CE 233 Construction Management Construction Risk Management Prepared by: Saransh Shah
Overview   Construction projects are shared efforts of multiple parties Project outcome is delivered from complex network of activities But the implementation of risk management is very scarce Up till now research is going on how to implement and manage it
What is risk management? It is an approach or dealing with hazards In areas of commerce and industry Critical and sensitive procedure Each and every construction project has risk in more or less amount So clause of risk management must be included
Role of Risk Management There are two stages: (i) Proposal submitted for the client’s approval (ii) Receipt of tenders
Risk management framework Three tired system Risk detection It is ongoing process in many projects though not documented.  They are part of different meetings to identify and handling. Identified before bidding through project manager. E.g. technical risks, environment risks etc. Risk analysis Qualitative and quantitative assessment of identified risks Probability of occurrence and potential impact Updating of risk management database
Risk management framework (cont.) Risk response Alternative approach to avoid risk Actions for reducing probability of risk Switching to different activities Increase work force Risk insurance
Preventive measures Effective communication Daily meetings Monitoring progress of the project Updating data Abundant finance Experienced engineers and skilled labors Experienced project managers
Co-operative risk management model Actor specific Knowledge, experience, main contractor: guidance and management Dyadic relational  Reduced need for contracts, good personal relationships, partnering Network groups Meetings, standards, partnering, trust, self -guidance; macro culture, reputation, Collective Sanctions, careful risk allocation, risk& reward systems
Benefits of model Environment becomes flexible, trustful and professional Lowers transaction cost Better allocation of risks to parties Stronger bonding of relationship
Conclusion Risks are not absolute They must be defined for particular situation in advance to minimize impact of risk Depends upon experiences, background knowledge and education of an individual
Thank you

Risk Management

  • 1.
    CE 233 ConstructionManagement Construction Risk Management Prepared by: Saransh Shah
  • 2.
    Overview Construction projects are shared efforts of multiple parties Project outcome is delivered from complex network of activities But the implementation of risk management is very scarce Up till now research is going on how to implement and manage it
  • 3.
    What is riskmanagement? It is an approach or dealing with hazards In areas of commerce and industry Critical and sensitive procedure Each and every construction project has risk in more or less amount So clause of risk management must be included
  • 4.
    Role of RiskManagement There are two stages: (i) Proposal submitted for the client’s approval (ii) Receipt of tenders
  • 5.
    Risk management frameworkThree tired system Risk detection It is ongoing process in many projects though not documented. They are part of different meetings to identify and handling. Identified before bidding through project manager. E.g. technical risks, environment risks etc. Risk analysis Qualitative and quantitative assessment of identified risks Probability of occurrence and potential impact Updating of risk management database
  • 6.
    Risk management framework(cont.) Risk response Alternative approach to avoid risk Actions for reducing probability of risk Switching to different activities Increase work force Risk insurance
  • 7.
    Preventive measures Effectivecommunication Daily meetings Monitoring progress of the project Updating data Abundant finance Experienced engineers and skilled labors Experienced project managers
  • 8.
    Co-operative risk managementmodel Actor specific Knowledge, experience, main contractor: guidance and management Dyadic relational Reduced need for contracts, good personal relationships, partnering Network groups Meetings, standards, partnering, trust, self -guidance; macro culture, reputation, Collective Sanctions, careful risk allocation, risk& reward systems
  • 9.
    Benefits of modelEnvironment becomes flexible, trustful and professional Lowers transaction cost Better allocation of risks to parties Stronger bonding of relationship
  • 10.
    Conclusion Risks arenot absolute They must be defined for particular situation in advance to minimize impact of risk Depends upon experiences, background knowledge and education of an individual
  • 11.