SlideShare a Scribd company logo
1 of 60
Project scheduling and
Maintenance
management
UNIT VI
Introduction
 Network analysis is one of the important tools for project
management.
 Whether major or minor a project has to be completed in a definite
time & at a definite cost.
 The necessary information of any particular data can be represented
as a project network.
 These techniques are very useful for planning, scheduling and
executing large-time bound projects involving careful co-ordination
of variety of complex and interrelated activities
Network Analysis
Objectives of network analysis
 Helpful in planning
 Inter-relationship of various activities
 Cost control
 Minimisation of maintenance time
 Reduction of time
 Control on idle resources
 Avoiding delays, interruptions, etc
Applications of network analysis
 Planning, scheduling, monitoring and control of
large and complex projects.
 Construction of factories, highways, building,
bridges, cinemas etc.
 Helpful to army for its missile development.
 Assembly line scheduling
 Installation of computers and high tech
machineries
 To make marketing strategies
Methodology Involved in Network
Analysis
Describing the Project
Diagramming the network
Estimating the time of completion
Deterministic
estimates
Probabilistic
estimates
Monitoring the project progress
Key terminology
 Activity : All projects may be viewed as composed of activities.
It is the smallest unit of work consuming both time & resources
that project manager should schedule & control.
 An activity is represented by an arrow in network diagram
The head of the arrow shows sequence of
activities.
 Classification of activities
 Predecessor activity: Activities that must be completed
immediately prior to the start of another activity are called
predecessor activities.
 Successor activity : activities that cannot be started until one or
more of other activities are completed but immediately succeed
them are called successor activities.
 Concurrent activities: activities that can be accomplished together
are known as concurrent activities.
 Dummy activity: An activity which does not consume any resource
but merely depicts the dependence of one activity on other is called
dummy activity. It is introduced in a network when two or more
parallel activities have the same start and finish nodes.
 Event:
 The beginning & end of an activities are called as events .
 Events are represented by numbered circles called nodes.
i j
Event
start
Event
finish
Types of Events
 Merge event
 Burst event
 Merge & Burst Event
Path & Network
 An unbroken chain of activity arrows connecting the initial event to
some other event is called a path.
 A network is the graphical representation of logically & sequentially
connected arrows & nodes representing activities & events of a
project . It is a diagram depicting precedence relationships between
different activities.
Key terminology continued…
Guidelines for Network
Construction
 A complete network diagram should have one stand point & one
finish point.
 The flow of the diagram should be from left to right.
 Arrows should not be crossed unless it is completely unavoidable.
 Arrows should be kept straight & not curved or bent.
 Angle between arrows should as large as possible.
 Each activity must have a tail or head event.. No two or more
activities may have same tail & head events.
 Once the diagram is complete the nodes should be numbered from
left to right. It should then be possible to address each activity
uniquely by its tail & head event.
Stages for project management
 Project planning stages : In order to
visualize the sequencing or precedence
requirements of the activities in a project, it
is helpful to draw a network diagram.
 Scheduling stage : Once all work
packages have been identified and given
unique names or identifiers, scheduling of
the project is required
 Project control stage :
Project control refers to evaluating
actual progress against the plan. If
significant differences are observed, then
the scheduling and resources allocation
decisions are changed to update and
revise the uncompleted part of the project
Advantages of PERT/CPM
 Planning & controlling projects
 Flexibility
 Designation of responsibilities
 Achievement of objective with least cost
 Better managerial control
Limitations of PERT /CPM
 Network diagrams should have clear starting & ending points , which
are independent of each other which may not be possible in real life.
 Another limitation is that it assumes that manager should focus on
critical activities.
 Resources will be available when needed for completion for an an
activity is again unreal.
Difficulties
 Difficulty in securing realistic time estimates.
 The planning & implementation of networks requires trained staff.
 Developing clear logical network is troublesome.
Example
Activity Predecessor
activity
A none
B none
C A
D A
E B
F C
G D & E
1
3
2
5
4
6
A
B
C
D
E
F
G
Draw the network diagram for the following
Activity Predecessor
activity
A none
B A
C A
D B
E C
F D ,E
1 2
3
4
5 6
A
B
C
D
E
F
Critical path
 Those activities which contribute directly to the overall duration of
the project constitute critical activities, the critical activities form a
chain running through the network which is called critical path.
 Critical event : The slack of an event is the difference between the
latest & earliest events time. The events with zero slack time are
called as critical events.
 Critical activities : The difference between latest start time &
earliest start time of an activity will indicate amount of time by which
the activity can be delayed without affecting the total project
duration. The difference is usually called total float. Activities with 0
total float are called as critical activities
Critical path
 The critical path is the longest path in the network from the starting
event to ending event & defines the minimum time required to
complete the project.
 The critical path is denoted by darker or double lines.
Fulkerson’s Rule for Numbering
the Events
Difference between PERT & CPM
PERT
A probability model with
uncertainty in activity
duration . The duration of
each activity is computed
from multiple time estimates
with a view to take into
account time uncertainty.
It is applied widely for
planning & scheduling
research projects.
PERT analysis does not
usually consider costs.
CPM
A deterministic model with well
known activity times based upon the
past experience.
It is used for construction projects &
business problems.
CPM deals with cost of project
schedules & minimization.
PERT
PERT is designed for scheduling complex projects that
involve many inter-related tasks. it improves
planning process because:
1. It forms planner to define the projects various
components activities.
2. It provides a basis for normal time estimates & yet
allows for some measure of optimism or pessimism
in estimating the completion dates.
3. It shows the effects of changes to overall plans they
contemplated.
4. It provides built in means for ongoing evaluation of
the plan.
ESTIMATING ACTIVITY TIMES
 Optimistic time ( t0 ) : is that time estimate of an
activity when everything is assumed to go as per plan.
In other words it is the estimate of minimum possible
time which an activity takes in completion under ideal
conditions.
 Most likely time ( tm ) : the time which the activity will
take most frequently if repeated number of times.
 Pessimistic time ( tp) : the unlikely but possible
performance time if whatever could go wrong , goes
wrong in series. In other words it is the longest time
the can take.
EXPECTED TIME
 The times are combined statically to develop the expected
time te .
te = to + 4tm + tp
6
Standard deviation of the time of the time required to
complete the project
St = tp - to
6
Variance Vt = St × St
STEPS INVOLVED IN PERT
 Develop list of activities.
 A rough network for PERT is drawn.
 Events are numbered from left to right.
 Time estimates for each activity are obtained.
 Expected time for each activity is calculated : to+4tm+tp / 6
 Using these expected times calculate earliest & latest finish
& start times of activities.
 Estimate the critical path.
 Using this estimate compute the probability of meeting a
specified completion date by using the standard normal
equation
Z = Due date – expected date of completion
standard deviation of critical path
Books for numerical practices
 INDUSTRIAL ENGINEERING & MANAGEMENT by
PRAVIN KUMAR, PEARSON
 INDUSTRIAL ENGINEERING AND PRODUCTION
MANAGMENT by MARTAND TELSANG, S. CHAND &
COMPANY
 INDUSTRIAL ENGINEERING AND MANAGEMENT by
RAVI SHANKAR, GALGOTIAPUBLICATIONS
Maintenance Planning
Maintenance
 All actions necessary for retaining an item,
or restoring to it, a serviceable condition,
include servicing, repair, modification,
overhaul, inspection and condition
verification
 Increase availability of a system
 Keep system’s equipment in working order
Purpose of Maintenance
 Attempt to maximize performance of
production equipment efficiently and
regularly
 Prevent breakdown or failures
 Minimize production loss from failures
 Increase reliability of the operating
systems
Principle Objectives in
Maintenance
 To achieve product quality and customer
satisfaction through adjusted and serviced
equipment
 Maximize useful life of equipment
 Keep equipment safe and prevent safety
hazards
 Minimize frequency and severity of interruptions
 Maximize production capacity – through high
utilization of facility
Problems in Maintenance
 Lack of management attention to maintenance
 Little participation by accounting in analyzing
and reporting costs
 Difficulties in applying quantitative analysis
 Difficulties in obtaining time and cost estimates
for maintenance works
 Difficulties in measuring performance
Maintenance Objectives
 Must be consistent with the goals of
production (cost, quality, delivery, safety)
 Must be comprehensive and include
specific responsibilities
Maintenance Costs
 Cost to replace or repair
 Losses of output
 Delayed shipment
 Scrap and rework
Types of Maintenance
 Maintenance may be classified into four
categories:
 Corrective or Breakdown maintenance
 Scheduled maintenance
 Preventive maintenance
 Predictive (Condition-based) maintenance
Corrective or Breakdown
Maintenance
 Corrective or Breakdown maintenance implies
that repairs are made after the equipment is
failed and can not perform its normal function
anymore
 Quite justified in small factories where:
 Down times are non-critical and repair costs are less
than other type of maintenance
 Financial justification for scheduling are not felt
Disadvantages of Corrective
Maintenance
 Breakdown generally occurs inappropriate times
leading to poor and hurried maintenance
 Excessive delay in production & reduces output
 Faster plant deterioration
 Increases chances of accidents and less safety for
both workers and machines
 More spoilt materials
 Direct loss of profit
 Can not be employed for equipments regulated by
statutory provisions e.g. cranes, lift and hoists etc
Scheduled Maintenance
 Scheduled maintenance is a stitch-in-time
procedure and incorporates
 inspection
 lubrication
 repair and overhaul of equipments
 If neglected can result in breakdown
 Generally followed for:
 overhauling of machines
 changing of heavy equipment oils
 cleaning of water and other tanks etc.
Preventive Maintenance
 Principle – “Prevention is better than cure”
 Procedure - Stitch-in-time
 It
 locates weak spots of machinery and equipments
 provides them periodic/scheduled inspections and
minor repairs to reduce the danger of unanticipated
breakdowns
Advantages
 Advantages:
 Reduces break down and thereby down time
 Lass odd-time repair and reduces over time of
crews
 Greater safety of workers
 Lower maintenance and repair costs
 Less stand-by equipments and spare parts
 Better product quality and fewer reworks and
scraps
 Increases plant life
 Increases chances to get production incentive
bonus
Predictive (Condition-based)
Maintenance
 In predictive maintenance, machinery conditions
are periodically monitored and this enables the
maintenance crews to take timely actions,
such as machine adjustment, repair or overhaul
 It makes use of human sense and other sensitive
instruments, such as
 audio gauge, vibration analyzer, amplitude meter,
pressure, temperature and resistance strain gauges
etc.
Predictive Maintenance (Contd.)
Unusual sounds coming out of a rotating
equipment predicts a trouble
An excessively hot electric cable predicts a
trouble
Simple hand touch can point out many
unusual equipment conditions and thus
predicts a trouble
Maintenance Costs
Maintenance
Commitment
Cost
Breakdown Cost
Maintenance Costs
Maintenance
Commitment
Cost
PM Cost
Breakdown Cost
Maintenance Costs
Maintenance
Commitment
Cost
PM Cost
Breakdown Cost
Total Maintenance Cost
Maintenance Costs
Maintenance
Commitment
Cost
PM Cost
Total Maintenance Cost
Breakdown Cost
Optimal
A760535773_16727_28_2018_u6.ppt

More Related Content

Similar to A760535773_16727_28_2018_u6.ppt

Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3ahsanrabbani
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptxBahredinAbdella1
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingHariasha
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxNaimishKishor
 
Control techniques
Control techniquesControl techniques
Control techniquesAdnan Shakir
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1ghulam MUSTAFA
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)AnkitaKadam20
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Project management Pert & cpm
Project management Pert & cpm Project management Pert & cpm
Project management Pert & cpm RandhirKumar172
 

Similar to A760535773_16727_28_2018_u6.ppt (20)

CPM and PERT
CPM and  PERTCPM and  PERT
CPM and PERT
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Control techniques
Control techniquesControl techniques
Control techniques
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Nce603 mod unit1
Nce603 mod unit1Nce603 mod unit1
Nce603 mod unit1
 
Project management Pert & cpm
Project management Pert & cpm Project management Pert & cpm
Project management Pert & cpm
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

A760535773_16727_28_2018_u6.ppt

  • 2. Introduction  Network analysis is one of the important tools for project management.  Whether major or minor a project has to be completed in a definite time & at a definite cost.  The necessary information of any particular data can be represented as a project network.  These techniques are very useful for planning, scheduling and executing large-time bound projects involving careful co-ordination of variety of complex and interrelated activities
  • 4. Objectives of network analysis  Helpful in planning  Inter-relationship of various activities  Cost control  Minimisation of maintenance time  Reduction of time  Control on idle resources  Avoiding delays, interruptions, etc
  • 5. Applications of network analysis  Planning, scheduling, monitoring and control of large and complex projects.  Construction of factories, highways, building, bridges, cinemas etc.  Helpful to army for its missile development.  Assembly line scheduling  Installation of computers and high tech machineries  To make marketing strategies
  • 6. Methodology Involved in Network Analysis Describing the Project Diagramming the network Estimating the time of completion Deterministic estimates Probabilistic estimates Monitoring the project progress
  • 7. Key terminology  Activity : All projects may be viewed as composed of activities. It is the smallest unit of work consuming both time & resources that project manager should schedule & control.  An activity is represented by an arrow in network diagram The head of the arrow shows sequence of activities.
  • 8.  Classification of activities  Predecessor activity: Activities that must be completed immediately prior to the start of another activity are called predecessor activities.  Successor activity : activities that cannot be started until one or more of other activities are completed but immediately succeed them are called successor activities.  Concurrent activities: activities that can be accomplished together are known as concurrent activities.  Dummy activity: An activity which does not consume any resource but merely depicts the dependence of one activity on other is called dummy activity. It is introduced in a network when two or more parallel activities have the same start and finish nodes.
  • 9.  Event:  The beginning & end of an activities are called as events .  Events are represented by numbered circles called nodes. i j Event start Event finish
  • 10. Types of Events  Merge event  Burst event  Merge & Burst Event
  • 11. Path & Network  An unbroken chain of activity arrows connecting the initial event to some other event is called a path.  A network is the graphical representation of logically & sequentially connected arrows & nodes representing activities & events of a project . It is a diagram depicting precedence relationships between different activities.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18. Guidelines for Network Construction  A complete network diagram should have one stand point & one finish point.  The flow of the diagram should be from left to right.  Arrows should not be crossed unless it is completely unavoidable.  Arrows should be kept straight & not curved or bent.  Angle between arrows should as large as possible.  Each activity must have a tail or head event.. No two or more activities may have same tail & head events.  Once the diagram is complete the nodes should be numbered from left to right. It should then be possible to address each activity uniquely by its tail & head event.
  • 19. Stages for project management  Project planning stages : In order to visualize the sequencing or precedence requirements of the activities in a project, it is helpful to draw a network diagram.  Scheduling stage : Once all work packages have been identified and given unique names or identifiers, scheduling of the project is required
  • 20.  Project control stage : Project control refers to evaluating actual progress against the plan. If significant differences are observed, then the scheduling and resources allocation decisions are changed to update and revise the uncompleted part of the project
  • 21. Advantages of PERT/CPM  Planning & controlling projects  Flexibility  Designation of responsibilities  Achievement of objective with least cost  Better managerial control
  • 22. Limitations of PERT /CPM  Network diagrams should have clear starting & ending points , which are independent of each other which may not be possible in real life.  Another limitation is that it assumes that manager should focus on critical activities.  Resources will be available when needed for completion for an an activity is again unreal.
  • 23. Difficulties  Difficulty in securing realistic time estimates.  The planning & implementation of networks requires trained staff.  Developing clear logical network is troublesome.
  • 24. Example Activity Predecessor activity A none B none C A D A E B F C G D & E 1 3 2 5 4 6 A B C D E F G
  • 25. Draw the network diagram for the following Activity Predecessor activity A none B A C A D B E C F D ,E
  • 27. Critical path  Those activities which contribute directly to the overall duration of the project constitute critical activities, the critical activities form a chain running through the network which is called critical path.  Critical event : The slack of an event is the difference between the latest & earliest events time. The events with zero slack time are called as critical events.  Critical activities : The difference between latest start time & earliest start time of an activity will indicate amount of time by which the activity can be delayed without affecting the total project duration. The difference is usually called total float. Activities with 0 total float are called as critical activities
  • 28. Critical path  The critical path is the longest path in the network from the starting event to ending event & defines the minimum time required to complete the project.  The critical path is denoted by darker or double lines.
  • 29. Fulkerson’s Rule for Numbering the Events
  • 30.
  • 31.
  • 32. Difference between PERT & CPM PERT A probability model with uncertainty in activity duration . The duration of each activity is computed from multiple time estimates with a view to take into account time uncertainty. It is applied widely for planning & scheduling research projects. PERT analysis does not usually consider costs. CPM A deterministic model with well known activity times based upon the past experience. It is used for construction projects & business problems. CPM deals with cost of project schedules & minimization.
  • 33. PERT PERT is designed for scheduling complex projects that involve many inter-related tasks. it improves planning process because: 1. It forms planner to define the projects various components activities. 2. It provides a basis for normal time estimates & yet allows for some measure of optimism or pessimism in estimating the completion dates. 3. It shows the effects of changes to overall plans they contemplated. 4. It provides built in means for ongoing evaluation of the plan.
  • 34. ESTIMATING ACTIVITY TIMES  Optimistic time ( t0 ) : is that time estimate of an activity when everything is assumed to go as per plan. In other words it is the estimate of minimum possible time which an activity takes in completion under ideal conditions.  Most likely time ( tm ) : the time which the activity will take most frequently if repeated number of times.  Pessimistic time ( tp) : the unlikely but possible performance time if whatever could go wrong , goes wrong in series. In other words it is the longest time the can take.
  • 35. EXPECTED TIME  The times are combined statically to develop the expected time te . te = to + 4tm + tp 6 Standard deviation of the time of the time required to complete the project St = tp - to 6 Variance Vt = St × St
  • 36. STEPS INVOLVED IN PERT  Develop list of activities.  A rough network for PERT is drawn.  Events are numbered from left to right.  Time estimates for each activity are obtained.  Expected time for each activity is calculated : to+4tm+tp / 6  Using these expected times calculate earliest & latest finish & start times of activities.  Estimate the critical path.  Using this estimate compute the probability of meeting a specified completion date by using the standard normal equation Z = Due date – expected date of completion standard deviation of critical path
  • 37.
  • 38.
  • 39.
  • 40. Books for numerical practices  INDUSTRIAL ENGINEERING & MANAGEMENT by PRAVIN KUMAR, PEARSON  INDUSTRIAL ENGINEERING AND PRODUCTION MANAGMENT by MARTAND TELSANG, S. CHAND & COMPANY  INDUSTRIAL ENGINEERING AND MANAGEMENT by RAVI SHANKAR, GALGOTIAPUBLICATIONS
  • 42. Maintenance  All actions necessary for retaining an item, or restoring to it, a serviceable condition, include servicing, repair, modification, overhaul, inspection and condition verification  Increase availability of a system  Keep system’s equipment in working order
  • 43. Purpose of Maintenance  Attempt to maximize performance of production equipment efficiently and regularly  Prevent breakdown or failures  Minimize production loss from failures  Increase reliability of the operating systems
  • 44. Principle Objectives in Maintenance  To achieve product quality and customer satisfaction through adjusted and serviced equipment  Maximize useful life of equipment  Keep equipment safe and prevent safety hazards  Minimize frequency and severity of interruptions  Maximize production capacity – through high utilization of facility
  • 45. Problems in Maintenance  Lack of management attention to maintenance  Little participation by accounting in analyzing and reporting costs  Difficulties in applying quantitative analysis  Difficulties in obtaining time and cost estimates for maintenance works  Difficulties in measuring performance
  • 46. Maintenance Objectives  Must be consistent with the goals of production (cost, quality, delivery, safety)  Must be comprehensive and include specific responsibilities
  • 47. Maintenance Costs  Cost to replace or repair  Losses of output  Delayed shipment  Scrap and rework
  • 48. Types of Maintenance  Maintenance may be classified into four categories:  Corrective or Breakdown maintenance  Scheduled maintenance  Preventive maintenance  Predictive (Condition-based) maintenance
  • 49. Corrective or Breakdown Maintenance  Corrective or Breakdown maintenance implies that repairs are made after the equipment is failed and can not perform its normal function anymore  Quite justified in small factories where:  Down times are non-critical and repair costs are less than other type of maintenance  Financial justification for scheduling are not felt
  • 50. Disadvantages of Corrective Maintenance  Breakdown generally occurs inappropriate times leading to poor and hurried maintenance  Excessive delay in production & reduces output  Faster plant deterioration  Increases chances of accidents and less safety for both workers and machines  More spoilt materials  Direct loss of profit  Can not be employed for equipments regulated by statutory provisions e.g. cranes, lift and hoists etc
  • 51. Scheduled Maintenance  Scheduled maintenance is a stitch-in-time procedure and incorporates  inspection  lubrication  repair and overhaul of equipments  If neglected can result in breakdown  Generally followed for:  overhauling of machines  changing of heavy equipment oils  cleaning of water and other tanks etc.
  • 52. Preventive Maintenance  Principle – “Prevention is better than cure”  Procedure - Stitch-in-time  It  locates weak spots of machinery and equipments  provides them periodic/scheduled inspections and minor repairs to reduce the danger of unanticipated breakdowns
  • 53. Advantages  Advantages:  Reduces break down and thereby down time  Lass odd-time repair and reduces over time of crews  Greater safety of workers  Lower maintenance and repair costs  Less stand-by equipments and spare parts  Better product quality and fewer reworks and scraps  Increases plant life  Increases chances to get production incentive bonus
  • 54. Predictive (Condition-based) Maintenance  In predictive maintenance, machinery conditions are periodically monitored and this enables the maintenance crews to take timely actions, such as machine adjustment, repair or overhaul  It makes use of human sense and other sensitive instruments, such as  audio gauge, vibration analyzer, amplitude meter, pressure, temperature and resistance strain gauges etc.
  • 55. Predictive Maintenance (Contd.) Unusual sounds coming out of a rotating equipment predicts a trouble An excessively hot electric cable predicts a trouble Simple hand touch can point out many unusual equipment conditions and thus predicts a trouble
  • 59. Maintenance Costs Maintenance Commitment Cost PM Cost Total Maintenance Cost Breakdown Cost Optimal