SlideShare a Scribd company logo
M1 M2 M3 M4 M5 M6
1 1 837,625.00
2 3 10% 558,416.67 558,416.67 558,416.67
3 9 25% 465,347.22 465,347.22 465,347.22
4 7 15%
5 7 15%
6 8 15%
7 5 5%
8 6 5%
9 2 10%
10 6
100%
- 1,396,041.67 558,416.67 1,023,763.89 465,347.22 465,347.22
- 1,396,041.67 1,954,458.33 2,978,222.22 3,443,569.44 3,908,916.67
- (139,604.17) (195,445.83) (297,822.22) (344,356.94) (390,891.67)
1,256,437.50 1,759,012.50 2,680,400.00 3,099,212.50 3,518,025.00
- 1,256,437.50 502,575.00 921,387.50 418,812.50 418,812.50
1,759,012.50 1,759,012.50
1,759,012.50 3,518,025.00Quarterly Cumulative Cash Outflow
Monthly Total Cash Outflow (Before Retention)
Monthly Cumulative Outflow (Before Retention)
Less Retention (10%, Limit 5%) 963,268.75
Monthly Cumulative Outflow (After Retention)
Monthly Total Cash Outflow (After Retention) 19,265,375.00
Quarterly Total Cash Outflow 20,584,634.38
INFRASTRUCTURE WORKS 1,675,250.00
Total Construction Cost 19,265,375.00
SEWERAGE WORKS 837,625.00
DRAINAGE WORKS 837,625.00
ROADWORKS 1,675,250.00
WALLS, DOORS & WINDOW FRAME 2,512,875.00
ROOFING, ELEC WIRING & PLUMBING 2,512,875.00
INTERNAL &EXTERNAL PLASTERING 2,512,875.00
EARTHWORKS 837,625.00
FOUNDATION 1,675,250.00
R.C. FRAMEWORK 4,188,125.00
Construction Costs
Q1 Q2
PROJECTED CASH OUTFLOW FOR 2013-2016
Item Description Months % Amount (RM)
2013
1
2
3
4
5
6
7
8
9
10
Quarterly Cumulative Cash Outflow
Monthly Total Cash Outflow (Before Retention)
Monthly Cumulative Outflow (Before Retention)
Less Retention (10%, Limit 5%)
Monthly Cumulative Outflow (After Retention)
Monthly Total Cash Outflow (After Retention)
Quarterly Total Cash Outflow
INFRASTRUCTURE WORKS
Total Construction Cost
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
Construction Costs
PROJECTED CASH OUTFLOW FOR 2013-2016
Item Description
M7 M8 M9 M10 M11 M12
465,347.22 465,347.22 465,347.22 465,347.22 465,347.22 465,347.22
358,982.14 358,982.14 358,982.14 358,982.14 358,982.14
358,982.14 358,982.14 358,982.14
314,109.38
465,347.22 824,329.37 824,329.37 1,183,311.51 1,183,311.51 1,497,420.88
4,374,263.89 5,198,593.25 6,022,922.62 7,206,234.13 8,389,545.63 9,886,966.52
(437,426.39) (519,859.33) (602,292.26) (720,623.41) (838,954.56) (963,268.75)
3,936,837.50 4,678,733.93 5,420,630.36 6,485,610.71 7,550,591.07 8,923,697.77
418,812.50 741,896.43 741,896.43 1,064,980.36 1,064,980.36 1,373,106.70
1,902,605.36 3,503,067.41
5,420,630.36 8,923,697.77
Q3 Q4
2013
1
2
3
4
5
6
7
8
9
10
Quarterly Cumulative Cash Outflow
Monthly Total Cash Outflow (Before Retention)
Monthly Cumulative Outflow (Before Retention)
Less Retention (10%, Limit 5%)
Monthly Cumulative Outflow (After Retention)
Monthly Total Cash Outflow (After Retention)
Quarterly Total Cash Outflow
INFRASTRUCTURE WORKS
Total Construction Cost
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
Construction Costs
PROJECTED CASH OUTFLOW FOR 2013-2016
Item Description
M13 M14 M15 M16 M17 M18 M19
358,982.14 358,982.14
358,982.14 358,982.14 358,982.14 358,982.14
314,109.38 314,109.38 314,109.38 314,109.38 314,109.38 314,109.38 314,109.38
139,604.17 139,604.17
279,208.33 279,208.33 279,208.33
1,032,073.66 1,032,073.66 673,091.52 673,091.52 593,317.71 732,921.88 732,921.88
10,919,040.18 11,951,113.84 12,624,205.36 13,297,296.88 13,890,614.58 14,623,536.46 15,356,458.33
(963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75)
9,955,771.43 10,987,845.09 11,660,936.61 12,334,028.13 12,927,345.83 13,660,267.71 14,393,189.58
1,032,073.66 1,032,073.66 673,091.52 673,091.52 593,317.71 732,921.88 732,921.88
2,737,238.84 1,999,331.10
11,660,936.61 13,660,267.71
Q3Q1 Q2
2014
1
2
3
4
5
6
7
8
9
10
Quarterly Cumulative Cash Outflow
Monthly Total Cash Outflow (Before Retention)
Monthly Cumulative Outflow (Before Retention)
Less Retention (10%, Limit 5%)
Monthly Cumulative Outflow (After Retention)
Monthly Total Cash Outflow (After Retention)
Quarterly Total Cash Outflow
INFRASTRUCTURE WORKS
Total Construction Cost
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
Construction Costs
PROJECTED CASH OUTFLOW FOR 2013-2016
Item Description
M20 M21 M22 M23 M24
167,525.00 167,525.00 167,525.00 167,525.00 167,525.00
139,604.17 139,604.17 139,604.17 139,604.17
837,625.00
279,208.33 279,208.33 279,208.33
586,337.50 586,337.50 586,337.50 307,129.17 1,005,150.00
15,942,795.83 16,529,133.33 17,115,470.83 17,422,600.00 18,427,750.00
(963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75)
14,979,527.08 15,565,864.58 16,152,202.08 16,459,331.25 17,464,481.25
586,337.50 586,337.50 586,337.50 307,129.17 1,005,150.00
1,905,596.88 1,898,616.67
15,565,864.58 17,464,481.25
Q3 Q4
2014
1
2
3
4
5
6
7
8
9
10
Quarterly Cumulative Cash Outflow
Monthly Total Cash Outflow (Before Retention)
Monthly Cumulative Outflow (Before Retention)
Less Retention (10%, Limit 5%)
Monthly Cumulative Outflow (After Retention)
Monthly Total Cash Outflow (After Retention)
Quarterly Total Cash Outflow
INFRASTRUCTURE WORKS
Total Construction Cost
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
Construction Costs
PROJECTED CASH OUTFLOW FOR 2013-2016
Item Description Q2
M25 M26 M27 … M42 M43 M44 M45
First Moiety Second Moiety
837,625.00
837625 0 0 0 0 0 0 0
19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00
(481,634.38) (481,634.38) (481,634.38) (481,634.38) (481,634.38) 0 0 0
18,783,740.63 18,783,740.63 18,783,740.63 18,783,740.63 18,783,740.63 19,265,375.00 19,265,375.00 19,265,375.00
1,319,259.38 - - - - 481,634.38 - -
1,319,259.38 1,319,259.38 481,634.38
18,783,740.63 18,783,740.63 19,265,375.00
-
Q1 Q3
2015 2016

More Related Content

What's hot

Tabela diametro-furo-para-fazer-rosca
Tabela diametro-furo-para-fazer-roscaTabela diametro-furo-para-fazer-rosca
Tabela diametro-furo-para-fazer-rosca
Braga2013
 
Inertia dynamics cb_couplings310_specsheet
Inertia dynamics cb_couplings310_specsheetInertia dynamics cb_couplings310_specsheet
Inertia dynamics cb_couplings310_specsheet
Electromate
 
Massey ferguson 4345 tractor service parts catalogue manual (part number 819...
Massey ferguson 4345 tractor service parts catalogue manual (part number  819...Massey ferguson 4345 tractor service parts catalogue manual (part number  819...
Massey ferguson 4345 tractor service parts catalogue manual (part number 819...
ufjjsekkemmd
 
Tech_Brochure_Cladding_Final_17-03-15_LQ_Email
Tech_Brochure_Cladding_Final_17-03-15_LQ_EmailTech_Brochure_Cladding_Final_17-03-15_LQ_Email
Tech_Brochure_Cladding_Final_17-03-15_LQ_Email
Cassandra Vaz
 
Technical metric fasteners
Technical metric fastenersTechnical metric fasteners
Technical metric fasteners
Pinak Nandasana
 
Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)
Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)
Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)
eisa chegini
 

What's hot (15)

Tabela diametro-furo-para-fazer-rosca
Tabela diametro-furo-para-fazer-roscaTabela diametro-furo-para-fazer-rosca
Tabela diametro-furo-para-fazer-rosca
 
Taya Day Cap Dien So 1 Taiwan
Taya Day Cap Dien So 1 TaiwanTaya Day Cap Dien So 1 Taiwan
Taya Day Cap Dien So 1 Taiwan
 
Massey ferguson mf 3315 vsf tractors parts catalogue manual
Massey ferguson mf 3315 vsf tractors parts catalogue manualMassey ferguson mf 3315 vsf tractors parts catalogue manual
Massey ferguson mf 3315 vsf tractors parts catalogue manual
 
Inertia dynamics cb_couplings310_specsheet
Inertia dynamics cb_couplings310_specsheetInertia dynamics cb_couplings310_specsheet
Inertia dynamics cb_couplings310_specsheet
 
Laboratorio 5 ley de crecimiento de una gota de aceite
Laboratorio 5 ley de crecimiento de una gota de aceiteLaboratorio 5 ley de crecimiento de una gota de aceite
Laboratorio 5 ley de crecimiento de una gota de aceite
 
Weld induced residual stress
Weld induced residual stressWeld induced residual stress
Weld induced residual stress
 
ZIPPGEAR Gearing solution catalog - 2020 Update
ZIPPGEAR Gearing solution catalog - 2020 UpdateZIPPGEAR Gearing solution catalog - 2020 Update
ZIPPGEAR Gearing solution catalog - 2020 Update
 
Massey ferguson 4345 tractor service parts catalogue manual (part number 819...
Massey ferguson 4345 tractor service parts catalogue manual (part number  819...Massey ferguson 4345 tractor service parts catalogue manual (part number  819...
Massey ferguson 4345 tractor service parts catalogue manual (part number 819...
 
Tech_Brochure_Cladding_Final_17-03-15_LQ_Email
Tech_Brochure_Cladding_Final_17-03-15_LQ_EmailTech_Brochure_Cladding_Final_17-03-15_LQ_Email
Tech_Brochure_Cladding_Final_17-03-15_LQ_Email
 
IRJET- Design of Steering System for All Terrain Vehicle
IRJET- Design of Steering System for All Terrain VehicleIRJET- Design of Steering System for All Terrain Vehicle
IRJET- Design of Steering System for All Terrain Vehicle
 
Baja wf
Baja wfBaja wf
Baja wf
 
Technical metric fasteners
Technical metric fastenersTechnical metric fasteners
Technical metric fasteners
 
Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)
Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)
Seun Sambath-ACI 318-05 Mathcad in Concrete Structures (2010)
 
Tablice beton
Tablice betonTablice beton
Tablice beton
 
Gam skb ek_Spec sheet
Gam skb ek_Spec sheetGam skb ek_Spec sheet
Gam skb ek_Spec sheet
 

Similar to De assignment-finalized-28112017 4

Thomson 400 series_profile_rail_catalog
Thomson 400 series_profile_rail_catalogThomson 400 series_profile_rail_catalog
Thomson 400 series_profile_rail_catalog
Electromate
 
Kollmorgen gold line_bh_with_servostar_600_tb_catalog
Kollmorgen gold line_bh_with_servostar_600_tb_catalogKollmorgen gold line_bh_with_servostar_600_tb_catalog
Kollmorgen gold line_bh_with_servostar_600_tb_catalog
Electromate
 

Similar to De assignment-finalized-28112017 4 (20)

Deforestation situation in portugal
Deforestation situation in portugalDeforestation situation in portugal
Deforestation situation in portugal
 
Thomson 400 Series Profile Rail Linear Guides
Thomson 400 Series Profile Rail Linear GuidesThomson 400 Series Profile Rail Linear Guides
Thomson 400 Series Profile Rail Linear Guides
 
Thomson 400 series_profile_rail_catalog
Thomson 400 series_profile_rail_catalogThomson 400 series_profile_rail_catalog
Thomson 400 series_profile_rail_catalog
 
ธนาคารกสิกรไทย
ธนาคารกสิกรไทย ธนาคารกสิกรไทย
ธนาคารกสิกรไทย
 
E4 03 שכר חודשי ממוצע לשכיר
E4 03 שכר חודשי ממוצע לשכירE4 03 שכר חודשי ממוצע לשכיר
E4 03 שכר חודשי ממוצע לשכיר
 
Harmonic shgshf 2uh_lw_catalog
Harmonic shgshf 2uh_lw_catalogHarmonic shgshf 2uh_lw_catalog
Harmonic shgshf 2uh_lw_catalog
 
Mmg cam sur finances 2
Mmg cam sur finances 2Mmg cam sur finances 2
Mmg cam sur finances 2
 
CONECTORES PARA ATERRIZAR CABLES BLINDADOS
CONECTORES PARA ATERRIZAR CABLES BLINDADOSCONECTORES PARA ATERRIZAR CABLES BLINDADOS
CONECTORES PARA ATERRIZAR CABLES BLINDADOS
 
Page530 skintop ms-npt-brush_ms-m-brush
Page530 skintop ms-npt-brush_ms-m-brushPage530 skintop ms-npt-brush_ms-m-brush
Page530 skintop ms-npt-brush_ms-m-brush
 
Tablaf
TablafTablaf
Tablaf
 
Гидромоторы Ms18 mse18-ser POCLAIN HYDRAULICS
Гидромоторы Ms18 mse18-ser POCLAIN HYDRAULICSГидромоторы Ms18 mse18-ser POCLAIN HYDRAULICS
Гидромоторы Ms18 mse18-ser POCLAIN HYDRAULICS
 
Pirson
PirsonPirson
Pirson
 
Mantenimiento
MantenimientoMantenimiento
Mantenimiento
 
Reference.pptx
Reference.pptxReference.pptx
Reference.pptx
 
Gam km_Spec Sheet
Gam km_Spec SheetGam km_Spec Sheet
Gam km_Spec Sheet
 
Fisher
FisherFisher
Fisher
 
Kollmorgen gold line_bh_with_servostar_600_tb_catalog
Kollmorgen gold line_bh_with_servostar_600_tb_catalogKollmorgen gold line_bh_with_servostar_600_tb_catalog
Kollmorgen gold line_bh_with_servostar_600_tb_catalog
 
Коническо-цилиндрические мотор-редукторы на постоянных магнитах ECMB Transtecno
Коническо-цилиндрические мотор-редукторы на постоянных магнитах ECMB TranstecnoКоническо-цилиндрические мотор-редукторы на постоянных магнитах ECMB Transtecno
Коническо-цилиндрические мотор-редукторы на постоянных магнитах ECMB Transtecno
 
Tabla salarial docentes decreto 1278 de 2002 historico
Tabla salarial docentes decreto 1278 de 2002 historicoTabla salarial docentes decreto 1278 de 2002 historico
Tabla salarial docentes decreto 1278 de 2002 historico
 
Tabelas1
Tabelas1Tabelas1
Tabelas1
 

More from Arthur Wilson

Pm project-control-compiled
Pm project-control-compiledPm project-control-compiled
Pm project-control-compiled
Arthur Wilson
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
Arthur Wilson
 
Vm assignment - presentation slide (1)
Vm   assignment - presentation slide (1)Vm   assignment - presentation slide (1)
Vm assignment - presentation slide (1)
Arthur Wilson
 
Vm compiled-edited (print)
Vm compiled-edited (print)Vm compiled-edited (print)
Vm compiled-edited (print)
Arthur Wilson
 
De assignment-finalized-28112017
De assignment-finalized-28112017De assignment-finalized-28112017
De assignment-finalized-28112017
Arthur Wilson
 
De assignment-finalized-28112017 6
De assignment-finalized-28112017 6De assignment-finalized-28112017 6
De assignment-finalized-28112017 6
Arthur Wilson
 
De assignment-finalized-28112017 5
De assignment-finalized-28112017 5De assignment-finalized-28112017 5
De assignment-finalized-28112017 5
Arthur Wilson
 
De assignment-finalized-28112017 3
De assignment-finalized-28112017 3De assignment-finalized-28112017 3
De assignment-finalized-28112017 3
Arthur Wilson
 
De assignment-finalized-28112017 2
De assignment-finalized-28112017 2De assignment-finalized-28112017 2
De assignment-finalized-28112017 2
Arthur Wilson
 
Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0
Arthur Wilson
 
De & be final workshop submission
De & be final workshop submissionDe & be final workshop submission
De & be final workshop submission
Arthur Wilson
 

More from Arthur Wilson (20)

Pm group-compileddd
Pm group-compiledddPm group-compileddd
Pm group-compileddd
 
Activity id
Activity idActivity id
Activity id
 
Pm project-control-compiled
Pm project-control-compiledPm project-control-compiled
Pm project-control-compiled
 
Final 2
Final  2Final  2
Final 2
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
Cl report final
Cl report finalCl report final
Cl report final
 
Vm assignment - presentation slide (1)
Vm   assignment - presentation slide (1)Vm   assignment - presentation slide (1)
Vm assignment - presentation slide (1)
 
Vm compiled-edited (print)
Vm compiled-edited (print)Vm compiled-edited (print)
Vm compiled-edited (print)
 
De assignment-finalized-28112017
De assignment-finalized-28112017De assignment-finalized-28112017
De assignment-finalized-28112017
 
De assignment-finalized-28112017 6
De assignment-finalized-28112017 6De assignment-finalized-28112017 6
De assignment-finalized-28112017 6
 
De assignment-finalized-28112017 5
De assignment-finalized-28112017 5De assignment-finalized-28112017 5
De assignment-finalized-28112017 5
 
De assignment-finalized-28112017 3
De assignment-finalized-28112017 3De assignment-finalized-28112017 3
De assignment-finalized-28112017 3
 
De assignment-finalized-28112017 2
De assignment-finalized-28112017 2De assignment-finalized-28112017 2
De assignment-finalized-28112017 2
 
Research proposal draft v3
Research proposal draft v3Research proposal draft v3
Research proposal draft v3
 
Chapter 2 draft v1
Chapter 2 draft v1Chapter 2 draft v1
Chapter 2 draft v1
 
Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0
 
De & be final workshop submission
De & be final workshop submissionDe & be final workshop submission
De & be final workshop submission
 
Community service
Community serviceCommunity service
Community service
 
Excavation
ExcavationExcavation
Excavation
 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysis
 

Recently uploaded

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
Kamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
Kamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
Kamal Acharya
 

Recently uploaded (20)

Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 

De assignment-finalized-28112017 4

  • 1. M1 M2 M3 M4 M5 M6 1 1 837,625.00 2 3 10% 558,416.67 558,416.67 558,416.67 3 9 25% 465,347.22 465,347.22 465,347.22 4 7 15% 5 7 15% 6 8 15% 7 5 5% 8 6 5% 9 2 10% 10 6 100% - 1,396,041.67 558,416.67 1,023,763.89 465,347.22 465,347.22 - 1,396,041.67 1,954,458.33 2,978,222.22 3,443,569.44 3,908,916.67 - (139,604.17) (195,445.83) (297,822.22) (344,356.94) (390,891.67) 1,256,437.50 1,759,012.50 2,680,400.00 3,099,212.50 3,518,025.00 - 1,256,437.50 502,575.00 921,387.50 418,812.50 418,812.50 1,759,012.50 1,759,012.50 1,759,012.50 3,518,025.00Quarterly Cumulative Cash Outflow Monthly Total Cash Outflow (Before Retention) Monthly Cumulative Outflow (Before Retention) Less Retention (10%, Limit 5%) 963,268.75 Monthly Cumulative Outflow (After Retention) Monthly Total Cash Outflow (After Retention) 19,265,375.00 Quarterly Total Cash Outflow 20,584,634.38 INFRASTRUCTURE WORKS 1,675,250.00 Total Construction Cost 19,265,375.00 SEWERAGE WORKS 837,625.00 DRAINAGE WORKS 837,625.00 ROADWORKS 1,675,250.00 WALLS, DOORS & WINDOW FRAME 2,512,875.00 ROOFING, ELEC WIRING & PLUMBING 2,512,875.00 INTERNAL &EXTERNAL PLASTERING 2,512,875.00 EARTHWORKS 837,625.00 FOUNDATION 1,675,250.00 R.C. FRAMEWORK 4,188,125.00 Construction Costs Q1 Q2 PROJECTED CASH OUTFLOW FOR 2013-2016 Item Description Months % Amount (RM) 2013
  • 2. 1 2 3 4 5 6 7 8 9 10 Quarterly Cumulative Cash Outflow Monthly Total Cash Outflow (Before Retention) Monthly Cumulative Outflow (Before Retention) Less Retention (10%, Limit 5%) Monthly Cumulative Outflow (After Retention) Monthly Total Cash Outflow (After Retention) Quarterly Total Cash Outflow INFRASTRUCTURE WORKS Total Construction Cost SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK Construction Costs PROJECTED CASH OUTFLOW FOR 2013-2016 Item Description M7 M8 M9 M10 M11 M12 465,347.22 465,347.22 465,347.22 465,347.22 465,347.22 465,347.22 358,982.14 358,982.14 358,982.14 358,982.14 358,982.14 358,982.14 358,982.14 358,982.14 314,109.38 465,347.22 824,329.37 824,329.37 1,183,311.51 1,183,311.51 1,497,420.88 4,374,263.89 5,198,593.25 6,022,922.62 7,206,234.13 8,389,545.63 9,886,966.52 (437,426.39) (519,859.33) (602,292.26) (720,623.41) (838,954.56) (963,268.75) 3,936,837.50 4,678,733.93 5,420,630.36 6,485,610.71 7,550,591.07 8,923,697.77 418,812.50 741,896.43 741,896.43 1,064,980.36 1,064,980.36 1,373,106.70 1,902,605.36 3,503,067.41 5,420,630.36 8,923,697.77 Q3 Q4 2013
  • 3. 1 2 3 4 5 6 7 8 9 10 Quarterly Cumulative Cash Outflow Monthly Total Cash Outflow (Before Retention) Monthly Cumulative Outflow (Before Retention) Less Retention (10%, Limit 5%) Monthly Cumulative Outflow (After Retention) Monthly Total Cash Outflow (After Retention) Quarterly Total Cash Outflow INFRASTRUCTURE WORKS Total Construction Cost SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK Construction Costs PROJECTED CASH OUTFLOW FOR 2013-2016 Item Description M13 M14 M15 M16 M17 M18 M19 358,982.14 358,982.14 358,982.14 358,982.14 358,982.14 358,982.14 314,109.38 314,109.38 314,109.38 314,109.38 314,109.38 314,109.38 314,109.38 139,604.17 139,604.17 279,208.33 279,208.33 279,208.33 1,032,073.66 1,032,073.66 673,091.52 673,091.52 593,317.71 732,921.88 732,921.88 10,919,040.18 11,951,113.84 12,624,205.36 13,297,296.88 13,890,614.58 14,623,536.46 15,356,458.33 (963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75) 9,955,771.43 10,987,845.09 11,660,936.61 12,334,028.13 12,927,345.83 13,660,267.71 14,393,189.58 1,032,073.66 1,032,073.66 673,091.52 673,091.52 593,317.71 732,921.88 732,921.88 2,737,238.84 1,999,331.10 11,660,936.61 13,660,267.71 Q3Q1 Q2 2014
  • 4. 1 2 3 4 5 6 7 8 9 10 Quarterly Cumulative Cash Outflow Monthly Total Cash Outflow (Before Retention) Monthly Cumulative Outflow (Before Retention) Less Retention (10%, Limit 5%) Monthly Cumulative Outflow (After Retention) Monthly Total Cash Outflow (After Retention) Quarterly Total Cash Outflow INFRASTRUCTURE WORKS Total Construction Cost SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK Construction Costs PROJECTED CASH OUTFLOW FOR 2013-2016 Item Description M20 M21 M22 M23 M24 167,525.00 167,525.00 167,525.00 167,525.00 167,525.00 139,604.17 139,604.17 139,604.17 139,604.17 837,625.00 279,208.33 279,208.33 279,208.33 586,337.50 586,337.50 586,337.50 307,129.17 1,005,150.00 15,942,795.83 16,529,133.33 17,115,470.83 17,422,600.00 18,427,750.00 (963,268.75) (963,268.75) (963,268.75) (963,268.75) (963,268.75) 14,979,527.08 15,565,864.58 16,152,202.08 16,459,331.25 17,464,481.25 586,337.50 586,337.50 586,337.50 307,129.17 1,005,150.00 1,905,596.88 1,898,616.67 15,565,864.58 17,464,481.25 Q3 Q4 2014
  • 5. 1 2 3 4 5 6 7 8 9 10 Quarterly Cumulative Cash Outflow Monthly Total Cash Outflow (Before Retention) Monthly Cumulative Outflow (Before Retention) Less Retention (10%, Limit 5%) Monthly Cumulative Outflow (After Retention) Monthly Total Cash Outflow (After Retention) Quarterly Total Cash Outflow INFRASTRUCTURE WORKS Total Construction Cost SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK Construction Costs PROJECTED CASH OUTFLOW FOR 2013-2016 Item Description Q2 M25 M26 M27 … M42 M43 M44 M45 First Moiety Second Moiety 837,625.00 837625 0 0 0 0 0 0 0 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 19,265,375.00 (481,634.38) (481,634.38) (481,634.38) (481,634.38) (481,634.38) 0 0 0 18,783,740.63 18,783,740.63 18,783,740.63 18,783,740.63 18,783,740.63 19,265,375.00 19,265,375.00 19,265,375.00 1,319,259.38 - - - - 481,634.38 - - 1,319,259.38 1,319,259.38 481,634.38 18,783,740.63 18,783,740.63 19,265,375.00 - Q1 Q3 2015 2016