Strengthen data center building to withstand hurricanes
Secondary Risk: Increased construction costs
Acceptance:
Do nothing, accept loss if hurricane hits
Residual Risk: Loss of data center still possible
Situation: Company’s data center is in a hurricane zone.
Risk: Loss of data center after major storm.
Options: What are they?
Strategies for Negative Risks (Threats)
39
Strategies for Positive Risks (Opportunities)
Exploitation:
Sharing:
Enhancement:
Acceptance:
Situation: New technology may reduce project costs
Risk: Cost savings opportunity
Options: What are they?
40
Strategies