Project Risk Register is one of the key elements of a project. Risk Register is a critical tool that is being used throughout the project. A Risk Register records all project risks, probability, impact, owner, initial responses and recorded date.
The above presentation talks about the risk involved in any project. The project risk identification, quantification, response and its control is also thoroughly explained.
A risk is defined as “an uncertain event or condition that, if it occurs, has a positive and negative effect on a project’s objectives.” Risk is inherent with any project, and project managers should assess risk continually and develop plan to address them. The risk management plan contains an analysis of likely risks with both high and low impact, as well as mitigation strategies to help the project avoid being derailed should common problems arise. Risk management plans should be periodically reviewed by the project team in order to avoid having the analysis become stale and not reflective of actual potential project risks. Most critical, risk management plans include a risk strategy.
This module on Managing Risk discusses different type of risk that needs to be taken into account by the management while implementing a project. The other topics converged in this module include probability-impact matrix, Risk Quantification; Mitigating/Transferring risk; Risk audits/Review; Sample Risk plan and how to initiate Risk Management Planning.
The above presentation talks about the risk involved in any project. The project risk identification, quantification, response and its control is also thoroughly explained.
A risk is defined as “an uncertain event or condition that, if it occurs, has a positive and negative effect on a project’s objectives.” Risk is inherent with any project, and project managers should assess risk continually and develop plan to address them. The risk management plan contains an analysis of likely risks with both high and low impact, as well as mitigation strategies to help the project avoid being derailed should common problems arise. Risk management plans should be periodically reviewed by the project team in order to avoid having the analysis become stale and not reflective of actual potential project risks. Most critical, risk management plans include a risk strategy.
This module on Managing Risk discusses different type of risk that needs to be taken into account by the management while implementing a project. The other topics converged in this module include probability-impact matrix, Risk Quantification; Mitigating/Transferring risk; Risk audits/Review; Sample Risk plan and how to initiate Risk Management Planning.
The concepts and processes on how to perform project risk management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan risk management, identify risks, perform qualitative & quantitative risks analysis, plan risk responses, implement risk responses, and monitor risks.
Presenting this set of slides with name - Risk Management Module PowerPoint Presentation Slides. The stages in this process are Risk Management Module, Risk Management Framework, Risk Management Structure.
Identify risks and hazards that have the potential to harm any process or project. Use content-ready Risk Assessment PowerPoint Presentation Slides to analyse what can go wrong, how likely it is to happen, what potential consequences are, and how tolerable the identified is. With the help of ready-made risk assessment PowerPoint presentation slideshow, use control measures to eliminate or reduce any potential risk related situation. This deck comprises of various templates to control risks such as types of risks, risk categories, identify the risk categories, stakeholder engagement, stakeholders risk appetite, risk tolerance, procedure, risk management plan, risk register, risk identification, risk assessment, risk analysis, risk response plan, risk response matrix, risk control matrix, risk item tracking, risk impact and probability analysis, risk mitigation strategies, qualitative risk analysis, quantitative risk analysis, risk management process, risk management steps, and more. These templates are completely customizable. You can easily edit the color, text, icon and font size as per your need. Add or remove content, if needed. Grab this easy-to-understand risk assessment PowerPoint templates to figure out what could cause harm to the project, whether the hazards could be eliminated or not, what preventive measures should be taken to control the risks. Download risk assessment PPT slides now to execute the project easily. Behave in a down to earth fashion with our Risk Assessment Powerpoint Presentation Slides. Give them a glimpse of your fact based approach.
Project risk analysis methodology and how RiskyProject software can be used for quantitative project risk analysis.
For more information how to perform schedule risk analysis using RiskyProject software please visit Intaver Institute web site: http://www.intaver.com.
About Intaver Institute.
Intaver Institute Inc. develops project risk management and project risk analysis software. Intaver's flagship product is RiskyProject: project risk management software. RiskyProject integrates with Microsoft Project, Oracle Primavera, other project management software or can run standalone. RiskyProject comes in three configurations: RiskyProject Lite, RiskyProject Professional, and RiskyProject Enterprise.
Risk Management Process And Procedures PowerPoint Presentation SlidesSlideTeam
Every organization needs to adapt to the ever-changing business environment. Sensing this need, we have come up with these content-ready change management PowerPoint presentation slides. These change management PPT templates will help you deal with any kind of an organizational change. Be it with people, goals or processes. The business solutions incorporated here will help you identify the organizational structure, create vision for change, implement strategies, identify resistance and risk, manage cost of change, get feedback and evaluation, and much more. With the help of various change management tools and techniques illustrated in this presentation design, you can achieve the desired business outcomes. This business transition PowerPoint design also covers certain related topics such as change model, transformation strategy, change readiness, change control, project management and business process. By implementing the change control methods mentioned in the presentation, you will be able to have a smooth transition in an organization. So, without waiting much, download our extensively researched change management framework presentation. With our Change Management Presentation slides, understand the need for change and plan to go through it without any hassles.
The concepts and processes on how to perform project risk management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan risk management, identify risks, perform qualitative & quantitative risks analysis, plan risk responses, implement risk responses, and monitor risks.
Presenting this set of slides with name - Risk Management Module PowerPoint Presentation Slides. The stages in this process are Risk Management Module, Risk Management Framework, Risk Management Structure.
Identify risks and hazards that have the potential to harm any process or project. Use content-ready Risk Assessment PowerPoint Presentation Slides to analyse what can go wrong, how likely it is to happen, what potential consequences are, and how tolerable the identified is. With the help of ready-made risk assessment PowerPoint presentation slideshow, use control measures to eliminate or reduce any potential risk related situation. This deck comprises of various templates to control risks such as types of risks, risk categories, identify the risk categories, stakeholder engagement, stakeholders risk appetite, risk tolerance, procedure, risk management plan, risk register, risk identification, risk assessment, risk analysis, risk response plan, risk response matrix, risk control matrix, risk item tracking, risk impact and probability analysis, risk mitigation strategies, qualitative risk analysis, quantitative risk analysis, risk management process, risk management steps, and more. These templates are completely customizable. You can easily edit the color, text, icon and font size as per your need. Add or remove content, if needed. Grab this easy-to-understand risk assessment PowerPoint templates to figure out what could cause harm to the project, whether the hazards could be eliminated or not, what preventive measures should be taken to control the risks. Download risk assessment PPT slides now to execute the project easily. Behave in a down to earth fashion with our Risk Assessment Powerpoint Presentation Slides. Give them a glimpse of your fact based approach.
Project risk analysis methodology and how RiskyProject software can be used for quantitative project risk analysis.
For more information how to perform schedule risk analysis using RiskyProject software please visit Intaver Institute web site: http://www.intaver.com.
About Intaver Institute.
Intaver Institute Inc. develops project risk management and project risk analysis software. Intaver's flagship product is RiskyProject: project risk management software. RiskyProject integrates with Microsoft Project, Oracle Primavera, other project management software or can run standalone. RiskyProject comes in three configurations: RiskyProject Lite, RiskyProject Professional, and RiskyProject Enterprise.
Risk Management Process And Procedures PowerPoint Presentation SlidesSlideTeam
Every organization needs to adapt to the ever-changing business environment. Sensing this need, we have come up with these content-ready change management PowerPoint presentation slides. These change management PPT templates will help you deal with any kind of an organizational change. Be it with people, goals or processes. The business solutions incorporated here will help you identify the organizational structure, create vision for change, implement strategies, identify resistance and risk, manage cost of change, get feedback and evaluation, and much more. With the help of various change management tools and techniques illustrated in this presentation design, you can achieve the desired business outcomes. This business transition PowerPoint design also covers certain related topics such as change model, transformation strategy, change readiness, change control, project management and business process. By implementing the change control methods mentioned in the presentation, you will be able to have a smooth transition in an organization. So, without waiting much, download our extensively researched change management framework presentation. With our Change Management Presentation slides, understand the need for change and plan to go through it without any hassles.
The purpose of this PID was to present a feasible strategy for the commercialization of decommissioning by entering into the consortium and to provide a basis for assessing the overall success of the project.
FREE MANAGEMENT CONSULTING COURSE on www.oeconsulting.be
Operational Excellence Consulting
Project management
A Project is a temporary attempt undertaken to create, adapt or stop a unique product or service. There is a clear definition of what needs to be delivered. It has a start and an end, it is temporary, and it is resulting in something unique and is outside of normal operations.
A project life cycle is a collection of generally sequential and sometimes overlapping project phases.
Feasibility study of the project
Budget Range and estimations
High level planning
High level scope
High level requirements
Start of project management :
Project management plan is the project baseline (budget baseline, scope baseline, schedule baseline). Progress will be measured against the baseline (are we on track ? time? budget?).
Quality assurance on budget, scheduling/timing, governance, risks, reporting, communication, resources, documents, outsourcing, change
If it is not a one-time project, then the procedure must be standardized.
Performance indicators
Lessons learned
Steps for the project manager:
Understanding the context. What is the strategy behind this project. What is the need or business problem/issue? What are the objectives and the success criteria of the project? When can we say that we have reached our goal ? What is the relation between the objectives and the means at your disposal (what is needed to do the project and what is the action plan to develop the missing skills or knowledge) ? What is the level of hostility of the environment?
Setting up logs of the business problem/issue to measure the problem
Defining the scope by gathering data via interviews or brainstorming
Define a project plan with phases (1) analysis phase of current situation “as-is”, (2) proposed solutions phase for the “to-be” situation, (3) implementation phase, and with room for uncertainties (contingency)
Setting up early warning systems (KPI)
What are the risks ? What is the action plan against it? Risk is a feared event that is not predictable. Every risk has a level of probability and a level of impact.
Carrying out the project : making the deliverables (e.g. coding, development, definition of parameters, interface, documentations, testing, prototype, end to end test), communication of it and provide feedback to client.
Project closing: handover, presentation, training.
Problem solving techniques :
Understand the business situation and make a list of the issues with the current situation in well defined activities (organizational issues, cultural issues, personal issues) “as is situation”
Define the most feasible solution or the requirements for the solution “to be situation”
Requirements describe how to develop and specify pieces of work in enough detail to allow them to be successfully implemented by a project team (work breakdown structure)
My presentation slides for a technical dinner presentation I delivered for the PMI\'s Arabian Gulf Chapter in Al-Khobar, KSA, on June 21, 2010.
Yousef Abugosh, PMP
Have you ever wondered what it takes to be a successful project manager? Need to learn how to manage and lead your team on your next project? Are you a team leader or project manager looking for ways to improve your project management skills? Do you need to learn how to manage projects, but don't want to spend months in a classroom?
In this course, you'll learn the fundamentals of project management and leadership through a series of lectures, discussions, and hands-on activities. Project management is a controlled process that manages complex projects and the resources required to complete them.
By the end of the class, you'll have an in-depth understanding of how to lead teams through all stages of a project: planning and organizing; initiating, executing, and controlling; closing out the project. You'll also have the skills necessary and an understanding of how leadership fits into the process of leading your team toward success on any team-based project. This course is designed to help students learn about the difference between project management and leadership and how they can be used in tandem to achieve success.
By the end of this course, you'll feel confident about managing any project or team without getting overwhelmed.
Read| The latest issue of The Challenger is here! We are thrilled to announce that our school paper has qualified for the NATIONAL SCHOOLS PRESS CONFERENCE (NSPC) 2024. Thank you for your unwavering support and trust. Dive into the stories that made us stand out!
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdfTechSoup
In this webinar you will learn how your organization can access TechSoup's wide variety of product discount and donation programs. From hardware to software, we'll give you a tour of the tools available to help your nonprofit with productivity, collaboration, financial management, donor tracking, security, and more.
How to Split Bills in the Odoo 17 POS ModuleCeline George
Bills have a main role in point of sale procedure. It will help to track sales, handling payments and giving receipts to customers. Bill splitting also has an important role in POS. For example, If some friends come together for dinner and if they want to divide the bill then it is possible by POS bill splitting. This slide will show how to split bills in odoo 17 POS.
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
Andreas Schleicher presents at the OECD webinar ‘Digital devices in schools: detrimental distraction or secret to success?’ on 27 May 2024. The presentation was based on findings from PISA 2022 results and the webinar helped launch the PISA in Focus ‘Managing screen time: How to protect and equip students against distraction’ https://www.oecd-ilibrary.org/education/managing-screen-time_7c225af4-en and the OECD Education Policy Perspective ‘Students, digital devices and success’ can be found here - https://oe.cd/il/5yV
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
4. Risk Register Example:
Training Project
S.No Risk Probability Impact Owner Score
1 Training material s not arriving on
time
Medium
5
High
10
Mr. 5 * 10 =
50
2 Computer/ Projector malfunction Low
2
Medium
5
Mr. 2 * 5 =
10
3 Trainer resigns without prior notice Low
2
High
10
Mr. 2 * 10 =
20
4 Training requirement (scope) changes Medium 5 Impact 10 Mr. 50
S.No Risk Probability Impact Owner Score
1 Training material s not arriving on
time
Medium
5
High
10
Mr. 50
2 Training requirement (scope) changes Medium 5 Impact 10 Mr. 50
3 Trainer resigns without prior notice Low
2
High
10
Mr. 20
4 Computer/ Projector malfunction Low
2
Medium
5
Mr. 10
7. Task Analysis
Understand Risk
Management Process
Model
Plan Risk
Define Probability
Criteria - Qualitative
(Low, Medium and High)
Define Probability
Criteria - Quantitative
(Numerical Scale e.g.
Low =2 Medium =5 High
= 10)
Define Impact Criteria -
Qualitative (Low,
Medium and High)
Define Impact Criteria -
Quantitative (Numerical
Scale e.g. Low =2
Medium =5 High = 10)
Perform Brainstorming
Discuss experts and
Underline ideas for
uncertainties
Perform SWOT Analysis
Review Threats further
for Negative Risks
Review Opportunities
further for Positive Risks
Risk Register Template
with Risk, Probability,
Impact, Owner and Score
(Probability * Impact)
Record Negative and
Positive Risks from SWOT
and Brainstorming
Sessions
Assign Risk Owner for
individual risks
Assign Probability and
Impact values for
individual risk
(Qualitative and
Quantitative)
Calculate Risk Score
which is the product of
probability and impact
values
Prioritize risks in
ascending or descending
order of risk scores and
finalize it.