SlideShare a Scribd company logo
Colt Hayes
Planning Approach
Vo 220121
Salient Features
Description Remarks
Project ID 281528
Project Name Construction of Data Centre
Project Sponsor Colt Data Centre Services UK Ltd
Project Contractor
Project Budget
Project Start Date 23rd August 2021
Project Duration 23rd Aug, 2021 ~ 22nd Dec, 2023
Project Location Hayes London
Project Scope
02 x Five Storey Buildings and 01 x Electrical Substation
Covered Area: 236,806 sft
Civil Works
MEP Works
Installation of Special Equipment
Obtaining of Utilities Connections
Testing & Commissioning
Project Stakeholders
Internal External
Concert
Nicholas Webb Architects (NWA)
Faithful & Gould
Linesight
ARUP
Black & White Engineering
Requirement Description Compliance
Y/N
Evidence / Comment
Detail Logic Linked Construction Programme including:
Pre-Construction Activities
Procurement Milestone Dates
Critical Path for Phase 1 (Building 1 incl: Shell & Core, Fit –out (6MW) and all associated External Works,
Connections Etc,
Critical Path Commentary
The programme is also to consider the remaining DH Fit –out Works post phase 1 Handover I’e’ on a 6MW
rolling basis up to 28.5MW (Total IT Capacity of Building 1).
The Contractor shall provide their proposed programme showing the sequence and timescale of
operations to achieve Completion of the Works on or before Q4 2023 taking due account of the
Employer's specific sequencing/programming requirements
Float Time
Target Handover Date
The Programme shall include a Design Programme (Stage 4B & Stage 5) with sufficient time for the
Employer and Third Parties to comment on design information.
A schedule of matters on which the Employer must or requires to comment, make decisions, approve
material samples etc., and the approximate dates when such information shall be available for the
Employer's comments etc. The schedule shall indicate the latest date when final comments, choices etc,
are required from the Employer. The Contractor must allow within the programme a minimum of 10
working days for the Employer to comment
PROGRAMME REQUIREMENTS
Requirement Description Compliance
Y/N
Evidence / Comment
The Programme should consider at high-level the following constraints which will be the responsibility
of the Contractor to manage:
• Construction Logistics
• Neighbourly Matters / Constraints Imposed by Adjoining Owners & Stakeholders
• Limitation of Working Hours
• Schedule of Conditions for Adjoining Property
The Programme is to consider the following Constraints and Client Milestones:
• Planning Committee (19/01/22)
• Planning - Clear of Judicial Review & S106 (Apr-22)
• Completion of Enabling Works (21/04/22)
• Complete Discharge of Pre-Commencement Conditions (Jun – 22)
• Start on Site (04/07/22)
• Substation Completion (SOS August-22) (27/03/23)
• Completion / RFS 6MW (Q4 – 2023)
PROGRAMME REQUIREMENTS
Key Dates
Description Completion Date
Customer Complete Demo & Enabling - Early Access, Start Surveys 21st Apr, 2022
Start on Site 04th July, 2022
Ground Breaking Ceremony 04th July, 2022
Substation Complete by Others 27th March, 2023
Instruct Phase Two 23rd June, 2023
UG Services: Fibre Branch complete 17th July, 2023
Water supply for flushing 31st Aug, 2023
UG Services: Electrical Branch complete 05th Sep, 2023
Electrical power required 15th Sep, 2023
UG Services: Water Branch complete 15th Sep, 2023
PC - 6MW 22nd Dec, 2023
Instruct Phase Two Demo 05th Feb, 2024
2022 2023
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
MEP Works
04/07/22
Start on Site
04/07/22
Ground Breaking Ceremony
23/06/23
Instruct Phase Two
27/03/23
Substation Complete by Others
17/07/23
UG Services: Fibre Branch complete
31/08/23
Water supply for flushing
31/08/23
UG Services: Electrical Branch complete
31/08/23
UG Services: Electrical Branch complete
15/09/23
UG Services: Water Branch complete
5/09/23
Electrical Power Required
Surface Water
Surveys
21/04/22
Customer Complete Demo &
Enabling - Early Access, Start Surveys
Mechanical - Lead-in periods
Electrical - Lead-in periods
Fire - Lead-in periods
Programme
22/12/23
PC
PRINCIPLE Programme Constraint Dates
Imtech Phase 1 works:-
• MV distribution including plant and UPSs. Generators. LV distribution including
plant, cables and busbars. Primary and secondary containment systems. Small
power. Lighting. Emergency lighting including static inverters. External lighting.
Lighting controls. Power management system. Energy management system.
Integration of EMS and PMS to BMS. Fire alarm. CCTV. Access control. Disabled
systems. Specialist earthing systems. Earthing systems. Lightning protection. Data
and communications network. Ventilation - including AHUs, water source heat
pump energy recovery systems on AHUs, ductwork, VCDs, grilles & diffusers,
attenuators and smoke dampers. Smoke extract - cold smoke extract in data hall
and stairs. Chilled water system - Chillers, pipework, insulation, pumps and large
buffer vessels. VRF / DX cooling system with condensate pipework. Process water
system. Water softening system. Main incoming cold water. Sprinkler system.
Gaseous suppression systems. Fire hydrant mains. Domestic water systems - point
of use hot water heaters. Above ground drainage. Rainwater harvesting to WCs.
Fuel and Urea pipework systems for the generators. Electrical heating to selected
areas. BMS. Trace heating. Testing and commissioning.
Phase 1 Scope of Works (SoW) Matrix
Definition of Catagories By Main
Contractor
By
Others
Shell &
Core
Fit Out Comments
Utilities
UT HV Power to Site (HV Sub-Station) X P P
UT Water Connection P X P
UT Fibre Connection P X P
UT Telecoms Connection P X P
UT Sewer / Drainage Connection P X P
External Works:
External Landscaping:
EXT Hard & Soft Landscaping P X P
EXT Bin Stores, Cycle Shelter, Smoking Shelters P X P
External Security:
EXT Perimeter Fence and Gates P X P
EXT Visitor Reception Centre P X P
EXT Below ground ducts to external security equipment locations P X P
EXT Poles for CCTV cameras P X P
EXT Bollards P X P
EXT Rising Blockers P X P
External Below Ground Services:
EXT Drainage - Foul & Surface P X P
EXT Water Services & Fire Main P X P
EXT MV/LV Ducts P X P
EXT Security ducts P X P
EXT Zero Cable Vaults P X P
Phase 1 Scope of Works (SoW) Matrix
Definition of Catagories By Main
Contractor
By
Others
Shell &
Core
Fit Out Comments
External Below Ground Services: continued
EXT Comms ducts X P P
External Above Ground Services:
EXT External lighting P X P
Data Centre Building (Building 1):
Building Envelope.
DC Steel / concrete frame to building P X P
DC Steelwork to Cooling Plant gantry P X P
DC Metalwork - Handrails to Cooling Plant Gantry P X P
DC Metalwork - mesh flooring in risers P X P
DC External walls - brickwork, cladding, living walls. P X P
DC External walls - Penetrations/Openings for Cooling Plant P X P
DC External walls - feature vertical fins / Punched Metal P X P
DC External walls - penetrations for M&E Services P X P
DC External screening - to roof plant (admin / core plant) P X P
DC External screening - to roof plant (DC plant) P X P
DC External Doors P X P
DC Roof - Flat roof system P X P
DC Roof -penetrations for M&E Services P X P
DC Roof - PV Cells P X P
Stair Cores and Risers:
DC Staircases
DC Balustrades and Handrails.
DC Stair core and riser walls.
Phase 1 Scope of Works (SoW) Matrix
Definition of Catagories By Main
Contractor
By
Others
Shell &
Core
Fit Out Comments
Stair Cores and Risers: Continued
DC Core doors from stair cores, with ironmongery. X P P
DC Riser Doors. P X P
Internal Fit-Out:
DC Internal walls to data halls and plant rooms. P X P
DC Internal doors to data halls and plant rooms P X P
DC Floor finishes. P X P
DC Wall finishes. P X P
DC Ceiling finishes. P X P
DC Electronic Security installation P X P
M&E Services Fit-Out:
DC Temporary lighting P X P
DC Temporary fire alarm P X P
DC Transformers P X P
DC LV Switchgear P X P
DC Primary Containment P X P
DC Secondary MEP containment in data halls P X P
DC Secondary Data containment in data halls P X P
DC Busbar to Cabinets P X P
DC Hot Aisle Containment P X P
DC Lighting P X P
DC Small Power P X P
DC Control Cabling P X P
DC Earthing, generally P X P
Phase 1 Scope of Works (SoW) Matrix
Definition of Catagories By Main
Contractor
By
Others
Shell &
Core
Fit Out Comments
M&E Services: Continued
DC Cabinet earthing Cu tape fixed to IT basket P X P
DC Fire Alarm & Sprinklers generally P X P
DC ire Alarm & Sprinklers (To Data Halls and data cabinet containment). P X P
DC PMS P X P
DC BMS P X P
DC BWIC, including bunding. P X P
Admin Areas and Core Building:
Building Envelope:
AACB Steel frame to building P X
P X
P X P
P X P
P X P
P X P
P X P
P X P
P X P
P X P
P X P
P X P
P X P
Total Floor G Floor 01 Floor 02 Floor 03 Floor 04 Roof
Gantry
Total Area Building 1 23,401 3984 3955 3968 3939 3921 3634
External Gantry Area Building 1 6,775 1242 1419 1420 1431 1263 0
Building 1 Total Floor G Floor 01 Floor 02 Floor 03 Floor 04 Roof
Data Hall (Standard) 4x932m² 8,829 981 1962 1962 1962 1962
Technical (M&E) 3,412 1108 576 575 577 576
Office 2,723 796 516 517 473 421
Storage (General)
Storage (Tenant)
Storage (COLT) 1,071 165 223 223 223 237
Storage (COLT Alternative)
Circulation 2,670 647 481 500 511 531
Circulation (Vertical) 915 146 155 149 151 152 162
Loading bay 99 99
Riser 211 43 42 42 42 42
Undercroft -
External Gantry 10,247 1242 1419 1420 1431 1263 3472
Phase 1 Scope of Total Area of the Works
Phase 1 Drawing
:Level 00
DCS20109-NWA-DC-01-00-DR-A-25200
List of Works
Cooling units
FLS Riser
BMS Server Room
Stairs
Fibre Riser
Elec Room
BMS Server Room
Corridor
Phase 1 Drawing
:Level 01
DCS20109-NWA-DC-01-01-DR-A-25210
List of Works
Cooling units
FLS Riser
BMS Server Room
Stairs
Fibre Riser
Elec Room
BMS Server Room
Corridor
Phase 1 Drawing
:Level 02
DCS20109-NWA-DC-01-02-DR-A-25220
List of Works
Cooling units
FLS Riser
BMS Server Room
Data Hall 4 & 5
Fibre Riser
Elec Room
BMS Server Room
Corridor
Phase 1 Drawing
:Level 03
DCS20109-NWA-DC-01-03-DR-A-25230
List of Works
Cooling units
FLS Riser
BMS Server Room
Data Hall 6 & 7
Fibre Riser
Elec Riser
BMS Server Room
Corridor
Phase 1 Drawing
Level 04
DCS20109-NWA-DC-01-04-DR-A-25240
List of Works
Corridor
Cooling Unit
BMS Server Room
Fibre Riser
Store
Elec Riser
BMS Server Room
Corridor
Phase 1 Drawing
:Level Roof
05-01
DCS20109-NWA-DC-01-05-DR-A-25250
List of Works
Cooling units
FLS Riser
BMS Server Room
Fibre Riser
Fibre Riser
Elec Room
BMS Server Room
Corridor
Phase 1 Drawing
Level Roof
05 02
DCS20109-NWA-DC-01-06-DR-A-25260
List of Works
Cooling Gantry
2002 - HH4 - Hemel Hempstead
Consolidation
Centre
Gen FAT Test
France
Gen Pod FAT Test
England
HV Switch Gear
FAT Test
HV Switch Pod
FAT Test
Ship Ship
LV Switch Gear
FAT Test
LV Switch Pod
FAT Test
Controls FI
FAT Test
Life Safety FI
FAT Test
Project Delivery LON
Free Issue Components
For incorporation into Pods
Ship
Programme – Consolidation Testing
Colt Hayes Planning Approach v1 220121.pptx

More Related Content

Similar to Colt Hayes Planning Approach v1 220121.pptx

Clelio alves petrobras english
Clelio alves petrobras englishClelio alves petrobras english
Clelio alves petrobras english
FieldComm Group
 
Baf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomsonBaf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomson
Ken Thomson
 
Commissioning Engineer
Commissioning EngineerCommissioning Engineer
Commissioning EngineerMathivanan K
 
A-Shiva YC@EPCC- 219KB
A-Shiva YC@EPCC- 219KBA-Shiva YC@EPCC- 219KB
A-Shiva YC@EPCC- 219KBShiva Y Cmath
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
ignitetribes
 
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan
 
SETHUMADHAVAN SENIOR COMMISSIONING ENGINEER
SETHUMADHAVAN SENIOR  COMMISSIONING ENGINEERSETHUMADHAVAN SENIOR  COMMISSIONING ENGINEER
SETHUMADHAVAN SENIOR COMMISSIONING ENGINEERSETHU MADHAVAN
 
project electrical engineer
project electrical engineerproject electrical engineer
project electrical engineer
Engr.Jahangir Ali Ahmed
 
Watkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptxWatkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptx
TanveerAziz7
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
PradeepKumar504728
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
SLIIT, Sri Lanka
 
Noli updated Resume
Noli updated ResumeNoli updated Resume
Noli updated Resumenoli donez
 
Naveen Curriculum vitae Project manager
Naveen Curriculum vitae Project managerNaveen Curriculum vitae Project manager
Naveen Curriculum vitae Project managerNaveen Rengasamy
 
c.v. of sales Engineer
c.v. of sales Engineerc.v. of sales Engineer
c.v. of sales EngineerMa Faiz
 

Similar to Colt Hayes Planning Approach v1 220121.pptx (20)

Clelio alves petrobras english
Clelio alves petrobras englishClelio alves petrobras english
Clelio alves petrobras english
 
Baf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomsonBaf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomson
 
Commissioning Engineer
Commissioning EngineerCommissioning Engineer
Commissioning Engineer
 
A-Shiva YC@EPCC- 219KB
A-Shiva YC@EPCC- 219KBA-Shiva YC@EPCC- 219KB
A-Shiva YC@EPCC- 219KB
 
Resume
ResumeResume
Resume
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16
 
SETHUMADHAVAN SENIOR COMMISSIONING ENGINEER
SETHUMADHAVAN SENIOR  COMMISSIONING ENGINEERSETHUMADHAVAN SENIOR  COMMISSIONING ENGINEER
SETHUMADHAVAN SENIOR COMMISSIONING ENGINEER
 
Presentation
PresentationPresentation
Presentation
 
talhadiploma.doc
talhadiploma.doctalhadiploma.doc
talhadiploma.doc
 
project electrical engineer
project electrical engineerproject electrical engineer
project electrical engineer
 
PROJECT ENGINEER- ELECTRICAL._L
PROJECT ENGINEER-  ELECTRICAL._LPROJECT ENGINEER-  ELECTRICAL._L
PROJECT ENGINEER- ELECTRICAL._L
 
Watkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptxWatkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptx
 
Somchai J.'s CV_2016 ++
Somchai J.'s CV_2016 ++Somchai J.'s CV_2016 ++
Somchai J.'s CV_2016 ++
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
Rajesh CV -
Rajesh CV - Rajesh CV -
Rajesh CV -
 
Noli updated Resume
Noli updated ResumeNoli updated Resume
Noli updated Resume
 
Naveen Curriculum vitae Project manager
Naveen Curriculum vitae Project managerNaveen Curriculum vitae Project manager
Naveen Curriculum vitae Project manager
 
c.v. of sales Engineer
c.v. of sales Engineerc.v. of sales Engineer
c.v. of sales Engineer
 

More from IrfanAwan25

cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
IrfanAwan25
 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.ppt
IrfanAwan25
 
Progress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptxProgress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptx
IrfanAwan25
 
Das HSE.ppt
Das HSE.pptDas HSE.ppt
Das HSE.ppt
IrfanAwan25
 
Progress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptxProgress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptx
IrfanAwan25
 
product-development-roadmap-template.pptx
product-development-roadmap-template.pptxproduct-development-roadmap-template.pptx
product-development-roadmap-template.pptx
IrfanAwan25
 
Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptx
IrfanAwan25
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
IrfanAwan25
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
IrfanAwan25
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
IrfanAwan25
 

More from IrfanAwan25 (10)

cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.ppt
 
Progress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptxProgress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptx
 
Das HSE.ppt
Das HSE.pptDas HSE.ppt
Das HSE.ppt
 
Progress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptxProgress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptx
 
product-development-roadmap-template.pptx
product-development-roadmap-template.pptxproduct-development-roadmap-template.pptx
product-development-roadmap-template.pptx
 
Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptx
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
 

Recently uploaded

Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 

Recently uploaded (20)

Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 

Colt Hayes Planning Approach v1 220121.pptx

  • 2. Salient Features Description Remarks Project ID 281528 Project Name Construction of Data Centre Project Sponsor Colt Data Centre Services UK Ltd Project Contractor Project Budget Project Start Date 23rd August 2021 Project Duration 23rd Aug, 2021 ~ 22nd Dec, 2023 Project Location Hayes London
  • 3. Project Scope 02 x Five Storey Buildings and 01 x Electrical Substation Covered Area: 236,806 sft Civil Works MEP Works Installation of Special Equipment Obtaining of Utilities Connections Testing & Commissioning
  • 4. Project Stakeholders Internal External Concert Nicholas Webb Architects (NWA) Faithful & Gould Linesight ARUP Black & White Engineering
  • 5. Requirement Description Compliance Y/N Evidence / Comment Detail Logic Linked Construction Programme including: Pre-Construction Activities Procurement Milestone Dates Critical Path for Phase 1 (Building 1 incl: Shell & Core, Fit –out (6MW) and all associated External Works, Connections Etc, Critical Path Commentary The programme is also to consider the remaining DH Fit –out Works post phase 1 Handover I’e’ on a 6MW rolling basis up to 28.5MW (Total IT Capacity of Building 1). The Contractor shall provide their proposed programme showing the sequence and timescale of operations to achieve Completion of the Works on or before Q4 2023 taking due account of the Employer's specific sequencing/programming requirements Float Time Target Handover Date The Programme shall include a Design Programme (Stage 4B & Stage 5) with sufficient time for the Employer and Third Parties to comment on design information. A schedule of matters on which the Employer must or requires to comment, make decisions, approve material samples etc., and the approximate dates when such information shall be available for the Employer's comments etc. The schedule shall indicate the latest date when final comments, choices etc, are required from the Employer. The Contractor must allow within the programme a minimum of 10 working days for the Employer to comment PROGRAMME REQUIREMENTS
  • 6. Requirement Description Compliance Y/N Evidence / Comment The Programme should consider at high-level the following constraints which will be the responsibility of the Contractor to manage: • Construction Logistics • Neighbourly Matters / Constraints Imposed by Adjoining Owners & Stakeholders • Limitation of Working Hours • Schedule of Conditions for Adjoining Property The Programme is to consider the following Constraints and Client Milestones: • Planning Committee (19/01/22) • Planning - Clear of Judicial Review & S106 (Apr-22) • Completion of Enabling Works (21/04/22) • Complete Discharge of Pre-Commencement Conditions (Jun – 22) • Start on Site (04/07/22) • Substation Completion (SOS August-22) (27/03/23) • Completion / RFS 6MW (Q4 – 2023) PROGRAMME REQUIREMENTS
  • 7. Key Dates Description Completion Date Customer Complete Demo & Enabling - Early Access, Start Surveys 21st Apr, 2022 Start on Site 04th July, 2022 Ground Breaking Ceremony 04th July, 2022 Substation Complete by Others 27th March, 2023 Instruct Phase Two 23rd June, 2023 UG Services: Fibre Branch complete 17th July, 2023 Water supply for flushing 31st Aug, 2023 UG Services: Electrical Branch complete 05th Sep, 2023 Electrical power required 15th Sep, 2023 UG Services: Water Branch complete 15th Sep, 2023 PC - 6MW 22nd Dec, 2023 Instruct Phase Two Demo 05th Feb, 2024
  • 8. 2022 2023 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC MEP Works 04/07/22 Start on Site 04/07/22 Ground Breaking Ceremony 23/06/23 Instruct Phase Two 27/03/23 Substation Complete by Others 17/07/23 UG Services: Fibre Branch complete 31/08/23 Water supply for flushing 31/08/23 UG Services: Electrical Branch complete 31/08/23 UG Services: Electrical Branch complete 15/09/23 UG Services: Water Branch complete 5/09/23 Electrical Power Required Surface Water Surveys 21/04/22 Customer Complete Demo & Enabling - Early Access, Start Surveys Mechanical - Lead-in periods Electrical - Lead-in periods Fire - Lead-in periods Programme 22/12/23 PC
  • 10. Imtech Phase 1 works:- • MV distribution including plant and UPSs. Generators. LV distribution including plant, cables and busbars. Primary and secondary containment systems. Small power. Lighting. Emergency lighting including static inverters. External lighting. Lighting controls. Power management system. Energy management system. Integration of EMS and PMS to BMS. Fire alarm. CCTV. Access control. Disabled systems. Specialist earthing systems. Earthing systems. Lightning protection. Data and communications network. Ventilation - including AHUs, water source heat pump energy recovery systems on AHUs, ductwork, VCDs, grilles & diffusers, attenuators and smoke dampers. Smoke extract - cold smoke extract in data hall and stairs. Chilled water system - Chillers, pipework, insulation, pumps and large buffer vessels. VRF / DX cooling system with condensate pipework. Process water system. Water softening system. Main incoming cold water. Sprinkler system. Gaseous suppression systems. Fire hydrant mains. Domestic water systems - point of use hot water heaters. Above ground drainage. Rainwater harvesting to WCs. Fuel and Urea pipework systems for the generators. Electrical heating to selected areas. BMS. Trace heating. Testing and commissioning.
  • 11. Phase 1 Scope of Works (SoW) Matrix Definition of Catagories By Main Contractor By Others Shell & Core Fit Out Comments Utilities UT HV Power to Site (HV Sub-Station) X P P UT Water Connection P X P UT Fibre Connection P X P UT Telecoms Connection P X P UT Sewer / Drainage Connection P X P External Works: External Landscaping: EXT Hard & Soft Landscaping P X P EXT Bin Stores, Cycle Shelter, Smoking Shelters P X P External Security: EXT Perimeter Fence and Gates P X P EXT Visitor Reception Centre P X P EXT Below ground ducts to external security equipment locations P X P EXT Poles for CCTV cameras P X P EXT Bollards P X P EXT Rising Blockers P X P External Below Ground Services: EXT Drainage - Foul & Surface P X P EXT Water Services & Fire Main P X P EXT MV/LV Ducts P X P EXT Security ducts P X P EXT Zero Cable Vaults P X P
  • 12. Phase 1 Scope of Works (SoW) Matrix Definition of Catagories By Main Contractor By Others Shell & Core Fit Out Comments External Below Ground Services: continued EXT Comms ducts X P P External Above Ground Services: EXT External lighting P X P Data Centre Building (Building 1): Building Envelope. DC Steel / concrete frame to building P X P DC Steelwork to Cooling Plant gantry P X P DC Metalwork - Handrails to Cooling Plant Gantry P X P DC Metalwork - mesh flooring in risers P X P DC External walls - brickwork, cladding, living walls. P X P DC External walls - Penetrations/Openings for Cooling Plant P X P DC External walls - feature vertical fins / Punched Metal P X P DC External walls - penetrations for M&E Services P X P DC External screening - to roof plant (admin / core plant) P X P DC External screening - to roof plant (DC plant) P X P DC External Doors P X P DC Roof - Flat roof system P X P DC Roof -penetrations for M&E Services P X P DC Roof - PV Cells P X P Stair Cores and Risers: DC Staircases DC Balustrades and Handrails. DC Stair core and riser walls.
  • 13. Phase 1 Scope of Works (SoW) Matrix Definition of Catagories By Main Contractor By Others Shell & Core Fit Out Comments Stair Cores and Risers: Continued DC Core doors from stair cores, with ironmongery. X P P DC Riser Doors. P X P Internal Fit-Out: DC Internal walls to data halls and plant rooms. P X P DC Internal doors to data halls and plant rooms P X P DC Floor finishes. P X P DC Wall finishes. P X P DC Ceiling finishes. P X P DC Electronic Security installation P X P M&E Services Fit-Out: DC Temporary lighting P X P DC Temporary fire alarm P X P DC Transformers P X P DC LV Switchgear P X P DC Primary Containment P X P DC Secondary MEP containment in data halls P X P DC Secondary Data containment in data halls P X P DC Busbar to Cabinets P X P DC Hot Aisle Containment P X P DC Lighting P X P DC Small Power P X P DC Control Cabling P X P DC Earthing, generally P X P
  • 14. Phase 1 Scope of Works (SoW) Matrix Definition of Catagories By Main Contractor By Others Shell & Core Fit Out Comments M&E Services: Continued DC Cabinet earthing Cu tape fixed to IT basket P X P DC Fire Alarm & Sprinklers generally P X P DC ire Alarm & Sprinklers (To Data Halls and data cabinet containment). P X P DC PMS P X P DC BMS P X P DC BWIC, including bunding. P X P Admin Areas and Core Building: Building Envelope: AACB Steel frame to building P X P X P X P P X P P X P P X P P X P P X P P X P P X P P X P P X P P X P
  • 15. Total Floor G Floor 01 Floor 02 Floor 03 Floor 04 Roof Gantry Total Area Building 1 23,401 3984 3955 3968 3939 3921 3634 External Gantry Area Building 1 6,775 1242 1419 1420 1431 1263 0 Building 1 Total Floor G Floor 01 Floor 02 Floor 03 Floor 04 Roof Data Hall (Standard) 4x932m² 8,829 981 1962 1962 1962 1962 Technical (M&E) 3,412 1108 576 575 577 576 Office 2,723 796 516 517 473 421 Storage (General) Storage (Tenant) Storage (COLT) 1,071 165 223 223 223 237 Storage (COLT Alternative) Circulation 2,670 647 481 500 511 531 Circulation (Vertical) 915 146 155 149 151 152 162 Loading bay 99 99 Riser 211 43 42 42 42 42 Undercroft - External Gantry 10,247 1242 1419 1420 1431 1263 3472 Phase 1 Scope of Total Area of the Works
  • 16. Phase 1 Drawing :Level 00 DCS20109-NWA-DC-01-00-DR-A-25200 List of Works Cooling units FLS Riser BMS Server Room Stairs Fibre Riser Elec Room BMS Server Room Corridor
  • 17. Phase 1 Drawing :Level 01 DCS20109-NWA-DC-01-01-DR-A-25210 List of Works Cooling units FLS Riser BMS Server Room Stairs Fibre Riser Elec Room BMS Server Room Corridor
  • 18. Phase 1 Drawing :Level 02 DCS20109-NWA-DC-01-02-DR-A-25220 List of Works Cooling units FLS Riser BMS Server Room Data Hall 4 & 5 Fibre Riser Elec Room BMS Server Room Corridor
  • 19. Phase 1 Drawing :Level 03 DCS20109-NWA-DC-01-03-DR-A-25230 List of Works Cooling units FLS Riser BMS Server Room Data Hall 6 & 7 Fibre Riser Elec Riser BMS Server Room Corridor
  • 20. Phase 1 Drawing Level 04 DCS20109-NWA-DC-01-04-DR-A-25240 List of Works Corridor Cooling Unit BMS Server Room Fibre Riser Store Elec Riser BMS Server Room Corridor
  • 21. Phase 1 Drawing :Level Roof 05-01 DCS20109-NWA-DC-01-05-DR-A-25250 List of Works Cooling units FLS Riser BMS Server Room Fibre Riser Fibre Riser Elec Room BMS Server Room Corridor
  • 22. Phase 1 Drawing Level Roof 05 02 DCS20109-NWA-DC-01-06-DR-A-25260 List of Works Cooling Gantry
  • 23. 2002 - HH4 - Hemel Hempstead Consolidation Centre Gen FAT Test France Gen Pod FAT Test England HV Switch Gear FAT Test HV Switch Pod FAT Test Ship Ship LV Switch Gear FAT Test LV Switch Pod FAT Test Controls FI FAT Test Life Safety FI FAT Test Project Delivery LON Free Issue Components For incorporation into Pods Ship Programme – Consolidation Testing