This slide show was presented at the November 19, 2015 Haddonfield Board of Education Meeting. This represents the specific projects with estimated costs that will be sent to the state DOE for evaluation of appropriateness as well as a determination of state aid in terms of debt service. The resolution to move forward with these projects at this time was unanimously agreed on by the BOE.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
Fairfax County walkway construction of 1,600 linear feet of concrete sidewalk, curb ramps, curb and gutter, retaining wall, pavement markings and signage, drainage improvements and utility adjustments.
CM&B has assembled a team of the most highly skilled and dedicated construction professionals in the industry. Those experienced individuals are still part of CM&B today, joined by a new generation of talent with the same energy and enthusiasm to lead the company into the future. In addition to the longevity of our people, CM&B has built solid and long-standing relationships with clients, subcontractors, architects and other business partners: a testament to our core values and business philosophy. The breadth of experience gained through this team’s approach shows a range of projects with varying degrees of complexity and unique requirements. No matter the challenge, CM&B understands our clients’ needs and builds on our vast experience to deliver the highest quality construction experience for every client.
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations ProjectFairfax County
The work under this project included provision for the replacement of all pumping, piping, valves, generator, electrical, and mechanical equipment at each pump station. Each pump station also included structural and architectural repairs for the buildings as well as the installation of a security system. Miscellaneous site and civil modifications were also completed. This project was substantially complete on May 27, 2021.
The four pump stations (PS) included, Lakevale PS (10209 Kenbrooke Ct, Vienna), High Ridge PS (3890 Fairfax Ridge Rd, Fairfax), Weid PS (8418A Holly Leaf Drive, McLean), and Langley Oaks PS (6526 Heather Brook Ct, McLean)
This document provides information about a stream restoration project on Pike Branch at Wilton Road in Fairfax County, Virginia. It outlines the project area limits, typical restoration practices that will be used such as native vegetation planting, reinforced streambeds, and instream rock structures. It also shows examples of construction efforts like access roads and channel grading. The presentation discusses the project overview, current steps being taken to get approvals, and outlines a timeline for advertising, beginning, and completing construction over the next 2-3 years.
2 semester Projekt på Masteren fokusere på varme og køle systemer i bygningen. ved at undersøge eksisterende forhold og evaluere via simulationer kunne vi skrædersyg en løsning, der kunne minimere overophedningstimer om sommeren, reducere energi forbrug om vinteren, samt reducere energi forbuget i bygningen.
The work on this project included investigation and repair to an 8-inch sewer line in Waterway Drive which had been previously lined with a plastic liner system. The project location was in Waterway Drive from Cavalier Court to the vicinity of Half Moon Circle. The project involved setting up a bypass system to remove sewage from the line so the pipe could be properly cleaned and inspected. Following this process, it was determined the plastic liner was causing capacity issues. It was determined that the liner could be repaired using internal methods and no excavation was needed. In addition, the five manholes associated with the segments of pipe in the project area were also rehabilitated. This project was substantially complete on June 25, 2021.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
Fairfax County walkway construction of 1,600 linear feet of concrete sidewalk, curb ramps, curb and gutter, retaining wall, pavement markings and signage, drainage improvements and utility adjustments.
CM&B has assembled a team of the most highly skilled and dedicated construction professionals in the industry. Those experienced individuals are still part of CM&B today, joined by a new generation of talent with the same energy and enthusiasm to lead the company into the future. In addition to the longevity of our people, CM&B has built solid and long-standing relationships with clients, subcontractors, architects and other business partners: a testament to our core values and business philosophy. The breadth of experience gained through this team’s approach shows a range of projects with varying degrees of complexity and unique requirements. No matter the challenge, CM&B understands our clients’ needs and builds on our vast experience to deliver the highest quality construction experience for every client.
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations ProjectFairfax County
The work under this project included provision for the replacement of all pumping, piping, valves, generator, electrical, and mechanical equipment at each pump station. Each pump station also included structural and architectural repairs for the buildings as well as the installation of a security system. Miscellaneous site and civil modifications were also completed. This project was substantially complete on May 27, 2021.
The four pump stations (PS) included, Lakevale PS (10209 Kenbrooke Ct, Vienna), High Ridge PS (3890 Fairfax Ridge Rd, Fairfax), Weid PS (8418A Holly Leaf Drive, McLean), and Langley Oaks PS (6526 Heather Brook Ct, McLean)
This document provides information about a stream restoration project on Pike Branch at Wilton Road in Fairfax County, Virginia. It outlines the project area limits, typical restoration practices that will be used such as native vegetation planting, reinforced streambeds, and instream rock structures. It also shows examples of construction efforts like access roads and channel grading. The presentation discusses the project overview, current steps being taken to get approvals, and outlines a timeline for advertising, beginning, and completing construction over the next 2-3 years.
2 semester Projekt på Masteren fokusere på varme og køle systemer i bygningen. ved at undersøge eksisterende forhold og evaluere via simulationer kunne vi skrædersyg en løsning, der kunne minimere overophedningstimer om sommeren, reducere energi forbrug om vinteren, samt reducere energi forbuget i bygningen.
The work on this project included investigation and repair to an 8-inch sewer line in Waterway Drive which had been previously lined with a plastic liner system. The project location was in Waterway Drive from Cavalier Court to the vicinity of Half Moon Circle. The project involved setting up a bypass system to remove sewage from the line so the pipe could be properly cleaned and inspected. Following this process, it was determined the plastic liner was causing capacity issues. It was determined that the liner could be repaired using internal methods and no excavation was needed. In addition, the five manholes associated with the segments of pipe in the project area were also rehabilitated. This project was substantially complete on June 25, 2021.
This presentation proposes constructing a new 3-story, 240,000 square foot parking facility on campus to address growth-related parking and traffic issues. It was presented by 7 individuals and discusses the Educational Activities Building, Student Enrichment Center, and proposed parking structure. Building Information Modeling (BIM) was used on the project. The parking structure would add over 368 new spaces and cost an estimated $6-8 million. Precast concrete would be used for its structural advantages and ease of construction.
This project included improvements/upgrades to the primary and scum collection systems, the dissolved air flotation thickeners, and rehabilitation of buildings Q1 and Q2 at the Noman M. Cole, Jr. Pollution Control Plant.
Richard Barker has 29 years of experience in civil engineering projects, mainly in the water industry. He has experience managing projects valued up to £6.5 million, including water and sewage treatment works. His most recent role is as Senior Site Manager at MWH/Biwater Treatment Ltd, where he has managed several projects involving upgrades and installations at water and sewage treatment works.
The Fairfax County Department of Public Works and Environmental Services conducted an emergency repair project at Graham Park Plaza to replace approximately 60 feet of broken 8-inch wastewater sewer pipe and retrieve a CCTV camera that was stuck in the pipe during routine maintenance. The project involved communicating with business owners, excavating to retrieve the camera, removing the broken pipe and installing new PVC pipe and laterals, and restoring the work site. The project was completed on May 14, 2021.
Chris Piche, Integral Group
Driving the building industry towards a culture of accountability and using energy codes to get high performance buildings into the mainstream
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Central West Fall Open House - Oct 28 2019Crosstown TO
This document provides information on the Metrolinx Eglinton Crosstown LRT project, including:
- Summaries of the project's mission, vision, services, and 2041 Regional Transportation Plan.
- Renderings and descriptions of construction progress and timelines at eight station sites: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, and Eglinton.
- Photos showing current construction stages like excavation, concrete work, and tunnel boring machine removal.
- Maps of upcoming traffic configurations during construction stages near each station.
Pohick Creek Restoration Project - Phase 1Fairfax County
The document summarizes Phase I of the Pohick Creek Restoration Project in Fairfax County, Virginia. The project involved constructing a rock wall and bench along the creek bank, installing live stakes and native plants, and adding soil lifts for stabilization. The project team from Fairfax County Public Works completed earthworks and bank stabilization along a section of Pohick Creek near the Noman M. Cole Jr. Pollution Control Plant by June 13, 2016.
Pohick Creek Restoration Project Phase I June 2016Fairfax County
The document summarizes Phase I of the Pohick Creek Restoration Project in Fairfax County, Virginia. The project involved constructing a rock wall and bench along the creek bank, installing live stakes and native plants, and adding soil lifts for stabilization. The project team from Fairfax County completed earthworks and bank stabilization along a section of Pohick Creek near the Noman M. Cole, Jr. Pollution Control Plant, removing and replacing existing riprap. The project was substantially completed on June 13, 2016.
The document discusses changes to Ontario's building code regarding energy efficiency from 2006 to 2012, including increasing stringency of requirements over time from exceeding the Model National Energy Code for Buildings by 25% in 2012 to aligning with ASHRAE 90.1-2010 plus 5% by 2012. It provides an overview of the supplementary standard SB-10 and software tools available or under development for analyzing building designs under the different compliance options.
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
Metrolinx is updating its Regional Transportation Plan (RTP) to 2041. The draft plan outlines how governments and transit agencies can work together to build an integrated transportation system. Metrolinx has developed the draft plan through consultation and is seeking public review and comment. The Eglinton Crosstown LRT project will include 15 underground stations and 10 surface stops along a 19-kilometre route. Safety is the top priority, and the project aims to minimize environmental impacts and maximize sustainability in design and construction. Community benefits programs also aim to ensure positive impacts for disadvantaged groups.
Director of Infrastructure and Development Services Lisa Pyles and Parks and Recreation Director Slade Strickland provided City Council with a quarterly update on Addison's Capital Improvement Program and other Town projects on February 10, 2015.
This document describes an expansion project of the Stringfellow Road Park and Ride Facility in Fairfax County, VA. The expansion added over 300 new parking spaces, a new transit building, bus bays and shelters, low impact development features like biofilters and porous pavement. The project was completed in May 2016 with a total budget of $7.2 million.
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...Fairfax County
The Fairfax County Park Authority restored an eroded 185-foot stream channel within the Pinecrest Golf Course that is owned by the Park Authority. The restoration project stabilized the stream bank and installed rock walls and structures to improve the channel. Native plants were also planted to enhance habitat. The project was completed on time and within budget in April 2016 to address erosion issues along Turkeycock Run.
This presentation discusses lessons learned in developing and implementing recreation management plans. It covers developing facilities and amenities tables to track recreation sites, evolving exhibit drawings from as-built construction drawings, and challenges with implementing plans. Key points include simplifying drawings, addressing facilities outside project boundaries, incorporating strategic planning into implementations, and addressing long-term maintenance agreements. The presentation aims to share best practices for effective recreation management planning.
Central Open House (Chaplin Station to Leaside Station) - spring 2018Crosstown TO
Metrolinx is building the Eglinton Crosstown LRT, a 19km light rail line running east-west through Toronto. The project includes 25 stations, many of which are undergoing construction using cut-and-cover or mined methods. Over $30 billion is being invested in transit expansion across the Greater Toronto and Hamilton Area as part of Metrolinx's regional transportation plan. Community engagement efforts include informing residents about construction progress, traffic changes, and programs to support local businesses and provide employment opportunities.
This document provides an overview of energy efficient installations that can be done in heritage buildings in Vancouver. It discusses the installation process which includes green building renovations, permits and regulations, construction damage deposits, inspections, and ensuring the locations of utilities. The benefits of implementing energy efficient measures in heritage buildings are also outlined, such as how chimneys and fireplaces can improve ventilation and heating. The overall document aims to balance building conservation with energy conservation when retrofitting heritage structures.
Chaplin & Avenue CLC - Construction Update - April 4, 2018Crosstown TO
Construction updates were provided for the Chaplin and Avenue stations of the Crosstown LRT. At Chaplin Station, piling and excavation work was ongoing in preparation for the station structure. Renderings showed the design of the main, secondary, and tertiary entrances as well as the exterior and interior spaces. For Avenue Station, short term construction activities over the next few months were outlined, including dewatering, sewer lining, watermain installations, and monitoring equipment installation around the station area. Site visits were also discussed to view current work.
Helping practitioners understand changes to Exempt and Complying DevelopmentPlanning & Infrastructure
This presentation supports a series of information sessions the department has organised to help industry and council planning practitioners understand the recent changes to the Exempt and Complying Development Policy and the EP&A Regulation 2000.
The St. Monica Facilities Committee met to discuss options for renovating or demolishing the Old School building on campus. The building was found to have structural issues including a compromised support beam, no concrete flooring underneath the wood flooring, and an inoperable heating system. Estimates to restore the building to basic functioning condition were $971,187. Estimates were also obtained to demolish the building for $121,000. The committee discussed 5 options - doing minimal repairs, mothballing, demolishing, full renovation, or demolishing and rebuilding. Each option had pros and cons considered regarding costs, needs outlined in the campus master plan, and budget/funding impacts. The committee requested additional information on current
The presentation of October 1st possible referendum project list from the Haddonfield BOE. The video that accompanies this show can be found at: https://vimeo.com/141159983
This presentation proposes constructing a new 3-story, 240,000 square foot parking facility on campus to address growth-related parking and traffic issues. It was presented by 7 individuals and discusses the Educational Activities Building, Student Enrichment Center, and proposed parking structure. Building Information Modeling (BIM) was used on the project. The parking structure would add over 368 new spaces and cost an estimated $6-8 million. Precast concrete would be used for its structural advantages and ease of construction.
This project included improvements/upgrades to the primary and scum collection systems, the dissolved air flotation thickeners, and rehabilitation of buildings Q1 and Q2 at the Noman M. Cole, Jr. Pollution Control Plant.
Richard Barker has 29 years of experience in civil engineering projects, mainly in the water industry. He has experience managing projects valued up to £6.5 million, including water and sewage treatment works. His most recent role is as Senior Site Manager at MWH/Biwater Treatment Ltd, where he has managed several projects involving upgrades and installations at water and sewage treatment works.
The Fairfax County Department of Public Works and Environmental Services conducted an emergency repair project at Graham Park Plaza to replace approximately 60 feet of broken 8-inch wastewater sewer pipe and retrieve a CCTV camera that was stuck in the pipe during routine maintenance. The project involved communicating with business owners, excavating to retrieve the camera, removing the broken pipe and installing new PVC pipe and laterals, and restoring the work site. The project was completed on May 14, 2021.
Chris Piche, Integral Group
Driving the building industry towards a culture of accountability and using energy codes to get high performance buildings into the mainstream
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Central West Fall Open House - Oct 28 2019Crosstown TO
This document provides information on the Metrolinx Eglinton Crosstown LRT project, including:
- Summaries of the project's mission, vision, services, and 2041 Regional Transportation Plan.
- Renderings and descriptions of construction progress and timelines at eight station sites: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, and Eglinton.
- Photos showing current construction stages like excavation, concrete work, and tunnel boring machine removal.
- Maps of upcoming traffic configurations during construction stages near each station.
Pohick Creek Restoration Project - Phase 1Fairfax County
The document summarizes Phase I of the Pohick Creek Restoration Project in Fairfax County, Virginia. The project involved constructing a rock wall and bench along the creek bank, installing live stakes and native plants, and adding soil lifts for stabilization. The project team from Fairfax County Public Works completed earthworks and bank stabilization along a section of Pohick Creek near the Noman M. Cole Jr. Pollution Control Plant by June 13, 2016.
Pohick Creek Restoration Project Phase I June 2016Fairfax County
The document summarizes Phase I of the Pohick Creek Restoration Project in Fairfax County, Virginia. The project involved constructing a rock wall and bench along the creek bank, installing live stakes and native plants, and adding soil lifts for stabilization. The project team from Fairfax County completed earthworks and bank stabilization along a section of Pohick Creek near the Noman M. Cole, Jr. Pollution Control Plant, removing and replacing existing riprap. The project was substantially completed on June 13, 2016.
The document discusses changes to Ontario's building code regarding energy efficiency from 2006 to 2012, including increasing stringency of requirements over time from exceeding the Model National Energy Code for Buildings by 25% in 2012 to aligning with ASHRAE 90.1-2010 plus 5% by 2012. It provides an overview of the supplementary standard SB-10 and software tools available or under development for analyzing building designs under the different compliance options.
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
Metrolinx is updating its Regional Transportation Plan (RTP) to 2041. The draft plan outlines how governments and transit agencies can work together to build an integrated transportation system. Metrolinx has developed the draft plan through consultation and is seeking public review and comment. The Eglinton Crosstown LRT project will include 15 underground stations and 10 surface stops along a 19-kilometre route. Safety is the top priority, and the project aims to minimize environmental impacts and maximize sustainability in design and construction. Community benefits programs also aim to ensure positive impacts for disadvantaged groups.
Director of Infrastructure and Development Services Lisa Pyles and Parks and Recreation Director Slade Strickland provided City Council with a quarterly update on Addison's Capital Improvement Program and other Town projects on February 10, 2015.
This document describes an expansion project of the Stringfellow Road Park and Ride Facility in Fairfax County, VA. The expansion added over 300 new parking spaces, a new transit building, bus bays and shelters, low impact development features like biofilters and porous pavement. The project was completed in May 2016 with a total budget of $7.2 million.
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...Fairfax County
The Fairfax County Park Authority restored an eroded 185-foot stream channel within the Pinecrest Golf Course that is owned by the Park Authority. The restoration project stabilized the stream bank and installed rock walls and structures to improve the channel. Native plants were also planted to enhance habitat. The project was completed on time and within budget in April 2016 to address erosion issues along Turkeycock Run.
This presentation discusses lessons learned in developing and implementing recreation management plans. It covers developing facilities and amenities tables to track recreation sites, evolving exhibit drawings from as-built construction drawings, and challenges with implementing plans. Key points include simplifying drawings, addressing facilities outside project boundaries, incorporating strategic planning into implementations, and addressing long-term maintenance agreements. The presentation aims to share best practices for effective recreation management planning.
Central Open House (Chaplin Station to Leaside Station) - spring 2018Crosstown TO
Metrolinx is building the Eglinton Crosstown LRT, a 19km light rail line running east-west through Toronto. The project includes 25 stations, many of which are undergoing construction using cut-and-cover or mined methods. Over $30 billion is being invested in transit expansion across the Greater Toronto and Hamilton Area as part of Metrolinx's regional transportation plan. Community engagement efforts include informing residents about construction progress, traffic changes, and programs to support local businesses and provide employment opportunities.
This document provides an overview of energy efficient installations that can be done in heritage buildings in Vancouver. It discusses the installation process which includes green building renovations, permits and regulations, construction damage deposits, inspections, and ensuring the locations of utilities. The benefits of implementing energy efficient measures in heritage buildings are also outlined, such as how chimneys and fireplaces can improve ventilation and heating. The overall document aims to balance building conservation with energy conservation when retrofitting heritage structures.
Chaplin & Avenue CLC - Construction Update - April 4, 2018Crosstown TO
Construction updates were provided for the Chaplin and Avenue stations of the Crosstown LRT. At Chaplin Station, piling and excavation work was ongoing in preparation for the station structure. Renderings showed the design of the main, secondary, and tertiary entrances as well as the exterior and interior spaces. For Avenue Station, short term construction activities over the next few months were outlined, including dewatering, sewer lining, watermain installations, and monitoring equipment installation around the station area. Site visits were also discussed to view current work.
Helping practitioners understand changes to Exempt and Complying DevelopmentPlanning & Infrastructure
This presentation supports a series of information sessions the department has organised to help industry and council planning practitioners understand the recent changes to the Exempt and Complying Development Policy and the EP&A Regulation 2000.
The St. Monica Facilities Committee met to discuss options for renovating or demolishing the Old School building on campus. The building was found to have structural issues including a compromised support beam, no concrete flooring underneath the wood flooring, and an inoperable heating system. Estimates to restore the building to basic functioning condition were $971,187. Estimates were also obtained to demolish the building for $121,000. The committee discussed 5 options - doing minimal repairs, mothballing, demolishing, full renovation, or demolishing and rebuilding. Each option had pros and cons considered regarding costs, needs outlined in the campus master plan, and budget/funding impacts. The committee requested additional information on current
The presentation of October 1st possible referendum project list from the Haddonfield BOE. The video that accompanies this show can be found at: https://vimeo.com/141159983
Colt Hayes Planning Approach v1 220121.pptxIrfanAwan25
The document provides details of the construction project for a new data centre in Hayes, London, including:
- The project will construct two five-story buildings and an electrical substation covering a total area of 236,806 square feet.
- Key milestones include starting construction on July 4th, 2022 and completing the first 6MW phase by the end of 2023.
- The scope of work for phase one includes civil works, MEP works, installing special equipment, and obtaining utility connections.
- Drawings are provided outlining the proposed layout and works to be completed on each level of the main building.
Colt Hayes Planning Approach v1 220121.pptxIrfanAwan25
The document provides details of the construction project for a new data centre in Hayes, London, including:
- The project will construct two five-storey buildings and an electrical substation covering a total area of 236,806 square feet.
- Key milestones include starting construction on July 4th, 2022 and completing the first 6MW of the data centre by the end of 2023.
- The scope of work involves civil works, MEP works, installation of special equipment, and obtaining utility connections for Phase 1 of the project.
This document summarizes the city hall complex budget from 2008 to present. It outlines the architectural services contracts, the project scope including rehabilitation of several buildings and a central plant, funding sources totaling over $16 million, and expenses of around $15.7 million. The majority of remaining funds will be used for furniture, landscaping, and moving services. A voter-approved $3.75 million is funding enhancements to the auditorium.
The document summarizes six cost options for a new or renovated middle school in Gloucester County. Option A1 would construct a new 800-student middle school on the Walker Road site for a total estimated cost of $28.2 million. Option A2 is similar but slightly cheaper at $27.9 million. Option B would build a new school on the existing Page site for $26.7 million. Additional potential costs discussed include adding a 9th grade wing, geothermal heating/cooling, and renovating or replacing athletic facilities. A renovation of the existing Page school is estimated at $22.2 million under Option C.
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
The summary provides an update on the status of Phase 2 of the Dulles Corridor Metrorail Project Silver Line extension:
Phase 2 construction is 83% complete overall. Sections of the third rail have been energized. Issues have been discovered with precast concrete panels supplied by Universal Concrete Products that may impact the 100-year durability requirement. The project remains on schedule with an estimated substantial completion in August 2019 and revenue operations to be established by WMATA. Construction of station facilities, rail infrastructure, and support facilities like rail yards and garages continues across the phase.
The school district allocated $3.75 million in bonds for auditorium renovations. So far $1.99 million has been spent or committed, leaving $1.76 million remaining. The auditorium needs several infrastructure upgrades like a new roof, electrical and HVAC systems, but reopening it temporarily would be problematic due to construction sequencing and safety issues. It is recommended to fully delay further renovations until a local arts non-profit completes fundraising for the remaining $2.5 million needed, estimated to be achieved by early 2013, so that all work can be done efficiently and cost-effectively in one phase.
Fairfax County Tertiary Filtration System Rehabilitation July 2020Fairfax County
This project rehabilitated tertiary filtration facilities at the Noman M. Cole Jr. Pollution Control Plant. Work included replacing valves, gates, and equipment at the DD facility; replacing the HVAC and stairs; replacing the EE building, pumps, and tanks; installing a waste backwash force main; and adding a sodium hypochlorite pump. The goal was to improve filtration and wastewater treatment. Construction was substantially completed in June 2020 by Ulliman Schutte Construction under the management of Fairfax County and design consultants.
UFI Operations Award 2010 presentation for Direct Energy Center , Toronto, Canada
By: Jeff Gay, Director of Event Management Services and Mark Goss, General Manager, Operations
The document discusses proposed updates to the city's water and wastewater impact fees, including: extending impact fee collection to portions of the city's extraterritorial jurisdiction; presenting land use assumptions and projected population growth through buildout; and outlining over $48 million in water and over $152 million in wastewater capital improvement projects to accommodate growth, including new water wells, pipelines, storage tanks, lift stations, and wastewater treatment plant expansions. City staff and a consultant presented the 10-step impact fee update process and sought comments on the land use assumptions and capital improvement plans from the impact fee advisory committee.
This document outlines the process and recommendations for updating the city's water and wastewater impact fees. It recommends including portions of the extraterritorial jurisdiction in the impact fee service areas. It presents the land use assumptions and projected growth in living unit equivalents for both water and wastewater. The capital improvements plans identify over $48 million in existing and future water projects and over $152 million in existing and future wastewater projects needed to accommodate the expected population growth. Richard Weatherly of FNI is the project manager overseeing the impact fee study.
Diana Hamilton of Delcan presents an industrial retrofit project to LEED silver standard.
Presented at the 5th annual Green Building Festival in Toronto, Canada, 2009.
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationFairfax County
The summary provides an update on the status of Phase 2 of the Dulles Corridor Metrorail Project Silver Line extension:
1) Construction of the five new stations along the rail line and the rail yard at Dulles Airport is 78% complete, with substantial completion scheduled for August 2019.
2) Work continues on station construction including mechanical, electrical and plumbing work, as well as canopy, platform, and pavilion erection. Guideway installation and utility relocation is also ongoing.
3) The project remains on budget at $2.778 billion with $353.5 million in contingency remaining unutilized from the $551.5 million total contingency budget.
Colt Hayes Planning Approach v2 220121.pptxIrfanAwan25
1. The project involves the construction of a new data centre in Hayes, London with a total covered area of 236,806 square feet across five storeys and an electrical substation.
2. The project budget, start date, and duration are not specified. The project is scheduled to be completed by the end of 2023.
3. The document outlines the project scope, stakeholders, requirements, key dates, and provides section drawings and lists of work for the different levels of the building.
This project included renovations and building systems replacement/upgrades at the Department of Vehicle Services’ West Ox Maintenance Facility, which provides vehicle maintenance and repair services for Fire and Rescue apparatus, heavy and light duty trucks, and FCPS school buses.
The objective of the webinar was to provide BER assessors an understanding of the National Retrofit programme, what is a one stop shop, key requirements and conditions, a home energy assessment and what Grants are available.
The document discusses several city special revenue and enterprise funds for the proposed FY17-18 budget. It provides financial forecasts and capital project plans for funds including Community Development, Roadway Maintenance, Water and Wastewater Impact Fees, Electric, Water, Wastewater, Sanitation, Northgate Parking, and Insurance funds. It notes factors like revenue growth, proposed rate increases, expense projections, and significant planned capital projects. Service level adjustments and additional positions are also proposed for some funds.
This document summarizes a value engineering study conducted for the Anacostia Gateway project in Washington D.C. The project involves constructing a 3-floor office building and underground parking. The value engineering team analyzed the project scope, schedule, costs and identified areas for improvement. They generated 30 ideas across architectural, structural, mechanical and general categories. These ideas were then evaluated based on criteria like cost, time, risk and benefits. The 5 highest ranking recommendations included reducing restroom size, eliminating metal canopies, using plastic windows, revising site schedules, and replacing light-weight masonry with precast concrete panels. Implementing all recommendations could save $1.24 million initially and $1,000 annually in maintenance
Similar to School Facilities Referendum Recommendations (20)
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...EduSkills OECD
Andreas Schleicher, Director of Education and Skills at the OECD presents at the launch of PISA 2022 Volume III - Creative Minds, Creative Schools on 18 June 2024.
🔥🔥🔥🔥🔥🔥🔥🔥🔥
إضغ بين إيديكم من أقوى الملازم التي صممتها
ملزمة تشريح الجهاز الهيكلي (نظري 3)
💀💀💀💀💀💀💀💀💀💀
تتميز هذهِ الملزمة بعِدة مُميزات :
1- مُترجمة ترجمة تُناسب جميع المستويات
2- تحتوي على 78 رسم توضيحي لكل كلمة موجودة بالملزمة (لكل كلمة !!!!)
#فهم_ماكو_درخ
3- دقة الكتابة والصور عالية جداً جداً جداً
4- هُنالك بعض المعلومات تم توضيحها بشكل تفصيلي جداً (تُعتبر لدى الطالب أو الطالبة بإنها معلومات مُبهمة ومع ذلك تم توضيح هذهِ المعلومات المُبهمة بشكل تفصيلي جداً
5- الملزمة تشرح نفسها ب نفسها بس تكلك تعال اقراني
6- تحتوي الملزمة في اول سلايد على خارطة تتضمن جميع تفرُعات معلومات الجهاز الهيكلي المذكورة في هذهِ الملزمة
واخيراً هذهِ الملزمة حلالٌ عليكم وإتمنى منكم إن تدعولي بالخير والصحة والعافية فقط
كل التوفيق زملائي وزميلاتي ، زميلكم محمد الذهبي 💊💊
🔥🔥🔥🔥🔥🔥🔥🔥🔥
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...indexPub
The recent surge in pro-Palestine student activism has prompted significant responses from universities, ranging from negotiations and divestment commitments to increased transparency about investments in companies supporting the war on Gaza. This activism has led to the cessation of student encampments but also highlighted the substantial sacrifices made by students, including academic disruptions and personal risks. The primary drivers of these protests are poor university administration, lack of transparency, and inadequate communication between officials and students. This study examines the profound emotional, psychological, and professional impacts on students engaged in pro-Palestine protests, focusing on Generation Z's (Gen-Z) activism dynamics. This paper explores the significant sacrifices made by these students and even the professors supporting the pro-Palestine movement, with a focus on recent global movements. Through an in-depth analysis of printed and electronic media, the study examines the impacts of these sacrifices on the academic and personal lives of those involved. The paper highlights examples from various universities, demonstrating student activism's long-term and short-term effects, including disciplinary actions, social backlash, and career implications. The researchers also explore the broader implications of student sacrifices. The findings reveal that these sacrifices are driven by a profound commitment to justice and human rights, and are influenced by the increasing availability of information, peer interactions, and personal convictions. The study also discusses the broader implications of this activism, comparing it to historical precedents and assessing its potential to influence policy and public opinion. The emotional and psychological toll on student activists is significant, but their sense of purpose and community support mitigates some of these challenges. However, the researchers call for acknowledging the broader Impact of these sacrifices on the future global movement of FreePalestine.
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptxCapitolTechU
Slides from a Capitol Technology University webinar held June 20, 2024. The webinar featured Dr. Donovan Wright, presenting on the Department of Defense Digital Transformation.
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.pptHenry Hollis
The History of NZ 1870-1900.
Making of a Nation.
From the NZ Wars to Liberals,
Richard Seddon, George Grey,
Social Laboratory, New Zealand,
Confiscations, Kotahitanga, Kingitanga, Parliament, Suffrage, Repudiation, Economic Change, Agriculture, Gold Mining, Timber, Flax, Sheep, Dairying,
Creative Restart 2024: Mike Martin - Finding a way around “no”Taste
Ideas that are good for business and good for the world that we live in, are what I’m passionate about.
Some ideas take a year to make, some take 8 years. I want to share two projects that best illustrate this and why it is never good to stop at “no”.
How to Manage Reception Report in Odoo 17Celine George
A business may deal with both sales and purchases occasionally. They buy things from vendors and then sell them to their customers. Such dealings can be confusing at times. Because multiple clients may inquire about the same product at the same time, after purchasing those products, customers must be assigned to them. Odoo has a tool called Reception Report that can be used to complete this assignment. By enabling this, a reception report comes automatically after confirming a receipt, from which we can assign products to orders.
Brand Guideline of Bashundhara A4 Paper - 2024khabri85
It outlines the basic identity elements such as symbol, logotype, colors, and typefaces. It provides examples of applying the identity to materials like letterhead, business cards, reports, folders, and websites.
1. LONG RANGE PLANNING COMMITTEE
School Facilities
Referendum
Recommendations
NOVEMBER 19, 2015
Haddonfield Public School District
2. Tonight’s goals
▪ Presentation of LRP Committee’s referendum
recommendations
▪ BOE vote on proposed referendum scope of work and
questions to meet state and county deadlines for March
referendum
▪ Upcoming meeting to address prior referendum work
after completion of State auditor report
School Facilities Referendum Recommendations
3. School Facilities Referendum Recommendations
Background information and previous presentations on facilities
conditions can be found at:
http://www.haddonfield.k12.nj.us/BOE/referendum.html
4. School Facilities Referendum Recommendation
Overview of Question Organization
▪ Question 1: critical work
▪ Question 2A: air-conditioning in all schools
▪ Question 2B: stadium, lighting and track
▪ Question 2C: building envelope work at Central/HMS and
HMHS
5. School Facilities Referendum Recommendation
Cost estimates:
▪ Developed by Becica and Associates, Preferred Construction
Management, Hill International and state-contract vendors
▪ Includes allowance for hazardous materials abatement, and
25% project “soft costs” per industry standards for renovation
work in old buildings
▪ State debt service aid estimated at 34%
▪ Illegal to use any surplus funds after construction to fund
projects not approved in referendum – excess funds will not
be bonded
6. Referendum Question 1
Criteria for scope inclusion:
▪ Non-functional and/or deteriorating conditions requiring
immediate attention
▪ Deteriorating components in danger of requiring upgrades
that cannot be addressed within constraints of operating
budget
▪ Security and safety considerations
▪ Select program needs at HMHS based on current enrollment
demands
7. Referendum Question 1: Elizabeth Haddon
Building Envelope
▪ All proposed exterior masonry and wood trim repairs
▪ New windows and doors in pre-2000s wings, incl. lintel restoration and door
hardware and electrical prep for future installation of controlled access devices
Site Work
▪ Rainwater drainage upgrades (1913, 1952 wings)
▪ Barrier-free accessible route upgrades, including signage, sidewalks, parking
Electrical
▪ Service and distribution upgrades for additional loads, incl. future window A/C
▪ Additional general use electrical outlets in 12 classrooms
Special Systems
▪ Intercom, telephone, master clock, and data system upgrades
HVAC
▪ Replacement of (3) multi-purpose room roof top units
▪ Boiler upgrades, incl. burner gas train components, indoor/outdoor reset controls,
and chimney liner restoration (excl. automatic controls)
8. Referendum Question 1: Tatem
Building Envelope
▪ All proposed exterior masonry and structural repairs
▪ EPDM roof replacement (1923 wing) and repairs (1990 wing), incl. decking
▪ New windows and doors, incl. lintel restoration and electrical prep for future
installation of controlled access devices (1913, 1954 wings)
Site Work
▪ Regrading and restoration of front yard to address drainage issues
▪ Barrier-free accessible route upgrades, incl. signage, sidewalks, parking, and ramp
▪ Sidewalk upgrades for parent drop-off
Electrical (same as Haddon)
▪ Service and distribution upgrades for additional loads, incl. future window A/C
▪ Additional general use electrical outlets in 12 classrooms
Special Systems (same as Haddon)
▪ Intercom, telephone, master clock, and data system upgrades
HVAC (same as Haddon)
▪ Boiler upgrades (excl. automatic controls)
9. Referendum Question 1: Central/HMS
Building Envelope
▪ New modificed bitumen roof, incl. roof deck repair and related work (1964 wing)
▪ All proposed exterior masonry and wood trim repairs, incl. portico
▪ Skylight removal, incl. ceiling/lighting replacement and plaster repairs at MS
rotunda (1964 wing)
Site Work
▪ Repairs to exterior concrete steps, cheek walls, railings, and sidewalks (1964 wing)
▪ Barrier-free accessible route and site upgrades, incl. widening of sidewalk along
Lincoln Ave. for student drop-off
Electrical
▪ Service and distribution upgrades for additional loads, incl. future window A/C
Special Systems (same as Haddon and Tatem)
▪ Intercom, telephone, master clock, and data system upgrades
HVAC
▪ Installation of A/C in MS cafeteria
▪ Boiler upgrades (excl. automatic controls)
10. Referendum Question 1: HMHS
Building Envelope (excl. B-wing)
▪ A-wing asphalt shingle roof replacement and C-wing modificed bitumen roof
replacement, incl. roof deck repairs and related work
B-wing Structural Repairs and Partial Reconstruction
▪ Gym exterior wall partial reconstruction and structural repairs, incl. new
windows and doors and roof repairs (no interior work)
▪ Comprehensive reconstruction of 2-story cafeteria section on existing footprint,
incl. structure for rooftop mechanical units and reconfigured cafeteria, kitchen,
toilet rooms, dance studio, and remote administrative offices
Site Work
▪ Reconstruction of exterior concrete steps, area ways and drains, walls, railings,
and sidewalks, providing barrier-free accessible routes to A and C wings
Electrical
▪ Service and distribution upgrades, including increased capacity for future A/C
installations in A-wing
continued…
11. Referendum Question 1: HMHS (continued)
Special Systems
▪ Intercom, telephone, master clock, and data system upgrades
HVAC
▪ A-wing auditorium HVAC replacement
▪ Boiler upgrades, incl. removal of existing chimney to roof line of stage and
installation of new metal flue pipe system connecting to existing boilers
▪ Upgrades to building utilities to A-wing, including sanitary and water piping
▪ A-wing crawl space repairs and upgrades to lighting and ventilation to improve
access
Educational Program Alterations and Renovations
▪ Reconfiguration of faculty room, guidance office, home economics classroom into
(1) practical arts lab and (1) science lab
12. Referendum Question 1: Estimated Costs
12
Scope Haddon Tatem Central/MS HMHS Total
Building envelope $840,000 $3,347,496 $2,052,800 $2,457,736 $8,698,032
B-wing reconst. $10,531,029 $10,531,029
Site work $135,000 $214,500 $145,000 $394,000 $888,500
Electrical $129,000 $118,000 $120,000 $148,000 $515,000
Special systems $211,707 $236,187 $630,918 $814,793 $1,893,605
HVAC $361,545 $79,125 $394,432 $1,384,572 $2,219,673
Program renovation $702,084 $702,084
HazMat + soft costs $441,813 $1,004,827 $860,787 $4,283,052 $6 ,590,479
Total project costs $2,119,065 $5,000,135 $4,203, 937 $20,715,266 $32,038,403
Est. state share $720,482 $1,700,046 $1,429,339 $7,043,191 $10,893,057
Est. local share $1,398,583 $3,300,089 $2,774,598 $13,672,076 $21,145,346
Est. yearly cost
(median home)
$225
13. Referendum Question 2A
Air-conditioning and building automation system control (BASC)
upgrades in all schools
Scope Haddon Tatem Central/MS HMHS Total
Air-conditioning and
BASC upgrades
12 clrms.
art room
offices
12 clrms.
2 SGIs
Central clrms.
MS art rm.
MS tech rm.
A-wing
$400,973 $418,403 $826,154 $631,822 $2,277,352
HazMat + soft costs $107,743 $106,600 $286,539 $182,955 $683,838
Total project costs $508,717 $525,003 $1,112,693 $814,777 $2,961,190
Est. state share $172,964 $178,501 $378,316 $277,024 $1,006,805
Est. local share $335,753 $346,502 $734,377 $537,753 $1,954,385
Est. avg. Yearly
assessment
$20
14. Referendum Question 2B
Critical upgrades to stadium and track at HMHS to maintain
current operations
Scope Total
Resurface running track $350,000
New stadium lighting and poles $350,000
Stadium structural repair allowance $800,00
Soft costs $354,152
Total project costs $1,854,152
Est. state share $148,750
Est. local share $1,705,402
Est. avg. yearly assessment (median home) $19
15. Referendum Question 2C
Building envelope work deferred from Question 1 –needed to
address ongoing deterioration but conditions not as critical
Scope Central/MS HMHS Total
New windows and doors, incl. lintel restoration and
electrical for future installation of controlled access
devices (Central - 1890, 1947, 1964 wings; HMHS – A
and C wings) $595,000 $1,976,000 $2,571,000
Masonry restoration, including canopies, in A-wing and
C-wing $590,000 $590,000
HazMat + soft costs $168,750 $691,500 $860,250
Total project costs $763,750 $3,257,500 $4,021,250
Est. state share $259,675 $1,107,550 $1,367,225
Est. local share $504,075 $2,149,950 $2,654,025
Est. avg. yearly assessment (median home) $23
16. Referendum Summary
16
Scope
Project
Total
Est.
State
Share
Est.
Local
Share
Est.
Average
Yearly
Assessment
Question 1
Building envelope (comprehensive
except Central/MS and HMHS);
site work; electrical; HVAC; HMHS
B-wing reconstruction and program
renovations
$32,038,403 $10,893,057 $21,145,346 $225
Question 2A
A/C and BASC
$2,961,190 $1,006,805 $1,954,385 $20
Question 2B
Stadium and track
$1,854,152 $148,750 $1,705,402 $19
Question 2C
Building envelope
$4,021,250 $1,367,225 $2,654,025 $23
Referendum Total $40,874,995 $13,415,837 $27,459,158 $287
17. Estimates Based On Two Assumptions:
● Median Haddonfield Home Value of
$484,225
● 20 year bonds @ 3.50% interest
Annual cost could be reduced further with
25 year bonds @ 3.75% interest
Basis For Cost Estimates
18. Annual cost could be reduced with 25 year bonds at 3.75%
20 year bond 25 year bond
Question 1 $225 $194
Question 2A $20 $18
Question 2B $19 $16
Question 2C $23 $19
Total $287 $247
19. Referendum Schedule
Mid-December Project application submission to the NJDOE
January 8, 2016 Notice to County Board of Elections
Referendum Date March 8, 2016
Tentative milestone dates, if referendum passes…
November 2016 Final submission to the NJDOE (HMHS only)
January 2017 Projects bid
April 2017 Construction start
Note: Dates are subject to final project scope of work determination and scenarios.
20. ▪ NJAC 6A:26-3.7 – Local support of school facilities projects
▪ All proposed work and corresponding local and state share must be listed
in referendum question(s).
▪ If construction costs are less than approved referendum budget,
additional work not identified in referendum cannot be added to the
project scope.
▪ Excess funds can only be used to offset shortages for other approved
work if specifically stated in referendum question.
▪ If bids are higher than estimated in the referendum question, approved
referendum work cannot be eliminated without another referendum.
▪ State closely monitors all bond proceeds to ensure proceeds are applied
to approved projects.
Key Referendum Regulations
20
21. ▪ Conformance with Public School Contract Law regulated by NJSA (NJSA
18A: 18A-1 et. seq).
▪ Public bids or state contract must be used.
▪ Lowest qualified bid must be accepted.
▪ All bids must be reviewed by school board solicitor per compliance with
bidding requirements prior to award of contract.
Key Bidding Regulations
21