Example Risk Register Example Risk Register.xlsx | WBS 1 2014-04-29, 17:19 WBS_ID Task Task Level Risk Risk Category (Type) Risk Probability Risk Consequenc es (Impact) Initial Risk Score (Probabil. * Impact) Risk Handling Category Risk Handling/Control Plan Risk Owner (Risk Manager) 0 SERVER AND SYSTEM UPGRADE PROJECT 0 Project funding not obtained External, Financial 25% $500,000 $125,000 Accept Cancel the project PM 0 SERVER AND SYSTEM UPGRADE PROJECT 0 Project funds cut External, Financial 50% $250,000 $125,000 Mitigate Re-plan the project with reduced scope PM 0 SERVER AND SYSTEM UPGRADE PROJECT 0 Lack of client or sponsor support External 33% $250,000 $82,500 Accept If it happens, it happens. Deal with it. PM : : 1 INITIATE PROJECT (phase 1) 1.1 Analyze requirements 1.1.1 Contact customer - Start project initiation 3 Customer non-responsive or schedule conflicts External 10% $10,000 $1,000 Mitigate Keep trying to arrange acceptable schedule. PM 1.1.2 Manage project initiation 1.1.3 Engage customer 3 Customer non-responsive or schedule conflicts External 15% $10,000 $1,500 Mitigate Keep trying to arrange acceptable schedule. PM 1.1.3.1 Conduct initial requirements analysis 4 Requirements scope exceeds budget External, Financial 10% $50,000 $5,000 Mitigate Re-plan project for reduced scope. PM 1.1.3.2 Review concept of operations (if any) 1.1.4 Establish integrated cost estimating team 3 Participants non-responsive or schedule conflicts or unable to obtain expertise External 25% $50,000 $12,500 Mitigate Keep trying to arrange acceptable schedule. PM 1.1.5 Conduct joint analysis (a'la JAD) 3 Participants non-responsive or schedule conflicts External 50% $10,000 $5,000 Mitigate Keep trying to arrange acceptable schedule. PM 1.1.5.1 Generate cost estimate 4 Cost estimate exceeds project budget Financial 10% $50,000 $5,000 Mitigate Re-plan project for reduced scope. PM : : 4.3.2 Develop system 4.3.2.1 Precure servers 4 Servers delayed in shipment External 10% $10,000 $1,000 Transfer Insure the shipment Chief engineer 4.3.2.2 Procure/build network 4 Technical difficulties building network Technical 10% $25,000 $2,500 Mitigate Bring in technical experts to assist; delay project if necessary Chief engineer 4.3.2.3 Procure/build databases 4 Technical difficulties buildind databse Technical 10% $10,000 $1,000 Mitigate Bring in technical experts to assist; delay project if necessary DBA : : Example Risk Register (Partial) Example Risk Register Example Risk Register.xlsx | WBS 2 2014-04-29, 17:19 WBS_ID Task Task Level Risk 0 SERVER AND SYSTEM UPGRADE PROJECT 0 Project funding not obtained 0 SERVER AND SYSTEM UPGRADE PROJECT 0 Project funds cut 0 SERVER AND SYSTEM UPGRADE PROJECT 0 Lack of client or sponsor support : : 1 INITIATE PROJECT (phase 1) 1.1 Analyze requirements 1.1.1 Contact customer - Start project initiation 3 Customer non-respon ...