling spectrum of changes and procedure for handling
  • 10.
    troubleshooting arrangement termination arrangement procedure tofollow and arrangement applicable upon termination dispute resolution procedures, preferred dispute resolution & applicable jurisdiction
  • 11.
    delivery terms incoterms transfer ofliability at what point is the ownership transferred to buyer globally accepted incoterms is globally accepted to regulate trade activities current version: 2020 versions are updated every four years
  • 12.
    common incoterms EXW ex-works – loadedon carriage CIF carriage up to destination port with cargo insurance DPU unloaded at destination excluding destination customs FOB on board shipping vessel DAP carriage up to destination excluding destination customs DDP carriage up to destination including destination customs
  • 13.
    technical specifications material grade specific gradeor quality of raw material to be used drawings designs or detailed drawings to be provided for manufacturing procedure requirements any pre-requisites or mandatory procedures to be followed built specifications / features regarding the product-built quality confirming standards established standards for product design or quality
  • 14.
    other provisions progress reporting items coveredand frequency of progress reporting site inspection authority of client to visit supplier site during the process third party validation participation and scope of third parties in the process periodic review joint review of the status with client and supplier reps client representative point of contact for the supplier for coordinating the process
  • 15.
    new courses business essentials all fundamentalsthat you need to know about business along with an interesting section on evolution of business. product costing and pricing calculating product cost with fundamental understanding of business and various pricing strategies! procurement management ultimate guide to managing procurement by understanding the fundamentals, selection criteria, risk management, contracts & more