SlideShare a Scribd company logo
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 14, Issue 1 Ver. II (Jan. - Feb. 2017), PP 52-56
www.iosrjournals.org
DOI: 10.9790/1684-1401025256 www.iosrjournals.org 52 | Page
Risk Severity Framework for a BOT Highway Project
By K.Srinivas, Assistant Professor,
National Institute of Construction Management and Research (NICMAR)
Abstract: Adequate attention needs to be given to project risk management for reaping the benefits by way of
meeting the objectives of an organisation. Organisations which implement good risk management practices
derive maximum advantage by way of fewer risks which are quite manageable in general and more so in
infrastructure sector which is subjected to plethora of risks. The role of infrastructure in the overall
development of a nation cannot be underscored. Considering this, a study has been carried out for an ongoing
highway project being executed in the state of Telangana (India) under NHAI. The study was carried out by
administering the questionnaire to 250 experts associated with highway sector and the response received was
110. The respondents were asked to identify the risks in four phases of a project namely Feasibility phase,
Development Phase, Execution Phase and Operation phase and also the likelihood and impact of each of the
identified risks. The severity of risk was determined based on the likelihood and impact of risks and was
categorized accordingly. The severity of risk indicates the extent to which the project is exposed to that
particular risk and the mitigation measures need to be taken accordingly to minimise the effect of risk.
Keywords: Risk assessment, Risk severity
I. Introduction
Construction industry right from the conceptual phase to commissioning of project is subjected to risks
which needs to be addressed by the stakeholders concerned. In recent times, the nature, incident and impact of
risk in construction industry has become a topic of interest because of its effects on quality, time and cost of
construction projects (Ojo, 2010, Windap et al 2010 and Joshua 2010) Risk is important to contractors, clients
and consultants within the construction industry. Construction activities are subjected to plethora of risks which
have to be considered by the management if they are to achieve their objectives.As per Project Management
Institute (PMI, 1996) “Risk is uncertainty and result of the uncertainty or lack of predictability about structure,
outcome or consequences in a planning or decision situation”. Risk management is defined as “entire set of
activities and measures that are aimed at dealing with risks in order to maintain control over the project”
Construction risk management is the process of identifying, analyzing and mitigating the risks in the project by
proper response (PMI,2003).According to www.antive.net(2012),project risk management involves risk
identification, risk analysis, creating a risk response action plan, monitoring and controlling of risks in a project.
ISO 31000 defines “Risk Management as identification, assessment, and prioritisation of risks followed by
coordinated and economical application of resources to minimise, monitor, and control the probability and/or
impact of unfortunate events or to maximize the realization of opportunities. Risk Management’s objective is to
assure uncertainty does not deflect the endeavor from the business goals. Martin Schieg (2006) defines “Risk
management constitutes a strategy to avoid losses and use available chances potentially arising from risks. The
strategy demands from the person to take a precise “consideration” and “assessment” of the situation and the
scenarios likely to occur in future. This means recognising potential risks and circumventing a threat by
averting , evading or reducing their negative effects”An infrastructure project by its very nature is subjected to
variety of risks and hence the impact of risks on the project if it were to occur will be substantial. This study is
confined to a highway project in state of Telangana (India) by considering various risks in the four phases of the
project and calculating the severity of each risk based on which suitable risk mitigation measures have been
proposed.
II. Literature Survey
Al-Bahar and Crandall1
on systematic risk management approach for construction projects have
concluded that brainstorming sessions and analysis of historical data of similar projects were found to be the
most preferred methods of risk identification in construction industry and that formal risk management process
is used infrequently. Ahmed et al2
in his study has concluded that complexities of projects, locations and type of
contracts are significant contributors to risk in construction projects. Ijigah Edoka Augustine et al3
on risk
management practices in Nigerian construction industry have concluded that risks are not properly managed
and that there is need for strategy to reduce the risks by way of formulation of effective risk management
index.YYL Florence et al4
have concluded that every infrastructure project is subjected to multiple risks and it
is the responsibility of promoter to promoter to mitigate the risks by having a strong management team and a
Risk Severity Framework For A BOT Highway Project
DOI: 10.9790/1684-1401025256 www.iosrjournals.org 53 | Page
comprehensive risk management should be conducted and mitigation plan be prepared for ensuing the success
of project. Baloi et al5
did a modeling study on global risk factors affecting the cost performance in construction
projects and have concluded that there is need to incorporate global risk factors in any project for effective
project mitigation. Debasis Sarkar et al 6
on Project Risk Management Framework for PPP models for Indian
highway projects have developed a framework for project risk management for PPP models for Indian Highway
projects. Jonathan k.Fabi et al7
have conducted a study on risk Management practice of highway projects in
Nigeria and recommended that adequate training for all stakeholders in highway construction sector for
effective management of risks and for meeting the project objectives. Kansal RK et al8
in their study on risk
assessment methods and application in construction have concluded that various methods of risk assessment like
brainstorming, checklist, Delphi method and risk significant index methods are used and each method has its
own limitation and that risk assessment methods can be integrated for applying risk management effectively.
Shehu et al9
have stressed that construction is a risk prone industry with poor track record of coping with risks as
a result of which clients are not able to reap full benefits of their investment. Nerija Banaitiene et al10
have
concluded that risk management is the core of project management and that success of any project depends on
how effectively uncertainties are handled. DadaJ O et al11
on evaluation of impact of risk in construction
industry have identified political risk as the main risk factor and that contingency amount in the estimate should
be based on procurement method. Debasis Sarkar et al12
in their study on project risk management in
underground construction of metro rail have concluded that cost uncertainties and risks should essentially be
carried out for infrastructure projects and that risks involved in infrastructure project from concept to
commissioning, if not treated properly, probability of successful completion of project gets diminished.Shen LY
and et al13
in their study on risk assessment for construction joint ventures in china have observed that risk
transfer is an effective tool for mitigating the risks in infrastructure projects. Martina Claudia Garrido et al14
in
their study have concluded that formal risk identification and application techniques in Brazilian construction
industry is rarely used and that more informal methods are applied for risk identification.Rinaj Pathan et al15
in
their study on Risk assessment of BOT projects have evaluated the role of financial stability of the project and
its subsequent effect on risks and concluded that a BOT project gets affected by various parameters like toll
structure, toll revision schedule , extent of government grant etc and that project sponsor and promoter need to
arrive at an agreement on sharing of risks for effective risk mitigation.
III. Research Methodology
Data for the study was collated through a questionnaire that was administered to 250 participants of the
project which is being executed in the state of Telangana (India). The recipients of Questionnaire were clients/
developers, architects, contractors, consultants, engineers etc who were involved in construction of project.. The
response received was 110(44%). The respondents were asked to furnish the likelihood of occurrence of a
risk(L) and its impact(I) on a scale of 1 to 5 whose connotation is given below
Table:1 : Connotation for Likelihood and Impact of risk
Scale Connotation for
likelihood
Connotation
for Impact
1 Improbable Insignificant
2 Unlikely Marginal
3 As likely as not Serious
4 Probable Critical
5 Highly probable Catastrophe
Based on the responses furnished by the respondents, the weighted average likelihood and impact is calculated
as follows:
Weighted average = ∑(Number of responses *Concerned Numerical scale )/response received
After calculating the weighted average likelihood and impact, the severity of risk was calculated as L + I – (
L*I) where L & I are brought on a scale of 0 to 1 by dividing with 5.The connotation for severity of risk is
given as follows
Table 2: Connotation for Severity of Risk
Range of Values Severity of Risk
0.0-0.2 Nil
0.21-0.4 Insignificant
0.41-0.6 Significant
0.61-0.8 High
0.81-1.00 Very high
Risk Severity Framework For A BOT Highway Project
DOI: 10.9790/1684-1401025256 www.iosrjournals.org 54 | Page
IV. Risk Assessment
Table 3: Risk Assessment (Feasibility phase)
Risk Responses
( Likelihood)
Responses
( Impact)
Weighted
average
Likelihood of
risk
Weighted
average
impact of risk
1 2 3 4 5 1 2 3 4 5
Reliability of
Feasibility Report
42 34 17 13 6 34 28 29 13 6 2.21 2.35
Approval and
permit risks
11 33 41 14 11 8 14 36 30 22 2.83 3.4
Political risks 30 41 17 14 8 18 25 47 14 6 2.35 2.68
Legal risks 38 41 19 8 4 22 28 30 14 16 2.08 2.76
Environment and
social risks
24 28 35 12 11 21 30 34 19 6 2.61 2.63
Table 4: Risk Assessment (Development phase)
Risk Responses
( Likelihood)
Responses
( Impact)
Weighted average
Likelihood of risk
Weighted
average
impact of risk
1 2 3 4 5 1 2 3 4 5
Land Acquisition 16 31 45 11 7 7 42 38 14 9 2.65 2.78
Resettlement &
Rehabilitation
19 27 48 11 5 23 30 43 11 3 2.06 2.46
Design 24 33 27 16 10 19 24 35 22 10 2.59 2.81
Bidding 20 40 27 13 10 33 44 16 11 6 2.57 2.2
Environment and
social risks
22 30 33 13 12 20 22 38 18 12 2.66 2.81
Market 18 26 37 16 13 23 30 33 17 7 2.81 2.59
Legal 19 38 41 7 5 23 27 30 14 16 2.46 2.75
Political 29 53 13 9 6 22 27 49 8 4 2.18 2.5
Financial closure 27 33 21 18 11 29 36 25 14 6 2.57 2.38
Technology
Selection
28 34 33 9 6 38 34 18 11 9 2.37 2.26
Table 5: Risk Assessment (Execution phase)
Risk Responses
( Likelihood)
Responses
( Impact)
Weighted
average
Likelihood
of risk
Weighted
average
impact of
risk
1 2 3 4 5 1 2 3 4 5
Utility diversion 20 28 16 19 27 16 33 31 23 7 3.05 2.74
Force Majeure 22 30 35 15 8 7 11 22 39 31 2.61 3.69
Traffic diversion 3 18 20 52 17 10 13 25 40 22 3.56 3.46
Safety 20 27 43 13 7 11 25 38 23 13 2.64 3.01
Time over run 9 22 49 21 9 8 10 36 33 23 2.99 3.48
Cost Overrun 11 24 39 26 10 8 16 42 25 19 3 3.28
Construction 24 33 27 16 10 16 34 31 23 6 2.59 2.71
Inflation 25 34 23 16 12 17 25 31 24 13 2.6 2.91
Contractual 29 30 25 15 11 18 20 22 40 10 2.54 3.03
Table 6: Risk Assessment (Operation phase)
Risk Responses
( Likelihood)
Responses
( Impact)
Weighted average
Likelihood of risk
Weighted
average
impact of risk
1 2 3 4 5 1 2 3 4 5
Traffic Revenue 19 26 37 16 12 23 30 33 18 6 2.78 2.58
Market 16 25 30 29 10 21 29 34 24 2 2.92 2.61
Safety 28 30 33 14 5 20 32 37 18 3 2.44 2.56
Force Majeure 29 33 21 17 10 17 22 31 26 14 2.51 2.98
Social and
Environmental
13 42 35 18 2 11 43 35 17 4 2.58 2.64
Legal 19 39 41 8 3 23 29 30 13 15 2.42 2.71
Transportation
of hazardous
chemicals
9 24 29 32 16 7 15 22 40 29 3.2 3.71
Risk Severity Framework For A BOT Highway Project
DOI: 10.9790/1684-1401025256 www.iosrjournals.org 55 | Page
5. Risk Severity
Table 7 : Risk Severity(All Phases)
Risk Likelihood Impact Risk value
L+I –( L*I)
Risk Severity
Feasibility Phase
Reliability of Feasibility Report 2.21 2.35 0.704 High
Approval and permit risks 2.83 3.4 0.861 Very High
Political risks 2.35 2.68 0.754 High
Legal risks 2.08 2.76 0.738 High
Environment and social risks 2.61 2.63 0.773 High
Development Phase
Land Acquisition 2.65 2.78 0.791 High
Resettlement & Rehabilitation 2.06 2.46 0.701 High
Design 2.59 2.81 0.789 High
Bidding 2.57 2.2 0.728 High
Environment and social risks 2.66 2.81 0.795 Very High
Market 2.81 2.59 0.789 High
Legal 2.46 2.75 0.771 High
Political 2.18 2.5 0.718 High
Financial closure 2.57 2.38 0.745 High
Technology Selection 2.37 2.26 0.711 High
Execution Phase
Utility diversion 3.05 2.74 0.823 Very High
Force Majeure 2.61 3.69 0.874 Very High
Traffic diversion 3.56 3.46 0.911 Very High
Safety 2.64 3.01 0.812 Very High
Time over run 2.99 3.48 0.878 Very High
Cost Overrun 3 3.28 0.862 Very High
Construction 2.59 2.71 0.779 High
Inflation 2.6 2.91 0.799 Very High
Contractual 2.54 3.03 0.806 Very High
Operation Phase
Traffic Revenue 2.78 2.58 0.785 High
Market 2.92 2.61 0.801 Very High
Safety 2.44 2.56 0.750 High
Force Majeure 2.51 2.98 0.799 Very High
Social and Environmental 2.58 2.64 0.771 High
Legal 2.42 2.71 0.764 High
Transportation of hazardous
chemicals
3.2 3.71 0.907 Very High
V. Conclusions
1. All the risks are in the category of high and very high and hence as such risks in the project are quite
substantial
2. Almost all the risks in the execution phase are in very high category which means that these risks have the
potential to derail the project
3. In the development phase, environment and social risks is in very high category which meant that risk of
displacement of people as well as the effect on the environment is substantial
4. In the feasibility phase, risk of approval and permit is in very high category and hence sufficient attention
should be paid to mitigate this risk.
5. Adequate attention should be given to Market, Force Majeure and Transportation risks in Operation phase.
6. Suitable risk mitigation measures by way of risk transfer, risk sharing and risk reduction is to be put in
place so as to minimise the effect of risk in the event of its occurrence.
7. On the whole it can be inferred that risks in infrastructure projects are of potentially damaging nature and
unless suitable risk management is in place, the chances of a successful project outcome is remote.
References
[1]. Al-Bahar J and Crandall K(1990), Systematic Risk Management Approach for Construction Projects, Journal of Construction
Engineering and Management116(3),pp533-546
[2]. Ahmed, et al(1990),Decision support system for modeling bid/no-bid decision problems, Journal of Construction Engineering and
Management, ASCE,116(4), pp595-608
[3]. Ijigah Edoka Augustine, Jimoh Richard Ajayi, et al, (2013), Assessment of Risk Management Practices in Nigerian Construction
Industry-Toward establishing Risk Management Index, International Journal of Pure and Applied Sciences and Technology,16(2),
pp20-31
Risk Severity Framework For A BOT Highway Project
DOI: 10.9790/1684-1401025256 www.iosrjournals.org 56 | Page
[4]. Florence YYL and Linda H (2006),Risk faced by Singapore Firms When undertaking Construction projects in India, International
Journal of Project Management,24(38),pp261-270
[5]. Baloi D and price ADF (2003),Modelling Global Risk factors Affecting Construction Cost Performance, International Journal of
Project Management,21,pp261-269
[6]. Debasis Sarkar and Kintan Patel ( 2012), Project Risk management Framework for PPP models for Indian Highway Projects, Ciivl
engineering and Construction review Journal, 25(03), pp 104-112
[7]. Jonathan.k.Fabi and Jacob A.B.Awolesi ( 2015), A study of Risk Management practice of Highway projects in Nigeria,Journal of
Economics and Sustainable Development, 6(18), pp 171-177
[8]. Kansal RK and Manoj Sharma (2012),Risk Assessment methods and Applications in Construction Projects,2(3), pp1081-1085
[9]. Shehu Z and Sommerville J (2006),Real Time Risk Management Approach in Construction Projects, Glasgow University, Glasgow,
United Kingdom
[10]. Nerija Banaitiene and Audrius Banaitis, Risk Management-Current Issues and Challenges, ISBN 978-953-51-0747-7, InTech,
September 9, 2012
[11]. Dada J O and Jagboro G O (2007),Evaluation of Impact of Risk on Project Cost Overrun in Nigerian Construction Industry, Journal
of Financial Management of property and Construction, 12(1), pp37-44
[12]. Debasis Sarkar and Goutam Datta(2011),A framework of Project Risk Management for the Underground Corridor Construction of
Metro Rail, Indian Institute of Management, W.P No:2011-02-05
[13]. Shen LY and Ng, CSK(2001),Risk Assessment for Construction Joint Venture in China, Journal of Construction Engineering and
Management,127(1),pp76-81
[14]. Martina Claudia Garrido, Morano Cassia,Riberio and Assed (2011),Risk Identification Techniques Knowledge and Application in
Brazilian Construction,2(11), pp242-252
[15]. Rinaj Pathan and Dr Pilplikar S S( 2013), Risk Assessment of BOT Road Projects,IOSR journal of mechanical and Civil
Engineering, 5(3), pp 40-59

More Related Content

What's hot

Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
Sibo Kanyambari Aimable
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
theijes
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET Journal
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET Journal
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
Dr. Amarjeet Singh
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
Fredy Kurniawan
 
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
ijtsrd
 
This is an empirical study of industry practice in the management of softwar...
This is an empirical study of  industry practice in the management of softwar...This is an empirical study of  industry practice in the management of softwar...
This is an empirical study of industry practice in the management of softwar...
AYESHA JAVED
 
Investigating the use of uncertainty
Investigating the use of uncertaintyInvestigating the use of uncertainty
Investigating the use of uncertainty
civej
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET Journal
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET Journal
 
Factors affecting risk appetite
Factors affecting risk appetiteFactors affecting risk appetite
Factors affecting risk appetite
UmarAslam31
 
Safety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projectsSafety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projects
eSAT Publishing House
 
Safety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projectsSafety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projects
eSAT Journals
 

What's hot (17)

Risk Management
Risk ManagementRisk Management
Risk Management
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
 
Project risk management
Project risk managementProject risk management
Project risk management
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
 
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
 
Ijetcas14 370
Ijetcas14 370Ijetcas14 370
Ijetcas14 370
 
This is an empirical study of industry practice in the management of softwar...
This is an empirical study of  industry practice in the management of softwar...This is an empirical study of  industry practice in the management of softwar...
This is an empirical study of industry practice in the management of softwar...
 
Investigating the use of uncertainty
Investigating the use of uncertaintyInvestigating the use of uncertainty
Investigating the use of uncertainty
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
 
Factors affecting risk appetite
Factors affecting risk appetiteFactors affecting risk appetite
Factors affecting risk appetite
 
Safety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projectsSafety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projects
 
Safety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projectsSafety and health risk assessment at oman building construction projects
Safety and health risk assessment at oman building construction projects
 

Similar to Risk Severity Framework for a BOT Highway Project

risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
RidaShahid36
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
A Makwana
 
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
IAEME Publication
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingAlexander Decker
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
2020) Comparison Of Risk Management Analysis Between Pmbok
2020) Comparison Of Risk Management Analysis Between Pmbok2020) Comparison Of Risk Management Analysis Between Pmbok
2020) Comparison Of Risk Management Analysis Between Pmbok
Anna Landers
 
IRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In KeralaIRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET Journal
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
IRJET Journal
 
IRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail ProjectIRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET Journal
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
IAEME Publication
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paper
Molay Reja
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
IRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
IRJET Journal
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
IRJET Journal
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
Oyeniyi Samuel
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
Dr.Madhav Prasad Koirala
 
C1303032126
C1303032126C1303032126
C1303032126
IOSR Journals
 
EFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECT
EFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECTEFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECT
EFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECT
IRJET Journal
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction Projects
IJMER
 

Similar to Risk Severity Framework for a BOT Highway Project (20)

risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
 
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
2020) Comparison Of Risk Management Analysis Between Pmbok
2020) Comparison Of Risk Management Analysis Between Pmbok2020) Comparison Of Risk Management Analysis Between Pmbok
2020) Comparison Of Risk Management Analysis Between Pmbok
 
IRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In KeralaIRJET- Risk Assessment of Public Private Partnership Projects In Kerala
IRJET- Risk Assessment of Public Private Partnership Projects In Kerala
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
IRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail ProjectIRJET-Risk Management Analysis on Cochin Metro Rail Project
IRJET-Risk Management Analysis on Cochin Metro Rail Project
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paper
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
C1303032126
C1303032126C1303032126
C1303032126
 
EFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECT
EFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECTEFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECT
EFFECTIVE MANAGEMENT IN PUBLIC PRIVATE PARTNERSHIP PROJECT
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction Projects
 

More from IOSRJMCE

Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...
Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...
Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...
IOSRJMCE
 
Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...
Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...
Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...
IOSRJMCE
 
Experimental and Numerical Modal Analysis of a Compressor Mounting Bracket
Experimental and Numerical Modal Analysis of a Compressor Mounting BracketExperimental and Numerical Modal Analysis of a Compressor Mounting Bracket
Experimental and Numerical Modal Analysis of a Compressor Mounting Bracket
IOSRJMCE
 
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
IOSRJMCE
 
A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...
A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...
A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...
IOSRJMCE
 
Experimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134a
Experimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134aExperimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134a
Experimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134a
IOSRJMCE
 
Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...
Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...
Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...
IOSRJMCE
 
Study on Transverse Displacement in Composite Laminated Plates across Thickne...
Study on Transverse Displacement in Composite Laminated Plates across Thickne...Study on Transverse Displacement in Composite Laminated Plates across Thickne...
Study on Transverse Displacement in Composite Laminated Plates across Thickne...
IOSRJMCE
 
Study of Forced Convection Heat Transfer with Single phase and mixture phase ...
Study of Forced Convection Heat Transfer with Single phase and mixture phase ...Study of Forced Convection Heat Transfer with Single phase and mixture phase ...
Study of Forced Convection Heat Transfer with Single phase and mixture phase ...
IOSRJMCE
 
Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...
Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...
Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...
IOSRJMCE
 
Mechanical Analysis of an Ixtle Based Cable for Its Use in Architecture
Mechanical Analysis of an Ixtle Based Cable for Its Use in ArchitectureMechanical Analysis of an Ixtle Based Cable for Its Use in Architecture
Mechanical Analysis of an Ixtle Based Cable for Its Use in Architecture
IOSRJMCE
 
Application of Artificial Neural Networking for Determining the Plane of Vibr...
Application of Artificial Neural Networking for Determining the Plane of Vibr...Application of Artificial Neural Networking for Determining the Plane of Vibr...
Application of Artificial Neural Networking for Determining the Plane of Vibr...
IOSRJMCE
 
Effect of Stiffening System on Building Resistance to Earthquake Forces
Effect of Stiffening System on Building Resistance to Earthquake ForcesEffect of Stiffening System on Building Resistance to Earthquake Forces
Effect of Stiffening System on Building Resistance to Earthquake Forces
IOSRJMCE
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
IOSRJMCE
 
Optimization of Electrical Discharge Machining Process Parameters using SCM42...
Optimization of Electrical Discharge Machining Process Parameters using SCM42...Optimization of Electrical Discharge Machining Process Parameters using SCM42...
Optimization of Electrical Discharge Machining Process Parameters using SCM42...
IOSRJMCE
 
Efficient Mass Participation Ratio of Building with Basement
Efficient Mass Participation Ratio of Building with BasementEfficient Mass Participation Ratio of Building with Basement
Efficient Mass Participation Ratio of Building with Basement
IOSRJMCE
 
Literature Review of Experimental Study on Load Bearing Masonry Wall
Literature Review of Experimental Study on Load Bearing Masonry WallLiterature Review of Experimental Study on Load Bearing Masonry Wall
Literature Review of Experimental Study on Load Bearing Masonry Wall
IOSRJMCE
 
Structural Design of Concrete Structure Using E-Tabs
Structural Design of Concrete Structure Using E-TabsStructural Design of Concrete Structure Using E-Tabs
Structural Design of Concrete Structure Using E-Tabs
IOSRJMCE
 
Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...
Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...
Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...
IOSRJMCE
 
Influence of Combine Vertical Irregularities in the Response of Earthquake Re...
Influence of Combine Vertical Irregularities in the Response of Earthquake Re...Influence of Combine Vertical Irregularities in the Response of Earthquake Re...
Influence of Combine Vertical Irregularities in the Response of Earthquake Re...
IOSRJMCE
 

More from IOSRJMCE (20)

Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...
Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...
Axial Capacity Enhancement of CFRP Confined Columns Made of Steel Fiber Reinf...
 
Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...
Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...
Smart Response Surface Models using Legacy Data for Multidisciplinary Optimiz...
 
Experimental and Numerical Modal Analysis of a Compressor Mounting Bracket
Experimental and Numerical Modal Analysis of a Compressor Mounting BracketExperimental and Numerical Modal Analysis of a Compressor Mounting Bracket
Experimental and Numerical Modal Analysis of a Compressor Mounting Bracket
 
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
 
A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...
A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...
A Review: Effect of Laser Peening Treatment on Properties And Life Cycle of D...
 
Experimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134a
Experimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134aExperimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134a
Experimental Evaluation of Refrigerant Mixtures as Substitutes for HFC134a
 
Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...
Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...
Simulation and Analysis of Electrolyte Flow Pattern in ECM for L-Shaped Tool ...
 
Study on Transverse Displacement in Composite Laminated Plates across Thickne...
Study on Transverse Displacement in Composite Laminated Plates across Thickne...Study on Transverse Displacement in Composite Laminated Plates across Thickne...
Study on Transverse Displacement in Composite Laminated Plates across Thickne...
 
Study of Forced Convection Heat Transfer with Single phase and mixture phase ...
Study of Forced Convection Heat Transfer with Single phase and mixture phase ...Study of Forced Convection Heat Transfer with Single phase and mixture phase ...
Study of Forced Convection Heat Transfer with Single phase and mixture phase ...
 
Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...
Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...
Eigenvalue Buckling Computation and Impact on Pipeline Wall Thickness and Sub...
 
Mechanical Analysis of an Ixtle Based Cable for Its Use in Architecture
Mechanical Analysis of an Ixtle Based Cable for Its Use in ArchitectureMechanical Analysis of an Ixtle Based Cable for Its Use in Architecture
Mechanical Analysis of an Ixtle Based Cable for Its Use in Architecture
 
Application of Artificial Neural Networking for Determining the Plane of Vibr...
Application of Artificial Neural Networking for Determining the Plane of Vibr...Application of Artificial Neural Networking for Determining the Plane of Vibr...
Application of Artificial Neural Networking for Determining the Plane of Vibr...
 
Effect of Stiffening System on Building Resistance to Earthquake Forces
Effect of Stiffening System on Building Resistance to Earthquake ForcesEffect of Stiffening System on Building Resistance to Earthquake Forces
Effect of Stiffening System on Building Resistance to Earthquake Forces
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Optimization of Electrical Discharge Machining Process Parameters using SCM42...
Optimization of Electrical Discharge Machining Process Parameters using SCM42...Optimization of Electrical Discharge Machining Process Parameters using SCM42...
Optimization of Electrical Discharge Machining Process Parameters using SCM42...
 
Efficient Mass Participation Ratio of Building with Basement
Efficient Mass Participation Ratio of Building with BasementEfficient Mass Participation Ratio of Building with Basement
Efficient Mass Participation Ratio of Building with Basement
 
Literature Review of Experimental Study on Load Bearing Masonry Wall
Literature Review of Experimental Study on Load Bearing Masonry WallLiterature Review of Experimental Study on Load Bearing Masonry Wall
Literature Review of Experimental Study on Load Bearing Masonry Wall
 
Structural Design of Concrete Structure Using E-Tabs
Structural Design of Concrete Structure Using E-TabsStructural Design of Concrete Structure Using E-Tabs
Structural Design of Concrete Structure Using E-Tabs
 
Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...
Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...
Finite Element Analysis of Opening Plate, Fixed Tube Sheet and Floating Sheet...
 
Influence of Combine Vertical Irregularities in the Response of Earthquake Re...
Influence of Combine Vertical Irregularities in the Response of Earthquake Re...Influence of Combine Vertical Irregularities in the Response of Earthquake Re...
Influence of Combine Vertical Irregularities in the Response of Earthquake Re...
 

Recently uploaded

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 

Recently uploaded (20)

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 

Risk Severity Framework for a BOT Highway Project

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 14, Issue 1 Ver. II (Jan. - Feb. 2017), PP 52-56 www.iosrjournals.org DOI: 10.9790/1684-1401025256 www.iosrjournals.org 52 | Page Risk Severity Framework for a BOT Highway Project By K.Srinivas, Assistant Professor, National Institute of Construction Management and Research (NICMAR) Abstract: Adequate attention needs to be given to project risk management for reaping the benefits by way of meeting the objectives of an organisation. Organisations which implement good risk management practices derive maximum advantage by way of fewer risks which are quite manageable in general and more so in infrastructure sector which is subjected to plethora of risks. The role of infrastructure in the overall development of a nation cannot be underscored. Considering this, a study has been carried out for an ongoing highway project being executed in the state of Telangana (India) under NHAI. The study was carried out by administering the questionnaire to 250 experts associated with highway sector and the response received was 110. The respondents were asked to identify the risks in four phases of a project namely Feasibility phase, Development Phase, Execution Phase and Operation phase and also the likelihood and impact of each of the identified risks. The severity of risk was determined based on the likelihood and impact of risks and was categorized accordingly. The severity of risk indicates the extent to which the project is exposed to that particular risk and the mitigation measures need to be taken accordingly to minimise the effect of risk. Keywords: Risk assessment, Risk severity I. Introduction Construction industry right from the conceptual phase to commissioning of project is subjected to risks which needs to be addressed by the stakeholders concerned. In recent times, the nature, incident and impact of risk in construction industry has become a topic of interest because of its effects on quality, time and cost of construction projects (Ojo, 2010, Windap et al 2010 and Joshua 2010) Risk is important to contractors, clients and consultants within the construction industry. Construction activities are subjected to plethora of risks which have to be considered by the management if they are to achieve their objectives.As per Project Management Institute (PMI, 1996) “Risk is uncertainty and result of the uncertainty or lack of predictability about structure, outcome or consequences in a planning or decision situation”. Risk management is defined as “entire set of activities and measures that are aimed at dealing with risks in order to maintain control over the project” Construction risk management is the process of identifying, analyzing and mitigating the risks in the project by proper response (PMI,2003).According to www.antive.net(2012),project risk management involves risk identification, risk analysis, creating a risk response action plan, monitoring and controlling of risks in a project. ISO 31000 defines “Risk Management as identification, assessment, and prioritisation of risks followed by coordinated and economical application of resources to minimise, monitor, and control the probability and/or impact of unfortunate events or to maximize the realization of opportunities. Risk Management’s objective is to assure uncertainty does not deflect the endeavor from the business goals. Martin Schieg (2006) defines “Risk management constitutes a strategy to avoid losses and use available chances potentially arising from risks. The strategy demands from the person to take a precise “consideration” and “assessment” of the situation and the scenarios likely to occur in future. This means recognising potential risks and circumventing a threat by averting , evading or reducing their negative effects”An infrastructure project by its very nature is subjected to variety of risks and hence the impact of risks on the project if it were to occur will be substantial. This study is confined to a highway project in state of Telangana (India) by considering various risks in the four phases of the project and calculating the severity of each risk based on which suitable risk mitigation measures have been proposed. II. Literature Survey Al-Bahar and Crandall1 on systematic risk management approach for construction projects have concluded that brainstorming sessions and analysis of historical data of similar projects were found to be the most preferred methods of risk identification in construction industry and that formal risk management process is used infrequently. Ahmed et al2 in his study has concluded that complexities of projects, locations and type of contracts are significant contributors to risk in construction projects. Ijigah Edoka Augustine et al3 on risk management practices in Nigerian construction industry have concluded that risks are not properly managed and that there is need for strategy to reduce the risks by way of formulation of effective risk management index.YYL Florence et al4 have concluded that every infrastructure project is subjected to multiple risks and it is the responsibility of promoter to promoter to mitigate the risks by having a strong management team and a
  • 2. Risk Severity Framework For A BOT Highway Project DOI: 10.9790/1684-1401025256 www.iosrjournals.org 53 | Page comprehensive risk management should be conducted and mitigation plan be prepared for ensuing the success of project. Baloi et al5 did a modeling study on global risk factors affecting the cost performance in construction projects and have concluded that there is need to incorporate global risk factors in any project for effective project mitigation. Debasis Sarkar et al 6 on Project Risk Management Framework for PPP models for Indian highway projects have developed a framework for project risk management for PPP models for Indian Highway projects. Jonathan k.Fabi et al7 have conducted a study on risk Management practice of highway projects in Nigeria and recommended that adequate training for all stakeholders in highway construction sector for effective management of risks and for meeting the project objectives. Kansal RK et al8 in their study on risk assessment methods and application in construction have concluded that various methods of risk assessment like brainstorming, checklist, Delphi method and risk significant index methods are used and each method has its own limitation and that risk assessment methods can be integrated for applying risk management effectively. Shehu et al9 have stressed that construction is a risk prone industry with poor track record of coping with risks as a result of which clients are not able to reap full benefits of their investment. Nerija Banaitiene et al10 have concluded that risk management is the core of project management and that success of any project depends on how effectively uncertainties are handled. DadaJ O et al11 on evaluation of impact of risk in construction industry have identified political risk as the main risk factor and that contingency amount in the estimate should be based on procurement method. Debasis Sarkar et al12 in their study on project risk management in underground construction of metro rail have concluded that cost uncertainties and risks should essentially be carried out for infrastructure projects and that risks involved in infrastructure project from concept to commissioning, if not treated properly, probability of successful completion of project gets diminished.Shen LY and et al13 in their study on risk assessment for construction joint ventures in china have observed that risk transfer is an effective tool for mitigating the risks in infrastructure projects. Martina Claudia Garrido et al14 in their study have concluded that formal risk identification and application techniques in Brazilian construction industry is rarely used and that more informal methods are applied for risk identification.Rinaj Pathan et al15 in their study on Risk assessment of BOT projects have evaluated the role of financial stability of the project and its subsequent effect on risks and concluded that a BOT project gets affected by various parameters like toll structure, toll revision schedule , extent of government grant etc and that project sponsor and promoter need to arrive at an agreement on sharing of risks for effective risk mitigation. III. Research Methodology Data for the study was collated through a questionnaire that was administered to 250 participants of the project which is being executed in the state of Telangana (India). The recipients of Questionnaire were clients/ developers, architects, contractors, consultants, engineers etc who were involved in construction of project.. The response received was 110(44%). The respondents were asked to furnish the likelihood of occurrence of a risk(L) and its impact(I) on a scale of 1 to 5 whose connotation is given below Table:1 : Connotation for Likelihood and Impact of risk Scale Connotation for likelihood Connotation for Impact 1 Improbable Insignificant 2 Unlikely Marginal 3 As likely as not Serious 4 Probable Critical 5 Highly probable Catastrophe Based on the responses furnished by the respondents, the weighted average likelihood and impact is calculated as follows: Weighted average = ∑(Number of responses *Concerned Numerical scale )/response received After calculating the weighted average likelihood and impact, the severity of risk was calculated as L + I – ( L*I) where L & I are brought on a scale of 0 to 1 by dividing with 5.The connotation for severity of risk is given as follows Table 2: Connotation for Severity of Risk Range of Values Severity of Risk 0.0-0.2 Nil 0.21-0.4 Insignificant 0.41-0.6 Significant 0.61-0.8 High 0.81-1.00 Very high
  • 3. Risk Severity Framework For A BOT Highway Project DOI: 10.9790/1684-1401025256 www.iosrjournals.org 54 | Page IV. Risk Assessment Table 3: Risk Assessment (Feasibility phase) Risk Responses ( Likelihood) Responses ( Impact) Weighted average Likelihood of risk Weighted average impact of risk 1 2 3 4 5 1 2 3 4 5 Reliability of Feasibility Report 42 34 17 13 6 34 28 29 13 6 2.21 2.35 Approval and permit risks 11 33 41 14 11 8 14 36 30 22 2.83 3.4 Political risks 30 41 17 14 8 18 25 47 14 6 2.35 2.68 Legal risks 38 41 19 8 4 22 28 30 14 16 2.08 2.76 Environment and social risks 24 28 35 12 11 21 30 34 19 6 2.61 2.63 Table 4: Risk Assessment (Development phase) Risk Responses ( Likelihood) Responses ( Impact) Weighted average Likelihood of risk Weighted average impact of risk 1 2 3 4 5 1 2 3 4 5 Land Acquisition 16 31 45 11 7 7 42 38 14 9 2.65 2.78 Resettlement & Rehabilitation 19 27 48 11 5 23 30 43 11 3 2.06 2.46 Design 24 33 27 16 10 19 24 35 22 10 2.59 2.81 Bidding 20 40 27 13 10 33 44 16 11 6 2.57 2.2 Environment and social risks 22 30 33 13 12 20 22 38 18 12 2.66 2.81 Market 18 26 37 16 13 23 30 33 17 7 2.81 2.59 Legal 19 38 41 7 5 23 27 30 14 16 2.46 2.75 Political 29 53 13 9 6 22 27 49 8 4 2.18 2.5 Financial closure 27 33 21 18 11 29 36 25 14 6 2.57 2.38 Technology Selection 28 34 33 9 6 38 34 18 11 9 2.37 2.26 Table 5: Risk Assessment (Execution phase) Risk Responses ( Likelihood) Responses ( Impact) Weighted average Likelihood of risk Weighted average impact of risk 1 2 3 4 5 1 2 3 4 5 Utility diversion 20 28 16 19 27 16 33 31 23 7 3.05 2.74 Force Majeure 22 30 35 15 8 7 11 22 39 31 2.61 3.69 Traffic diversion 3 18 20 52 17 10 13 25 40 22 3.56 3.46 Safety 20 27 43 13 7 11 25 38 23 13 2.64 3.01 Time over run 9 22 49 21 9 8 10 36 33 23 2.99 3.48 Cost Overrun 11 24 39 26 10 8 16 42 25 19 3 3.28 Construction 24 33 27 16 10 16 34 31 23 6 2.59 2.71 Inflation 25 34 23 16 12 17 25 31 24 13 2.6 2.91 Contractual 29 30 25 15 11 18 20 22 40 10 2.54 3.03 Table 6: Risk Assessment (Operation phase) Risk Responses ( Likelihood) Responses ( Impact) Weighted average Likelihood of risk Weighted average impact of risk 1 2 3 4 5 1 2 3 4 5 Traffic Revenue 19 26 37 16 12 23 30 33 18 6 2.78 2.58 Market 16 25 30 29 10 21 29 34 24 2 2.92 2.61 Safety 28 30 33 14 5 20 32 37 18 3 2.44 2.56 Force Majeure 29 33 21 17 10 17 22 31 26 14 2.51 2.98 Social and Environmental 13 42 35 18 2 11 43 35 17 4 2.58 2.64 Legal 19 39 41 8 3 23 29 30 13 15 2.42 2.71 Transportation of hazardous chemicals 9 24 29 32 16 7 15 22 40 29 3.2 3.71
  • 4. Risk Severity Framework For A BOT Highway Project DOI: 10.9790/1684-1401025256 www.iosrjournals.org 55 | Page 5. Risk Severity Table 7 : Risk Severity(All Phases) Risk Likelihood Impact Risk value L+I –( L*I) Risk Severity Feasibility Phase Reliability of Feasibility Report 2.21 2.35 0.704 High Approval and permit risks 2.83 3.4 0.861 Very High Political risks 2.35 2.68 0.754 High Legal risks 2.08 2.76 0.738 High Environment and social risks 2.61 2.63 0.773 High Development Phase Land Acquisition 2.65 2.78 0.791 High Resettlement & Rehabilitation 2.06 2.46 0.701 High Design 2.59 2.81 0.789 High Bidding 2.57 2.2 0.728 High Environment and social risks 2.66 2.81 0.795 Very High Market 2.81 2.59 0.789 High Legal 2.46 2.75 0.771 High Political 2.18 2.5 0.718 High Financial closure 2.57 2.38 0.745 High Technology Selection 2.37 2.26 0.711 High Execution Phase Utility diversion 3.05 2.74 0.823 Very High Force Majeure 2.61 3.69 0.874 Very High Traffic diversion 3.56 3.46 0.911 Very High Safety 2.64 3.01 0.812 Very High Time over run 2.99 3.48 0.878 Very High Cost Overrun 3 3.28 0.862 Very High Construction 2.59 2.71 0.779 High Inflation 2.6 2.91 0.799 Very High Contractual 2.54 3.03 0.806 Very High Operation Phase Traffic Revenue 2.78 2.58 0.785 High Market 2.92 2.61 0.801 Very High Safety 2.44 2.56 0.750 High Force Majeure 2.51 2.98 0.799 Very High Social and Environmental 2.58 2.64 0.771 High Legal 2.42 2.71 0.764 High Transportation of hazardous chemicals 3.2 3.71 0.907 Very High V. Conclusions 1. All the risks are in the category of high and very high and hence as such risks in the project are quite substantial 2. Almost all the risks in the execution phase are in very high category which means that these risks have the potential to derail the project 3. In the development phase, environment and social risks is in very high category which meant that risk of displacement of people as well as the effect on the environment is substantial 4. In the feasibility phase, risk of approval and permit is in very high category and hence sufficient attention should be paid to mitigate this risk. 5. Adequate attention should be given to Market, Force Majeure and Transportation risks in Operation phase. 6. Suitable risk mitigation measures by way of risk transfer, risk sharing and risk reduction is to be put in place so as to minimise the effect of risk in the event of its occurrence. 7. On the whole it can be inferred that risks in infrastructure projects are of potentially damaging nature and unless suitable risk management is in place, the chances of a successful project outcome is remote. References [1]. Al-Bahar J and Crandall K(1990), Systematic Risk Management Approach for Construction Projects, Journal of Construction Engineering and Management116(3),pp533-546 [2]. Ahmed, et al(1990),Decision support system for modeling bid/no-bid decision problems, Journal of Construction Engineering and Management, ASCE,116(4), pp595-608 [3]. Ijigah Edoka Augustine, Jimoh Richard Ajayi, et al, (2013), Assessment of Risk Management Practices in Nigerian Construction Industry-Toward establishing Risk Management Index, International Journal of Pure and Applied Sciences and Technology,16(2), pp20-31
  • 5. Risk Severity Framework For A BOT Highway Project DOI: 10.9790/1684-1401025256 www.iosrjournals.org 56 | Page [4]. Florence YYL and Linda H (2006),Risk faced by Singapore Firms When undertaking Construction projects in India, International Journal of Project Management,24(38),pp261-270 [5]. Baloi D and price ADF (2003),Modelling Global Risk factors Affecting Construction Cost Performance, International Journal of Project Management,21,pp261-269 [6]. Debasis Sarkar and Kintan Patel ( 2012), Project Risk management Framework for PPP models for Indian Highway Projects, Ciivl engineering and Construction review Journal, 25(03), pp 104-112 [7]. Jonathan.k.Fabi and Jacob A.B.Awolesi ( 2015), A study of Risk Management practice of Highway projects in Nigeria,Journal of Economics and Sustainable Development, 6(18), pp 171-177 [8]. Kansal RK and Manoj Sharma (2012),Risk Assessment methods and Applications in Construction Projects,2(3), pp1081-1085 [9]. Shehu Z and Sommerville J (2006),Real Time Risk Management Approach in Construction Projects, Glasgow University, Glasgow, United Kingdom [10]. Nerija Banaitiene and Audrius Banaitis, Risk Management-Current Issues and Challenges, ISBN 978-953-51-0747-7, InTech, September 9, 2012 [11]. Dada J O and Jagboro G O (2007),Evaluation of Impact of Risk on Project Cost Overrun in Nigerian Construction Industry, Journal of Financial Management of property and Construction, 12(1), pp37-44 [12]. Debasis Sarkar and Goutam Datta(2011),A framework of Project Risk Management for the Underground Corridor Construction of Metro Rail, Indian Institute of Management, W.P No:2011-02-05 [13]. Shen LY and Ng, CSK(2001),Risk Assessment for Construction Joint Venture in China, Journal of Construction Engineering and Management,127(1),pp76-81 [14]. Martina Claudia Garrido, Morano Cassia,Riberio and Assed (2011),Risk Identification Techniques Knowledge and Application in Brazilian Construction,2(11), pp242-252 [15]. Rinaj Pathan and Dr Pilplikar S S( 2013), Risk Assessment of BOT Road Projects,IOSR journal of mechanical and Civil Engineering, 5(3), pp 40-59