SlideShare a Scribd company logo
The Biogas Thailand Forum 2015
"Renewable Energy and Grid Integration / Energy transition"
25 November 2015 in Chiang Mai
Revise Connecting Code & Set up an inspection
and standard certification agent
IMPACT of Renewable Connection
Tasks -ENERGY AND ENVIRONMENTAL ENGINEERING DEPARTMENT
CONTENTS
Structure of Power Sector: Enhanced Single Buyer Model
IPP SPP VSPP Import
(34%) (12%) (4%) (7%)
EGAT
MEA PEA
(42%)
(100%)
(30%) (70%)
Generation
Capacity
(35,329 MW*)
Transmission
Network
(32,503 Circuit-km)
Distribution
& Retail
(168,650 GWh)
(20.5 Million Customers)
(99.8% access)
Private Power Producers
State Owned Enterprises (SOEs)
As of December 2013
* Contracted Capacity
EGAT
Voltage Level 500 kV 300 kV 230 kV 132 kV** 115 kV 69 kV Total
Transmission Line
(circuit-km)
4,167 23 14,505 9 13,780 19 32,503
Transmission Line Length by Voltage
** Thailand-Malaysia Transmission Line
Source: Electricity Generating Authority of Thailand 3
Network
System
Operator &
Single Buyer
IPPs = Independent Power Producers
(Capacity sold to EGAT > 90 MW)
SPPs = Small Power Producers
(Capacity sold to EGAT ≤ 90 MW)
VSPPs = Very Small Power Producers
(Capacity sold to MEA/PEA ≤10 MW)
Main
responsibilities
of ERC
Granting of license/and
develop operate
tracking scheme
Price regulation :
Fuel Adjustment Charge (FT)
and pipeline tariff
Regulating
competition
Assurance of sufficient
supply of energy
Promotion of participation of energy
consumers: to further develop rural
areas and communities
Organizational
Development
Engineering Standard for:
Regulations/Standardization,
Interoperability
Safety , Alleviate Environmental
impact for construction &
operation
ensure fair rates to
consumers
Settling disputes between
consumers and operators
Power Development Fund
and 13Regional Energy
Consumer Committee
4
Engineering standard for
supply and system
operation:
Access Code
Dispatching
Energy Regulatory Commission (ERC): Energy-Related Policies and Activities
seeks to create a new dialogue
between civil society and sector
actors: Representatives of
Government, Utilities, NGO
Ensure that all license
holders are capable of
financing the undertaking
of their licensed activities
Tasks -ENERGY AND ENVIRONMENTAL ENGINEERING DEPTMENT
-Establishment of Technical Standards and Safety of the Energy Industry Operation.
-Review and Analysis of Efficiency of Power Plant Operating Data (Licensees proposed investments).
-Preparing Specific Requirements for Connection of Renewable Energy Power Systems (REPS).
-Supporting steering committee and working group for revision Grid Code Connecting Code and Distribution Code.
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR
(Section 79 – Section 88)
Section 81 A licensee who owns an energy network system must allow other licensees or energy industry operators to utilize or
connect to his system in accordance with terms stipulated and announced by the licensee who owns the energy network system.
The terms under paragraph one shall comprise term on connection of an energy network system, term on utilization of energy
network system facilities and term on energy network system operation, such terms shall be based on the following principles:
(1) They must not adversely affect security, safety and quality of energy system.
(2) They must not disadvantage energy consumers and the public.
(3) They must not discriminate or hinder other licensees or energy industry operators.
(4) The technical specifications at the end-use points or at the point of connection to an energy
network system must be clear, technically feasible and must not impose an undue burden on
the person who requests utilization of or connection to the energy network system.
(5) They must have a clear description of duty and responsibility of a person who requests utilization of and connection to an
energy network system and a person who allows utilization of or connection to the system.
(6) Any other characteristic as announced by the Commission.
The term under paragraphs one and two shall not cause a licensee who owns an energy network system to lose benefits or to be
at a disadvantage in
renewable energy
Status of renewable energy in Year 2014 compare with the target in
Alternative Energy Development Plan: AEDP of 20% for 20 years as follows
Year SOLAR WIND HYDRO MSW BIOMASS BIOGAS
ENERGY
CROPS
TOTAL
(MW)
2014 1,298.5 224.5 3,048.4 65.7 2,541.8 311.5 - 7,490.4
2036 6,000.0 3,002.0 3,282.4 500.0 5,570.0 600.0 680.0 19,634.4
REMARK: * INSTALLED CAPACITY
SOURCE: POWER DEVELOPMENT PLAN 2015
YEAR 2014 YEAR 2026 YEAR 2036
IMPORT 7 10 - 15 15 - 20
COAL AND LIGNITE 20 20 - 25 20 - 25
RE AND HYDRO POWER 8 10 – 20 15 - 20
NATURAL GAS 64 45 -50 30 - 40
NUCLEAR - - 0 -5
DIESEL/FUEL OIL 1 - -
Security Energy System & Reverse Power Flow from
RENEWABLE ENERGY
77
Reverse Power Flow can make Margin Reducing in
Transmission System, Contingency Reserves are
designed for only EMERGENCY CASE.
Otherwise, Reverse Power Flow can be cause reliability
reducing in the power system and might occur missing
N-1 Criterion and the black out.
SECURITY ENERGY SYSTEM
The N-1 Criterion
8
22/33 kV
115 kV
.
./ .
Generator
Transmission LineTransmission Line
Length > 60 km.
RE
RE
RE
RE
RE
115 kV
22/33 kV
.
./ .
DS switch
Tie Feeder
ความมั่นคงระบบไฟฟ้ า
ระบบไฟฟ้ าไม่รองรับ N-1
เมื่อเกิดเหตุขัดข้องระบบไม่
รองรับ N-1
9
ศักยภาพของสายส่งลดลง เนื่องจาก RE
ที่ไหลย้อน
ระบบส่งไฟฟ้ าของประเทศไทยไม่ได้ถูกออกแบบมาเพื่อรองรับ Source จาก
Distribution Feeder
ค่าความสูญเสียของระบบไฟฟ้ า (Loss)
CASE STUDY RE 75% of each Transformer
Power Demand การเกิดไฟไหลย้อน (Reverse Power)
Load 100% Not Occur (Receive from
Transmission System)
Load 75% Not Occur
Load 50% Power Reverse Flow 12.5 MVA
เกิดไฟไหลย้อน 12.5 MVA
75% of Transformer 115/22-33 kV Size 50MVA = 37.5 MVA
10
IMPACT of Renewable Connection
IMPACT of Renewable Connection
• FULL GRID CONNECTION CAPACITIES
• REVERSE POWER FLOWS
• VOLTAGE CONTROL IN DISTRIBUTION
GRID
• PROTECTION COORDINATION IN
DISTRIBUTION GRID
Develop real time
data monitoring
forecast for
dispatchable VSPP
Use smart grid device &
equipment
(Move to smart grid)
Revise Connecting Code
Energy mix and Asset planning
Plan for using renewable energy
(Find exactly RE potential area)
Redesign power grid for
RE connection
(Expand grid to RE area)
Revise Power
Purchase
Agreement &
Contract
Feeder
Management
Centralized/Distributed
Operation Model and
business models
Balancing Technology in various
time ranges
IMPACT of Renewable Connection
Revise Connecting Code & Set up an inspection
and standard certification agent
A (Draft)Requirements on Power Network System Connection with Distribution Authority
(MEA/PEA) B.E. 2558 (Old B.E. 2551)
B Regulation for an Invertor Used in Grid – Connected Power Generating System
C Set up a license as an inspection and standard certification agent for equipment
connected to an energy network system
Section 76 Any person wishing to become an inspection and standard certification agent for equipment connected to an energy
network system shall have to acquire a license as an inspection and standard certification agent from the Commission.
Section 73 Standards of equipment used to connect an energy network system of a licensee who has its own system, including
methods of inspection and certification of inspection results, shall be in conformity with the regulations prescribed by the
Commission.
Regulations under paragraph one may require that certain types of equipment used to connect to an energy network system be
inspected and certified prior to their utilization in energy industry operation.
In preparation of regulations under paragraph one, a licensee who has an energy network system shall prepare the details for
consideration to the Commission.
Section 82 In the case where the Commission views that the term on connection of an energy network system, the term on utilization of
energy network system facilities and the term on energy network system operation do not comply with the principles under Section 81,
the Commission shall have the power to order the licensee who issues such terms to revise or improve the terms to comply with the
principles under Section 81.
Your personal experiences with renewable energy
Revise Connecting Code & Set up an inspection
and standard certification agent
A (Draft)Requirements on Power Network System Connection with Distribution Authority
(MEA/PEA) B.E. 2558 (Old B.E. 2551)
B Regulation for an Invertor Used in Grid – Connected Power Generating System
C Set up a license as an inspection and standard certification agent for equipment
connected to an energy network system
Different inverter testing procedures for MEA and PEA //Type testing for
selected inverter of a defined series to certify all inverters of the same series
//Routine testing for all applied inverters required //Confusion as to the
“official bodies” that are allowed to perform testing
Harmonize testing procedures between both authorities (PEA/MEA)
Limitation for grid connection capacity/Supervisory Control And Data
Acquisition/Distribution Management System (DMS)/P.F. Control
/Dispatching for RE-VSPP/Voltage Control/Grid-connected Inverter/etc.
Your personal experiences with renewable energy
(Draft)Requirements on Power Network System Connection
with Distribution Authority
(MEA/PEA) B.E. 2558 (Old B.E. 2551)0
Regulation for an Invertor Used in Grid – Connected
Power Generating System
สำนักงำนคณะกรรมกำรกำกับกิจกำรพลังงำน
319 อำคำรจัตุรัสจำมจุรี ชั้น 19 ถนนพญำไท แขวงปทุมวัน เขตปทุมวัน กรุงเทพ 10330
โทร : 0-2207-3599
http://www.erc.or.th
THANK YOU
The Office of the Energy Regulatory Commission of Thailand (OERC)
Telephone 0-2207-3599
Facsimile 0-2207-3502
Website: www.erc.or.th
BACK UP
Back Up
Energy Industry Act 2007
Energy Industry Act 2007
DIVISION 3
REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 3
ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION
PART 4
THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION
( Section 72 - Section 78 )
Section 72 Energy industry operation shall comply with engineering standards and shall ensure safety pursuant to the regulations
prescribed by the Commission which are as follows:
(1) shall not impose an undue burden on the licensees;
(2) shall not be so rigid that they would limit or hinder competition;
(3) shall not offer benefits to any particular licensee; and
(4) shall be transparent.
In the event that energy industry operation of a licensee fails to comply with the regulations under paragraph one, the
Commission shall have the authority to order the licensee to improve or to rectify the operation.
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION
( Section 72 - Section 78 )
Section 73 Standards of equipment used to connect an energynetwork system of a licensee who has its own system, including
methods of inspection and certification of inspection results, shall be in conformity with the regulations prescribed by the
Commission.
Regulations under paragraph one may require that certain types of equipment used to connect to an energy network system be
inspected and certified prior to their utilization in energy industry operation.
In preparation of regulations under paragraph one, a licensee who has an energy network system shall prepare the details for
consideration to the Commission.
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION
( Section 72 - Section 78 )
Section 74 A licensee shall have to maintain, repair and improve an energy network system, equipment or other devices used for
energy industry operation to ensure that their operating efficiency and standards comply with the regulations under Section 72,
paragraph one. In the case of any damage or breakdown, repair must be expeditiously taken to restore the operation.
Section 75 In establishing the standards under Section 72, paragraph one, and Section 73, paragraph one, the Commission may
refer to the standards prescribed by other agencies having authority and duties under the law on those respective matters.
Section 76 Any person wishing to become an inspection and standard certification agent for equipment connected to an energy
network system shall have to acquire a license as an inspection and standard certification agent from the Commission.
The qualifications of an applicant for a license to be an inspection and standard certification agenty, submission of application for
a license, issuance of a license, extension of a license, term of a license, fees for issuance and extension of a license, including fee
for the inspection and certification, shall be in conformity with the criteria, procedures and conditions prescribed by the
Commission.
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION
( Section 72 - Section 78 )
Section 77 The Commission shall have the authority to revoke a license for inspection and standard certification agent for equipment used to
connect an energy network system in the following cases:
(1) lack of qualifications as stipulated in the announcement issued under Section 76, paragraph two;
(2) dishonest inspection, reporting of inspection result, or certification of inspection results;
(3) delay in inspection, report of inspection results or certification of inspection results, with undue reasons, causing serious damage to a
person requesting inspection; or
(4) having inspectors whose qualifications do not meet standards or whose numbers are less than requirement as stipulated in the
announcement issued under Section 76, paragraph two.
Section 78 Revocation of a license for an inspection and standard certification agency under Section 77 shall not affect standard certification
undertaken by the agency prior to the revocation of the license except that the certification previously made was below the standards
specified by the Commission, in which case the Commission may consider ordering revocation of such certification.
In the case where any person is affected by damage from standard certification which is below standards and has been revoked under
paragraph one, the inspection and standard certification agency whose license is revoked shall be liable for the compensation for such
damages.
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR
(Section 79 – Section 88)
Section 79 A licensee who owns an energy network system shall carry out the operation in line with what is stipulated in the energy network
system expansion plan.
A licensee who owns an energy network system and is a government agency as determined by the Commission shall develop an energy
network system expansion plan and present it to the Minister for further submission to
the Cabinet for approval.
In considering of the energy network system expansion plan under paragraph two, the Commission shall provide comments on the subject. In
this regard, if the mentioned plan has significant impacts on general public, the Commission shall organize an opinion hearing process in
accordance with Section 26.
A licensee who owns an energy network system and is not a government agency under paragraph two shall develop an energy network
system expansion plan for submission to the Commission for approval in compliance with the scope and criteria specified by the Commission.
Section 80 A licensee who owns an energy network system shall carry out energy industry operation fairly without unjust discrimination.
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR
(Section 79 – Section 88)
Section 81 A licensee who owns an energy network system must allow other licensees or energy industry operators to utilize or
connect to his system in accordance with terms stipulated and announced by the licensee who owns the energy network system.
The terms under paragraph one shall comprise term on connection of an energy network system, term on utilization of energy
network system facilities and term on energy network system operation, such terms shall be based on the following principles:
(1) They must not adversely affect security, safety and quality of energy system.
(2) They must not disadvantage energy consumers and the public.
(3) They must not discriminate or hinder other licensees or energy industry operators.
(4) The technical specifications at the end-use points or at the point of connection to an energy network system must be clear,
technically feasible and must not impose an undue burden on the person who requests utilization of or connection to the energy
network system.
(5) They must have a clear description of duty and responsibility of a person who requests utilization of and connection to an
energy network system and a person who allows utilization of or connection to the system.
(6) Any other characteristic as announced by the Commission.
The term under paragraphs one and two shall not cause a licensee who owns an energy network system to lose benefits or to be
at a disadvantage in
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR
(Section 79 – Section 88)
Section 82 In the case where the Commission views that the term on connection of an energy network system, the term on utilization of
energy network system facilities and the term on energy network system operation do not comply with the principles under Section 81, the
Commission shall have the power to order the licensee who issues such terms to revise or improve the terms to comply with the principles
under Section 81.
Section 83 In the case where a licensee or an energy industry operator, wishing to utilize or connect an energy network system, views that
a term on connection of energy network system connection, term on utilization of energy network system facilities and term on energy
network system operation do not comply with the principles under Section 81, the licensee or the energy industry operator can make a
request to the Commission for consideration.
In the case where the Commission views that the terms do not comply with the principles under Section 81, the Commission shall have the
power to order the licensee who issues such terms to revise or improve the terms to comply with the principles under Section 81.
Section 84 In the case that a licensee who owns an energy network system refuses to allow utilization of or connection to his system, the
person who has been refused has the right to make a request to the Commission for consideration. When the Commission has made a
decision on the request under paragraph one hereof, the concerned parties shall abide by the decision.
Section 85 A licensee who owns an energy network system must provide a person who requests the utilization of or connection to his system
with accurate information necessary for utilization of or connection to the system. He shall not take any action that would disrupt the normal
utilization of and connection to an energy network system of other licensee or energy industry operator.
Energy Industry Act 2007
DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION
PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR
(Section 79 – Section 88)
Section 86 A licensee who owns an energy network system must disclose contracts, agreements, conditions and tariffs for the utilization of or
connection to his system, according to the criteria, procedures and conditions announced by the Commission.
Section 87 A licensee with an energy network system operator shall be responsible for control, management and overseeing of energy
system to ensure balance, security, stability, efficiency and reliability of overall system, and shall have authority and duties to execute other
tasks as specified by the Commission under conditions of the license issuance. The licensee with an electricity system operator shall order
licensees who operate electricity industry to generate electricity fairly without unjust discrimination.
Section 88 In the case that a person makes a complaint to the Commission that a licensee with an electricity system operator has breached
Section 87, paragraph two, the Commission shall make decision on the complaint within thirty days as from the date of receipt of written
complaint. In the case where the Commission considers that the licensee with the electricity system operator has breached Section 87,
paragraph two, causing damage to the complainant, the Commission shall preliminarily determine amount of compensation for such damage.

More Related Content

What's hot

Grid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and SolutionsGrid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and Solutions
Power System Operation
 
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Pradeep Avanigadda
 
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
Sandia National Laboratories: Energy & Climate: Renewables
 
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
IRJET-  	  Optimization of Renewable Energy Sources for DC MicrogridIRJET-  	  Optimization of Renewable Energy Sources for DC Microgrid
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
IRJET Journal
 
Smart grid technologies after midsem slides
Smart grid technologies after midsem slidesSmart grid technologies after midsem slides
Smart grid technologies after midsem slides
IIIT Bhubaneswar
 
Related standards and specifications for the smart grid Class-20
Related standards and specifications for the smart grid Class-20Related standards and specifications for the smart grid Class-20
Related standards and specifications for the smart grid Class-20
Siksha 'O' Anusandhan (Deemed to be University )
 
Advanced Power Distribution System Configuration for Smart Grid
Advanced Power Distribution System Configuration for Smart GridAdvanced Power Distribution System Configuration for Smart Grid
Advanced Power Distribution System Configuration for Smart Grid
Hossain Asad
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimet
Rick Case, PMP, P.E.
 
Session 10 grid interconnections & commissioning test procedures
Session 10   grid interconnections & commissioning test proceduresSession 10   grid interconnections & commissioning test procedures
Session 10 grid interconnections & commissioning test procedures
Chirag Jain
 
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET Journal
 
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRIDDISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
NIT MEGHALAYA
 
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Power System Operation
 
SMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation Series
SMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation SeriesSMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation Series
SMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation Series
Rick Case, PMP, P.E.
 
Impact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power systemImpact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power system
Muwaf_5
 
The merits of integrating renewables with smarter grid carilec
The merits of integrating renewables with smarter grid   carilecThe merits of integrating renewables with smarter grid   carilec
The merits of integrating renewables with smarter grid carilec
Rick Case, PMP, P.E.
 
Solar power integration with grid
Solar power integration with gridSolar power integration with grid
Solar power integration with grid
ashishant
 
A grid connected dual voltage source inverter with power quality improvement ...
A grid connected dual voltage source inverter with power quality improvement ...A grid connected dual voltage source inverter with power quality improvement ...
A grid connected dual voltage source inverter with power quality improvement ...
LeMeniz Infotech
 
Powergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engrPowergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engrAbhijit Sahare
 
Restoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disasterRestoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disaster
Rick Case, PMP, P.E.
 
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET Journal
 

What's hot (20)

Grid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and SolutionsGrid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and Solutions
 
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
Grid Interconnection of Renewable Energy Sources at the Distribution Level Wi...
 
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
 
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
IRJET-  	  Optimization of Renewable Energy Sources for DC MicrogridIRJET-  	  Optimization of Renewable Energy Sources for DC Microgrid
IRJET- Optimization of Renewable Energy Sources for DC Microgrid
 
Smart grid technologies after midsem slides
Smart grid technologies after midsem slidesSmart grid technologies after midsem slides
Smart grid technologies after midsem slides
 
Related standards and specifications for the smart grid Class-20
Related standards and specifications for the smart grid Class-20Related standards and specifications for the smart grid Class-20
Related standards and specifications for the smart grid Class-20
 
Advanced Power Distribution System Configuration for Smart Grid
Advanced Power Distribution System Configuration for Smart GridAdvanced Power Distribution System Configuration for Smart Grid
Advanced Power Distribution System Configuration for Smart Grid
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimet
 
Session 10 grid interconnections & commissioning test procedures
Session 10   grid interconnections & commissioning test proceduresSession 10   grid interconnections & commissioning test procedures
Session 10 grid interconnections & commissioning test procedures
 
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
IRJET- A Grid-Control Scheme Connected to a Wind Energy System for Improving ...
 
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRIDDISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
 
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...Challenges and Benefits of Integrating the Renewable Energy Technologies into...
Challenges and Benefits of Integrating the Renewable Energy Technologies into...
 
SMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation Series
SMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation SeriesSMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation Series
SMARTER Grid Initiatives & Grid Modernization - CAREC Energy Presentation Series
 
Impact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power systemImpact of high level penetration of photovoltaics on Power system
Impact of high level penetration of photovoltaics on Power system
 
The merits of integrating renewables with smarter grid carilec
The merits of integrating renewables with smarter grid   carilecThe merits of integrating renewables with smarter grid   carilec
The merits of integrating renewables with smarter grid carilec
 
Solar power integration with grid
Solar power integration with gridSolar power integration with grid
Solar power integration with grid
 
A grid connected dual voltage source inverter with power quality improvement ...
A grid connected dual voltage source inverter with power quality improvement ...A grid connected dual voltage source inverter with power quality improvement ...
A grid connected dual voltage source inverter with power quality improvement ...
 
Powergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engrPowergrid ppt campus_v1.33 engr
Powergrid ppt campus_v1.33 engr
 
Restoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disasterRestoring jamaica’s power after a natural disaster
Restoring jamaica’s power after a natural disaster
 
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
 

Viewers also liked

กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงานกรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
Narinporn Malasri
 
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงานกรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
Denpong Soodphakdee
 
8. ความรู้และความเข้าใจพื้นฐานด้านพลังงาน
8. ความรู้และความเข้าใจพื้นฐานด้านพลังงาน8. ความรู้และความเข้าใจพื้นฐานด้านพลังงาน
8. ความรู้และความเข้าใจพื้นฐานด้านพลังงานguestf181d72
 
Living, Learning, & Working Smart @KKU
Living, Learning, & Working Smart @KKULiving, Learning, & Working Smart @KKU
Living, Learning, & Working Smart @KKU
Denpong Soodphakdee
 
Workshop2 tiwawan
Workshop2 tiwawanWorkshop2 tiwawan
Workshop2 tiwawan
Tiwawannew
 
ใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4page
ใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4pageใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4page
ใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4page
Prachoom Rangkasikorn
 
Household Energy Saving
Household Energy SavingHousehold Energy Saving
Household Energy Saving
Narinporn Malasri
 
ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...
ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...
ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...
LaiLa Kbn
 
Renewable energy grid integration
Renewable energy grid integrationRenewable energy grid integration
Renewable energy grid integration
RCREEE
 
Energy พลังงานในประเทศไทย
Energy พลังงานในประเทศไทยEnergy พลังงานในประเทศไทย
Energy พลังงานในประเทศไทย
Yaowaluk Chaobanpho
 
Thailand Energy Management System
Thailand Energy Management SystemThailand Energy Management System
Thailand Energy Management System
Narinporn Malasri
 
Innovation Journey 20160613 TOT
Innovation Journey 20160613 TOTInnovation Journey 20160613 TOT
Innovation Journey 20160613 TOT
pantapong
 
พลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทน
พลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทนพลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทน
พลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทนnuchida suwapaet
 
บทที่ 3 พลังงานไฟฟ้า
บทที่ 3  พลังงานไฟฟ้าบทที่ 3  พลังงานไฟฟ้า
บทที่ 3 พลังงานไฟฟ้า
Pinutchaya Nakchumroon
 
แผนผังความคิดเรื่องพลังงาน
แผนผังความคิดเรื่องพลังงานแผนผังความคิดเรื่องพลังงาน
แผนผังความคิดเรื่องพลังงาน
Wuttipong Tubkrathok
 

Viewers also liked (17)

กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงานกรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
 
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงานกรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
กรณีศึกษาที่ดี การจัดการและการอนุรักษ์พลังงาน
 
8. ความรู้และความเข้าใจพื้นฐานด้านพลังงาน
8. ความรู้และความเข้าใจพื้นฐานด้านพลังงาน8. ความรู้และความเข้าใจพื้นฐานด้านพลังงาน
8. ความรู้และความเข้าใจพื้นฐานด้านพลังงาน
 
Living, Learning, & Working Smart @KKU
Living, Learning, & Working Smart @KKULiving, Learning, & Working Smart @KKU
Living, Learning, & Working Smart @KKU
 
Workshop2 tiwawan
Workshop2 tiwawanWorkshop2 tiwawan
Workshop2 tiwawan
 
ใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4page
ใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4pageใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4page
ใบความรู้+อนุรักษ์พลังงานและสิ่งแวดล้อม+ป.6+297+dltvscip6+55t2sci p06 f27-4page
 
Household Energy Saving
Household Energy SavingHousehold Energy Saving
Household Energy Saving
 
พลังงานไฟฟ้า
พลังงานไฟฟ้าพลังงานไฟฟ้า
พลังงานไฟฟ้า
 
ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...
ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...
ไฟล์ power point อ.เบิร์ด "ความจริงประเทศไทย...พลังงาน...กว่าจะเข้าใจก็สายเสี...
 
Renewable energy grid integration
Renewable energy grid integrationRenewable energy grid integration
Renewable energy grid integration
 
Energy พลังงานในประเทศไทย
Energy พลังงานในประเทศไทยEnergy พลังงานในประเทศไทย
Energy พลังงานในประเทศไทย
 
Thailand Energy Management System
Thailand Energy Management SystemThailand Energy Management System
Thailand Energy Management System
 
Innovation Journey 20160613 TOT
Innovation Journey 20160613 TOTInnovation Journey 20160613 TOT
Innovation Journey 20160613 TOT
 
พลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทน
พลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทนพลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทน
พลังงานทดแทนและโรงไฟฟ้าพลังงานทดแทน
 
บทที่ 3 พลังงานไฟฟ้า
บทที่ 3  พลังงานไฟฟ้าบทที่ 3  พลังงานไฟฟ้า
บทที่ 3 พลังงานไฟฟ้า
 
แผนผังความคิดเรื่องพลังงาน
แผนผังความคิดเรื่องพลังงานแผนผังความคิดเรื่องพลังงาน
แผนผังความคิดเรื่องพลังงาน
 
พลังงาน (Energy)
พลังงาน (Energy)พลังงาน (Energy)
พลังงาน (Energy)
 

Similar to Renewable energy and grid integration energy transition

Draft Article - V1
Draft Article - V1Draft Article - V1
Draft Article - V1Ajay Nanda
 
IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2fboshell
 
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
Sandia National Laboratories: Energy & Climate: Renewables
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Harish Sharma
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringAnil Kumar Bohra
 
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANT
WHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANTWHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANT
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANT
Power System Operation
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
Private Consultants
 
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
IRJET Journal
 
Arai crash test facility at chakan
Arai crash test facility at chakanArai crash test facility at chakan
Arai crash test facility at chakan
RushLane
 
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
IRJET Journal
 
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET Journal
 
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
IRJET Journal
 
A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...
A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...
A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...
IRJET Journal
 
Grid code
Grid codeGrid code
Grid code
NAVEENGEHLOT5
 
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
Sandia National Laboratories: Energy & Climate: Renewables
 
A Grid-Tied Solar Power System with Harmonic Filter to Enhance Power Quality
A Grid-Tied Solar Power System with Harmonic Filter to Enhance Power QualityA Grid-Tied Solar Power System with Harmonic Filter to Enhance Power Quality
A Grid-Tied Solar Power System with Harmonic Filter to Enhance Power Quality
IRJET Journal
 
IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...
IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...
IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...
IRJET Journal
 
IRJET- A Review on Load Frequency Control Strategy
IRJET- A Review on Load Frequency Control StrategyIRJET- A Review on Load Frequency Control Strategy
IRJET- A Review on Load Frequency Control Strategy
IRJET Journal
 

Similar to Renewable energy and grid integration energy transition (20)

Draft Article - V1
Draft Article - V1Draft Article - V1
Draft Article - V1
 
IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2
 
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
 
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANT
WHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANTWHY ARE GRID CODES  INTERCONNECTIONS  STANDARDS SO IMPORTANT
WHY ARE GRID CODES INTERCONNECTIONS STANDARDS SO IMPORTANT
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
 
SCE smart grid development, Paul De Martini, SCE
SCE smart grid development, Paul De Martini,  SCESCE smart grid development, Paul De Martini,  SCE
SCE smart grid development, Paul De Martini, SCE
 
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
1MWH SOLAR PLANT CONNECTED TO MICROGRID WITH BESS CONTROLLER
 
Arai crash test facility at chakan
Arai crash test facility at chakanArai crash test facility at chakan
Arai crash test facility at chakan
 
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
A Review paper on Power Quality Improvement Techniques in a Grid Integrated S...
 
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
 
storagePMR
storagePMRstoragePMR
storagePMR
 
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
 
A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...
A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...
A Review on Methodologies of Multi Array PV Battery Based Bi- Directional Con...
 
Grid code
Grid codeGrid code
Grid code
 
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
1.1_Power Systems Engineering R&D_Ton_EPRI/SNL Symposium
 
A Grid-Tied Solar Power System with Harmonic Filter to Enhance Power Quality
A Grid-Tied Solar Power System with Harmonic Filter to Enhance Power QualityA Grid-Tied Solar Power System with Harmonic Filter to Enhance Power Quality
A Grid-Tied Solar Power System with Harmonic Filter to Enhance Power Quality
 
IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...
IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...
IRJET- STATCOM based Control Scheme for Power Quality Improvement in Grid-Con...
 
IRJET- A Review on Load Frequency Control Strategy
IRJET- A Review on Load Frequency Control StrategyIRJET- A Review on Load Frequency Control Strategy
IRJET- A Review on Load Frequency Control Strategy
 

Recently uploaded

Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Matjaž Lipuš
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
OECD Directorate for Financial and Enterprise Affairs
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Sebastiano Panichella
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
IP ServerOne
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
Access Innovations, Inc.
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Access Innovations, Inc.
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
Vladimir Samoylov
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Orkestra
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
khadija278284
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
Faculty of Medicine And Health Sciences
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Sebastiano Panichella
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
OWASP Beja
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
Sebastiano Panichella
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
eCommerce Institute
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
faizulhassanfaiz1670
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
Howard Spence
 

Recently uploaded (16)

Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
 

Renewable energy and grid integration energy transition

  • 1. The Biogas Thailand Forum 2015 "Renewable Energy and Grid Integration / Energy transition" 25 November 2015 in Chiang Mai
  • 2. Revise Connecting Code & Set up an inspection and standard certification agent IMPACT of Renewable Connection Tasks -ENERGY AND ENVIRONMENTAL ENGINEERING DEPARTMENT CONTENTS
  • 3. Structure of Power Sector: Enhanced Single Buyer Model IPP SPP VSPP Import (34%) (12%) (4%) (7%) EGAT MEA PEA (42%) (100%) (30%) (70%) Generation Capacity (35,329 MW*) Transmission Network (32,503 Circuit-km) Distribution & Retail (168,650 GWh) (20.5 Million Customers) (99.8% access) Private Power Producers State Owned Enterprises (SOEs) As of December 2013 * Contracted Capacity EGAT Voltage Level 500 kV 300 kV 230 kV 132 kV** 115 kV 69 kV Total Transmission Line (circuit-km) 4,167 23 14,505 9 13,780 19 32,503 Transmission Line Length by Voltage ** Thailand-Malaysia Transmission Line Source: Electricity Generating Authority of Thailand 3 Network System Operator & Single Buyer IPPs = Independent Power Producers (Capacity sold to EGAT > 90 MW) SPPs = Small Power Producers (Capacity sold to EGAT ≤ 90 MW) VSPPs = Very Small Power Producers (Capacity sold to MEA/PEA ≤10 MW)
  • 4. Main responsibilities of ERC Granting of license/and develop operate tracking scheme Price regulation : Fuel Adjustment Charge (FT) and pipeline tariff Regulating competition Assurance of sufficient supply of energy Promotion of participation of energy consumers: to further develop rural areas and communities Organizational Development Engineering Standard for: Regulations/Standardization, Interoperability Safety , Alleviate Environmental impact for construction & operation ensure fair rates to consumers Settling disputes between consumers and operators Power Development Fund and 13Regional Energy Consumer Committee 4 Engineering standard for supply and system operation: Access Code Dispatching Energy Regulatory Commission (ERC): Energy-Related Policies and Activities seeks to create a new dialogue between civil society and sector actors: Representatives of Government, Utilities, NGO Ensure that all license holders are capable of financing the undertaking of their licensed activities Tasks -ENERGY AND ENVIRONMENTAL ENGINEERING DEPTMENT -Establishment of Technical Standards and Safety of the Energy Industry Operation. -Review and Analysis of Efficiency of Power Plant Operating Data (Licensees proposed investments). -Preparing Specific Requirements for Connection of Renewable Energy Power Systems (REPS). -Supporting steering committee and working group for revision Grid Code Connecting Code and Distribution Code.
  • 5. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR (Section 79 – Section 88) Section 81 A licensee who owns an energy network system must allow other licensees or energy industry operators to utilize or connect to his system in accordance with terms stipulated and announced by the licensee who owns the energy network system. The terms under paragraph one shall comprise term on connection of an energy network system, term on utilization of energy network system facilities and term on energy network system operation, such terms shall be based on the following principles: (1) They must not adversely affect security, safety and quality of energy system. (2) They must not disadvantage energy consumers and the public. (3) They must not discriminate or hinder other licensees or energy industry operators. (4) The technical specifications at the end-use points or at the point of connection to an energy network system must be clear, technically feasible and must not impose an undue burden on the person who requests utilization of or connection to the energy network system. (5) They must have a clear description of duty and responsibility of a person who requests utilization of and connection to an energy network system and a person who allows utilization of or connection to the system. (6) Any other characteristic as announced by the Commission. The term under paragraphs one and two shall not cause a licensee who owns an energy network system to lose benefits or to be at a disadvantage in
  • 6. renewable energy Status of renewable energy in Year 2014 compare with the target in Alternative Energy Development Plan: AEDP of 20% for 20 years as follows Year SOLAR WIND HYDRO MSW BIOMASS BIOGAS ENERGY CROPS TOTAL (MW) 2014 1,298.5 224.5 3,048.4 65.7 2,541.8 311.5 - 7,490.4 2036 6,000.0 3,002.0 3,282.4 500.0 5,570.0 600.0 680.0 19,634.4 REMARK: * INSTALLED CAPACITY SOURCE: POWER DEVELOPMENT PLAN 2015 YEAR 2014 YEAR 2026 YEAR 2036 IMPORT 7 10 - 15 15 - 20 COAL AND LIGNITE 20 20 - 25 20 - 25 RE AND HYDRO POWER 8 10 – 20 15 - 20 NATURAL GAS 64 45 -50 30 - 40 NUCLEAR - - 0 -5 DIESEL/FUEL OIL 1 - -
  • 7. Security Energy System & Reverse Power Flow from RENEWABLE ENERGY 77
  • 8. Reverse Power Flow can make Margin Reducing in Transmission System, Contingency Reserves are designed for only EMERGENCY CASE. Otherwise, Reverse Power Flow can be cause reliability reducing in the power system and might occur missing N-1 Criterion and the black out. SECURITY ENERGY SYSTEM The N-1 Criterion 8
  • 9. 22/33 kV 115 kV . ./ . Generator Transmission LineTransmission Line Length > 60 km. RE RE RE RE RE 115 kV 22/33 kV . ./ . DS switch Tie Feeder ความมั่นคงระบบไฟฟ้ า ระบบไฟฟ้ าไม่รองรับ N-1 เมื่อเกิดเหตุขัดข้องระบบไม่ รองรับ N-1 9 ศักยภาพของสายส่งลดลง เนื่องจาก RE ที่ไหลย้อน ระบบส่งไฟฟ้ าของประเทศไทยไม่ได้ถูกออกแบบมาเพื่อรองรับ Source จาก Distribution Feeder
  • 10. ค่าความสูญเสียของระบบไฟฟ้ า (Loss) CASE STUDY RE 75% of each Transformer Power Demand การเกิดไฟไหลย้อน (Reverse Power) Load 100% Not Occur (Receive from Transmission System) Load 75% Not Occur Load 50% Power Reverse Flow 12.5 MVA เกิดไฟไหลย้อน 12.5 MVA 75% of Transformer 115/22-33 kV Size 50MVA = 37.5 MVA 10
  • 11. IMPACT of Renewable Connection IMPACT of Renewable Connection • FULL GRID CONNECTION CAPACITIES • REVERSE POWER FLOWS • VOLTAGE CONTROL IN DISTRIBUTION GRID • PROTECTION COORDINATION IN DISTRIBUTION GRID Develop real time data monitoring forecast for dispatchable VSPP Use smart grid device & equipment (Move to smart grid) Revise Connecting Code Energy mix and Asset planning Plan for using renewable energy (Find exactly RE potential area) Redesign power grid for RE connection (Expand grid to RE area) Revise Power Purchase Agreement & Contract Feeder Management Centralized/Distributed Operation Model and business models Balancing Technology in various time ranges
  • 12. IMPACT of Renewable Connection Revise Connecting Code & Set up an inspection and standard certification agent A (Draft)Requirements on Power Network System Connection with Distribution Authority (MEA/PEA) B.E. 2558 (Old B.E. 2551) B Regulation for an Invertor Used in Grid – Connected Power Generating System C Set up a license as an inspection and standard certification agent for equipment connected to an energy network system Section 76 Any person wishing to become an inspection and standard certification agent for equipment connected to an energy network system shall have to acquire a license as an inspection and standard certification agent from the Commission. Section 73 Standards of equipment used to connect an energy network system of a licensee who has its own system, including methods of inspection and certification of inspection results, shall be in conformity with the regulations prescribed by the Commission. Regulations under paragraph one may require that certain types of equipment used to connect to an energy network system be inspected and certified prior to their utilization in energy industry operation. In preparation of regulations under paragraph one, a licensee who has an energy network system shall prepare the details for consideration to the Commission. Section 82 In the case where the Commission views that the term on connection of an energy network system, the term on utilization of energy network system facilities and the term on energy network system operation do not comply with the principles under Section 81, the Commission shall have the power to order the licensee who issues such terms to revise or improve the terms to comply with the principles under Section 81.
  • 13. Your personal experiences with renewable energy Revise Connecting Code & Set up an inspection and standard certification agent A (Draft)Requirements on Power Network System Connection with Distribution Authority (MEA/PEA) B.E. 2558 (Old B.E. 2551) B Regulation for an Invertor Used in Grid – Connected Power Generating System C Set up a license as an inspection and standard certification agent for equipment connected to an energy network system Different inverter testing procedures for MEA and PEA //Type testing for selected inverter of a defined series to certify all inverters of the same series //Routine testing for all applied inverters required //Confusion as to the “official bodies” that are allowed to perform testing Harmonize testing procedures between both authorities (PEA/MEA) Limitation for grid connection capacity/Supervisory Control And Data Acquisition/Distribution Management System (DMS)/P.F. Control /Dispatching for RE-VSPP/Voltage Control/Grid-connected Inverter/etc.
  • 14. Your personal experiences with renewable energy (Draft)Requirements on Power Network System Connection with Distribution Authority (MEA/PEA) B.E. 2558 (Old B.E. 2551)0 Regulation for an Invertor Used in Grid – Connected Power Generating System
  • 15.
  • 16.
  • 17. สำนักงำนคณะกรรมกำรกำกับกิจกำรพลังงำน 319 อำคำรจัตุรัสจำมจุรี ชั้น 19 ถนนพญำไท แขวงปทุมวัน เขตปทุมวัน กรุงเทพ 10330 โทร : 0-2207-3599 http://www.erc.or.th THANK YOU The Office of the Energy Regulatory Commission of Thailand (OERC) Telephone 0-2207-3599 Facsimile 0-2207-3502 Website: www.erc.or.th
  • 20. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR
  • 21. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION ( Section 72 - Section 78 ) Section 72 Energy industry operation shall comply with engineering standards and shall ensure safety pursuant to the regulations prescribed by the Commission which are as follows: (1) shall not impose an undue burden on the licensees; (2) shall not be so rigid that they would limit or hinder competition; (3) shall not offer benefits to any particular licensee; and (4) shall be transparent. In the event that energy industry operation of a licensee fails to comply with the regulations under paragraph one, the Commission shall have the authority to order the licensee to improve or to rectify the operation.
  • 22. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION ( Section 72 - Section 78 ) Section 73 Standards of equipment used to connect an energynetwork system of a licensee who has its own system, including methods of inspection and certification of inspection results, shall be in conformity with the regulations prescribed by the Commission. Regulations under paragraph one may require that certain types of equipment used to connect to an energy network system be inspected and certified prior to their utilization in energy industry operation. In preparation of regulations under paragraph one, a licensee who has an energy network system shall prepare the details for consideration to the Commission.
  • 23. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION ( Section 72 - Section 78 ) Section 74 A licensee shall have to maintain, repair and improve an energy network system, equipment or other devices used for energy industry operation to ensure that their operating efficiency and standards comply with the regulations under Section 72, paragraph one. In the case of any damage or breakdown, repair must be expeditiously taken to restore the operation. Section 75 In establishing the standards under Section 72, paragraph one, and Section 73, paragraph one, the Commission may refer to the standards prescribed by other agencies having authority and duties under the law on those respective matters. Section 76 Any person wishing to become an inspection and standard certification agent for equipment connected to an energy network system shall have to acquire a license as an inspection and standard certification agent from the Commission. The qualifications of an applicant for a license to be an inspection and standard certification agenty, submission of application for a license, issuance of a license, extension of a license, term of a license, fees for issuance and extension of a license, including fee for the inspection and certification, shall be in conformity with the criteria, procedures and conditions prescribed by the Commission.
  • 24. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION ( Section 72 - Section 78 ) Section 77 The Commission shall have the authority to revoke a license for inspection and standard certification agent for equipment used to connect an energy network system in the following cases: (1) lack of qualifications as stipulated in the announcement issued under Section 76, paragraph two; (2) dishonest inspection, reporting of inspection result, or certification of inspection results; (3) delay in inspection, report of inspection results or certification of inspection results, with undue reasons, causing serious damage to a person requesting inspection; or (4) having inspectors whose qualifications do not meet standards or whose numbers are less than requirement as stipulated in the announcement issued under Section 76, paragraph two. Section 78 Revocation of a license for an inspection and standard certification agency under Section 77 shall not affect standard certification undertaken by the agency prior to the revocation of the license except that the certification previously made was below the standards specified by the Commission, in which case the Commission may consider ordering revocation of such certification. In the case where any person is affected by damage from standard certification which is below standards and has been revoked under paragraph one, the inspection and standard certification agency whose license is revoked shall be liable for the compensation for such damages.
  • 25. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR (Section 79 – Section 88) Section 79 A licensee who owns an energy network system shall carry out the operation in line with what is stipulated in the energy network system expansion plan. A licensee who owns an energy network system and is a government agency as determined by the Commission shall develop an energy network system expansion plan and present it to the Minister for further submission to the Cabinet for approval. In considering of the energy network system expansion plan under paragraph two, the Commission shall provide comments on the subject. In this regard, if the mentioned plan has significant impacts on general public, the Commission shall organize an opinion hearing process in accordance with Section 26. A licensee who owns an energy network system and is not a government agency under paragraph two shall develop an energy network system expansion plan for submission to the Commission for approval in compliance with the scope and criteria specified by the Commission. Section 80 A licensee who owns an energy network system shall carry out energy industry operation fairly without unjust discrimination.
  • 26. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR (Section 79 – Section 88) Section 81 A licensee who owns an energy network system must allow other licensees or energy industry operators to utilize or connect to his system in accordance with terms stipulated and announced by the licensee who owns the energy network system. The terms under paragraph one shall comprise term on connection of an energy network system, term on utilization of energy network system facilities and term on energy network system operation, such terms shall be based on the following principles: (1) They must not adversely affect security, safety and quality of energy system. (2) They must not disadvantage energy consumers and the public. (3) They must not discriminate or hinder other licensees or energy industry operators. (4) The technical specifications at the end-use points or at the point of connection to an energy network system must be clear, technically feasible and must not impose an undue burden on the person who requests utilization of or connection to the energy network system. (5) They must have a clear description of duty and responsibility of a person who requests utilization of and connection to an energy network system and a person who allows utilization of or connection to the system. (6) Any other characteristic as announced by the Commission. The term under paragraphs one and two shall not cause a licensee who owns an energy network system to lose benefits or to be at a disadvantage in
  • 27. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR (Section 79 – Section 88) Section 82 In the case where the Commission views that the term on connection of an energy network system, the term on utilization of energy network system facilities and the term on energy network system operation do not comply with the principles under Section 81, the Commission shall have the power to order the licensee who issues such terms to revise or improve the terms to comply with the principles under Section 81. Section 83 In the case where a licensee or an energy industry operator, wishing to utilize or connect an energy network system, views that a term on connection of energy network system connection, term on utilization of energy network system facilities and term on energy network system operation do not comply with the principles under Section 81, the licensee or the energy industry operator can make a request to the Commission for consideration. In the case where the Commission views that the terms do not comply with the principles under Section 81, the Commission shall have the power to order the licensee who issues such terms to revise or improve the terms to comply with the principles under Section 81. Section 84 In the case that a licensee who owns an energy network system refuses to allow utilization of or connection to his system, the person who has been refused has the right to make a request to the Commission for consideration. When the Commission has made a decision on the request under paragraph one hereof, the concerned parties shall abide by the decision. Section 85 A licensee who owns an energy network system must provide a person who requests the utilization of or connection to his system with accurate information necessary for utilization of or connection to the system. He shall not take any action that would disrupt the normal utilization of and connection to an energy network system of other licensee or energy industry operator.
  • 28. Energy Industry Act 2007 DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR (Section 79 – Section 88) Section 86 A licensee who owns an energy network system must disclose contracts, agreements, conditions and tariffs for the utilization of or connection to his system, according to the criteria, procedures and conditions announced by the Commission. Section 87 A licensee with an energy network system operator shall be responsible for control, management and overseeing of energy system to ensure balance, security, stability, efficiency and reliability of overall system, and shall have authority and duties to execute other tasks as specified by the Commission under conditions of the license issuance. The licensee with an electricity system operator shall order licensees who operate electricity industry to generate electricity fairly without unjust discrimination. Section 88 In the case that a person makes a complaint to the Commission that a licensee with an electricity system operator has breached Section 87, paragraph two, the Commission shall make decision on the complaint within thirty days as from the date of receipt of written complaint. In the case where the Commission considers that the licensee with the electricity system operator has breached Section 87, paragraph two, causing damage to the complainant, the Commission shall preliminarily determine amount of compensation for such damage.