4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26
ID Week
1 Site Preparation
2 Site Survey
3 Site Clearance
4 Earthwork
5 Inspection and Approval
6 Main Building Work
7 Setting out, Inspection and Approval
8 Foundation Work
9 Form Foundation
10 Foundation Utilities
11 Backfilling
12 Ground Beam Work
13 Ground Slab Work
14 Column Work
15 Roof Work
16 Roof Frame
17 Installation of Fascia Board
18 Installation of Rainwater Goods
19 Roof Tiling
20 Brickwall
21 Install Doors and Windows
22 Finishes
23 Plastering
24 Painting
25 Tiling
26 Ceiling Work
27 M&E Works
28 Testing for M&E Works
29 External Works
30 Clean Up
31 Final Inspections
32 Punch Out
April May June
12 months
February
Date
Month
Duration
July August MarchSeptember October November December January

Schedule of works

  • 1.
    4 11 1825 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 ID Week 1 Site Preparation 2 Site Survey 3 Site Clearance 4 Earthwork 5 Inspection and Approval 6 Main Building Work 7 Setting out, Inspection and Approval 8 Foundation Work 9 Form Foundation 10 Foundation Utilities 11 Backfilling 12 Ground Beam Work 13 Ground Slab Work 14 Column Work 15 Roof Work 16 Roof Frame 17 Installation of Fascia Board 18 Installation of Rainwater Goods 19 Roof Tiling 20 Brickwall 21 Install Doors and Windows 22 Finishes 23 Plastering 24 Painting 25 Tiling 26 Ceiling Work 27 M&E Works 28 Testing for M&E Works 29 External Works 30 Clean Up 31 Final Inspections 32 Punch Out April May June 12 months February Date Month Duration July August MarchSeptember October November December January