SlideShare a Scribd company logo
1 of 8
Download to read offline
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item Sales percentage
M1 M2 M3 M4 M5 M6
1 5.18%
2 64.08% 30.00% 20.00%
3 30.74% 10.00% 10.00%
100.00% 22.30% 0.00% 0.00% 0.00% 0.00% 15.89%
22.30% 22.30% 22.30% 22.30% 22.30% 38.19%
Months
1 1 22.30% 15.89%
2 3 7.43% 7.43% 7.43% 15.89%
3 9 2.48% 2.48% 2.48% 5.13%
4 7
5 7
6 8
7 5
8 6
9 2
10 6
22.30% 15.89%
1 10.00% 1,214,449.50 865,436.00
7.433% 7.433% 7.433%
2 10.00% 404,816.50 404,816.50 404,816.50
2.48% 2.48% 2.48%
3 15.00% 202,408.25 202,408.25 202,408.25
4 10.00%
5 10.00%
6 10.00%
7 5.00%
8 2.50%
9 2.50%
10 17.50%
11 2.50%
12 2.50%
13 2.50%
100.00% 1,214,449.50 404,816.50 404,816.50 607,224.75 202,408.25 1,067,844.25
1,214,449.50 1,619,266.00 2,024,082.50 2,631,307.25 2,833,715.50 3,901,559.75
2,024,082.50 1,877,477.25
Quarterly Cummulative Cash Inflow 2,024,082.50 3,901,559.75
Quarterly Total Cash Inflow 54,461,770.00
Monthly Total Cash Flow 54,461,770.00
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
1,361,544.25
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
1,361,544.25
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
1,361,544.25
Roadworks 1,361,544.25
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
9,530,809.75
Drainage works 1,361,544.25
Internal &External plastering 5,446,177.00
Sewerage works 2,723,088.50
Roofing, Electrical wiring & plumbing 5,446,177.00
R.C. Framwork 8,169,265.50
Walls, Doors & Window frame 5,446,177.00
Foundation 5,446,177.00
Sales Proceeds
Signing of S&P Agreement (Clause 5) 5,446,177.00
INFRASTRUCTURE WORKS 100.00%
SEWERAGE WORKS 100.00%
DRAINAGE WORKS 100.00%
ROADWORKS 100.00%
WALLS, DOORS & WINDOW FRAME 100.00%
ROOFING, ELEC WIRING & PLUMBING 100.00%
INTERNAL &EXTERNAL PLASTERING 100.00%
EARTHWORKS 100.00%
FOUNDATION 100.00%
R.C. FRAMEWORK 100.00%
% of Cumulative Sales
D/S Terrace 34,901,350.00
D/S Shop/Office 16,740,900.00
Monthly Total 54,461,770.00
Sale Projection
D/S Low Cost 2,819,520.00
Q1 Q2
Description Amount (RM) 2013
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M7 M8 M9 M10 M11 M12
50.0%
20.0% 10.0%
10.0% 10.0%
0.0% 0.0% 18.5% 0.0% 0.0% 9.5%
38.19% 38.19% 56.67% 56.67% 56.67% 66.15%
18.48% 9.48%
18.48% 9.48%
5.13% 5.13% 11.29% 11.29% 11.29% 9.48%
5.46% 5.46% 9.15% 9.15% 9.15% 13.89%
8.10% 8.10% 8.10% 10.47%
7.08% 8.44%
18.48% 9.48%
1,006,412.00 516,422.50
15.89% 18.48%
865,436.00 1,006,412.00
5.13% 5.13% 5.13% 11.29% 11.29% 11.29%
418,767.25 418,767.25 418,767.25 921,973.25 921,973.25 921,973.25
5.46% 5.46% 9.15% 9.15% 9.15%
297,126.50 297,126.50 498,408.90 498,408.90 498,408.90
8.10% 8.10% 8.10%
440,899.64 440,899.64 440,899.64
7.08%
385,787.19
1,284,203.25 715,893.75 1,722,305.75 2,867,693.79 1,861,281.79 2,763,491.48
5,185,763.00 5,901,656.75 7,623,962.50 10,491,656.29 12,352,938.09 15,116,429.57
3,722,402.75 7,492,467.07
7,623,962.50 15,116,429.57
Q3 Q4
2013
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M13 M14 M15 M16 M17 M18 M19 M20
50.0%
20.0%
10.0% 20.0%
0.0% 0.0% 18.5% 0.0% 0.0% 6.1% 0.0% 0.0%
66.15% 66.15% 84.63% 84.63% 84.63% 90.78% 90.78% 90.78%
18.48% 6.15%
18.48% 6.15%
18.48% 6.15%
13.89% 18.48% 6.15%
10.47% 10.47% 28.95% 6.15%
8.44% 8.44% 13.06% 13.06% 13.06% 19.21%
18.16% 18.16%
14.11% 15.33% 15.33% 15.33%
14.11% 14.11% 15.64% 15.64% 15.64%
18.48% 6.15%
1,006,412.00 334,818.00
9.5% 18.48% 6.15%
516,422.50 1,006,412.00 334,818.00
9.48% 18.48% 6.15%
774,633.75 1,509,618.00 502,227.00
13.89% 13.89% 18.48% 6.15%
756,620.15 756,620.15 1,006,412.00 334,818.00
10.47% 10.47% 10.47% 28.95% 6.15%
570,005.27 570,005.27 570,005.27 1,576,417.27 334,818.00
8.44% 8.44% 8.44% 13.06% 13.06% 13.06% 19.21%
459,561.83 459,561.83 459,561.83 711,164.83 711,164.83 711,164.83 1,045,982.83
18.16%
494,395.00
14.11% 15.33% 15.33%
192,047.17 208,788.07 208,788.07
3,077,243.50 1,786,187.25 2,035,979.10 5,810,024.10 711,164.83 1,238,030.00 2,761,451.90 703,183.07
18,193,673.06 19,979,860.31 22,015,839.41 27,825,863.51 28,537,028.34 29,775,058.34 32,536,510.23 33,239,693.30
6,899,409.84 7,759,218.93
22,015,839.41 29,775,058.34
Q1 Q2 Q3
2014
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M21 M22 M23 M24
30.0%
9.2% 0.0% 0.0% 0.0%
100.00% 100.00% 100.00% 100.00%
9.22%
9.22%
9.22%
9.22%
9.22%
9.22%
21.23% 21.23% 21.23%
19.95% 19.95%
50.00% 50.00%
24.86%
9.22% 0.00%
502,227.00 -
9.22%
502,227.00
9.22%
753,340.50
9.22%
502,227.00
9.22%
502,227.00
9.22%
502,227.00
18.16% 21.23% 21.23% 21.23%
494,395.00 578,099.50 578,099.50 578,099.50
15.33% 19.95% 19.95%
208,788.07 271,566.44 271,566.44
50.00%
680,772.13
1,205,410.07 3,611,914.44 849,665.94 1,258,871.63
34,445,103.37 38,057,017.81 38,906,683.75 40,165,555.38
4,670,045.03 5,720,452.01
34,445,103.37 40,165,555.38
Q3 Q4
2014
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M25 M26 M27 M28 M29 M30 M31 M32
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
50.00%
680,772.13
100.00%
9,530,809.75
100.00%
1,361,544.25
10,211,581.88 1,361,544.25 0 0 0 0 0 0
50,377,137.25 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50
11,573,126.13 0
51,738,681.50 51,738,681.50
Q3Q1 Q2
2015
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M33 M34 M35 M36
100.00% 100.00% 100.00% 100.00%
100.00%
1,361,544.25
1,361,544.25 0 0 0
53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75
1,361,544.25 0
53,100,225.75 53,100,225.75
Q3 Q4
2015
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M37 M38 M39 M40 M41 M42 M43 M44
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
0 0 0 0 0 0 0 0
53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75
0 0
53,100,225.75 53,100,225.75
Q1
2016
Q2 Q3
4.0 Cash Flow for Project
The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developerā€™s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaserā€™s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M45 M46 M47 M48 M49 M50 M51
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
100.0%
1,361,544.25
0 0 0 0 1,361,544.25 0 0
53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 54,461,770.00 54,461,770.00 54,461,770.00
0 0 1,361,544.25
53,100,225.75 53,100,225.75 54,461,770.00
2016 2017
Q1Q3 Q4

More Related Content

Similar to De assignment-finalized-28112017 3

Item # 5&6 - Water & Sewer Rate Study
Item # 5&6 - Water & Sewer Rate StudyItem # 5&6 - Water & Sewer Rate Study
Item # 5&6 - Water & Sewer Rate Studyahcitycouncil
Ā 
BriteCon 2014 - Keynote
BriteCon 2014 - KeynoteBriteCon 2014 - Keynote
BriteCon 2014 - KeynotePhil Reynolds
Ā 
JLL Cleveland Industrial Outlook: Q3 2020
JLL Cleveland Industrial Outlook: Q3 2020JLL Cleveland Industrial Outlook: Q3 2020
JLL Cleveland Industrial Outlook: Q3 2020Andrew Batson
Ā 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
Ā 
JLL Cleveland Industrial Outlook: Q4 2020
JLL Cleveland Industrial Outlook: Q4 2020JLL Cleveland Industrial Outlook: Q4 2020
JLL Cleveland Industrial Outlook: Q4 2020Andrew Batson
Ā 
JLL Cincinnati Industrial Outlook Q4 2017
JLL Cincinnati Industrial Outlook Q4 2017JLL Cincinnati Industrial Outlook Q4 2017
JLL Cincinnati Industrial Outlook Q4 2017Abby Armbruster
Ā 
JLL Cleveland Industrial Outlook Q4 2019
JLL Cleveland Industrial Outlook Q4 2019JLL Cleveland Industrial Outlook Q4 2019
JLL Cleveland Industrial Outlook Q4 2019Johnathan Miller
Ā 
JLL Cleveland Industrial Outlook: Q1 2019
JLL Cleveland Industrial Outlook: Q1 2019JLL Cleveland Industrial Outlook: Q1 2019
JLL Cleveland Industrial Outlook: Q1 2019Andrew Batson
Ā 
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...Aadhar Homes
Ā 
viability-presentation-se-98b.pptx
viability-presentation-se-98b.pptxviability-presentation-se-98b.pptx
viability-presentation-se-98b.pptxSAYKEATTAN
Ā 
Project Management Services
Project Management ServicesProject Management Services
Project Management ServicesBruce Tharp
Ā 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogdenahcitycouncil
Ā 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxsyedaliabl2023
Ā 
JLL Pittsburgh Industrial Insight & Statistics - Q2 2018
JLL Pittsburgh Industrial Insight & Statistics - Q2 2018JLL Pittsburgh Industrial Insight & Statistics - Q2 2018
JLL Pittsburgh Industrial Insight & Statistics - Q2 2018Tobiah Bilski
Ā 
Potential Study Presentation - 6/11/14
Potential Study Presentation - 6/11/14Potential Study Presentation - 6/11/14
Potential Study Presentation - 6/11/14CapeLightEnergy
Ā 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
Ā 
Presentations
PresentationsPresentations
PresentationsEucatexRI
Ā 

Similar to De assignment-finalized-28112017 3 (20)

Item # 5&6 - Water & Sewer Rate Study
Item # 5&6 - Water & Sewer Rate StudyItem # 5&6 - Water & Sewer Rate Study
Item # 5&6 - Water & Sewer Rate Study
Ā 
BriteCon 2014 - Keynote
BriteCon 2014 - KeynoteBriteCon 2014 - Keynote
BriteCon 2014 - Keynote
Ā 
JLL Cleveland Industrial Outlook: Q3 2020
JLL Cleveland Industrial Outlook: Q3 2020JLL Cleveland Industrial Outlook: Q3 2020
JLL Cleveland Industrial Outlook: Q3 2020
Ā 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
Ā 
JLL Cleveland Industrial Outlook: Q4 2020
JLL Cleveland Industrial Outlook: Q4 2020JLL Cleveland Industrial Outlook: Q4 2020
JLL Cleveland Industrial Outlook: Q4 2020
Ā 
JLL Cincinnati Industrial Outlook Q4 2017
JLL Cincinnati Industrial Outlook Q4 2017JLL Cincinnati Industrial Outlook Q4 2017
JLL Cincinnati Industrial Outlook Q4 2017
Ā 
JLL Cleveland Industrial Outlook Q4 2019
JLL Cleveland Industrial Outlook Q4 2019JLL Cleveland Industrial Outlook Q4 2019
JLL Cleveland Industrial Outlook Q4 2019
Ā 
JLL Cleveland Industrial Outlook: Q1 2019
JLL Cleveland Industrial Outlook: Q1 2019JLL Cleveland Industrial Outlook: Q1 2019
JLL Cleveland Industrial Outlook: Q1 2019
Ā 
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...
Ā 
viability-presentation-se-98b.pptx
viability-presentation-se-98b.pptxviability-presentation-se-98b.pptx
viability-presentation-se-98b.pptx
Ā 
2015 Savings Achieved
2015 Savings Achieved2015 Savings Achieved
2015 Savings Achieved
Ā 
US20140180938
US20140180938US20140180938
US20140180938
Ā 
US20140180938
US20140180938US20140180938
US20140180938
Ā 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
Ā 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogden
Ā 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Ā 
JLL Pittsburgh Industrial Insight & Statistics - Q2 2018
JLL Pittsburgh Industrial Insight & Statistics - Q2 2018JLL Pittsburgh Industrial Insight & Statistics - Q2 2018
JLL Pittsburgh Industrial Insight & Statistics - Q2 2018
Ā 
Potential Study Presentation - 6/11/14
Potential Study Presentation - 6/11/14Potential Study Presentation - 6/11/14
Potential Study Presentation - 6/11/14
Ā 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
Ā 
Presentations
PresentationsPresentations
Presentations
Ā 

More from Arthur Wilson

Pm group-compileddd
Pm group-compiledddPm group-compileddd
Pm group-compiledddArthur Wilson
Ā 
Pm project-control-compiled
Pm project-control-compiledPm project-control-compiled
Pm project-control-compiledArthur Wilson
Ā 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-paymentArthur Wilson
Ā 
Cl report final
Cl report finalCl report final
Cl report finalArthur Wilson
Ā 
Vm assignment - presentation slide (1)
Vm   assignment - presentation slide (1)Vm   assignment - presentation slide (1)
Vm assignment - presentation slide (1)Arthur Wilson
Ā 
Vm compiled-edited (print)
Vm compiled-edited (print)Vm compiled-edited (print)
Vm compiled-edited (print)Arthur Wilson
Ā 
De assignment-finalized-28112017
De assignment-finalized-28112017De assignment-finalized-28112017
De assignment-finalized-28112017Arthur Wilson
Ā 
De assignment-finalized-28112017 6
De assignment-finalized-28112017 6De assignment-finalized-28112017 6
De assignment-finalized-28112017 6Arthur Wilson
Ā 
De assignment-finalized-28112017 5
De assignment-finalized-28112017 5De assignment-finalized-28112017 5
De assignment-finalized-28112017 5Arthur Wilson
Ā 
De assignment-finalized-28112017 4
De assignment-finalized-28112017 4De assignment-finalized-28112017 4
De assignment-finalized-28112017 4Arthur Wilson
Ā 
De assignment-finalized-28112017 2
De assignment-finalized-28112017 2De assignment-finalized-28112017 2
De assignment-finalized-28112017 2Arthur Wilson
Ā 
Research proposal draft v3
Research proposal draft v3Research proposal draft v3
Research proposal draft v3Arthur Wilson
Ā 
Chapter 2 draft v1
Chapter 2 draft v1Chapter 2 draft v1
Chapter 2 draft v1Arthur Wilson
Ā 
Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0Arthur Wilson
Ā 
De & be final workshop submission
De & be final workshop submissionDe & be final workshop submission
De & be final workshop submissionArthur Wilson
Ā 
Community service
Community serviceCommunity service
Community serviceArthur Wilson
Ā 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysisArthur Wilson
Ā 

More from Arthur Wilson (20)

Pm group-compileddd
Pm group-compiledddPm group-compileddd
Pm group-compileddd
Ā 
Activity id
Activity idActivity id
Activity id
Ā 
Pm project-control-compiled
Pm project-control-compiledPm project-control-compiled
Pm project-control-compiled
Ā 
Final 2
Final  2Final  2
Final 2
Ā 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
Ā 
Cl report final
Cl report finalCl report final
Cl report final
Ā 
Vm assignment - presentation slide (1)
Vm   assignment - presentation slide (1)Vm   assignment - presentation slide (1)
Vm assignment - presentation slide (1)
Ā 
Vm compiled-edited (print)
Vm compiled-edited (print)Vm compiled-edited (print)
Vm compiled-edited (print)
Ā 
De assignment-finalized-28112017
De assignment-finalized-28112017De assignment-finalized-28112017
De assignment-finalized-28112017
Ā 
De assignment-finalized-28112017 6
De assignment-finalized-28112017 6De assignment-finalized-28112017 6
De assignment-finalized-28112017 6
Ā 
De assignment-finalized-28112017 5
De assignment-finalized-28112017 5De assignment-finalized-28112017 5
De assignment-finalized-28112017 5
Ā 
De assignment-finalized-28112017 4
De assignment-finalized-28112017 4De assignment-finalized-28112017 4
De assignment-finalized-28112017 4
Ā 
De assignment-finalized-28112017 2
De assignment-finalized-28112017 2De assignment-finalized-28112017 2
De assignment-finalized-28112017 2
Ā 
Research proposal draft v3
Research proposal draft v3Research proposal draft v3
Research proposal draft v3
Ā 
Chapter 2 draft v1
Chapter 2 draft v1Chapter 2 draft v1
Chapter 2 draft v1
Ā 
Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0Fm assignment-final-updated v2.0
Fm assignment-final-updated v2.0
Ā 
De & be final workshop submission
De & be final workshop submissionDe & be final workshop submission
De & be final workshop submission
Ā 
Community service
Community serviceCommunity service
Community service
Ā 
Excavation
ExcavationExcavation
Excavation
Ā 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysis
Ā 

Recently uploaded

Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...akbard9823
Ā 
FULL ENJOY - 9953040155 Call Girls in Paschim Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Paschim Vihar | DelhiFULL ENJOY - 9953040155 Call Girls in Paschim Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Paschim Vihar | DelhiMalviyaNagarCallGirl
Ā 
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...akbard9823
Ā 
Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...anilsa9823
Ā 
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service AkolaAkola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service Akolasrsj9000
Ā 
Bridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.comBridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.comthephillipta
Ā 
RAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAKRAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAKedwardsara83
Ā 
FULL ENJOY - 9953040155 Call Girls in Mahipalpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Mahipalpur | DelhiFULL ENJOY - 9953040155 Call Girls in Mahipalpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Mahipalpur | DelhiMalviyaNagarCallGirl
Ā 
FULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | DelhiFULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | DelhiMalviyaNagarCallGirl
Ā 
Jagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call GirlsJagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call Girlsashishs7044
Ā 
Roadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMRoadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMroute66connected
Ā 
(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad Escorts
(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad Escorts(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad Escorts
(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad EscortsCall girls in Ahmedabad High profile
Ā 
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857delhimodel235
Ā 
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | DelhiMalviyaNagarCallGirl
Ā 
Mandi House Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Mandi House Call Girls : ā˜Ž 8527673949, Low rate Call GirlsMandi House Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Mandi House Call Girls : ā˜Ž 8527673949, Low rate Call Girlsashishs7044
Ā 
Alex and Chloe by Daniel Johnson Storyboard
Alex and Chloe by Daniel Johnson StoryboardAlex and Chloe by Daniel Johnson Storyboard
Alex and Chloe by Daniel Johnson Storyboardthephillipta
Ā 
Vip Hisar Call Girls #9907093804 Contact Number Escorts Service Hisar
Vip Hisar Call Girls #9907093804 Contact Number Escorts Service HisarVip Hisar Call Girls #9907093804 Contact Number Escorts Service Hisar
Vip Hisar Call Girls #9907093804 Contact Number Escorts Service Hisarsrsj9000
Ā 
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...akbard9823
Ā 
FULL ENJOY - 9953040155 Call Girls in Burari | Delhi
FULL ENJOY - 9953040155 Call Girls in Burari | DelhiFULL ENJOY - 9953040155 Call Girls in Burari | Delhi
FULL ENJOY - 9953040155 Call Girls in Burari | DelhiMalviyaNagarCallGirl
Ā 
Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...akbard9823
Ā 

Recently uploaded (20)

Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) šŸ§ˆ 8923113531 š“€“ Esco...
Ā 
FULL ENJOY - 9953040155 Call Girls in Paschim Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Paschim Vihar | DelhiFULL ENJOY - 9953040155 Call Girls in Paschim Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Paschim Vihar | Delhi
Ā 
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment šŸ§„ 89231135...
Ā 
Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow šŸ’‹ Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Ā 
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service AkolaAkola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
Ā 
Bridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.comBridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.com
Ā 
RAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAKRAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAK
Ā 
FULL ENJOY - 9953040155 Call Girls in Mahipalpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Mahipalpur | DelhiFULL ENJOY - 9953040155 Call Girls in Mahipalpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Mahipalpur | Delhi
Ā 
FULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | DelhiFULL ENJOY - 9953040155 Call Girls in Noida | Delhi
FULL ENJOY - 9953040155 Call Girls in Noida | Delhi
Ā 
Jagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call GirlsJagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Ā 
Roadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMRoadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NM
Ā 
(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad Escorts
(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad Escorts(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad Escorts
(NEHA) Call Girls Ahmedabad Booking Open 8617697112 Ahmedabad Escorts
Ā 
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Ā 
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Uttam Nagar | Delhi
Ā 
Mandi House Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Mandi House Call Girls : ā˜Ž 8527673949, Low rate Call GirlsMandi House Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Mandi House Call Girls : ā˜Ž 8527673949, Low rate Call Girls
Ā 
Alex and Chloe by Daniel Johnson Storyboard
Alex and Chloe by Daniel Johnson StoryboardAlex and Chloe by Daniel Johnson Storyboard
Alex and Chloe by Daniel Johnson Storyboard
Ā 
Vip Hisar Call Girls #9907093804 Contact Number Escorts Service Hisar
Vip Hisar Call Girls #9907093804 Contact Number Escorts Service HisarVip Hisar Call Girls #9907093804 Contact Number Escorts Service Hisar
Vip Hisar Call Girls #9907093804 Contact Number Escorts Service Hisar
Ā 
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment šŸµ 8923113...
Ā 
FULL ENJOY - 9953040155 Call Girls in Burari | Delhi
FULL ENJOY - 9953040155 Call Girls in Burari | DelhiFULL ENJOY - 9953040155 Call Girls in Burari | Delhi
FULL ENJOY - 9953040155 Call Girls in Burari | Delhi
Ā 
Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone šŸ«— 8923113531 ā˜› Escorts Service at 6...
Ā 

De assignment-finalized-28112017 3

  • 1. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item Sales percentage M1 M2 M3 M4 M5 M6 1 5.18% 2 64.08% 30.00% 20.00% 3 30.74% 10.00% 10.00% 100.00% 22.30% 0.00% 0.00% 0.00% 0.00% 15.89% 22.30% 22.30% 22.30% 22.30% 22.30% 38.19% Months 1 1 22.30% 15.89% 2 3 7.43% 7.43% 7.43% 15.89% 3 9 2.48% 2.48% 2.48% 5.13% 4 7 5 7 6 8 7 5 8 6 9 2 10 6 22.30% 15.89% 1 10.00% 1,214,449.50 865,436.00 7.433% 7.433% 7.433% 2 10.00% 404,816.50 404,816.50 404,816.50 2.48% 2.48% 2.48% 3 15.00% 202,408.25 202,408.25 202,408.25 4 10.00% 5 10.00% 6 10.00% 7 5.00% 8 2.50% 9 2.50% 10 17.50% 11 2.50% 12 2.50% 13 2.50% 100.00% 1,214,449.50 404,816.50 404,816.50 607,224.75 202,408.25 1,067,844.25 1,214,449.50 1,619,266.00 2,024,082.50 2,631,307.25 2,833,715.50 3,901,559.75 2,024,082.50 1,877,477.25 Quarterly Cummulative Cash Inflow 2,024,082.50 3,901,559.75 Quarterly Total Cash Inflow 54,461,770.00 Monthly Total Cash Flow 54,461,770.00 Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) 1,361,544.25 (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) 1,361,544.25 On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) 1,361,544.25 Roadworks 1,361,544.25 On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) 9,530,809.75 Drainage works 1,361,544.25 Internal &External plastering 5,446,177.00 Sewerage works 2,723,088.50 Roofing, Electrical wiring & plumbing 5,446,177.00 R.C. Framwork 8,169,265.50 Walls, Doors & Window frame 5,446,177.00 Foundation 5,446,177.00 Sales Proceeds Signing of S&P Agreement (Clause 5) 5,446,177.00 INFRASTRUCTURE WORKS 100.00% SEWERAGE WORKS 100.00% DRAINAGE WORKS 100.00% ROADWORKS 100.00% WALLS, DOORS & WINDOW FRAME 100.00% ROOFING, ELEC WIRING & PLUMBING 100.00% INTERNAL &EXTERNAL PLASTERING 100.00% EARTHWORKS 100.00% FOUNDATION 100.00% R.C. FRAMEWORK 100.00% % of Cumulative Sales D/S Terrace 34,901,350.00 D/S Shop/Office 16,740,900.00 Monthly Total 54,461,770.00 Sale Projection D/S Low Cost 2,819,520.00 Q1 Q2 Description Amount (RM) 2013
  • 2. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M7 M8 M9 M10 M11 M12 50.0% 20.0% 10.0% 10.0% 10.0% 0.0% 0.0% 18.5% 0.0% 0.0% 9.5% 38.19% 38.19% 56.67% 56.67% 56.67% 66.15% 18.48% 9.48% 18.48% 9.48% 5.13% 5.13% 11.29% 11.29% 11.29% 9.48% 5.46% 5.46% 9.15% 9.15% 9.15% 13.89% 8.10% 8.10% 8.10% 10.47% 7.08% 8.44% 18.48% 9.48% 1,006,412.00 516,422.50 15.89% 18.48% 865,436.00 1,006,412.00 5.13% 5.13% 5.13% 11.29% 11.29% 11.29% 418,767.25 418,767.25 418,767.25 921,973.25 921,973.25 921,973.25 5.46% 5.46% 9.15% 9.15% 9.15% 297,126.50 297,126.50 498,408.90 498,408.90 498,408.90 8.10% 8.10% 8.10% 440,899.64 440,899.64 440,899.64 7.08% 385,787.19 1,284,203.25 715,893.75 1,722,305.75 2,867,693.79 1,861,281.79 2,763,491.48 5,185,763.00 5,901,656.75 7,623,962.50 10,491,656.29 12,352,938.09 15,116,429.57 3,722,402.75 7,492,467.07 7,623,962.50 15,116,429.57 Q3 Q4 2013
  • 3. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M13 M14 M15 M16 M17 M18 M19 M20 50.0% 20.0% 10.0% 20.0% 0.0% 0.0% 18.5% 0.0% 0.0% 6.1% 0.0% 0.0% 66.15% 66.15% 84.63% 84.63% 84.63% 90.78% 90.78% 90.78% 18.48% 6.15% 18.48% 6.15% 18.48% 6.15% 13.89% 18.48% 6.15% 10.47% 10.47% 28.95% 6.15% 8.44% 8.44% 13.06% 13.06% 13.06% 19.21% 18.16% 18.16% 14.11% 15.33% 15.33% 15.33% 14.11% 14.11% 15.64% 15.64% 15.64% 18.48% 6.15% 1,006,412.00 334,818.00 9.5% 18.48% 6.15% 516,422.50 1,006,412.00 334,818.00 9.48% 18.48% 6.15% 774,633.75 1,509,618.00 502,227.00 13.89% 13.89% 18.48% 6.15% 756,620.15 756,620.15 1,006,412.00 334,818.00 10.47% 10.47% 10.47% 28.95% 6.15% 570,005.27 570,005.27 570,005.27 1,576,417.27 334,818.00 8.44% 8.44% 8.44% 13.06% 13.06% 13.06% 19.21% 459,561.83 459,561.83 459,561.83 711,164.83 711,164.83 711,164.83 1,045,982.83 18.16% 494,395.00 14.11% 15.33% 15.33% 192,047.17 208,788.07 208,788.07 3,077,243.50 1,786,187.25 2,035,979.10 5,810,024.10 711,164.83 1,238,030.00 2,761,451.90 703,183.07 18,193,673.06 19,979,860.31 22,015,839.41 27,825,863.51 28,537,028.34 29,775,058.34 32,536,510.23 33,239,693.30 6,899,409.84 7,759,218.93 22,015,839.41 29,775,058.34 Q1 Q2 Q3 2014
  • 4. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M21 M22 M23 M24 30.0% 9.2% 0.0% 0.0% 0.0% 100.00% 100.00% 100.00% 100.00% 9.22% 9.22% 9.22% 9.22% 9.22% 9.22% 21.23% 21.23% 21.23% 19.95% 19.95% 50.00% 50.00% 24.86% 9.22% 0.00% 502,227.00 - 9.22% 502,227.00 9.22% 753,340.50 9.22% 502,227.00 9.22% 502,227.00 9.22% 502,227.00 18.16% 21.23% 21.23% 21.23% 494,395.00 578,099.50 578,099.50 578,099.50 15.33% 19.95% 19.95% 208,788.07 271,566.44 271,566.44 50.00% 680,772.13 1,205,410.07 3,611,914.44 849,665.94 1,258,871.63 34,445,103.37 38,057,017.81 38,906,683.75 40,165,555.38 4,670,045.03 5,720,452.01 34,445,103.37 40,165,555.38 Q3 Q4 2014
  • 5. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M25 M26 M27 M28 M29 M30 M31 M32 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 50.00% 680,772.13 100.00% 9,530,809.75 100.00% 1,361,544.25 10,211,581.88 1,361,544.25 0 0 0 0 0 0 50,377,137.25 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 11,573,126.13 0 51,738,681.50 51,738,681.50 Q3Q1 Q2 2015
  • 6. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M33 M34 M35 M36 100.00% 100.00% 100.00% 100.00% 100.00% 1,361,544.25 1,361,544.25 0 0 0 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 1,361,544.25 0 53,100,225.75 53,100,225.75 Q3 Q4 2015
  • 7. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M37 M38 M39 M40 M41 M42 M43 M44 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 0 0 0 0 0 0 0 0 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 0 0 53,100,225.75 53,100,225.75 Q1 2016 Q2 Q3
  • 8. 4.0 Cash Flow for Project The cash flow for this project is based on ā€˜Sell-then-Buildā€™ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developerā€™s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaserā€™s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M45 M46 M47 M48 M49 M50 M51 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.0% 1,361,544.25 0 0 0 0 1,361,544.25 0 0 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 54,461,770.00 54,461,770.00 54,461,770.00 0 0 1,361,544.25 53,100,225.75 53,100,225.75 54,461,770.00 2016 2017 Q1Q3 Q4