SlideShare a Scribd company logo
1 of 53
Rana Plaza Collapse:
Causes and Our Role to Ensure Construction of Safer Buildings
P R E S E N T E D B Y
M D . M A F I Z U R R A H M A N
E X E C U T I V E E N G I N E E R
P W D D E S I G N D I V I S I O N - V & D P M , C N C R P .
A N U P K U M A R H A L D E R
S U B D I V I S I O N A L E N G I N E E R
P W D D E S I G N D I V I S I O N - V & M E M B E R T E A M - 2 C N C R P .
15th May, 2013.
RANA PLAZA
23rd April, 2013
OUTLINE OF THE PRESENTATION
1. BUILDING DESCRIPTION
2. APPROVAL OF THE BUILDING
3. STRUCTURAL ASSESSMENT
4. CONSTRUCTION AND QUALITY CONTROL
5. OCCUPANCY OF THE BUILDING
6. SUMMARY OF FINDINGS
7. RECOMMENDATIONS
LOCATION MAP
BUILDING DESCRIPTION
(Before Collapse)
Name RANA PLAZA
Location Savar Bazar Bus stand, Savar, Dhaka.
Storey 1 Basement+ 9 Storey
Building Height 108’-0” Above plinth
Structure Type R.C.C. Frame Structure
Foundation Type Pile Foundation
App. Length of Building (Column c/c) 220’-0”
App. Width of Building(Column c/c) 85’-0”
Building Area 20,000 Sft (approx.) per floor.
Total floor Area 2,00,000 Sft (approx.)
Year of Design 2005
Year of Construction Started in 2006
BUILDING DESCRIPTION Cont…
 Relevant Information :
 Developer: Tonmoy Housing Ltd ( up to 1st Floor)
Building Owner (from 2nd to 8th Floor)
 Consultant: Vaastukalpa Architects (up to 5th Floor)
 Architect : Architects of Vaastukalpa (up to 5th Floor)
 Structural Engineer: Engr. Sajjad Hossain, IEB M-1016380,Rajuk E-00152
 Supervising Engineer: None (Owner’s supervision)
 Completion Date: Incomplete
 Opening of the Building: 2010
 Date of Collapse: 24th April,2013
FLOOR PLAN
(FROM APPROVED DRAWING)
SECTION &
ELEVATION
(FROM APPROVED
DRAWING 2006)
AS BUILT DRAWING (prepared by CNCRP)
COLUMN LAYOUT
OPENING IN 1ST FLOOR
AS BUILT DRAWING (prepared by CNCRP)
BEAM LAYOUT
AS BUILT DRAWING
(prepared by CNCRP)
SECTION
APPROVAL OF THE BUILDING
Approval Stage (stage 1) 2006
Approving Authority Savar Pourashabha
Usage Basement for parking, level 1 to 3 as shops, 4 to 6 as office
Number of story 1 Basement+ 6 Storey
Available Drawings Two architectural drawing sheets containing
 Floor plan
 Section
 Elevation
No structural drawings and Soil Investigation Report found
in Pourashabha office.
Approval Stage (stage 2) 2008
Approving Authority Savar Pourashabha
Usage Basement for parking, level 1 to 3 as shops, 4 to 10 as office
Number of story 1 Basement+ 10 Storey
Available Drawings Three architectural drawing sheets containing
 Floor plan
 Section
 Elevation
Two structural drawing sheets found in Pourashabha office
(Not approved)
APPROVAL OF THE BUILDING
ASSESSMENT OF THE STRUCTURE
Assessment Criteria Considered (Stage: 1 for Seven Story)
Compressive Strength of Concrete f’c=2,500 psi with brick chips
Rebar Yield Strength fy=60,000 psi
Dead load Slab 6” =75 psf , Floor finish=25 psf
Partition wall=40 psf (shop), 20 psf (office)
Live load For shop=80 psf, for office=60psf
Wind Load 210 Km/hr ( For Dhaka)
Earthquake Load z=0.15 As per BNBC-93
Column Size 20”X20” in Basement
18”X18” in Ground & First floor levels
15”X15” in rest of Top levels
Beam Size 20”X30”/20”X20”/12”X20”
Analysis Method 3-D finite element analysis
Software Used Staad Pro V8i and ETABS 2013
Seismic assessment (Japanese Method ) Seismic Evaluation of Existing Reinforced
Concrete Buildings, 2001
ANALYSIS BY STAAD PRO & ETABS
STAAD PRO 3-D MODEL ETABS 3-D MODEL
CHECK FOR FOUNDATION DESIGN
UN FACTORED SERVICE LOAD
SOIL INVESTIGATION DONE FOR THIS STUDY SUBMITTED PILE DRAWING
PILE LAYOUT (Submitted drawing)
Foundation Type Pile (Cast in situ pile)
Length 60 ‘-0”
Rebar 6-20Φ
Pile diameter 18 “
Mat Thickness 15”
Pile Capacity 90 Ton (estimated )
Remark: Inadequate foundation design
ANALYSIS RESULTS
OVER STRESSED COLUMN AT BASEMENT FLOOR LEVEL (Staad analysis)
Column Size 20”X20”
Rebar provided 16-22Φ (2.4%)
Highly stressed columns More than 4% rebar demand
OVER STRESSED COLUMN AT BASEMENT FLOOR LEVEL (Etabs analysis)
OVER STRESSED COLUMN AT GR. FLOOR LEVEL (Staad analysis)
Column Size 18”X18”
Rebar provided 16-22Φ (2.96%)
Highly stressed column More than 4% rebar demand
OVER STRESSED COLUMN AT GR. FLOOR LEVEL (Etabs analysis)
OVER STRESSED COLUMN AT 1ST FLOOR LEVEL (Staad analysis)
Column Size 18”X18”
Rebar provided 16-22Φ (2.96%)
Over stressed column More than 4% rebar demand
OVER STRESSED COLUMN AT 1ST FLOOR LEVEL (Etabs analysis)
OVER STRESSED COLUMN AT 2ND FLOOR LEVEL (Staad analysis)
Column Size 15”X15”
Rebar provided 16-20Φ (3.45%)
Over stressed column More than 4% rebar demand
OVER STRESSED COLUMN AT 2ND FLOOR LEVEL (Etabs analysis)
OVER STRESSED COLUMN AT 3RD FLOOR LEVEL (Staad analysis)
Column Size 15”X15”
Rebar provided 16-20Φ (3.45%)
Over stressed column More than 4%
OVER STRESSED COLUMN AT 3RD FLOOR LEVEL (Etabs analysis)
SUMMARY OF ANALYSIS
FLOOR COLUMN % REBAR
PROVIDED
No of Columns where Rebar
demand >4%
STAAD ETABS
5TH 15”x15” 2.2% Design OK Design OK
4TH 15”x15” 3.45% Design OK Design OK
3RD 15”x15” 3.45% 8 12
2ND 15”x15” 3.45% 30 35
1ST 18”X18” 2.96% 5 19
GROUND 18”X18” 2.96% 25 32
BASEMENT 20”X20” 2.4% 20 30
COLUMN SIZE
REDUCTION
SEISMIC ASSESSMENT BY JAPANESE METHOD
(1ST LEVEL)
 BASIC ASSUMPTIONS
 Material strength and cross sectional dimensions required for calculation of
strength of structural member
 Cracking of concrete and deformations of structure for evaluation of time index.
 Building configuration for evaluation of irregularity index.
 Is >0.8 for 1st level Screening (standard for Japan)
Is >0.3 for 1st level Screening ( Proposed Standard for Bangladesh)
 RESULTS SUMMARY
Story
∑W (Kn) τ. Ac (N) f'c(Mpa) (n+1)/(n+i) βc Cc F Eo T Sd Is
6 13950 6004687.5 17.24 0.57 0.86 0.37 1 0.21 1 1 0.21
5 35805 6004687.5 17.24 0.62 0.86 0.14 1 0.09 1 1 0.09
4 49755 6004687.5 17.24 0.67 0.86 0.10 1 0.07 1 1 0.07
3 71610 6004687.5 17.24 0.73 0.86 0.07 1 0.05 1 1 0.05
2 93465 8646750 17.24 0.80 0.86 0.08 1 0.06 1 1 0.06
1 115320 8646750 17.24 0.89 0.86 0.06 1 0.06 1 1 0.06
Basement 137175 10675000 17.24 1.00 0.86 0.07 1 0.07 1 1 0.07
Where:
Is=Seismic index of structure
Eo=Basic seismic index of structure
SD=Irregularity index
T= Time index
n = Number of stories of a building.
i = Number of the story for evaluation,
CW = Strength index of the walls.
CC = Strength index of the columns.
α1 = Effective strength factor of the columns at the ultimate deformation of the walls, which
may be taken as 0.7. The value should be 1.0 in case of Cw=0.
FW = Ductility index of the walls , which may be taken as 1.0.
Fc = Ductility index of columns, which may be taken as 1.0
1st level Screening
Seismic Index of Structure(Is)
1st level screening procedure
Classification of vertical members in the
Vertical Member Definition Ductility Index F
Column ho/D>2 1.0
Extremely Short
Column
ho/D≤2 0.8
Wall Walls including those without
boundary columns
1.0
Strength Index:
Ductility Index:
1Basement + 9 Story BUILDING
(Load case: Factored Gravity Load only)
3-D VIEW OF OVER
STRESSED COLUMNS
ALL MOST ALL COLUMNS ARE OVER STRESSED
AT 2ND FLOOR LEVEL (COLUMN SIZE 15”X15”)
OVER STRESSED COLUMN AT BASEMENT FLOOR LEVEL
(Load case: Factored Gravity Load only)
1463 K 2019 K
1756 K 1858 K
2130K
MAX. COLUMN CAPACITY =1000 K
1915K
1780K1708 K
1538 K
STAAD Pro OUTPUT
ETABS OUTPUT
HAND CALCULATION BASED ON TRIBUTARY AREA
CONSTRUCTION AND QUALITY CONTROL
 No working structural drawing was available
 Design concrete strength f’c and steel strength fy was not
specified in the submitted structural design.
 Brick chips was used as coarse aggregate.
 Test of construction materials (rebar, cement, concrete etc )
was never done.
 Work progress was never submitted to Pourashabha authority.
 Faulty construction sequence/ method
 Absence of proper detailing.
 No standard QC and QA was followed.
CONSTRUCTION AND QUALITY CONTROL cont..
CONSTRUCTION AND QUALITY CONTROL cont..
CONSTRUCTION AND QUALITY CONTROL cont..
CONSTRUCTION AND QUALITY CONTROL cont..
USE OF PLAIN BAR USE OF DEFORMED BAR
CONSTRUCTION AND QUALITY CONTROL cont..
NON MONOLITHIC BEAM-SLAB CASTING
OCCUPANCY OF THE BUILDING
(At final stage)
FLOOR PERMITTED USE ACTUAL OCCUPANCY
Basement Parking Parking & Garments office
Ground Floor Shop Shop
1ST Floor Shop Shop
2ND Floor Shop Garments
3RD Floor Office Garments
4TH Floor Office Garments
5TH Floor Office Garments
6TH Floor Office Garments
7TH Floor Office Garments
8TH Floor Office Unoccupied
OCCUPANCY OF THE BUILDING cont..
OCCUPANCY OF THE BUILDING cont..
GENERATOR INSTALLED IN 2ND , 6TH AND 7TH FLOOR
OCCUPANCY OF THE BUILDING cont..
FLOOR USED AS
GARMENTS GO-DOWN
SUMMARY OF FINDINGS
1. Wrong building approval.
2. No provision for verification and approval of structural
design by approving authority (Savar pourashabha)
3. Faulty and inadequate structural design.
4. Gross structural irregularity due to architectural design.
5. Non engineered construction.
6. No material standard.
7. Change of occupancy.
8. Administrative failure to prevent use of the building
despite getting advance signs and symptoms of collapse.
RECOMMENDATIONS
[A] BUILDING APPROVAL
 Authority of building approval and regulation must be entrusted to a
single office, Building Regulatory Authority(BRA), as proposed in BNBC. No
overlapping of jurisdiction shall be allowed.
 Building Regulatory Authority (BRA) should not be engaged in any activity
which would create conflict of interest.
 Approval of structural design drawings, electro-mechanical and building
services design drawings along with architectural design drawings must be
incorporated in the approving procedure.
 The Building Regulatory Authority(BRA) shall open design review wing.
They may engage qualified registered consultant for this purpose, in case
the authority lacks in capacity.
 ‘Approval Fee’ may be increased to bear the extra costs.
RECOMMENDATIONS Cont…
[B]BUILDING DESIGN
 Building owner shall engage qualified registered architect,
structural design engineer, electro-mechanical engineer &
building services engineer/ consulting firm for design of
buildings.
 Only registered architect and engineers shall prepare
architectural, structural, electro-mechanical and building
services design drawings.
 A government statutory professional registration body should
be set up for this purpose. A model of any developed country
could be followed.
 Information of all such registered architects and engineers/
consultancy firm should be displayed in the website of the
professional registration body.
RECOMMENDATIONS cont…
[C] BUILDING CONSTRUCTION & QUALITY CONTROL
 The Building Regulatory Authority(BRA) shall monitor whether
construction of buildings are being executed as per approved design
drawings following standard quality control procedure.
 A standard quality control and assurance system has to be established to
ensure standard of construction. All building owners will follow that
standard. The Building Regulatory Authority(BRA) shall develop a system
to monitor the matter.
 Building owner shall engage qualified, registered construction
company/developer for construction of buildings.
 Only qualified registered engineers shall supervise the construction work.
 Regular progress reports in prescribed forms has to be submitted by
supervising engineer to Building Regulatory Authority(BRA) at certain
stages of construction. This provision is already in Dhaka Mahanagar
Imarat Bidhimala 2008 but needs immediate and stringent enforcement.
 Standard of construction material must conform to provisions of BNBC.
RECOMMENDATIONS cont…
[D] BUILDING OCCUPANCY
 The Building Regulatory Authority (BRA) shall strictly enforce issuance of
“Occupancy Certificate”(as per provision of Dhaka Mahanagar Imarat
Bidhimala-2008) after checking thoroughly all relevant reports and
certificate from architect, structural engineer, eloctro-mechanical and
building services engineers, supervising engineer, etc. employed by the
building owner.
 Building permit and occupancy certificate should be displayed at some
suitable place of the building.
 Building permit related information including “Occupancy Certificate” shall
be displayed in the website of the Building Regulatory Authority(BRA).
RECOMMENDATIONS cont…
[E] BUILDING MAINTENANCE & EVALUATION
 “Occupancy Certificate” has to be renewed every three years instead of
every five years (As prescribed in Dhaka Mahanagar Imarat Bidhimala
2008). BRA shall renew the certificate after inspecting maintenance and
occupancy situtuation.
 In any reported case of building distress, Building Regulatory
Authority(BRA) shall assess the building and take necessary action to
ensure safety of the building and its occupants.
 Evaluation of existing buildings shall be the responsibility of BRA and shall
suggest retrofit measures for vulnerable buildings.
ACKNOWLEDGEMENT
 Dhaka District Administration
 Bangladesh Army
 Fire Service and Civil Defense Department
 Bangladesh Police
 LGED
 HBRI
 RAJUK
 IEB
 IAB
 Local Volunteers
THANK YOU

More Related Content

What's hot

Lateral load resisting systems
Lateral load resisting systemsLateral load resisting systems
Lateral load resisting systemsAhmad T.
 
TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?
TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?
TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?Amar Gohel
 
COMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURES
COMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURESCOMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURES
COMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURESMohammed Tajammul Ahmed
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildingsRithika Ravishankar
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
 
Mini sky city, china
Mini sky city, chinaMini sky city, china
Mini sky city, chinaHimaniMishra7
 
DESIGN OF HOSTEL BUILDING G+5
DESIGN OF HOSTEL BUILDING G+5DESIGN OF HOSTEL BUILDING G+5
DESIGN OF HOSTEL BUILDING G+5anvesh reddy
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Prateek Srivastava
 

What's hot (20)

Lateral load resisting systems
Lateral load resisting systemsLateral load resisting systems
Lateral load resisting systems
 
Wind load
Wind  loadWind  load
Wind load
 
Report on High Rise
Report on High RiseReport on High Rise
Report on High Rise
 
TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?
TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?
TIPS:16 - HOW TO MAKE STONE MASONRY BUILDINGS EARTHQUAKE RESISTANT?
 
Shear Wall
Shear WallShear Wall
Shear Wall
 
COMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURES
COMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURESCOMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURES
COMPARATIVE STUDY OF RCC AND COMPOSITE STRUCTURES
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildings
 
Manhattan skyscrapers
Manhattan skyscrapersManhattan skyscrapers
Manhattan skyscrapers
 
The Shard
The ShardThe Shard
The Shard
 
floating coloumn.pptx
floating coloumn.pptxfloating coloumn.pptx
floating coloumn.pptx
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Truss
Truss  Truss
Truss
 
Retrofitting
RetrofittingRetrofitting
Retrofitting
 
Mini sky city, china
Mini sky city, chinaMini sky city, china
Mini sky city, china
 
DESIGN OF HOSTEL BUILDING G+5
DESIGN OF HOSTEL BUILDING G+5DESIGN OF HOSTEL BUILDING G+5
DESIGN OF HOSTEL BUILDING G+5
 
Petronas towers
Petronas towersPetronas towers
Petronas towers
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
 
presentation ON TALL BUILDING
 presentation ON TALL BUILDING presentation ON TALL BUILDING
presentation ON TALL BUILDING
 

Viewers also liked

Rana Plaza disaster and rehabilitation by CDD Bangladesh
Rana Plaza disaster and rehabilitation by CDD BangladeshRana Plaza disaster and rehabilitation by CDD Bangladesh
Rana Plaza disaster and rehabilitation by CDD BangladeshLIGHT FOR THE WORLD
 
Rana plaza workplace safety in bangladesh
Rana plaza workplace safety in bangladeshRana plaza workplace safety in bangladesh
Rana plaza workplace safety in bangladeshSohel Rana
 
One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...
One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...
One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...Centre for Policy Dialogue (CPD)
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projectsSULAKSHYA GAUR
 
The 2013 Savar Building Collapse
The 2013 Savar Building CollapseThe 2013 Savar Building Collapse
The 2013 Savar Building Collapsebaumjam
 
Compensation Package for Savar Victims
Compensation Package for Savar VictimsCompensation Package for Savar Victims
Compensation Package for Savar VictimsSavarTragedy
 
Building Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresBuilding Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresRithika Ravishankar
 
BUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSIS
BUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSISBUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSIS
BUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSISYaseen Syed
 
civil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasancivil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasanEngr Mirza S Hasan
 
setting out & column marking plan-09.02
setting out & column marking plan-09.02setting out & column marking plan-09.02
setting out & column marking plan-09.02goutam mondal
 
Intro to Confined Masonry
Intro to Confined MasonryIntro to Confined Masonry
Intro to Confined MasonryEERI
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab constructiontivar rose
 
Module 4 module 2 structural layout & details
Module 4   module 2 structural layout & detailsModule 4   module 2 structural layout & details
Module 4 module 2 structural layout & detailsGilbert Bautista
 
How to Tackle SBQ - Social Studies
How to Tackle SBQ - Social StudiesHow to Tackle SBQ - Social Studies
How to Tackle SBQ - Social StudiesRahim Springfields
 
Rana Plaza incident: The Right to Remedy
Rana Plaza incident: The Right to RemedyRana Plaza incident: The Right to Remedy
Rana Plaza incident: The Right to RemedyIsabelle Attallah
 

Viewers also liked (20)

Rana Plaza disaster and rehabilitation by CDD Bangladesh
Rana Plaza disaster and rehabilitation by CDD BangladeshRana Plaza disaster and rehabilitation by CDD Bangladesh
Rana Plaza disaster and rehabilitation by CDD Bangladesh
 
Rana plaza workplace safety in bangladesh
Rana plaza workplace safety in bangladeshRana plaza workplace safety in bangladesh
Rana plaza workplace safety in bangladesh
 
One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...
One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...
One Year after the Rana Plaza Tragedy: Where Do We Stand? the Victims, the Se...
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projects
 
The 2013 Savar Building Collapse
The 2013 Savar Building CollapseThe 2013 Savar Building Collapse
The 2013 Savar Building Collapse
 
Compensation Package for Savar Victims
Compensation Package for Savar VictimsCompensation Package for Savar Victims
Compensation Package for Savar Victims
 
Building Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresBuilding Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structures
 
BUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSIS
BUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSISBUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSIS
BUILDING STRUCTURES 1 COLUMN AND BEAM ANALYSIS
 
Post lintel structre
Post lintel structrePost lintel structre
Post lintel structre
 
civil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasancivil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasan
 
setting out & column marking plan-09.02
setting out & column marking plan-09.02setting out & column marking plan-09.02
setting out & column marking plan-09.02
 
Intro to Confined Masonry
Intro to Confined MasonryIntro to Confined Masonry
Intro to Confined Masonry
 
foundation
foundationfoundation
foundation
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
 
Drafting technology y3
Drafting technology y3Drafting technology y3
Drafting technology y3
 
Compare Contrast Powerpoint
Compare Contrast PowerpointCompare Contrast Powerpoint
Compare Contrast Powerpoint
 
Module 4 module 2 structural layout & details
Module 4   module 2 structural layout & detailsModule 4   module 2 structural layout & details
Module 4 module 2 structural layout & details
 
How to Tackle SBQ - Social Studies
How to Tackle SBQ - Social StudiesHow to Tackle SBQ - Social Studies
How to Tackle SBQ - Social Studies
 
Rana Plaza incident: The Right to Remedy
Rana Plaza incident: The Right to RemedyRana Plaza incident: The Right to Remedy
Rana Plaza incident: The Right to Remedy
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
 

Similar to Rana plaza present 30 7-13

Seismic Drift Control in soft storied RCC buildings
Seismic Drift Control in soft storied RCC buildingsSeismic Drift Control in soft storied RCC buildings
Seismic Drift Control in soft storied RCC buildingsIJERA Editor
 
Group 2 , ce471
Group 2  ,  ce471Group 2  ,  ce471
Group 2 , ce471ktx500
 
Etabs BY Subash Pathak
Etabs BY Subash PathakEtabs BY Subash Pathak
Etabs BY Subash PathakSubash Pathak
 
Behaviour of Flat Slab by Varying Stiffness in High Seismic Zone
Behaviour of Flat Slab by Varying Stiffness in High Seismic ZoneBehaviour of Flat Slab by Varying Stiffness in High Seismic Zone
Behaviour of Flat Slab by Varying Stiffness in High Seismic ZoneIRJET Journal
 
Seismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storeySeismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storeyeSAT Publishing House
 
Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...
Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...
Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...IOSR Journals
 
Comparative Study of Seismic Analysis of Ground Storey and Parking Storey
Comparative Study of Seismic Analysis of Ground Storey and Parking StoreyComparative Study of Seismic Analysis of Ground Storey and Parking Storey
Comparative Study of Seismic Analysis of Ground Storey and Parking StoreyIRJET Journal
 
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...IRJET Journal
 
IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...
IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...
IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...IRJET Journal
 
STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...
STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...
STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...IRJET Journal
 
IRJET- Review on Study of Behaviour of Seismic Analysis of Floating Colum...
IRJET-  	  Review on Study of Behaviour of Seismic Analysis of Floating Colum...IRJET-  	  Review on Study of Behaviour of Seismic Analysis of Floating Colum...
IRJET- Review on Study of Behaviour of Seismic Analysis of Floating Colum...IRJET Journal
 
Analysis, Design and Estimation of Basement +G+2 Residential Building
Analysis, Design and Estimation of Basement +G+2 Residential BuildingAnalysis, Design and Estimation of Basement +G+2 Residential Building
Analysis, Design and Estimation of Basement +G+2 Residential BuildingIRJET Journal
 
Seismic Analysis of Multi Storied Irregular Building using Flat Slab and Gri...
Seismic Analysis of Multi Storied Irregular Building  using Flat Slab and Gri...Seismic Analysis of Multi Storied Irregular Building  using Flat Slab and Gri...
Seismic Analysis of Multi Storied Irregular Building using Flat Slab and Gri...IRJET Journal
 
IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...
IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...
IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...IRJET Journal
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Blockjeyanthi4
 
Seismic Performance of Flat Slab Structures Under Static and Dynamic Loads
Seismic Performance of Flat Slab Structures Under Static and Dynamic LoadsSeismic Performance of Flat Slab Structures Under Static and Dynamic Loads
Seismic Performance of Flat Slab Structures Under Static and Dynamic LoadsIRJET Journal
 
Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...
Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...
Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...IRJET Journal
 

Similar to Rana plaza present 30 7-13 (20)

Seismic Drift Control in soft storied RCC buildings
Seismic Drift Control in soft storied RCC buildingsSeismic Drift Control in soft storied RCC buildings
Seismic Drift Control in soft storied RCC buildings
 
Group 2 , ce471
Group 2  ,  ce471Group 2  ,  ce471
Group 2 , ce471
 
Etabs BY Subash Pathak
Etabs BY Subash PathakEtabs BY Subash Pathak
Etabs BY Subash Pathak
 
Behaviour of Flat Slab by Varying Stiffness in High Seismic Zone
Behaviour of Flat Slab by Varying Stiffness in High Seismic ZoneBehaviour of Flat Slab by Varying Stiffness in High Seismic Zone
Behaviour of Flat Slab by Varying Stiffness in High Seismic Zone
 
Seismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storeySeismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storey
 
Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...
Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...
Static and Dynamic Behavior of Reinforced Concrete Framed Building: A Compara...
 
Comparative Study of Seismic Analysis of Ground Storey and Parking Storey
Comparative Study of Seismic Analysis of Ground Storey and Parking StoreyComparative Study of Seismic Analysis of Ground Storey and Parking Storey
Comparative Study of Seismic Analysis of Ground Storey and Parking Storey
 
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
 
Hospital building project
Hospital building projectHospital building project
Hospital building project
 
IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...
IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...
IRJET- A Study on RCC Frames under Sloping Ground with Different Shear Wall C...
 
STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...
STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...
STUDY OF COMPARISON BETWEEN TWO ATRIUM BUILDINGS IN VARIOUS SEISMIC ZONES WIT...
 
IRJET- Review on Study of Behaviour of Seismic Analysis of Floating Colum...
IRJET-  	  Review on Study of Behaviour of Seismic Analysis of Floating Colum...IRJET-  	  Review on Study of Behaviour of Seismic Analysis of Floating Colum...
IRJET- Review on Study of Behaviour of Seismic Analysis of Floating Colum...
 
Analysis, Design and Estimation of Basement +G+2 Residential Building
Analysis, Design and Estimation of Basement +G+2 Residential BuildingAnalysis, Design and Estimation of Basement +G+2 Residential Building
Analysis, Design and Estimation of Basement +G+2 Residential Building
 
Hostel
HostelHostel
Hostel
 
Seismic Analysis of Multi Storied Irregular Building using Flat Slab and Gri...
Seismic Analysis of Multi Storied Irregular Building  using Flat Slab and Gri...Seismic Analysis of Multi Storied Irregular Building  using Flat Slab and Gri...
Seismic Analysis of Multi Storied Irregular Building using Flat Slab and Gri...
 
Bl4201416420
Bl4201416420Bl4201416420
Bl4201416420
 
IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...
IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...
IRJET- Evaluation of R.C. Multi-Storey Building Response under the Effect of ...
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Block
 
Seismic Performance of Flat Slab Structures Under Static and Dynamic Loads
Seismic Performance of Flat Slab Structures Under Static and Dynamic LoadsSeismic Performance of Flat Slab Structures Under Static and Dynamic Loads
Seismic Performance of Flat Slab Structures Under Static and Dynamic Loads
 
Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...
Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...
Seismic Behaviour of Rc Building Resting on Plain and Sloping Ground with Bra...
 

More from Dr. H.M.A. Mahzuz

Lecture 4, constituents of concrete-coarse aggregate
Lecture 4, constituents of concrete-coarse aggregateLecture 4, constituents of concrete-coarse aggregate
Lecture 4, constituents of concrete-coarse aggregateDr. H.M.A. Mahzuz
 
Lecture 3, constituents of concrete-fine aggregate
Lecture 3, constituents of concrete-fine aggregateLecture 3, constituents of concrete-fine aggregate
Lecture 3, constituents of concrete-fine aggregateDr. H.M.A. Mahzuz
 
Lecture 2, constituents of concrete-cement
Lecture 2, constituents of concrete-cementLecture 2, constituents of concrete-cement
Lecture 2, constituents of concrete-cementDr. H.M.A. Mahzuz
 
Lecture 5 rcc building design considering earthquake and wind load
Lecture 5 rcc building design considering earthquake and wind loadLecture 5 rcc building design considering earthquake and wind load
Lecture 5 rcc building design considering earthquake and wind loadDr. H.M.A. Mahzuz
 
Lecture 6 steel building design considering earthquake and wind load
Lecture 6 steel building design considering earthquake and wind loadLecture 6 steel building design considering earthquake and wind load
Lecture 6 steel building design considering earthquake and wind loadDr. H.M.A. Mahzuz
 
Lecture 4 beam design and load combination
Lecture 4 beam design and load combinationLecture 4 beam design and load combination
Lecture 4 beam design and load combinationDr. H.M.A. Mahzuz
 
Lecture 3 section identify and 3 d frame
Lecture 3 section identify and 3 d frameLecture 3 section identify and 3 d frame
Lecture 3 section identify and 3 d frameDr. H.M.A. Mahzuz
 
Lecture 1 what is rcc column and its importance
Lecture 1 what is rcc column and its importanceLecture 1 what is rcc column and its importance
Lecture 1 what is rcc column and its importanceDr. H.M.A. Mahzuz
 

More from Dr. H.M.A. Mahzuz (20)

Column math
Column mathColumn math
Column math
 
Lecture 7 steel
Lecture 7 steelLecture 7 steel
Lecture 7 steel
 
Lecture 5, concrete-hmm
Lecture 5, concrete-hmmLecture 5, concrete-hmm
Lecture 5, concrete-hmm
 
Lecture 4, constituents of concrete-coarse aggregate
Lecture 4, constituents of concrete-coarse aggregateLecture 4, constituents of concrete-coarse aggregate
Lecture 4, constituents of concrete-coarse aggregate
 
Lecture 3, constituents of concrete-fine aggregate
Lecture 3, constituents of concrete-fine aggregateLecture 3, constituents of concrete-fine aggregate
Lecture 3, constituents of concrete-fine aggregate
 
Lecture 11, paint
Lecture 11, paintLecture 11, paint
Lecture 11, paint
 
Lecture 2, constituents of concrete-cement
Lecture 2, constituents of concrete-cementLecture 2, constituents of concrete-cement
Lecture 2, constituents of concrete-cement
 
Some fun facts
Some fun factsSome fun facts
Some fun facts
 
Lecture 5 rcc building design considering earthquake and wind load
Lecture 5 rcc building design considering earthquake and wind loadLecture 5 rcc building design considering earthquake and wind load
Lecture 5 rcc building design considering earthquake and wind load
 
Lecture 7 shear wall
Lecture 7 shear wallLecture 7 shear wall
Lecture 7 shear wall
 
Lecture 6 steel building design considering earthquake and wind load
Lecture 6 steel building design considering earthquake and wind loadLecture 6 steel building design considering earthquake and wind load
Lecture 6 steel building design considering earthquake and wind load
 
Lecture 4 beam design and load combination
Lecture 4 beam design and load combinationLecture 4 beam design and load combination
Lecture 4 beam design and load combination
 
Lecture 3 section identify and 3 d frame
Lecture 3 section identify and 3 d frameLecture 3 section identify and 3 d frame
Lecture 3 section identify and 3 d frame
 
Lecture 2 grid system
Lecture 2 grid systemLecture 2 grid system
Lecture 2 grid system
 
Lecture 1 outline -latest
Lecture 1 outline -latestLecture 1 outline -latest
Lecture 1 outline -latest
 
Lecture 1 what is rcc column and its importance
Lecture 1 what is rcc column and its importanceLecture 1 what is rcc column and its importance
Lecture 1 what is rcc column and its importance
 
Tannery hmm
Tannery hmmTannery hmm
Tannery hmm
 
River bank erosion hmm
River bank erosion hmmRiver bank erosion hmm
River bank erosion hmm
 
Public health in disaster
Public health in disasterPublic health in disaster
Public health in disaster
 
Lecture 2 flood
Lecture 2 floodLecture 2 flood
Lecture 2 flood
 

Recently uploaded

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 

Rana plaza present 30 7-13

  • 1. Rana Plaza Collapse: Causes and Our Role to Ensure Construction of Safer Buildings P R E S E N T E D B Y M D . M A F I Z U R R A H M A N E X E C U T I V E E N G I N E E R P W D D E S I G N D I V I S I O N - V & D P M , C N C R P . A N U P K U M A R H A L D E R S U B D I V I S I O N A L E N G I N E E R P W D D E S I G N D I V I S I O N - V & M E M B E R T E A M - 2 C N C R P .
  • 4. OUTLINE OF THE PRESENTATION 1. BUILDING DESCRIPTION 2. APPROVAL OF THE BUILDING 3. STRUCTURAL ASSESSMENT 4. CONSTRUCTION AND QUALITY CONTROL 5. OCCUPANCY OF THE BUILDING 6. SUMMARY OF FINDINGS 7. RECOMMENDATIONS
  • 6. BUILDING DESCRIPTION (Before Collapse) Name RANA PLAZA Location Savar Bazar Bus stand, Savar, Dhaka. Storey 1 Basement+ 9 Storey Building Height 108’-0” Above plinth Structure Type R.C.C. Frame Structure Foundation Type Pile Foundation App. Length of Building (Column c/c) 220’-0” App. Width of Building(Column c/c) 85’-0” Building Area 20,000 Sft (approx.) per floor. Total floor Area 2,00,000 Sft (approx.) Year of Design 2005 Year of Construction Started in 2006
  • 7. BUILDING DESCRIPTION Cont…  Relevant Information :  Developer: Tonmoy Housing Ltd ( up to 1st Floor) Building Owner (from 2nd to 8th Floor)  Consultant: Vaastukalpa Architects (up to 5th Floor)  Architect : Architects of Vaastukalpa (up to 5th Floor)  Structural Engineer: Engr. Sajjad Hossain, IEB M-1016380,Rajuk E-00152  Supervising Engineer: None (Owner’s supervision)  Completion Date: Incomplete  Opening of the Building: 2010  Date of Collapse: 24th April,2013
  • 10. AS BUILT DRAWING (prepared by CNCRP) COLUMN LAYOUT
  • 11. OPENING IN 1ST FLOOR AS BUILT DRAWING (prepared by CNCRP) BEAM LAYOUT
  • 12. AS BUILT DRAWING (prepared by CNCRP) SECTION
  • 13. APPROVAL OF THE BUILDING Approval Stage (stage 1) 2006 Approving Authority Savar Pourashabha Usage Basement for parking, level 1 to 3 as shops, 4 to 6 as office Number of story 1 Basement+ 6 Storey Available Drawings Two architectural drawing sheets containing  Floor plan  Section  Elevation No structural drawings and Soil Investigation Report found in Pourashabha office. Approval Stage (stage 2) 2008 Approving Authority Savar Pourashabha Usage Basement for parking, level 1 to 3 as shops, 4 to 10 as office Number of story 1 Basement+ 10 Storey Available Drawings Three architectural drawing sheets containing  Floor plan  Section  Elevation Two structural drawing sheets found in Pourashabha office (Not approved)
  • 14. APPROVAL OF THE BUILDING
  • 15. ASSESSMENT OF THE STRUCTURE Assessment Criteria Considered (Stage: 1 for Seven Story) Compressive Strength of Concrete f’c=2,500 psi with brick chips Rebar Yield Strength fy=60,000 psi Dead load Slab 6” =75 psf , Floor finish=25 psf Partition wall=40 psf (shop), 20 psf (office) Live load For shop=80 psf, for office=60psf Wind Load 210 Km/hr ( For Dhaka) Earthquake Load z=0.15 As per BNBC-93 Column Size 20”X20” in Basement 18”X18” in Ground & First floor levels 15”X15” in rest of Top levels Beam Size 20”X30”/20”X20”/12”X20” Analysis Method 3-D finite element analysis Software Used Staad Pro V8i and ETABS 2013 Seismic assessment (Japanese Method ) Seismic Evaluation of Existing Reinforced Concrete Buildings, 2001
  • 16. ANALYSIS BY STAAD PRO & ETABS STAAD PRO 3-D MODEL ETABS 3-D MODEL
  • 17. CHECK FOR FOUNDATION DESIGN UN FACTORED SERVICE LOAD
  • 18. SOIL INVESTIGATION DONE FOR THIS STUDY SUBMITTED PILE DRAWING
  • 19. PILE LAYOUT (Submitted drawing) Foundation Type Pile (Cast in situ pile) Length 60 ‘-0” Rebar 6-20Φ Pile diameter 18 “ Mat Thickness 15” Pile Capacity 90 Ton (estimated ) Remark: Inadequate foundation design
  • 20. ANALYSIS RESULTS OVER STRESSED COLUMN AT BASEMENT FLOOR LEVEL (Staad analysis) Column Size 20”X20” Rebar provided 16-22Φ (2.4%) Highly stressed columns More than 4% rebar demand
  • 21. OVER STRESSED COLUMN AT BASEMENT FLOOR LEVEL (Etabs analysis)
  • 22. OVER STRESSED COLUMN AT GR. FLOOR LEVEL (Staad analysis) Column Size 18”X18” Rebar provided 16-22Φ (2.96%) Highly stressed column More than 4% rebar demand
  • 23. OVER STRESSED COLUMN AT GR. FLOOR LEVEL (Etabs analysis)
  • 24. OVER STRESSED COLUMN AT 1ST FLOOR LEVEL (Staad analysis) Column Size 18”X18” Rebar provided 16-22Φ (2.96%) Over stressed column More than 4% rebar demand
  • 25. OVER STRESSED COLUMN AT 1ST FLOOR LEVEL (Etabs analysis)
  • 26. OVER STRESSED COLUMN AT 2ND FLOOR LEVEL (Staad analysis) Column Size 15”X15” Rebar provided 16-20Φ (3.45%) Over stressed column More than 4% rebar demand
  • 27. OVER STRESSED COLUMN AT 2ND FLOOR LEVEL (Etabs analysis)
  • 28. OVER STRESSED COLUMN AT 3RD FLOOR LEVEL (Staad analysis) Column Size 15”X15” Rebar provided 16-20Φ (3.45%) Over stressed column More than 4%
  • 29. OVER STRESSED COLUMN AT 3RD FLOOR LEVEL (Etabs analysis)
  • 30. SUMMARY OF ANALYSIS FLOOR COLUMN % REBAR PROVIDED No of Columns where Rebar demand >4% STAAD ETABS 5TH 15”x15” 2.2% Design OK Design OK 4TH 15”x15” 3.45% Design OK Design OK 3RD 15”x15” 3.45% 8 12 2ND 15”x15” 3.45% 30 35 1ST 18”X18” 2.96% 5 19 GROUND 18”X18” 2.96% 25 32 BASEMENT 20”X20” 2.4% 20 30 COLUMN SIZE REDUCTION
  • 31. SEISMIC ASSESSMENT BY JAPANESE METHOD (1ST LEVEL)  BASIC ASSUMPTIONS  Material strength and cross sectional dimensions required for calculation of strength of structural member  Cracking of concrete and deformations of structure for evaluation of time index.  Building configuration for evaluation of irregularity index.  Is >0.8 for 1st level Screening (standard for Japan) Is >0.3 for 1st level Screening ( Proposed Standard for Bangladesh)  RESULTS SUMMARY Story ∑W (Kn) τ. Ac (N) f'c(Mpa) (n+1)/(n+i) βc Cc F Eo T Sd Is 6 13950 6004687.5 17.24 0.57 0.86 0.37 1 0.21 1 1 0.21 5 35805 6004687.5 17.24 0.62 0.86 0.14 1 0.09 1 1 0.09 4 49755 6004687.5 17.24 0.67 0.86 0.10 1 0.07 1 1 0.07 3 71610 6004687.5 17.24 0.73 0.86 0.07 1 0.05 1 1 0.05 2 93465 8646750 17.24 0.80 0.86 0.08 1 0.06 1 1 0.06 1 115320 8646750 17.24 0.89 0.86 0.06 1 0.06 1 1 0.06 Basement 137175 10675000 17.24 1.00 0.86 0.07 1 0.07 1 1 0.07
  • 32. Where: Is=Seismic index of structure Eo=Basic seismic index of structure SD=Irregularity index T= Time index n = Number of stories of a building. i = Number of the story for evaluation, CW = Strength index of the walls. CC = Strength index of the columns. α1 = Effective strength factor of the columns at the ultimate deformation of the walls, which may be taken as 0.7. The value should be 1.0 in case of Cw=0. FW = Ductility index of the walls , which may be taken as 1.0. Fc = Ductility index of columns, which may be taken as 1.0 1st level Screening Seismic Index of Structure(Is)
  • 33. 1st level screening procedure Classification of vertical members in the Vertical Member Definition Ductility Index F Column ho/D>2 1.0 Extremely Short Column ho/D≤2 0.8 Wall Walls including those without boundary columns 1.0 Strength Index: Ductility Index:
  • 34. 1Basement + 9 Story BUILDING (Load case: Factored Gravity Load only) 3-D VIEW OF OVER STRESSED COLUMNS ALL MOST ALL COLUMNS ARE OVER STRESSED AT 2ND FLOOR LEVEL (COLUMN SIZE 15”X15”)
  • 35. OVER STRESSED COLUMN AT BASEMENT FLOOR LEVEL (Load case: Factored Gravity Load only) 1463 K 2019 K 1756 K 1858 K 2130K MAX. COLUMN CAPACITY =1000 K 1915K 1780K1708 K 1538 K STAAD Pro OUTPUT ETABS OUTPUT HAND CALCULATION BASED ON TRIBUTARY AREA
  • 36. CONSTRUCTION AND QUALITY CONTROL  No working structural drawing was available  Design concrete strength f’c and steel strength fy was not specified in the submitted structural design.  Brick chips was used as coarse aggregate.  Test of construction materials (rebar, cement, concrete etc ) was never done.  Work progress was never submitted to Pourashabha authority.  Faulty construction sequence/ method  Absence of proper detailing.  No standard QC and QA was followed.
  • 37. CONSTRUCTION AND QUALITY CONTROL cont..
  • 38. CONSTRUCTION AND QUALITY CONTROL cont..
  • 39. CONSTRUCTION AND QUALITY CONTROL cont..
  • 40. CONSTRUCTION AND QUALITY CONTROL cont.. USE OF PLAIN BAR USE OF DEFORMED BAR
  • 41. CONSTRUCTION AND QUALITY CONTROL cont.. NON MONOLITHIC BEAM-SLAB CASTING
  • 42. OCCUPANCY OF THE BUILDING (At final stage) FLOOR PERMITTED USE ACTUAL OCCUPANCY Basement Parking Parking & Garments office Ground Floor Shop Shop 1ST Floor Shop Shop 2ND Floor Shop Garments 3RD Floor Office Garments 4TH Floor Office Garments 5TH Floor Office Garments 6TH Floor Office Garments 7TH Floor Office Garments 8TH Floor Office Unoccupied
  • 43. OCCUPANCY OF THE BUILDING cont..
  • 44. OCCUPANCY OF THE BUILDING cont.. GENERATOR INSTALLED IN 2ND , 6TH AND 7TH FLOOR
  • 45. OCCUPANCY OF THE BUILDING cont.. FLOOR USED AS GARMENTS GO-DOWN
  • 46. SUMMARY OF FINDINGS 1. Wrong building approval. 2. No provision for verification and approval of structural design by approving authority (Savar pourashabha) 3. Faulty and inadequate structural design. 4. Gross structural irregularity due to architectural design. 5. Non engineered construction. 6. No material standard. 7. Change of occupancy. 8. Administrative failure to prevent use of the building despite getting advance signs and symptoms of collapse.
  • 47. RECOMMENDATIONS [A] BUILDING APPROVAL  Authority of building approval and regulation must be entrusted to a single office, Building Regulatory Authority(BRA), as proposed in BNBC. No overlapping of jurisdiction shall be allowed.  Building Regulatory Authority (BRA) should not be engaged in any activity which would create conflict of interest.  Approval of structural design drawings, electro-mechanical and building services design drawings along with architectural design drawings must be incorporated in the approving procedure.  The Building Regulatory Authority(BRA) shall open design review wing. They may engage qualified registered consultant for this purpose, in case the authority lacks in capacity.  ‘Approval Fee’ may be increased to bear the extra costs.
  • 48. RECOMMENDATIONS Cont… [B]BUILDING DESIGN  Building owner shall engage qualified registered architect, structural design engineer, electro-mechanical engineer & building services engineer/ consulting firm for design of buildings.  Only registered architect and engineers shall prepare architectural, structural, electro-mechanical and building services design drawings.  A government statutory professional registration body should be set up for this purpose. A model of any developed country could be followed.  Information of all such registered architects and engineers/ consultancy firm should be displayed in the website of the professional registration body.
  • 49. RECOMMENDATIONS cont… [C] BUILDING CONSTRUCTION & QUALITY CONTROL  The Building Regulatory Authority(BRA) shall monitor whether construction of buildings are being executed as per approved design drawings following standard quality control procedure.  A standard quality control and assurance system has to be established to ensure standard of construction. All building owners will follow that standard. The Building Regulatory Authority(BRA) shall develop a system to monitor the matter.  Building owner shall engage qualified, registered construction company/developer for construction of buildings.  Only qualified registered engineers shall supervise the construction work.  Regular progress reports in prescribed forms has to be submitted by supervising engineer to Building Regulatory Authority(BRA) at certain stages of construction. This provision is already in Dhaka Mahanagar Imarat Bidhimala 2008 but needs immediate and stringent enforcement.  Standard of construction material must conform to provisions of BNBC.
  • 50. RECOMMENDATIONS cont… [D] BUILDING OCCUPANCY  The Building Regulatory Authority (BRA) shall strictly enforce issuance of “Occupancy Certificate”(as per provision of Dhaka Mahanagar Imarat Bidhimala-2008) after checking thoroughly all relevant reports and certificate from architect, structural engineer, eloctro-mechanical and building services engineers, supervising engineer, etc. employed by the building owner.  Building permit and occupancy certificate should be displayed at some suitable place of the building.  Building permit related information including “Occupancy Certificate” shall be displayed in the website of the Building Regulatory Authority(BRA).
  • 51. RECOMMENDATIONS cont… [E] BUILDING MAINTENANCE & EVALUATION  “Occupancy Certificate” has to be renewed every three years instead of every five years (As prescribed in Dhaka Mahanagar Imarat Bidhimala 2008). BRA shall renew the certificate after inspecting maintenance and occupancy situtuation.  In any reported case of building distress, Building Regulatory Authority(BRA) shall assess the building and take necessary action to ensure safety of the building and its occupants.  Evaluation of existing buildings shall be the responsibility of BRA and shall suggest retrofit measures for vulnerable buildings.
  • 52. ACKNOWLEDGEMENT  Dhaka District Administration  Bangladesh Army  Fire Service and Civil Defense Department  Bangladesh Police  LGED  HBRI  RAJUK  IEB  IAB  Local Volunteers