This document defines and documents a project to design and build a Recreational Station at Taylor's University by August 2018. It introduces the client, project goals and scope. It provides background on TWY Consultants, the project management company, including their organization chart and profiles of key team members from various disciplines. It also reviews case studies of similar shipping container projects for reference. The document outlines the project work breakdown by phases for scheduling and risk management. It presents preliminary site analysis and the initial design concept. It provides an overview of subsequent sections that will cover landscape design, civil and structural engineering, mechanical and electrical systems, costing, and conclusions.
Project Management Project 1 Report: Defining & Documenting A Project
Ft. Tamarind Square, Kuala Lumpur ,Malaysia (A project from Castmet Sdn. Bhd. and etc.)
This document outlines the roles and responsibilities of the project team involved in the 9 unit Kuarters dan Menaiktaraf Masjid Saidina Abu Bakar AS-Siddiq project. It includes the project manager overseeing planning, scheduling, budgeting, and monitoring progress. The architect is responsible for design drawings and advising throughout implementation. Other roles include the landscape architect, quantity surveyor, civil and structural engineers, and mechanical and electrical engineers, all providing specialized services and working closely together.
The document provides plans and details for a case study of the building services at the New PAM Centre in Bangsar, Kuala Lumpur. It includes floor plans for 6 levels of the building as well as sections on the methodology, fire protection systems, mechanical ventilation, air conditioning, mechanical transportation, and mechanical parking systems. The case study examines both the active and passive fire safety systems, various mechanical ventilation components, the variable refrigerant flow air conditioning system, elevator systems, and the type of mechanical parking system used in the building.
This document outlines the phases and tools used to manage the HighPark Suites project in Kelana Jaya, Malaysia. It includes defining the roles of project team members, developing a work breakdown structure and schedule, identifying stakeholders, and describing the key phases of schematic design, design development, documentation, construction, and final completion. The goal is to complete the project on time, on budget, and meeting quality standards through careful planning and coordination of all involved parties.
The document provides details on the proposed design of a service apartment building consisting of 2 towers - Tower A and Tower B. It includes 38 storeys with a total of 404 residential units. It will have 7 levels of podium including facilities, 2 basement levels, and ground floor. Bored piling and post-tensioned slabs will be used as the foundation and flooring construction methods. The finishes proposed include granite, tiles, and painted plaster/render. Rainwater harvesting and clay facade are part of the sustainable design features.
This document defines the project team for the O'Hako Residence development project in Puchong, Malaysia. The project team includes a project manager from Puls PM Consultant S.B., architects from Verge Architects, mechanical and electrical consultants from YG Ung Consultant, civil and structural consultants from D&O Konsultant S.B. and an initial consultant Perunding Reka Cekap S.B., quantity surveyor consultants from DK-QS Sdn.Bhd and an initial consultant, landscape architects from Engky Design S.B., and the main contractor PEMBINAAN INFRA E&J S.B. The document outlines the roles and responsibilities of each
Methods of Documentation and Measured Drawingkimberleyee95
This document is a report submitted by 14 students from Taylor's University for their subject on documentation and measured drawings. It details their group project documenting the architectural features of three shophouses - No. 3, 5, and 7 Lorong Ikan in George Town, Penang. The report includes over 80 figures of drawings, diagrams and photos taken during their site visit and documentation of the shophouses. It provides information on the architectural styles, building materials, spatial layout and other characteristics of the conserved shophouses. The group expresses gratitude to those who helped and supported their project work.
Project Management Project 1 Report: Defining & Documenting A Project
Ft. Tamarind Square, Kuala Lumpur ,Malaysia (A project from Castmet Sdn. Bhd. and etc.)
This document outlines the roles and responsibilities of the project team involved in the 9 unit Kuarters dan Menaiktaraf Masjid Saidina Abu Bakar AS-Siddiq project. It includes the project manager overseeing planning, scheduling, budgeting, and monitoring progress. The architect is responsible for design drawings and advising throughout implementation. Other roles include the landscape architect, quantity surveyor, civil and structural engineers, and mechanical and electrical engineers, all providing specialized services and working closely together.
The document provides plans and details for a case study of the building services at the New PAM Centre in Bangsar, Kuala Lumpur. It includes floor plans for 6 levels of the building as well as sections on the methodology, fire protection systems, mechanical ventilation, air conditioning, mechanical transportation, and mechanical parking systems. The case study examines both the active and passive fire safety systems, various mechanical ventilation components, the variable refrigerant flow air conditioning system, elevator systems, and the type of mechanical parking system used in the building.
This document outlines the phases and tools used to manage the HighPark Suites project in Kelana Jaya, Malaysia. It includes defining the roles of project team members, developing a work breakdown structure and schedule, identifying stakeholders, and describing the key phases of schematic design, design development, documentation, construction, and final completion. The goal is to complete the project on time, on budget, and meeting quality standards through careful planning and coordination of all involved parties.
The document provides details on the proposed design of a service apartment building consisting of 2 towers - Tower A and Tower B. It includes 38 storeys with a total of 404 residential units. It will have 7 levels of podium including facilities, 2 basement levels, and ground floor. Bored piling and post-tensioned slabs will be used as the foundation and flooring construction methods. The finishes proposed include granite, tiles, and painted plaster/render. Rainwater harvesting and clay facade are part of the sustainable design features.
This document defines the project team for the O'Hako Residence development project in Puchong, Malaysia. The project team includes a project manager from Puls PM Consultant S.B., architects from Verge Architects, mechanical and electrical consultants from YG Ung Consultant, civil and structural consultants from D&O Konsultant S.B. and an initial consultant Perunding Reka Cekap S.B., quantity surveyor consultants from DK-QS Sdn.Bhd and an initial consultant, landscape architects from Engky Design S.B., and the main contractor PEMBINAAN INFRA E&J S.B. The document outlines the roles and responsibilities of each
Methods of Documentation and Measured Drawingkimberleyee95
This document is a report submitted by 14 students from Taylor's University for their subject on documentation and measured drawings. It details their group project documenting the architectural features of three shophouses - No. 3, 5, and 7 Lorong Ikan in George Town, Penang. The report includes over 80 figures of drawings, diagrams and photos taken during their site visit and documentation of the shophouses. It provides information on the architectural styles, building materials, spatial layout and other characteristics of the conserved shophouses. The group expresses gratitude to those who helped and supported their project work.
The document discusses Building Information Modeling (BIM) and its various dimensions ranging from 3D to 7D modeling. It provides details on the services, software, advantages and disadvantages of each dimension. The 3D model refers to visualization and clash detection. 4D adds a time component for construction planning and scheduling. 5D enables cost estimation and quantity take-off. 6D performs energy consumption analysis during design and operation. 7D covers facility management. The document is a group project report submitted by students for their Construction Supply Chain Management course that analyzes how each BIM dimension benefits supply chain management.
This document provides instructions for Architecture Design Studio 1 Project 3, which asks students to design a "dreamspace" or hideout for a predetermined user. The space must fit within given dimensions on an empty lot between two existing buildings. Students must consider the user's personality, body type, activities and needs to design an attached interior space. The project involves developing a narrative about the user, exploring design concepts, and presenting final plans, sections, perspectives and a 1:50 scale model showing how the hideout integrates with the site and buildings. Submissions will be evaluated based on functionality for the user, form articulation, quality of drawings and models, and evidence of the design process.
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...Angeline KH
Measuring these shop houses for conservation purposes the condition of the shop houses as well as their architectural development are analyzed and recorded.
BSC (H) ARCHITECTURE DEGREE SEM 4.5 INTERNSHIP REPORT FINALjolynnTJL
Tan Jo Lynn completed an internship with Unit One Design Sdn. Bhd. The report summarizes her experiences in various roles including programming schedules, 3D modeling, site visits, measurements, and contract documentation. She learned skills like using SketchUp, observing client interactions, drafting reflected ceiling plans, and producing tender drawings. The internship provided opportunities to apply classroom knowledge and gain exposure to real work in an architecture firm.
Architects Professional Liability
Whether a small architecture enterprise or a multinational million dollar conglomerate, the work of architects and engineers is constantly under the spotlight. No matter how careful and exact an architect or engineer is, their work is constantly scrutinized by clients, leaving the chance of facing a lawsuit alleging negligence or failure to render professional services. Working in an industry that continues to feel the negative effects of the economy, architects and engineers cannot afford to take this risk - and that is where we can help.
This document provides a case study and documentation of the building services systems at Wisma Lembaga Jurukur Tanah in Kuala Lumpur, Malaysia. It examines the fire protection system, air conditioning system, mechanical ventilation system, electricity supply system, and mechanical transportation system. For the fire protection system, the document analyzes the active fire protection components including the fire detection systems, fire alarm bells, horn loudspeakers, and fire control room. It provides details on the types of components used and their functions based on literature reviews and findings from the field study of Wisma Lembaga Jurukur Tanah.
The document discusses the traditional procurement method for construction projects. It begins by outlining the key aspects of the traditional method, including that the client hires consultants to handle design, cost control, and administration, while a contractor is hired to carry out the construction works. It then discusses the advantages and disadvantages of the traditional method based on a client's request to build a RM1.2 billion hotel and shopping complex within 5 years while maintaining full design control and minimal variations. The document recommends using the traditional method to meet the client's needs and control over the project. It provides a timeline and overview of risks associated with the traditional procurement approach.
The document outlines the design development process for the Taylor's Recreation Station project. It includes sections on architectural, interior, landscape, civil and structural, mechanical and electrical designs. It also includes project management aspects such as the work breakdown structure, table of dependencies, PERT chart and Gantt chart which outline the project timeline and dependencies between tasks from schematic design to final completion.
This report summarizes the documentation and research of the Sin Sze Si Ya Temple in Kuala Lumpur, Malaysia by 27 architecture students. It describes the temple's historical and cultural significance, including its role in reconciling warring groups in the city's founding years. The students measured the temple to document its structure and spaces. They also researched the temple's rituals, activities, hierarchy of deities, and how it responds to the cultural needs of its users. The report aims to provide an understanding of the temple from architectural, historical, and cultural perspectives.
The document provides details about Dewan Tunku Canselor (DTC) at University of Malaya. It discusses the building's history, architect, site context, and surrounding area. DTC was constructed in 1965-1966 in a Brutalist architectural style influenced by Le Corbusier. It serves as the convention center for University of Malaya and is located in the center of the campus surrounded by educational and commercial buildings within 100m to provide convenience. The site context analysis examines accessibility, relation to the natural environment, and comparison to surrounding structures.
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
The document discusses industrialized building systems (IBS) and provides a case study of Seri Jati Apartments in Setia Alam, Malaysia.
[1] It introduces IBS, including the main types used in Malaysia like precast concrete, blockwork, and steel framing systems, and discusses advantages like reduced costs and time as well as disadvantages like high initial costs.
[2] A case study of Seri Jati Apartments is presented, which utilized a precast concrete structural frame with in-situ concrete floors. Standard component sizes, construction processes, and drawings are shown.
[3] The architectural and structural drawings of the proposed IBS building are provided, along with
The document provides an analysis of the Menara Tabung Haji building in Kuala Lumpur, Malaysia. It discusses the building's site context, architectural layout, construction, and various architectural elements. The building takes the form of an hourglass to symbolize spiritual enlightenment from pilgrimage. It uses Islamic architectural influences like five pillars representing the five pillars of Islam. The 152m tall building consists mainly of offices and parking. Precast concrete and glass were the main materials used in its construction. The building combines traditional Malaysian elements with modern design.
DEWAN TUNKU CANSELOR, UNIVERSITI MALAYAJoe Onn Lim
Dewan Tunku Canselor is an iconic building at University Malaya designed in the Brutalist style by Datuk Kington Loo. The building uses reinforced concrete as its primary material and features exposed concrete surfaces that reveal the wooden forms used in construction. It has a symmetrical layout and uses geometry like rectangles and circles. Natural light penetrates through windows and skylights. The building was inspired by Le Corbusier's works and uses similar concrete louvers to aid ventilation in Malaysia's tropical climate.
Stadium Negara is the first indoor stadium built in Malaysia, located in Kuala Lumpur. It was designed by the Public Works Department and constructed between 1960-1962 at a cost of RM34 million. The original roof structure spanned 300 feet without columns, but it was replaced in the 1980s with a domed roof. The stadium has hosted many sporting and cultural events over the years and was designated a national heritage building in 2003 for its architectural and historical significance.
Asian Architecture - Telegraph Poles House Case Study ReportAlfred Tan
Telegraph Poles House in Langkawi acts as an example of passive design architecture adapted for the tropical climate of Malaysia. It is built on stilts with an open floor plan and large overhanging roof to promote cross ventilation. Reclaimed materials like telegraph poles and salvaged wood are used for the structure and roof to reduce environmental impact. The orientation, surrounding vegetation, and design features allow for passive cooling through airflow while achieving thermal comfort for occupants.
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
The document discusses two issues regarding a construction contract:
1) Whether a contractor is entitled to an extension of time if a project is suspended by a stop work order from local authorities. The answer depends on whether the stop work was due to the contractor's fault.
2) Whether an employer can take over a project from the contractor and appoint a third party to finish without terminating the original contract. Generally no, unless the contract allows termination for convenience or there is a breach by the contractor. Simply facing delays does not allow the employer to replace the contractor.
Project Management Essentials for Engineers and Architects explains basic project management principles and illustrates how to manage and align technology projects for success.
Architecture Culture & History 2_Project_02_Web bookWinnie Ang
The TNB Headquarters building in Kuala Lumpur has 11 floors that house various functions for TNB staff. The building was constructed in the 1960s and has undergone renovations while maintaining its original exterior design. Spatially, the building contains offices on each floor organized around a central spiral staircase. Floors are designated for different departments, with executive offices on upper floors and more public functions like reception on the lower floors.
The contractor submitted a final claim for a variation order totalling RM55,000 for excavating 100m3 of rock. The original bill of quantities stated 10m3 of rock excavation priced at RM50/m3. However, there was a mistake in the original pricing and the quantity was significantly understated. As such, the quantity surveyor can value the variation using fair market rates to compensate the contractor for additional expenses incurred due to the mistake and change in quantity, as allowed for under the contract terms.
Building science report [malaysia] finalmiranazrin
The document summarizes the passive green design features of the DiGi Technology Operations Centre in Malaysia. Key features include extensive vegetated green walls that filter air, reduce solar heat gain, and provide acoustic insulation. A low-e curtain wall system allows daylight penetration while minimizing heat transfer. While the building orientation is not ideal, strategies like glazing and overhangs help induce daylight and reduce solar heat gain on the eastern and western facades. Evapotranspiration from the green walls helps cool surrounding air for ventilation.
Project Management - Recreation District in Taylor's University Subang JayaJoe Onn Lim
The proposed recreational district at Taylor's University Lakeside Campus aims to provide indoor and outdoor activities for students and staff to unwind. It will be located at Site B, an open parking area next to the Syopz Mall.
The design focuses on sustainability through green features like a green trellis facade, rainwater harvesting, and maximizing natural ventilation. It aims to be completed by August 2018 for under RM1.5 million on the existing land size of around 600 square meters.
The preliminary studies found the current site to be barren, hot and uncomfortable. The design will address this through adding more vegetation, shade and improving the road surface. An environmentally friendly design using sustainable systems and requiring low maintenance is
Project Management (Project 1 - Defining and documenting a project) Presentat...Tan Jaden
The document provides details of a proposed project by TWY Consultants to develop a recreation station and architectural workshop at Taylor's University. It includes information on the company background, team members, design concept, and project management plans. The team aims to complete the project within 1 year with a budget of RM1.5M, utilizing shipping containers to take advantage of their modular and durable properties. Site analysis found its strategic location near campus entrances is a strength but environmental threats will require mitigation.
The document discusses Building Information Modeling (BIM) and its various dimensions ranging from 3D to 7D modeling. It provides details on the services, software, advantages and disadvantages of each dimension. The 3D model refers to visualization and clash detection. 4D adds a time component for construction planning and scheduling. 5D enables cost estimation and quantity take-off. 6D performs energy consumption analysis during design and operation. 7D covers facility management. The document is a group project report submitted by students for their Construction Supply Chain Management course that analyzes how each BIM dimension benefits supply chain management.
This document provides instructions for Architecture Design Studio 1 Project 3, which asks students to design a "dreamspace" or hideout for a predetermined user. The space must fit within given dimensions on an empty lot between two existing buildings. Students must consider the user's personality, body type, activities and needs to design an attached interior space. The project involves developing a narrative about the user, exploring design concepts, and presenting final plans, sections, perspectives and a 1:50 scale model showing how the hideout integrates with the site and buildings. Submissions will be evaluated based on functionality for the user, form articulation, quality of drawings and models, and evidence of the design process.
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...Angeline KH
Measuring these shop houses for conservation purposes the condition of the shop houses as well as their architectural development are analyzed and recorded.
BSC (H) ARCHITECTURE DEGREE SEM 4.5 INTERNSHIP REPORT FINALjolynnTJL
Tan Jo Lynn completed an internship with Unit One Design Sdn. Bhd. The report summarizes her experiences in various roles including programming schedules, 3D modeling, site visits, measurements, and contract documentation. She learned skills like using SketchUp, observing client interactions, drafting reflected ceiling plans, and producing tender drawings. The internship provided opportunities to apply classroom knowledge and gain exposure to real work in an architecture firm.
Architects Professional Liability
Whether a small architecture enterprise or a multinational million dollar conglomerate, the work of architects and engineers is constantly under the spotlight. No matter how careful and exact an architect or engineer is, their work is constantly scrutinized by clients, leaving the chance of facing a lawsuit alleging negligence or failure to render professional services. Working in an industry that continues to feel the negative effects of the economy, architects and engineers cannot afford to take this risk - and that is where we can help.
This document provides a case study and documentation of the building services systems at Wisma Lembaga Jurukur Tanah in Kuala Lumpur, Malaysia. It examines the fire protection system, air conditioning system, mechanical ventilation system, electricity supply system, and mechanical transportation system. For the fire protection system, the document analyzes the active fire protection components including the fire detection systems, fire alarm bells, horn loudspeakers, and fire control room. It provides details on the types of components used and their functions based on literature reviews and findings from the field study of Wisma Lembaga Jurukur Tanah.
The document discusses the traditional procurement method for construction projects. It begins by outlining the key aspects of the traditional method, including that the client hires consultants to handle design, cost control, and administration, while a contractor is hired to carry out the construction works. It then discusses the advantages and disadvantages of the traditional method based on a client's request to build a RM1.2 billion hotel and shopping complex within 5 years while maintaining full design control and minimal variations. The document recommends using the traditional method to meet the client's needs and control over the project. It provides a timeline and overview of risks associated with the traditional procurement approach.
The document outlines the design development process for the Taylor's Recreation Station project. It includes sections on architectural, interior, landscape, civil and structural, mechanical and electrical designs. It also includes project management aspects such as the work breakdown structure, table of dependencies, PERT chart and Gantt chart which outline the project timeline and dependencies between tasks from schematic design to final completion.
This report summarizes the documentation and research of the Sin Sze Si Ya Temple in Kuala Lumpur, Malaysia by 27 architecture students. It describes the temple's historical and cultural significance, including its role in reconciling warring groups in the city's founding years. The students measured the temple to document its structure and spaces. They also researched the temple's rituals, activities, hierarchy of deities, and how it responds to the cultural needs of its users. The report aims to provide an understanding of the temple from architectural, historical, and cultural perspectives.
The document provides details about Dewan Tunku Canselor (DTC) at University of Malaya. It discusses the building's history, architect, site context, and surrounding area. DTC was constructed in 1965-1966 in a Brutalist architectural style influenced by Le Corbusier. It serves as the convention center for University of Malaya and is located in the center of the campus surrounded by educational and commercial buildings within 100m to provide convenience. The site context analysis examines accessibility, relation to the natural environment, and comparison to surrounding structures.
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
The document discusses industrialized building systems (IBS) and provides a case study of Seri Jati Apartments in Setia Alam, Malaysia.
[1] It introduces IBS, including the main types used in Malaysia like precast concrete, blockwork, and steel framing systems, and discusses advantages like reduced costs and time as well as disadvantages like high initial costs.
[2] A case study of Seri Jati Apartments is presented, which utilized a precast concrete structural frame with in-situ concrete floors. Standard component sizes, construction processes, and drawings are shown.
[3] The architectural and structural drawings of the proposed IBS building are provided, along with
The document provides an analysis of the Menara Tabung Haji building in Kuala Lumpur, Malaysia. It discusses the building's site context, architectural layout, construction, and various architectural elements. The building takes the form of an hourglass to symbolize spiritual enlightenment from pilgrimage. It uses Islamic architectural influences like five pillars representing the five pillars of Islam. The 152m tall building consists mainly of offices and parking. Precast concrete and glass were the main materials used in its construction. The building combines traditional Malaysian elements with modern design.
DEWAN TUNKU CANSELOR, UNIVERSITI MALAYAJoe Onn Lim
Dewan Tunku Canselor is an iconic building at University Malaya designed in the Brutalist style by Datuk Kington Loo. The building uses reinforced concrete as its primary material and features exposed concrete surfaces that reveal the wooden forms used in construction. It has a symmetrical layout and uses geometry like rectangles and circles. Natural light penetrates through windows and skylights. The building was inspired by Le Corbusier's works and uses similar concrete louvers to aid ventilation in Malaysia's tropical climate.
Stadium Negara is the first indoor stadium built in Malaysia, located in Kuala Lumpur. It was designed by the Public Works Department and constructed between 1960-1962 at a cost of RM34 million. The original roof structure spanned 300 feet without columns, but it was replaced in the 1980s with a domed roof. The stadium has hosted many sporting and cultural events over the years and was designated a national heritage building in 2003 for its architectural and historical significance.
Asian Architecture - Telegraph Poles House Case Study ReportAlfred Tan
Telegraph Poles House in Langkawi acts as an example of passive design architecture adapted for the tropical climate of Malaysia. It is built on stilts with an open floor plan and large overhanging roof to promote cross ventilation. Reclaimed materials like telegraph poles and salvaged wood are used for the structure and roof to reduce environmental impact. The orientation, surrounding vegetation, and design features allow for passive cooling through airflow while achieving thermal comfort for occupants.
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
The document discusses two issues regarding a construction contract:
1) Whether a contractor is entitled to an extension of time if a project is suspended by a stop work order from local authorities. The answer depends on whether the stop work was due to the contractor's fault.
2) Whether an employer can take over a project from the contractor and appoint a third party to finish without terminating the original contract. Generally no, unless the contract allows termination for convenience or there is a breach by the contractor. Simply facing delays does not allow the employer to replace the contractor.
Project Management Essentials for Engineers and Architects explains basic project management principles and illustrates how to manage and align technology projects for success.
Architecture Culture & History 2_Project_02_Web bookWinnie Ang
The TNB Headquarters building in Kuala Lumpur has 11 floors that house various functions for TNB staff. The building was constructed in the 1960s and has undergone renovations while maintaining its original exterior design. Spatially, the building contains offices on each floor organized around a central spiral staircase. Floors are designated for different departments, with executive offices on upper floors and more public functions like reception on the lower floors.
The contractor submitted a final claim for a variation order totalling RM55,000 for excavating 100m3 of rock. The original bill of quantities stated 10m3 of rock excavation priced at RM50/m3. However, there was a mistake in the original pricing and the quantity was significantly understated. As such, the quantity surveyor can value the variation using fair market rates to compensate the contractor for additional expenses incurred due to the mistake and change in quantity, as allowed for under the contract terms.
Building science report [malaysia] finalmiranazrin
The document summarizes the passive green design features of the DiGi Technology Operations Centre in Malaysia. Key features include extensive vegetated green walls that filter air, reduce solar heat gain, and provide acoustic insulation. A low-e curtain wall system allows daylight penetration while minimizing heat transfer. While the building orientation is not ideal, strategies like glazing and overhangs help induce daylight and reduce solar heat gain on the eastern and western facades. Evapotranspiration from the green walls helps cool surrounding air for ventilation.
Project Management - Recreation District in Taylor's University Subang JayaJoe Onn Lim
The proposed recreational district at Taylor's University Lakeside Campus aims to provide indoor and outdoor activities for students and staff to unwind. It will be located at Site B, an open parking area next to the Syopz Mall.
The design focuses on sustainability through green features like a green trellis facade, rainwater harvesting, and maximizing natural ventilation. It aims to be completed by August 2018 for under RM1.5 million on the existing land size of around 600 square meters.
The preliminary studies found the current site to be barren, hot and uncomfortable. The design will address this through adding more vegetation, shade and improving the road surface. An environmentally friendly design using sustainable systems and requiring low maintenance is
Project Management (Project 1 - Defining and documenting a project) Presentat...Tan Jaden
The document provides details of a proposed project by TWY Consultants to develop a recreation station and architectural workshop at Taylor's University. It includes information on the company background, team members, design concept, and project management plans. The team aims to complete the project within 1 year with a budget of RM1.5M, utilizing shipping containers to take advantage of their modular and durable properties. Site analysis found its strategic location near campus entrances is a strength but environmental threats will require mitigation.
The document provides details about a proposed project by TWY Consultants to develop a recreation station and architectural workshop at Taylor's University. It includes information about the company background, team members, project scope and requirements, site analysis, design concept, and container studies. The team aims to complete the project within 1 year with a budget of RM1.5M utilizing shipping containers and 50% renewable energy.
The document provides information on the proposed project of building a pavilion at Taylor's University to display students' architectural designs. It introduces the client, scope, and objectives of the project. It also outlines the background and qualifications of the various consultants that will be involved, including the project manager, architect, landscape architect, structural engineer, and mechanical & electrical engineer. The document includes case studies and figures to support the project proposal.
This document provides details on a proposed recreational district pavilion project at Taylor's University Lakeside Campus. Key points:
- The project involves constructing a recreational facility using shipping containers on a 600m2 site currently used as a parking area.
- The facility will include indoor and outdoor recreation spaces, a lounge, cafeteria, offices, and other amenities to accommodate workshops and events.
- Sustainability is a priority, requiring reuse of materials and renewable energy sources like solar power.
- Initial site analysis was conducted to understand the context and constraints. Container structures were selected for their modular design and quick assembly.
- A project team is assembled with defined roles for architects, engineers, landscape
TW Landscaping Sdn Bhd is a landscape architecture and design firm founded in 2000 by Cheah Teck Wei, a registered landscape architect. The company provides comprehensive landscape design, construction, and maintenance services with a focus on creating innovative and engaging outdoor spaces. It has completed several residential and commercial projects across Malaysia. Cheah leads a team that includes other landscape architects, architects, administrators, and financial staff to handle all phases of a project from initial consultation through construction administration.
This document outlines a proposed project to build a shopping mall called "SMART" near Taylor's University Lakeside Campus. It will provide an easier place for students to buy and prepare food at cheaper prices. The project aims to use land wisely, improve campus services, and increase attractiveness. A project management team is assembled consisting of an architect, landscape architect, civil engineer, contractor, and quantity surveyor. Each team member's roles and objectives are defined. Potential risks to the project are identified, such as flooding from the site's location beside a lake. The success criteria for the project are completing it on time and within budget with an encouraging plan.
This document provides details on the proposed development of a recreation district at the commercial block carpark of Taylor's University in Subang Jaya, Selangor. It outlines the project brief, success criteria, implementation plan, constraints, and management strategies. The project involves converting 600 sqm of the existing carpark into a two-storey recreation facility containing offices, lounges, toilets, recreation areas, a cafeteria, and magazine corner. The design will utilize repurposed shipping containers and emphasize low-energy features, natural ventilation, lighting, and rainwater harvesting.
The document provides profiles for the project team members working on Taylor's University Container Pavilion Project. It introduces 7 key members, including their professional backgrounds, qualifications, education, and experience. The members include architects, a landscape architect, and an interior architect from 3 different consulting firms: One Associates, P&F Engineering, and MBC QS Consultancy.
The document provides profiles for the project team members working on Taylor's University Container Pavilion Project. It introduces 7 key members, including their professional backgrounds, qualifications, education, and experience. The members include architects, a landscape architect, and an interior architect from 1Associates and P&F Engineering.
This document provides a final project management report for a mixed-use development project in Johor Bahru, Malaysia. It includes sections on the project introduction and objectives, site analysis, proposed design and programs, project viability, procurement process, risk analysis and mitigation strategies, maintenance plans, success criteria, work breakdown structure, and Gantt chart. The project aims to restore the meaning of "work" by providing a space for work, leisure and community activities that promotes positive social impact and keeps people in the area.
This document defines and documents a project for the development of a recreation district. It includes an introduction with the project briefing, company background and organizational chart. It then outlines the scope of works for various roles including the project manager, architect, civil & structural engineer, mechanical & electrical engineer, quantity surveyor, and landscape architect. It also includes sections on project management, architectural proposal, civil & structural works, mechanical & electrical engineering, quantity survey, and conclusion.
Architectural design project module outline august 2016Preston Liew
The document outlines the module for the Architectural Design Project, which is the capstone project for the Bachelor of Science (Honours) in Architecture programme. The module focuses on designing a building to address a social issue through integrating technology, environment, and cultural context. Students will develop a design strategy and detailed design for a site in Putrajaya, Malaysia, addressing the theme of establishing Malaysian identity in contemporary architectural design.
The document summarizes Foo Shi-Ko's 3-month internship at Haipo Architects (HPA) in Shanghai, China. It details tasks completed during different project phases. In the schematic design phase for the Qiantan 10-01 mixed-use development, Foo attended client meetings and helped address issues in the initial design concept to comply with regulations. Professionals from HPA presented modifications needed for utilities, structure, and more. Foo also witnessed design presentations and discussions between the client and various consultants to refine the project.
project management, documenting architect This involves the documentation of your Studio Vl Architectural Design Project, to apply the principles learned in
Assignment 1 to your final project. Students from Design Studio lV or V will use their design in Studio lV or V for
the study Your task is to document your own Design Studio Project from the point of view of an Architect, commissioned to
undertake this project.
This document is an internship report submitted by Nadia Othman to Garis Architects detailing her 2 month internship experience. During her internship, she worked on several projects including an MRT transit hub project, amendments to tender drawings for a clubhouse, and conceptual design of a pavilion for a service apartment building. She gained experience with CAD, 3D modeling, working to tight deadlines, and observing the project management process. The internship provided valuable hands-on learning about the real work of an architect.
This document provides details of a proposed recreational station project for a university, including:
1. The client, Taylor's Management, has approached the architectural firm Wabi Sabi Associates to design and build a recreational station for students by August 2018 on an existing parking site.
2. The project objectives, budget of RM1.5 million, and requirements including recreational and operational facilities are outlined.
3. The project management plan includes success criteria focusing on being on time and on budget, a work breakdown structure dividing tasks among architects, landscape architects, civil/structural engineers and MEP engineers, and a Gantt chart and PERT chart to monitor schedule and risks.
4. Details of the
The document provides details of an architectural project to design a pavilion using shipping containers at Taylor's Lakeside University. It includes an introduction to the client, project brief, site analysis, and profiles of the project team members from CreaDev Design Sdn Bhd who are managing the project. The project team includes an architect, civil and structural engineer, mechanical and electrical engineer, quantity surveyor, landscape architect, and interior designer.
PROJECT MANAGEMENT PROJECT 1-A PLACE FOR ALLCrysmond Goh
This document provides details for the Contena Pavilion project, including an introduction to the client and project requirements, company and team member profiles, and preliminary studies. CreaDev Design Sdn Bhd was commissioned by Taylor's University to design and build a pavilion using shipping containers to house architecture models and serve up to 150 people. The project team includes architects, engineers, a quantity surveyor, and landscape architect. Site analysis identifies opportunities for natural light and ventilation.
This document provides details for the Contena Pavilion project, including an introduction to the client and project requirements, company and team member profiles, and preliminary studies. CreaDev Design Sdn Bhd was commissioned by Taylor's University to design and build a pavilion using shipping containers to house architecture models and serve up to 150 people. The project team includes architects, engineers, a quantity surveyor, and landscape architect. Site analysis identifies adequate sunlight and natural ventilation. Profiles describe the team members' qualifications and responsibilities.
Similar to Project Management (Project 1 - Defining and documenting a project) (20)
Project Management (Project 2 - Documentation of a medium-sized project)Tan Jaden
The document provides details of a project proposal for a Traditional Games and Recreation Park in Taman Tasik Titiwangsa, Kuala Lumpur. It includes a project introduction outlining the project brief, site context, objectives and goals. A design analysis through SWOT and PESTLE is presented. The proposed programme includes a mix of traditional, present and future recreational activities. Stakeholders include the Ministry of Youth and Sports, Tourism Malaysia and Kuala Lumpur City Hall. Design sustainability strategies incorporate activities within the landscape, a green roof, and a feature wall. The massing and layout maximize green space while minimizing building footprint.
Architectural Design Project (Project 1C- Final Executive Report)Tan Jaden
This document provides an executive report for a project to design a traditional games and recreation park in Taman Tasik Titiwangsa, Kuala Lumpur. It includes an introduction to the project, aims and objectives, site context analysis, and environmental and design strategies. The project aims to revive traditional Malaysian games, add more activities to the park, and improve community recreation. Site analyses identify opportunities and issues, such as a lack of connectivity between residential and institutional areas. Design strategies will incorporate site studies, programming, sustainability concepts, and technological resolutions.
The document discusses two potential sites, Site 1 and Site 4, for a new development in Titiwangsa, Kuala Lumpur. It analyzes the context, restrictions, users and activities, and precedents to inform the design. Site 1 has multiple ingress points but is exposed, while Site 4 has a single entry point but lacks a central node. Precedent projects like Fala Park in Poland and a gym in China are examined for how they promote activity and engagement through their programming and spatial arrangements.
Food and Culture assignment 1B experience & capture group presentationTan Jaden
The document discusses several aspects of food preparation and consumption in various locations in Malaysia. It examines the flow of food preparation in different local cuisines and compares the experiences between an open kitchen and closed kitchen setup. Several studies analyze how factors like lighting, crowd levels, table spacing and food quality can impact the dining experience. The effects of seeing the food preparation process and having an open display area are also considered. In conclusion, food quality appears to have the greatest influence on customer satisfaction compared to other environmental factors.
Food and Culture assignment 1A research proposalTan Jaden
Tan Wen Hao proposes research on how food quality and dining environment affect customer satisfaction in restaurants. He will conduct interviews and experiments with 10 consumers visiting 2 oppositional restaurants, one with good atmosphere but poor food, the other average atmosphere but good food. Surveys will also be used to determine which factor, food or environment, most influences customer preferences and return visits. The results could help restaurant owners improve their businesses and guide industry trends towards prioritizing quality food over superficial attributes.
Theories of Architecture and Urbanism Project Part 2Tan Jaden
This document compares the urban spaces of Jalan Tuanku Abdul Rahman in Kuala Lumpur and Central Hong Kong. It finds that Central Hong Kong has a more permeable pedestrian environment with blurred boundaries between different land uses, supporting a variety of daily social activities. In contrast, Jalan TAR has a more planned separation of uses with less organic social interaction. Both spaces show an evolution from traditional shophouses to modern development, but Central Hong Kong has found a way to better integrate the old and new in a living city.
Building Science 2 Project 2 Integration projectTan Jaden
This document contains a lighting analysis and proposal for two community library spaces (Spaces A and B). For Space A, the average daylight factor is calculated to be 4.6%, providing adequate natural light. Artificial lighting is proposed using suspended LED luminaires in three zones, controlled individually. For Space B, the average daylight factor is 3.1%. Artificial lighting using recessed CFL downlights and LED uplights is proposed, with the two types controlled separately for different functions. Layout diagrams and illuminance renderings are provided to illustrate the lighting schemes.
This document provides details on the design of a proposed community library, including precedent studies, facade and structural system proposals, and sectional perspectives. Precedent studies explore twisting textile facades, expanded metal mesh corridors, polycarbonate multiwall roofs, and hybrid masonry structural systems. Two facade scheme proposals are presented with front and rear elevations. Sectional perspectives from the ground floor to first floor and third floor to roof illustrate the structural system integrating a composite steel deck floor, reinforced masonry panels, and polycarbonate roofing. References are provided on the researched design elements.
This document outlines the terms and conditions for a rental agreement between John Doe and Jane Doe for the property located at 123 Main St. It specifies the monthly rent amount and due date, the security deposit required, the utilities included, and responsibilities of landlord and tenant regarding repairs, guests, parking, pets, and termination of the lease. The agreement is for a period of one year beginning on January 1st and automatically renews month-to-month unless proper notice is given.
Asian Architecture Project Part B Case study paper presentationTan Jaden
The document discusses the evolution of Japanese architecture over time. It began with traditional wooden structures influenced by Chinese styles. After World War 2 destroyed many cities, Western architectural styles using steel and concrete were adopted for reconstruction. However, the Japanese modified Western styles to suit their culture and climate, and to improve earthquake resistance. They also preserved traditional building types. Now Japanese architecture blends indigenous and imported influences, with modern buildings coexisting with historical structures.
Building services project 2 proposal reportTan Jaden
The document provides details on the passive fire protection system for an old folks home community library. It discusses components of the passive fire protection system including fire dampers for the air conditioning system ducts, fire-rated doors, and fire-stopping walls. Fire dampers are designed to close during a fire to prevent the spread of fire and smoke through ventilation ducts. Fire-rated doors and fire-stopping walls have a fire resistance rating to compartmentalize the building and slow the spread of fire. The document also provides information on the operation of fire dampers and regulatory requirements for fire precautions in air conditioning systems.
Building services project 2 presentation slidesTan Jaden
This document provides information on the proposed mechanical ventilation system for a public building project. It discusses the benefits of a balanced ventilation system to ventilate the building. The system uses two sets of ductwork and fans to supply fresh air into the building and extract stale air out, maintaining neutral pressure. Floor plans show the layout of the ventilation system on each level, including components like exhaust fans, filters, galvanized steel ducts, fire dampers, and diffusers. Details are provided on the types and purposes of fans, ducts, dampers and other components. Regulations on required fresh air changes are also cited.
The document appears to be a structural analysis report for a bungalow project. It includes floor plans, structural plans showing beams and columns, and analysis reports from three group members analyzing various beams and columns. The analyses determine the dead and live loads, calculate the ultimate loads, draw free body diagrams to determine reaction forces, and provide shear force and bending moment diagrams.
Project 1 Skeletal Construction (Temporary Bus Shelter) A3 ReportTan Jaden
The document summarizes the design of a temporary bus shelter constructed primarily of bamboo. Key points:
- The shelter is designed to be resistant to weather, easily accessible, light and portable using recyclable materials like bamboo and plastic bottles.
- Stress analysis found highest stresses at joints connecting the roof to columns and at the base where columns meet foundations, due to loads transferring through the structure.
- Construction followed a process of measuring, cutting, joining bamboo components with lashings and connectors to form the columns, roof structure and connections.
Sarang Paloh Heritage stay & event hall building reportTan Jaden
This document provides information on measured drawings conducted of the Sarang Paloh Heritage Stay & Event Hall located in Ipoh, Perak, Malaysia. A group of 25 students measured, documented, and analyzed the building which was built in the 1900s and exhibits a unique mix of architectural styles including Art Deco and Neoclassical influences depicting Chinese culture of the time. The building underwent refurbishment to preserve its condition and adapt to changing times, and now serves as a boutique hotel and event hall while maintaining its heritage features.
The chapter Lifelines of National Economy in Class 10 Geography focuses on the various modes of transportation and communication that play a vital role in the economic development of a country. These lifelines are crucial for the movement of goods, services, and people, thereby connecting different regions and promoting economic activities.
Walmart Business+ and Spark Good for Nonprofits.pdfTechSoup
"Learn about all the ways Walmart supports nonprofit organizations.
You will hear from Liz Willett, the Head of Nonprofits, and hear about what Walmart is doing to help nonprofits, including Walmart Business and Spark Good. Walmart Business+ is a new offer for nonprofits that offers discounts and also streamlines nonprofits order and expense tracking, saving time and money.
The webinar may also give some examples on how nonprofits can best leverage Walmart Business+.
The event will cover the following::
Walmart Business + (https://business.walmart.com/plus) is a new shopping experience for nonprofits, schools, and local business customers that connects an exclusive online shopping experience to stores. Benefits include free delivery and shipping, a 'Spend Analytics” feature, special discounts, deals and tax-exempt shopping.
Special TechSoup offer for a free 180 days membership, and up to $150 in discounts on eligible orders.
Spark Good (walmart.com/sparkgood) is a charitable platform that enables nonprofits to receive donations directly from customers and associates.
Answers about how you can do more with Walmart!"
This presentation was provided by Racquel Jemison, Ph.D., Christina MacLaughlin, Ph.D., and Paulomi Majumder. Ph.D., all of the American Chemical Society, for the second session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session Two: 'Expanding Pathways to Publishing Careers,' was held June 13, 2024.
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxEduSkills OECD
Iván Bornacelly, Policy Analyst at the OECD Centre for Skills, OECD, presents at the webinar 'Tackling job market gaps with a skills-first approach' on 12 June 2024
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumMJDuyan
(𝐓𝐋𝐄 𝟏𝟎𝟎) (𝐋𝐞𝐬𝐬𝐨𝐧 𝟏)-𝐏𝐫𝐞𝐥𝐢𝐦𝐬
𝐃𝐢𝐬𝐜𝐮𝐬𝐬 𝐭𝐡𝐞 𝐄𝐏𝐏 𝐂𝐮𝐫𝐫𝐢𝐜𝐮𝐥𝐮𝐦 𝐢𝐧 𝐭𝐡𝐞 𝐏𝐡𝐢𝐥𝐢𝐩𝐩𝐢𝐧𝐞𝐬:
- Understand the goals and objectives of the Edukasyong Pantahanan at Pangkabuhayan (EPP) curriculum, recognizing its importance in fostering practical life skills and values among students. Students will also be able to identify the key components and subjects covered, such as agriculture, home economics, industrial arts, and information and communication technology.
𝐄𝐱𝐩𝐥𝐚𝐢𝐧 𝐭𝐡𝐞 𝐍𝐚𝐭𝐮𝐫𝐞 𝐚𝐧𝐝 𝐒𝐜𝐨𝐩𝐞 𝐨𝐟 𝐚𝐧 𝐄𝐧𝐭𝐫𝐞𝐩𝐫𝐞𝐧𝐞𝐮𝐫:
-Define entrepreneurship, distinguishing it from general business activities by emphasizing its focus on innovation, risk-taking, and value creation. Students will describe the characteristics and traits of successful entrepreneurs, including their roles and responsibilities, and discuss the broader economic and social impacts of entrepreneurial activities on both local and global scales.
Project Management (Project 1 - Defining and documenting a project)
1. School of Architecture , Building and Design
Bachelor of Science (Hons) in Architecture
PROJECT MANAGEMENT (MGT60403 / ARC3612 / ARC3614)
PROJECT 1: DEFINING AND
DOCUMENTING A PROJECT
Group members:
Tan Wen Hao 0319923
Wong Zhen Fai 0317890
Yan Wai Chun 0319626
Yeoh Xiang Ann 0322691
Jack Too Mun Fai 0318214
Teo Hong Wei 0322990
Tutor:
Ar. Emmanuel O. Canlas
2. CONTENT
1.0 introduction
1.1 Project introduction
1.1.1 Case study
1.2 Company Profile
1.2.1 Company background
1.2.2 Company organization chart
1.2.3 Team member profile
2.0 Project Management
2.1 Success Criteria
2.1.1 Triple constraint
2.1.2 Success factors
2.2 Work breakdown structure
2.2.1 Phase oriented
2.2.2 Schedule oriented
2.3 Risk analysis
2.4 Gantt Chart
2.5 Pert Chart
3.0 Preliminary study
3.1 Site analysis
3.1.1 Site location
3.1.2 View and vistas
3.1.3 Circulation
3.1.4 SWOT analysis
4.0 Design Concept
4.1 Design Approach
4.2 Schematic Design
4.2.1 Container Studies
4.2.2 Design Development
4.2.3 Spatial Analysis
4.2.4 Schedule of space
4.3 Orthographic drawings
4.4 Renderings
4.5 Cost breakdown
3. 5.0 Landscape Design
5.1 Existing Softscape Condition
5.2 Existing Hardscape Condition
5.3 Proposed landscape layout
5.3.1 Softscape layout
5.3.2 Hardscape layout
5.4 Selection of vegetation
5.5 Renderings
5.6 Cost breakdown
6.0 Civil & Structural Engineering
6.1 Earthwork and roadwork
6.2 Foundation system
6.3 Structural components
6.3.1 Container to foundation
6.3.2 Container to container
6.3.3 Connection to connection
6.4 Tensile roof construction
6.5 Container Modification
6.6 Construction process
6.7 Cost breakdown
7.0 Mechanical & Electrical Engineering
7.1 Electrical system
7.2 Stormwater and wastewater system
7.3 Fire protection system
7.4 Mechanical ventilation system
7.5 Renderings
7.6 Cost breakdown
8.0 Costing
8.1 Property details
8.2 Overcome tight budget
8.3 Bill of quantities
8.4 Summary
9.0 Conclusion
10.0 Appendix
10.1 Meeting minutes
4. 1.0 Introduction
1.1 Project introduction
Client:
Taylor’s University SDN. BHD.
Mr. Emmanuel as the client representative
Requirements:
1. Maximum land size: as per site given by client
2. Usage of 50% reusable energy sources (Calculated by value)
3. Site layout and landscaping
Goals:
1. To become a design innovation and excellence center
2. To encourage the community to be appreciative towards arts and
technology
3. To promote creative excellence to a higher level
Scope:
Taylor’s University SDN BHD’s idea is to build a ‘Recreational Station’ to
house selected architecture and interior design models in conjunction with its
architectural faculty’s excellence. The ‘Recreation Station’ is aimed to be used
during the upcoming Architectural Workshop to be held at the University
compound in August 2018 and be carefully planned and implemented to its
completion before August 2018. In order not to interfere with the campus
activities during the semester, a proper project management plan has to
prepare. It aims to become a “Recreational Station” by following guidelines to
provide a progressive image by the university and the group of consultants.
Site at Zone I free parking
5. 1.1.1 Case study
Sion music venue
In developing the project, the architects sought to take advantage of shipping
container’s beneficial characteristics. standardised dimensions allow the units
to be readily stacked, while the inherent resistance of the large steel boxes
protects against vandalism and other forms of incidental damage. The
modular nature of the design ensures that the scheme can easily be added to,
or subtracted from, allowing a large degree of flexibility throughout the
process.
the two-storey scheme contains
rehearsal rooms and breakout space
the focal point of the design is a
300-seat concert hall
a steel bar has been crafted from the
form of a single container the bar in operation
7. Lightbox restroom
Architect Rohan Chavan has constructed a public restroom in Mumbai, India,
from an old shipping container. The structure which stands at the side of the
eastern express highway – one of the busiest roads in the Mumbai
metropolitan area – has been constructed under an overhanging tree which
allows light to filter down onto the fuchsia pink floor. The layout features a
toilet situated at both sides, with an open space at the middle for people to
meet and interact.
The center features a small space used for various activities such as a
free gallery to display art for amateur artists, an area for lectures and
awareness campaigns, celebrating festivals, seasonal activities and
events. the project introduces an alternative solution towards architecture
for public use, in an area where people seek refuge, interaction and basic
needs.
Floor plan
8. 1.2 Company background
1.2.1 Company history
TWY Consultants is a multinational conglomerate operating in many different
industries as well as sectors within the Asian region. Based in Kuala Lumpur,
TWY Consultants primarily focuses on efforts to providing building and
construction to Malaysia through the vast array of support departments within
the company which include a fully functioning architecture firm, quantity
surveying unit, engineering office and even a landscaping department.
Closing in on its quarter century since its foundation, the present owners of
TWY Consultants have not strayed from the original visions of the founders in
which to provide a quality product at a competitive price. As the company
continues on into the next decade TWY Consultants is determined to cement
it's place as the industry leading and trailblazing company that all other
companies seek to aspire to as well as pit themselves against.
Mission:
-To produce eco friendly commercial and residential dwellings of excellence to
total customer satisfaction
-Building a better future at a competitive and reasonable value
- To building relationships forever with customer on the solid foundation of
trust
Vision:
-To ensure that the development of any project undertaken by the company is
produced to the best that the company has to offer
Company Name: TWY CONSULTANTS
Company Address: Lot 7, Jalan Petaling Street, 50000, Kuala Lumpur,
Malaysia.
Telephone: + 603-5214-4125
Fax: + 603-5214-4152
Email: twyconsultants@gmail.com
9. 1.2.2 Company organizational chart
Quantity Surveyor
Teo Hong Wei
Architect
Jack Too Mun Fai
Project Manager
James Wong Zhen Fai
C&S Engineer
Bryan Yeoh Xiang Ann
M&E Engineer
Cedric Yan Wai Chun
Landscape Architect
Jaden Tan Wen Hao
Decision
Making
Problem
Solving
Project Inspection
Work Distribution
Client
Taylor’s University Management
10. 1.2.3 Team member profile
AR. JAMES WONG ZHEN FAI
Project Manager
TWY Consultant
Scope of work:
-Specifying in project objective and plan including handling job scopes, budgeting,
scheduling, and setting performances requirements.
-Control and management in resources utilization through procurement of labor,
materials and equipment according to prescribed schedule and plan.
-Proper coordination of planning, design, estimating, costing, contracting and
constructing of the entire construction process.
-Interpret and explain contracts and technical information to other professionals
-Report work progress and budget matters to clients
-Collaborate with architects, engineers and other construction specialists
- Ensure of effective delivery of messages and communication among the
participants of construction.
-Select, schedule and coordinate subcontractor activities
-Respond to work delays, emergencies and other problems
-Comply with legal requirements, building and safety codes and other regulations
Education Background:
-Bachelor In Architecture in University of Nottingham, Part 1 of the Architects
Registration Board (ARB) and Royal Institute of British Architects (RIBA) examination
-Master in Architecture in University of Havard, RIBA and ARB Part 2 accredited
-Registered Architect with Board of Architects Malaysia (LAM)
Professional Experience:
-Sanna Architects (2013-2014) – Assistant Architect
-Atelier Bow Wow (2014-2017) -Senior Architect
-TWY Consultant (2017-current)
11. AR. JACK TOO MUN FAI
Architect
JackedOff Studio Sdn Bhd
Scope of work:
-Creating building designs
-Discuss ideas, objectives and requirements of a project
-Working around constraining factors such as planning legislation, environmental
impact and project budget
-Collaborate with other professionals about design
-Assess needs of building and its users and advice client on the practicality of the
building
-Aware of financial budgets and deadlines
-Produce detailed drawings and specifications
-Specify the nature and quality of materials required
-Prepare tender applications and presentations
-Carry out regular site visits to check on progress
-Writing and presenting reports, proposals, and applications
-Ensure projects is running on time and to budget
Education Background:
-Bachelor in Architecture in Leeds University, Part 1 of the Architects Registration
Board (ARB) and Royal Institute of British Architects (RIBA) examination
-Masters of Architecture in Oxford Brookes University, RIBA and ARB Part 2
accredited
-Registered Architect with Board of Architects Malaysia (LAM)
Professional Experience:
-Gehi Architects (2013-2014) – Assistant Architect
-Herzog de Meuron(2014-2017) - Senior Architect
-JackedOff Studio Sdn Bhd (2017-current)
12. IR. BRYAN YEOH XIANG AN
C&S Engineer
BY Construction & Structural Sdn Bhd
Scope of work:
-Plan, design and observe construction and maintenance of building structures and
facilities
-Undertake technical and feasibility studies including site investigation
-Undertake complex and repetitive calculation
-Collaborate with clients and professionals including architects and subcontractors
-Schedule material and equipment purchase and deliveries
-Assess the sustainability and environmental impacts of projects
Education Background:
-Bachelor of Civil Engineering in University of Nottingham
-Masters in Civil Structure in University of Nottingham
-Registered Engineer with Board of Engineers Malaysia
Professional Experience:
-Elecon Engineering Company (2002-2010) – Assistant Structural Engineer
-KBR, Chicago (2010-2015 - Senior Structural Engineer
- BY Construction & Structural Sdn Bhd (2015-2017)
13. IR. CEDRIC YAN WAI CHUN
M&E Engineer
Swift Mechanical & Electrical Sdn Bhd
Scope of work:
-Design and oversea designs by designers and drafters in production of electrical
system construction documents for submittal and use in construction of various types
of buildings and other structures
-Interface with municipal and construction personnel during construction process
-Conduct on-site inspections to ascertain compliance with construction design
documents and specification
-On site Mechanical and Electrical Engineering providing Subject Matter Expertise
and project management support to the Construction Management Team
-Electrical installation management, generation and implementation of construction
schedules, observation and inspection of installations, report writing, constructability
problem analysis and resolution.
Education Background:
-Bachelor degree of mechanical & electrical engineering with first class honors in
Taylor's University Lakeside Campus.
-Bachelor degree of electrical engineering in Taylor's University Lakeside Campus,
Mechanics & Materials
-Registered Engineer with Board of Engineers Malaysia (BEM)
Professional Experience:
-KBR, Chicago (2010-2014) – Assistant M&E Engineer
-Skidmore Owings & Merrill (SOM) (2014-2017) – Seinor M&E Engineer
- Swift Mechanical & Electrical Sdn Bhd (2017-current)
14. LAR. JADEN TAN WEN HAO
Landscape Architect
JDscape Sdn Bhd
Scope of work:
-Confer with clients, engineers, and building architects to understand a project
-Conduct preliminary studies of the site including the walkway, vegetation and the
climate condition
-Provide landscape design for the project
-Prepare and present landscape plan with understandable rendering images,
specifications, and cost estimates
- Analyze environmental reports on land conditions, such as drainage and energy
- Coordinate the arrangement of existing and proposed land features and structures
-Collaborate with other professionals in the team
-Monitor and check work on-site
-Seek new work through marketing or by giving presentations
Education Background:
-BA (Hon) Landscape Architecture in University of Greenwich, London, Part 1 of the
Architects Registration Board (ARB) and Royal Institute of British Architects (RIBA)
examination
-Master in Landscape Architecture in University of Greenwich, London, RIBA and
ARB Part 2 accredited
-Registered Architect with Board of Architects Malaysia (LAM)
Professional Experience:
-Terrix Architects (2013-2014) – Assistant Architect
-Le Bruez, Switzerland (2014-2017) - Senior Architect
- JDscape Sdn Bhd (2017-current)
15. SR. TEO HONG WEI
Quantity Surveyor
THW Quantity Surveyor Sdn Bhd
Scope of work:
-Preparation of contracts, including details regarding quantities of required materials
-On-going cost analysis of maintenance and repair work
-Feasibility studies of client's requests Analyze completed work and arrange payment
to contractors
-Allocate upcoming work to contractor
-Site visits, assessments and projections for future work
Education Background:
-Bachelor of Quantity Surveying in Bauhaus University, Dessau, Germany
-Master of Quantity Surveying in Bauhaus University, Dessau, Germany
- Registered SR. with Board Quantity Surveyors Malaysia (BQSM)
Professional Experience:
-Elecon Consultant Company (2013-2014) – Assistant Quantity Surveyor
-Jurukur Bahan Maju Bina Sdn Bhd (SOM) (2014-2017) – Senior Quantity Surveyor
- THW Quantity Surveyor Sdn Bhd (2017-current)
16. 2.0 Project Management
2.1 Success Criteria
The project can be said to be a success, or said to reach the project goals,
when the project fulfill its success criteria. The triple constraint, not only act as
a manual of the project, also acts a guideline making sure that the project
team does not perform out of track, in any aspect, during the construction
period. Three factors are adopted in shaping quality of the project: time,
scope and cost.
1) The project must bring profit to the company and stakeholders in a
manner that goes by the proper construction process and stages in
meeting the client’s and related authorities requirement and
expectations.
2) The end product should be cost-effective and self-sustainable in an
economic aspect to maintain within the costing limitation given.
3) Project deliverables should be delivered on time according to the
construction timeline and completed within the given timeframe of 1
year.
2.1.1 Triple constraint
The triple constraint is the key determinant of quality of a project, being able
to meet the three factors means a success of a project.
Cost
1. Project team to be accounted for the cost of resources to monitor
budget compliance. Long-term durable materials are to be used for
structure components & furniture to attain the lowest cost possible.
This includes the reusing and upclying of materials. Materials should
be able to attained locally if possible and self-sustainable.
2. Construction materials should be in its optimal usage so that there is
no waste of material or over budget issue. Resources are to be
quality
Time
1 year
Scope
Recreation district for
architectural workshop
Cost
RM1.5 M
17. managed with the realization of creating value, or that the benefits
derived said to be exceeding the amount spent.
3. The company should reach an agreement with clients on selection of
materials and suggest appropriate and economic material as per
client’s request.
4. The company should not only focus on the standalone budget data to
decide under budget or over budget but by looking at the overall project
health in right schedule, cost and also job scope.
Scope
1. During project lifespan, parameters and scopes must be broken down
and managed through work breakdown structure (WBS), or Gantt chart,
to be clearly understood by construction team.
2. Project should always follow the status of schedule, to avoid
undesirable delay. in the event of schedule changes, project team
should be able to control the influences that cause such event and
manage the changes effectively, this suggests a time-to-time schedule
review and timescale estimation.
3. Risk analysis is needed in cultivating high awareness of health and
safety precautions implemented thoroughly on site or off site and might
get in the way of achieving project objective.
Time
1. The project must be completed within the given duration (1 year) and
shall not exceed the given timeframe to avoid higher exposure of risk
and dissatisfaction of client. Therefore, time management is important
in assuring the construction to be carried out in an effective manner;
this includes schedule development, schedule control and sequencing.
2. Transportation of materials on-site and off-site should be monitored
and planned, in a way that saves transportation cost and labor fees.
3. Construction workers to be supervised by assigned contractors,
ensuring their wellbeing and fair wage, in order for the construction to
be carried out smoothly.
4. Choice of materials are also important in terms of shorten construction
process and duration, in this case materials with flexibility and
modularity, especially of standard size and pre-completed structure,
shall be considered by the project team if appropriate and beneficial.
Quality
A quality project can be said to have achieved all 3 perimeters above upon
completion.
1. Project involves specific deliverable or work product. Quality means
able to produce these deliverables with clearly stated requirement, in
meeting project objectives and performance standard.
2. Client’s satisfaction is the best way to measure a project success, in
exchange being able to meet client’s requirement and expectation.
18. 3. Well management and coordination of project team and having each
consultants to complete their task each project stage.
2.1.2 Success factors
Back up plans
In the event of schedule
change or rejection of
design and documents, the
company is able to
produce a backup plan to
showcase our flexibility
and prompt changes and
improvements.
Close rapport
The project team
emphasises clear and
effective communication
not only within the team
itself but construction
team, authorities and
client, establishing rapport
with each parties making
sure project runs smoothly
and on track
Wellbeing of project
team
In promise of giving client
a quality project, the team
must first be ensured of
healthy working
environment, this includes
fixed working hours, fairly
paid wages and staff
benefits
Skill & experience
Our team is equipped with
masters from diffirent field,
providing best solution and
advice to the team and
guaranteeing the project’s
success
25. 3.0 Preliminary study
3.1 Site analysis
3.1.1 Site location
The proposed site is located in the existing open car park (Zone I) at Taylor’s
University Lakeside Campus, Petaling Jaya. Positioned at the turning corner
of one of the main entrance to Taylor’s University, it has a strategic location
where it is highly visible from and towards the campus, the high rise
residential buildings, and the sports complex.
26. 3.1.2 View and vistas
A strategic location where open views are available in all directions, and the
proposed building can be seen from the major circulation path and
surrounding buildings.
From South East From South West
From North East From South West
27. 3.1.3 Circulation
Vehicular circulation
Pedestrian circulation
Pedestrian path
from syopz mall to
the informal
entrance of site
Pedestrian from
academic blocks
connected to lower
ground carpark to the
informal entrance of
site
Pedestrian path
along one-way
road from car park
to academic blocks
Pedestrian path
along Jalan Taylor
connecting from D’
Latour apartment
to site
Ingress
Vehicle accessed
from Jalan Taylor
to site
Ingress
Vehicle enters via
one-way access
from academic
blocks to site
Egress
Vehicles exit site
via Jalan Taylors
28. 3.1.4 SWOT analysis
Strength
-Site easily accessed through
main road and campus routes
-Noticable as site is located near
the main access point of
Taylor’s University (T-Junction
area)
-Strategic location as students
uses area around site as
primary circulation to campus.
Weaknesses
-Site exposed to excessive
amount of sunlight, least amount
of vegetation available on site
for shading purposes.
-Vehicle access are only
available through one
ingress/egress point.
-Uneven, unpaved road and bad
soil condition.
Opportunities
-Students as potential users,
maily targeted before or after
class period where they can visit
building before class hours or
wait for traffic jam, rain before
exit campus after class.
Threats
-Existing facilities such as
tennis, futsal and basketball
court within the vicinity.
-Syopz mall, located in walking
distance, being a better shading
or entertainemnt spot.
-Foul smell spreaded from
sewerage pool/swamp across
site.
29. 4.0 Design Concept
4.1 Design Approach
As a well-known university that caters to many students who drive every day,
a proposal for a recreational station at the parking lot takes advantage of the
frequent human circulation of youths to and from campus. The site sits at the
edge of a parking lot, and faces northwestern side with the small gate that
leads to the campus located directly up north. Hence our design is laid out
along a diagonal axis that channels the people from the gate into the station
while also allowing for a shortcut through the station directly into the car park
for those who are not interested.
30. We decided to use shipping containers as our main building blocks due to the
minimal construction time and structural effort needed to build the station.
Containers are also cheap (if bought second-hand) and lightweight which
gives a modern and industrial feel to its users. The two sides of the containers
that face the eastern side have more openings and balconies to take full
advantage of the morning sunlight; while the sides that point to the west are
closed up to minimize exposure to the hot afternoon sun. The main
administrative space and food arena will be located down stairs to keep the
upper floors quiet and more student friendly. All these efforts are to ensure
high performance of the recreational center.
4.2 Schematic Design
Exposed side on the right of the structure that allows for view and vista
towards the entire campus and lake. The food arena is positioned below the
main recreational space to provide a cooling and comfortable outdoor space
for the students all day round.
This plan view shows the diagonal
axis of human circulation that
travels through the open ground
floor plan with trees and vegetation
greeting the users at the entrance
and exit of the station. The food
arena is located at the center of the
station to serve as an attraction for
the students to stop and socialize.
The entrance is located adjacent to
the main circulation through the
building. There are two access up
to the first floor to allow students to
reach and leave the recreational
spaces directly without passing
through in-between spaces.
31. The above sketch shows the sun path over the proposed station, and the
green facades are designed with openings or balconies to get full exposure to
the cool natural lighting in the morning, while the red regions are sealed up to
minimize penetration of hot sunlight in the afternoon. The vegetation also
serve as natural shading for the two inner facades, allowing there to still be
small amount of openings.
The simple site plan shows the direction from which a majority of students
access the car park from, making our site a very strategic location to take
advantage of the users. There also major exposure from the eastern and
northern direction, being the body of water, commercial block and hostel on
the north and the sports arena on the right.
32. 4.2.1Container Studies
The common types of ISO shipping containers are:
• 20 GP (standard type)
• 40 GP (standard type)
• 20 HC (meaning High Cube. It is 1 foot taller than a standard 20 GP)
• 40 HC (meaning High Cube. It is 1 foot taller than a standard 40 GP)
• Open top (not commonly used for construction)
• Open side (not commonly used for construction)
• Freezer or Refrigerated (not recommended for ISBU home construction
Standard Type Containers
Dry containers 20' and 40' (general purpose) are manufactured from either
aluminium or steel. They are suitable for most types of cargo. Aluminium dry
containers have a slightly larger payload than steel, and steel dry containers
have a slightly larger internal cube.
33. ISO Standard Type Container Specifications
20′ container 40′ container
Imperial Metric Imperial Metric
external
dimensions
length 19′ 10.5″ 6.058 m 40′ 0″ 12.192 m
width 8′ 0″ 2.438 m 8′ 0″ 2.438 m
height 8′ 6″ 2.591 m 8′ 6″ 2.591 m
interior
dimensions
length 19′ 3″ 5.867 m 39′ 5 45⁄64″ 12.032 m
width 7′ 8 19⁄32″ 2.352 m 7′ 8 19⁄32″ 2.352 m
height 7′ 9 57⁄64″ 2.385 m 7′ 9 57⁄64″ 2.385 m
door
aperture
width 7′ 8 ⅛″ 2.343 m 7′ 8 ⅛″ 2.343 m
height 7′ 5 ¾″ 2.280 m 7′ 5 ¾″ 2.280 m
internal volume 1,169 ft³ 33.1 m³ 2,385 ft³ 67.5 m³
Maximum gross weight 66,139 lb 30,400 kg 66,139 lb 30,400 kg
empty weight 4,850 lb 2,200 kg 8,380 lb 3,800 kg
net load 61,289 lb 28,200 kg 57,759 lb 26,200 kg
Advantages of using Containers as Building Component
Strength & Durability
-An ideal building material.
-Designed to carry heavy loads, stacked in high columns, resist harsh
environments - weather and resistant to salt corrosion, etc.
Modular
-Made to standard measurements and provide modular elements that
combine into larger structures - This simplifies design, planning and transport.
-Due to the containers modular design additional construction is as easy as
stacking more containers - They can be stacked up to 12 high when empty.
Transport
-Pre-fabricated modules can also be easily transported by ship, truck or rail
-Used shipping containers are easily available across the globe.
Low structural cost, high strength
-Available at low costs (compared to a finished structure built by labor-
intensive means such as bricks and mortar, which also require larger more
expensive foundations)
-Construction involves very little labor and requiring only simple modification
-Can be purchased from RM4800 each (used) to RM2500 (new)
-Shipping containers offer a huge structural strength for a fraction of the cost
of traditional timber steel and concrete constructions
34. 4.2.2 Design Development
1. The first massing model shows the basic form
that fits into the setback of the site boundary.
2. The second model is split diagonally by the
human circulation that cuts through the site to
get to and from the campus.
3. The third model shows the attempt to take
advantage of the high human circulation
through adding a main program which would
be the food arena because it suits the outdoor
space.
4. The forth model shows the addition of a
second floor to house the other main
programs which is the recreational space for
the students to interact in and socialize.
5. The subtraction of solids in the fifth model
gives opportunity for landscaping to be
introduced into the outdoor spaces while
allowing the upper floor to also enjoy the
greenery.
6. Adding a third floor to the top creates a new
program which is as an observation deck due
to its excellent vantage point for views and
vistas.
35. 4.2.3 Spatial Analysis
The first render is the front elevation and the second render is the side
elevation that faces the northwest. There are lots of openings and balconies
on both of these facades to allow healthy sunlight to illuminate the
recreational spaces on the first floor. The observation deck is located on the
upper floor for the views and vistas. The food arena is located on the ground
floor to attract users into the space with its noise and crowd, also to keep the
noisier spaces at the bottom to avoid disrupting the peace on the recreational
activities upstairs and also the observation deck. The services like toilets and
administrative office is also on the ground floor to provide a convenient
experience for users.
36. 4.2.4 Schedule of space
Name of space Level Space Type Area
Administrative Office G Administrative 12m2
Food Arena G Food & Beverages 106m2
Food Stalls G Commercial 24m2
Recreational Spaces 1 Public 75m2
Reading Lounge 1 Public 70m2
Relaxation & Pool Room 2 Public 55m2
Rooftop Observation
Deck
2 Outdoor Public 110m2
Toilets G Restroom 29m2
Ground floor
First floor
Rooftop
37. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
GROUND FLOOR PLAN
SCALE 1:100
Swift
4.3 Orthographic drawings
38. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
FIRST FLOOR PLAN
SCALE 1:100
Swift
39. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
SECOND FLOOR PLAN
SCALE 1:100
Swift
40. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
ROOF PLAN
SCALE 1:100
Swift
41. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
FRONT ELEVATION
SCALE 1:100
Swift
RIGHT ELEVATION
SCALE 1:100
42. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
BACK ELEVATION
SCALE 1:100
Swift
LEFT ELEVATION
SCALE 1:100
43. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
SECTION B - B
SCALE 1:100
Swift
SECTION A - A
SCALE 1:100
48. 5.0 Landscape Design
5.1 Existing Softscape Condition
1
2
3
1
Site condition
Pedestrian access to campus
West facing highway
South facing DK Senza
2
3
Exiting site is a post construction site with no proper management and being a
temporary informal parking spot. Trees and plants grew without being trimmed,
arranged or proper planning For Site 1 and 2, plants on site are rather short and
serves no shading purpose, more of being a mosquitoes breeding ground. Site 3
serves its purpose of shading the cars. However, if trees around the area is
removed, leaving more space for ingress and egress traffic and replant with proper
planning, it can serve more purpose of shading cars and being a wayfinding for
drivers to enter or exit the car park, but most importantly, it brings up the aesthetic
value, not only to the car park itself but also to the to-be-built architectural
workshop.
49. 5.2 Existing Hardscape Condition
3
Fence in strip 1 (stainless steel) is still in good condition, however fence in site 2 has
rusted,deformed and overgrew with creepers. New fence is needed, preferably same with
strip 1 for security purpose. Patrol booth has not been in use since years ago. Part of land
on site forms puddle during rain and can be dangerous to pedestrain and future users of
building, therefore the land need to be revised and flatten, paved with alsphalt if possible.
1
Site condition
Existing fence facing Jalan Taylors
Rusted fence and patrol booth
Existing soil condition
2
3
2
1
50. 5.3 Proposed landscape layout
Landscape design is seperated into exterior and interior landscape as stated
below and shown in site plan:
Exterior landscape Interior landscape
Softscape Hardscape Softscape Hardscape
Bucida Molineti tree Asphalt road Polyalthia
Longifolia tree
Wooden deck
Red sealing wax
palm
Red brick
pavement
Spider Plant Garden furnitures
Red ginger plant Wooden pergola Trellis panels
Lantana Camara
flower
Gravels
Interior landscape
Exterior landscape
Existing landscape
55. No. Name of
plant
Maxim-
um
height
Maxi-
mum
diam-
eter
Weight Root
depth
Price Description
1 Red
sealing
wax
palm
3m 30mm 5kg 40cm RM150
per pot
-Bright red crown shafts and leaf
sheaths
- High demand for gardening and a
landscaping projects in tropical
countries.
-Palm grows well in full sun or shade
but needs humid conditions and well-
draining soil
2 Red
ginger
plant
1m 15mm 1.5kg 15cm RM35
per pot
-native Malaysian plants with
showy flowers on long brightly colored
red bracts
- grown as a houseplant and its cut
flowers can be used in arrangements.
3 Big-sage 60cm 15mm 1.5kg 15cm RM30
per pot
-Often planted to embellish gardens,
native to the American tropics.
-Small tubular shaped flowers which
are arranged in clusters in terminal
areas stems.
-The flower has a Tutti Frutti smell
with a pepper undertone.
4 Ashoka 4m 50mm 4kg 40cm RM200
per pot
-Commonly planted due to its
effectiveness in alleviating noise
pollution
-Tree exhibits symmetrical pyramidal
growth with willowy weeping
pendulous branches and long narrow
lanceolate leaves with undulate
margins.
5 Spider
plant
30cm 10mm 1kg 10cm RM20
per pot
-Easy to grow as
a houseplant; variegated forms are the
most popular.
-Flowers are produced in a long
branched inflorescence
-The inflorescences carry plantlets at
the tips of their branches, which
eventually droop and touch the soil,
developing adventitious roots.
6 Dwarf
Geometry
tree
4m 50mm 5kg 50cm RM250
per pot
-Small, low and picturesque spreading
plant with unique ‘flat’ branch grow
pattern.
-The twigs are growing densely in
storeys on whorls around the trunk.
Flowers are yellow and insignificant,
followed by clusters of tiny brown
fruits.
5.4 Selection of vegetations
60. 6.0 Civil & Structural Engineering
6.1 Earthwork and roadwork
Earthworks
The site is an open public parking area for Taylor’s student; it is covered with
sand and crusher run stone with serious flooding issue after rain. In
preparation for start work, a portion of the crusher run stone surface will be
cleared before flattening, leveling and excavating the soil for the ‘Recreational
District’.
In preparation for start work, a portion of the crusher run stone surface will be
cleared before flattening, leveling and excavating the soil for the pavilion.
Area of clearance and excavation
61. Road works
To incorporate with landscaping system of our site we are proposing turf
stone paving works for car parks around the building to link from the main
vehicular entrance and small pedestrian opening to our site for ease
movement.
62. 6.2 Foundation system
Raft foundation
As this is a ‘Recreational District’, a basic raft foundation using large concrete
slab is proposed, at the highlighted area, for its cheaper, easier to install and
most importantly, did not require as much excavation as the usual strip
foundations. The foundation shown below is a typical slab on grade
application for a 1000sf (three 40' containers) shipping container
home design. There is a 24' x 40' perimeter foundation wall made from
precast concrete panels, but could easily be CMU block or poured
concrete. The perimeter was excavated and trench filled with gravel (for
drainage). The precast panels were dropped in via a crane and tied together.
The panels included insulation and exterior water proofing membranes added
at the factory. Utilities (water, electrical, and gas supply lines) are run to the
base of the foundation and then to there respective locations in
plan. Foundation walls were then back-filled, soil compacted, gravel added,
rebar laid out, and then slab poured. In addition, raft foundation spreads the
weight of the container over the whole ground floor area. The raft is laid on a
hardcore, or scalping bed and usually thickened at the edges, especially in
very poor ground. Rafts are most suitable when the ground is of good load
bearing capacity and little work is required to get a solid foundation.
Image of raft foundation after rebar
was laid out before concrete
finishing was poured.
Image of completed raft foundation
Raft foundation details
63. Container Footing
A container is built as an in part connected with its entire periphery welded to
the body, the chances of uplift and suction force is highly impossible. However,
the whole container would need to be secure on the ground or on foundation
to prevent it being blown away by storm or strong wind. The containers units
are welded on steel post with 500 x 500mm width footing buried at 500mm
deep into the ground. The utilities (water, electrical, and gas supply lines) are
run to the base of the container to the respective locations proposed in plan
by M&E engineer.
Image of steel footing
to be connected to
base of container
Workers welding steel footing to base of container
64. 6.3 Structural components
Exploded diagram of a container
Containers are designed to bear load at their corner post
The image illustrates the basic structural components of a container. The type
of containers we are using is 20ft Container (6.1m Lx 2.44m W x 2.6m H) and
40ft Container (122m Lx2.44m W x 2.6m H) due to its ease of availability in
the market The corrugation panels (roof, sides, and back floor, purlins, front
doors, frame, and rails of a container forms an integrated structural skin. They
are strong and made to carry floor loads far more than what is required for
typical home construction. Therefore, no extra structural support is required
on sidewalls and doors of the containers. However, modifying and cutting
openings weakens its existing structural system. It is recommended that
aluminum powder coated framing to be used to frame out the opening created.
65. Extra bracing can be added to the roof for hanging fixtures required. The
floors are made with treated plywood. Thus, it is strong, resilient, does not
dent, insect resistant and can be replaced easily for repair. A thin layer of
interior finishing (vinyl, carpet, etc.) can be laid on top for a more sophisticated
interior finishing.
Every container is designed with a fitting at every corner due to its original
intention to be stacked up during shipment. This design allows the load to be
distributed at the four corners through the corner posts. This explains the
importance of the corner post as well as the panels in contribution to the
structural rigidity and stability.
6.3.1 Container to foundation
A container for foundation plate weld
Installation of container to pad footing
66. Steel plate and reinforced concrete bars are being set in concrete off-site.
During installation, steel plates fitted inside the corner fittings, acting as heavy
duty washer for the blots.
Advantages
-The most secure method
-Not difficult for a handy person
-Simply weld the containers together
6.3.2 Container to container
Foundation to container details
Container to container weld
All corner blocks are
welded to each other to
make sure containers
will not dislocate
67. 6.3.3 Connection to connection
Corner castings also known as corner fittings are the structural element to
allow 2 shipping containers to be connected both vertically and horizontally at
the 8 corners of a shipping container.
Container to container connection
Corner castings around container
68. Installation process
1. Open bridge clamp by twisting shaft.
2. Insert bridge clamp across adjacent corner casting; ensure grip hooks
are inside the corner casting.
3. Use central spanner point to tighten grips
4. Tighten lock nut to adjacent grip to ensure its is tighten
The design construction and installation required perfect sealing of shipping
containers in order to prevent any means of damages. Another connection
method is known as welding.
Corner casting upper and lower dimensions
69. 6.4 Tensile roof construction
Tent structure system
Saddle Roof
-Four or more point system when the fabric is stretched between a set of
alternating high and low points
- By running a cable in a parallel pattern with opposite curvature, a slight
saddle is created. Alternating ridge and valley cables create a series of small
curvatures in the membrane—a scenario that creates a unique undulating
surface.
Construction Materials
-For external use we are proposing to use PVC coated polyester as daily use
element, it can transmit daylight and reflect heat,
Control sound, and be easy to keep clean.
-PVC-coated polyester fabric is the oldest and one of the most commonly
used materials on fabric structures. It has a high tensile and tear strength but
low durability as it tends to deteriorate from UV radiation. It also exhibits creep
behavior, losing significant levels of pre-stress over time and sometimes
requiring membrane re-stressing. Many consider its low durability and lifespan
of 10-15 years a barrier to application as permanent structure.
PVC coated polyester
Comparision of PTFE coated fiberglass and PVC coated polyester
Membrane tensile strength
70. Advantages Disadvantages
-Unique designs
-Lightweight and flexible
-Environmentally sensitive
-High strength weight ratio
-Little to no rigidity
-Loss of tension is dangerous for
stability
-Thermal values limit use
Membrane plate
-Provide a link between the membrane and structural elements
-Membrane plates accept centenary cables and pin connection hardware
Membrane forms the enclosure of the structure. Connections can be glued or
heat welded.
Tripod head with
centetary cables
Centenary cables at a
side connection
Extruded section with
membrane plate and
centenary cables
Tensioner
71. Cable clamps
Edge cable with clamps. Used mainly for PTFE-coated fiberglass fabric, but
also for PVC coated polyester fabric when edge spans are longer than 20m.
Environmental Impact
-Longer life cycles of materials
-Materials can be re-used in form
-Most materials are completely recyclable
-Less impact on site
-Less construction debris after demolition
Critical aspects to ensure that has an efficient installation process:
1.Develop an effective means and method of installation
2.Ensure that you have the right equipment and tools on site
3.Adequate shake out area. Protect the membrane form sharp surfaces
4.Be mindful of the weather
5.Thorough inspection of all connections
6.Close out and sign off with the client or GC
Solar behaviour
Sections of cable clamp cable clamp through membrane
72. 6.5 Container Modification
-When cutting or removing any of the panelings, considerable reinforcement
would be needed to replace the support being lost
-Steel Framing will be required to frame out the opening
Container Deformation Container Reinforcement
The Structural of Container Modifications Image of Container
73. 6.6 Construction process
1.Build a foundation
In our case where we are to build on the surface of the lake, the floating dock
system is used to provide buoyancy driven experience to the visitor. This
floating foundation system is chosen based on its features and advantages
that benefits the whole project economically and relating to the built context.
2. Place the containers
The containers are going to be placed on site using crane that Is easy,
efficient, and safety.
3. Connect the containers
Several ways are used on different parts to combine to containers, such as
bolts, specialized clamps, or through welding. Since the pavilion proposed is a
permanent builtform, welding is proposed as the connecting method for most
of the parts.
4.Add Reinforcement
Structural reinforcement are required to replace the support being lost when
the side panels are removed. The columns and beams are proposed to be
stitch welded to the containers for greater stability.
5. Modification
Removal of side panels is required if the passage between the containers or
the windows and door openings are needed. Plasma cutter and cutting torch
are proposed to make openings.
6. Seal the cracks
To seal the gaps between containers resulted by the removals of interior
walls, steel strips could be welded on the side gaps. Other solution could be
the backer rod. spray foam, and caulk. After all, doors, windows. subfloors
and electrical conduit are to be added based on the preference of the client.
7. Infill
After all, doors, windows, subfloors and electrical conduit are to be added
based on the preference at the client.
74. 6.7 Cost breakdown
No. Item Quantity Cost Total cost
Substructure
Excavation
1 Machine excavation remove top soil 16 300 4800
2
Excavation on trench to receive raft
foundation
30 78 2340
Foundation
3
Precase reinforced concrete (grade 45)
raft
75 20 1500
4
Foundation mild steel high tensile to raft
foundation trench
2000 2 4000
5
Reinforced concrete (grade25) in
substructural works
300 35 10500
6 Asphalt paving, road work 1200 110 132000
Superstructure
Structural Steel Work
7
Universal steel beam (4.8m x 8);
(84.5kg/m)
3245 2 6490
8
Universal steel column (3.3m x 12);
(84.5kg/m)
3346 2 6692
9
Apply 1 coat of intumescent 1 hour fire-
rating paint to hot dipped galvanized
structural steel
200 12 2400
PVC coated polyester tensile waterproof
membrane roof (30m2
x8)
30 60 1800
Joints
10 Stainless steel plate (200mm x 210mm) 60 11 660
Staircase and finishes
11
Stainless Steel Staircase with hot dipped
galvanised finish (overall size 912mm x
6970mm x 3450mm high)
3 3152 9456
Total cost for C&S Engineering: RM182638
75. 7.0 Mechanical & Electrical Engineering
7.1 Electrical system
First floor plan
Lighting plan
77. Types of lightings and fixtures
TYPES OF FIXTURE Pendant LED Bulb
IMAGE
TYPE OF LUMINOUS Warm White
LUMINOUS FLUX ( lm ) 2000 lm
POWER ( W ) 120 W
COLOR TEMPERATURE ( Kelvin ) 2700 Kelvin
BULB FINISH White coated
VOLTAGE ( V ) 220 - 240 V
COLOR RENDERING INDEX ( CRI ) 80
LUMEN MAINTENANCE FACTOR 0.7
DIMENSIONS ( mm ) H = 132 mm , W = 69 mm
LIFE HOURS ( Hours ) 15,000
QUANTITY 25
78. TYPES OF FIXTURE Patio Light Stringer
IMAGE
TYPE OF LUMINOUS Warm
LUMINOUS FLUX ( lm ) 1000 lm
POWER ( W ) 8 W
COLOR TEMPERATURE ( Kelvin ) 2200 Kelvin
BULB FINISH -
VOLTAGE ( V ) 120 V
COLOR RENDERING INDEX ( CRI ) 80
LUMEN MAINTENANCE FACTOR 0.7
DIMENSIONS ( mm ) L = 330 ft.
LIFE HOURS ( Hours ) 15,000
QUANTITY 15
79. TYPES OF FIXTURE LED Edison Bulb
IMAGE
TYPE OF LUMINOUS Very Warm White
LUMINOUS FLUX ( lm ) 800 lm
POWER ( W ) 6 W
COLOR TEMPERATURE ( Kelvin ) 2200 Kelvin
BULB FINISH White coated
VOLTAGE ( V ) 120 V
COLOR RENDERING INDEX ( CRI ) 93
LUMEN MAINTENANCE FACTOR 0.7
DIMENSIONS ( mm ) H = 100mm , L = 60mm
LIFE HOURS ( Hours ) 20,000
QUANTITY 60
80. TYPES OF FIXTURE Sconce Lighting Lamp
IMAGE
TYPE OF LUMINOUS Warm White
LUMINOUS FLUX ( lm ) 1540 lm
POWER ( W ) 14 W
COLOR TEMPERATURE ( Kelvin ) 2700 – 3200 Kelvin
BULB FINISH Painted
VOLTAGE ( V ) 110 V
COLOR RENDERING INDEX ( CRI ) 80
LUMEN MAINTENANCE FACTOR 0.7
DIMENSIONS ( mm ) H = 1.18 in. , W = 3.35 in. , L = 16.14
in.
LIFE HOURS ( Hours ) 50,000
QUANTITY 13
81. TYPES OF FIXTURE SINGLE GANG LIGHT SWITCH
IMAGE
WEIGHT 59g
QUANTITY 6
TYPES OF FIXTURE TWO GANG LIGHT SWITCH
IMAGE
WEIGHT 100g
QUANTITY 3
82. TYPES OF FIXTURE THREE GANG LIGHT SWITCH
IMAGE
WEIGHT 181g
QUANTITY 2
TYPES OF FIXTURE LIGHTING TIMER
IMAGE
DIMENSIONS 55 MM deep, 75MM square
CAPACITY 16A resistive load, up to 3840W at 240V
QUANTITY 1
83. 7.2 Stormwater and wastewater system
Stormwater system
Lightweight PVC Drainage system
PVC piping system is a product that offers reliable and durable service for
various usages. It provides tremendous weight advantage, reducing number
of installers needed as well as lower cost for transportation with higher
payloads. Its resistance to fracture increases its performance advantage due
to its ability to yield under loadings with its elasticity, which also reduces the
magnitude of pressure surges. Besides that it is a non-toxic, environmental
friendly, and safe material, it offers watertight joints that outperformed
traditional pipe products. Most importantly, it is durable and insulated from
exposing to direct sunlight when installed to the containers.
uPVC Sanitary System
The system is used for transportation of potable water for domestic usage as
well as ground water for land engineering. It also commonly used for
disposing off sewage and venting system. The piping system offers ability to
withstand the flow of aggressive water. This results in the piping system’s
suitability to be applied on site due its location beside Sungai Klang, and the
high average rainfall in Malaysia. It is also resistance to a number of
chemicals and corrosions, providing best solution of long-term piping system.
Besides that, it is ideal for water distribution systems that able to carry
drinking water and advantageous for sewage systems as there is no buildup
of deposits inside the surface. Thus, enabling consistent use of building
system components.
86. 7.3 Fire protection system
Active Fire Protection
Active fire protection is a group of system that requires some amount of action
in order to work efficiently in the event of fire. The systems can be manually
operated or automatically, with some amount of motion. It includes fire and
smoke alarm systems, sprinkler systems and fire extinguisher. The fire and
smoke alarm system are used to detect the event of fire, the sprinkler system
is used to slow the growth of fire activity, whereas the fire extinguishers are
used to put out the fire or to clear route for evacuation.
Fire Alarm System
The fire alarm system offers reliability and efficiency in the event of fire
emergency could occur, activated manually or automatically. The system
capability of alerting all individuals in a building ensure everyone is protected
and evacuate safely. Insurance fees are reduced at premium rates as well for
buildings installed with proper fire alarm system.
The system consists of a control panel that is connected to the smoke
detectors; break glass alarm trigger, heat detectors, water sprinklers, fire
alarm bell etc. During the fire activity, the heat detector will set off the water
sprinkler and fire alarm bell within the premises simultaneously.
Diagram of Fire Alarm System
90. Types of fire protection gadgets
Break Glass Alarm Trigger
Image of Fixture
Product Dimension (mm) 86mm x 86mm x 50mm
Voltage Range 24V DC
Alarm Current 30mA
Material Fire Proof Plastics
Weight 200g
Color Red
Sub-Function Phone jack: Confirmation
LED: Reset button
Quantity 6
KELUAR Signage
Image of Fixture
Product Dimension (mm) 576mm x 71mm x 165mm
Operating Voltage 240 VAC
Emergency Operation Duration Min. 4 hours
Light Source Super bright white LED
Charger Solid State Charger
Face Single
Enclosure Material ABS Engineering Plastic
Weight 1kg
Quantity 5
91. Dry Powder Fire Extinguisher
Image of Fixture
Product Dimension (mm) 405mm Height, 130mm DIA.
Propellant Nitrogen
Capacity 3kg dry powder
Head Valve Controllable Brass Valve with
Gauge
Working Temperature Range -20°C ~ 60°C
Discharge Time > 9sec.
Approx. Effective Range 3m
Body Material Mild Steel
Fire Rating 13A/55B
Quantity 6
Heat Detector
Image of Fixture
Product Dimension (mm) 111m DIA. x 45mm
Ambient Temperature 0°C ~ 55°C
Voltage Range 12V ~ 30V DC
Alarm Current 40mA
Material Fire-Proof Plastic
Weight 130g
Color White
Quantity 3
92. Fire Alarm
Image of Fixture
Product Dimension (mm) 152.4mm DIA.
Current Draw 0.030A
Operating Temperature Range -31°F ~ 140°F
Operating Voltage Range 19.2 - 26.4 V DC
Sound Output 85 dBA
Quantity 2
Fire Alarm Control Panel
Image of Fixture
Product Dimension (mm) 510mm x 1220mm x 230mm
Power Supply Input 240V AC 50Hz
Charger Auto
End of Line 8K2 Ohms
Auxiliary Output 24V 1Amp
Quantity 1
93. 7.4 Mechanical ventilation system
Types of indoor and outdoor units
Types of Fixture LG A5UQ48GFA0 5.0HP
Inverter Outdoor Unit
Image of Fixture
Product Dimension (mm) 950mm x 1170mm x 330mm
Cooling Capacity 7640 ~ 48000 ~ 55200
Total Piping Length (Max.) 85m
Power Supply ø,V,Hz 1/230/50
Net Weight 84kg
No. of Connection to Indoor Units (Max.) 5
Quantity 1
Types of Fixture LG - 18k BTU - Ceiling Cassette with Grille
Image of Fixture
Product Dimension (mm) 711.2mm x 711.2mm x 60.96mm
Air Flow 388CFM - 459CFM
Remote Control Wireless
Voltage 208Volts
Frequency 60Hz
Net Weight 19kg
Quantity 3
94. Types of Fixture LIBERO-E- 2.5kW Wall Mounted Inverter Air
Conditioner
Image of Fixture
Product Dimension (mm) 885mm x 285mm x 210mm
Air Flow 12m³/min - 27m³/min
Total Piping Length 3m - 15m
Power Supply Ø/V/HZ 1 / 220-240/ 50
Frequency 47Hz
Net Weight 11kg
Quantity 1
Ground floor plan
97. 7.6 Cost breakdown
No. Item Quantity Cost Total cost
Air Conditioning System
1
LG A5UQ48GFA0 5.0HP Inverter
Outdoor Unit
1 8840 8840
2
LG - 18k BTU - Ceiling Cassette
with Grille
3 4200 12600
3
LIBERO-E 2.5kW Wall Mounted
Inverter Air Conditioner
1 915 915
Electrical System
4 Lighting Timer 1 27 27
5 Distribution Box 1 180 180
6 Electric Meter 1 106 106
Light Fixtures
7 Philips Pendant LED Bulb 25 85 2125
8 Patio Light Stringer 15 19.80 297
9 PLT LED Edison Bulb 60 21 1260
10
ELINKUME Sconce Lighting
Lamp
13 170 2210
Plug points
11 10A One Gang One Way Switch 6 7 42
12 10A Two Gang One Way Switch 3 10 30
13 10A Three Gang One Way Switch 2 13 26
Drainage System
14
32-315mm uPVC Non-Pressure
Soil and Waste pipe
80
0.64-
424.20
16000
Rainwater Harvesting System
15
Harvest Rainwater Lightweight
PVC Rain Drain Pipe
140 0.42-7.64 1000
Fire Protection System
16 Break Glass Alarm Trigger 6 32 192
17 Econlite KELUAR Signage 5 118 590
18
Fire Fighter Dry Powder Fire
Extinguisher
6 115 690
19 Heat Detector 3 130 390
20 Fire Alarm Bell 2 130 260
21 Fire Alarm Control Panel 1 510 510
Total cost for M&E engineering: RM48290
98. 8.0 Costing
8.1 Property details
Location : No.1, Jalan Taylor’s, 47500 Subang Jaya,
Selangor Dahrul Ehsan, Malaysia.
Proposed Site : In existing open car park (Zone I), facing road
turning corner.
Function : Recreation Station
Time Frame : 1 year
Total Build up Area : 600m2
Project Budget : RM1,500,000
Estimated price per sq. ft: RM232
99. 8.2 Overcoming limited budget
All consultants had come to an agreement of using second hand shipping
containers as building components instead of buying new shipping containers
which costs 3 times higher.
Container Details
20′ container 40′ container
external
dimensions
length 6.058 m 12.192 m
width 2.438 m 2.438 m
height 2.591 m 2.591 m
interior
dimensions
length 5.867 m 12.032 m
width 2.352 m 2.352 m
height 2.385 m 2.385 m
door
aperture
width 2.343 m 2.343 m
height 2.280 m 2.280 m
internal volume 33.1 m³ 67.5 m³
maximum
gross weight
30,400 kg 30,400 kg
empty weight 2,200 kg 3,800 kg
New container which costs RM15,000 Used container which costs RM4,800
100. net load 28,200 kg 26,200 kg
8.2 Bill of quantities
Architectural
Item Description Unit
Unit
Price
(RM)
Quantity
Amount
(RM)
Container
1 20ft (Used) unit 4800 6 28800
2 40ft (Used) unit 7000 8 56000
Floor
Timber Floor Decking M2
50
3
2590mmx12000mm Timber Floor
Decking
unit 775 8 12400
4
2590mmx6000mm Timber Floor
Decking
unit 387.5 6 4650
Wall
Container Wall Insulation Foam
Panels
M2
5
5
2590mmx12000mm Insulation
Foam Panels
unit 155 11 1705
6
2590mmx6000mm Insulation
Foam Panels
unit 77.5 8 620
7
2590mmx2400mm Insulation
Foam Panels
unit 31 17 527
Container Timber Wall Decking M2
36
8
2590mmx12000mm Timber Wall
Decking
unit 372 11 12276
9
2590mmx6000mm Timber Wall
Decking
unit 186 8 4464
10
2590mmx2400mm Timber Wall
Decking
unit 75 17 3825
WIndows
11
1700mmx950mm window with
aluminum framing
unit 200 3 600
12
1400mmx650mm window with
aluminum framing
unit 170 3 510
13
1400mmx500mm window with
aluminum framing
unit 160 3 480
14 1400mmx700mm window with unit 180 6 1080
101. aluminum framing
15
4950mmx2400mm glazing
tempered glass with steel frame
unit 3500 1 3500
16
2590mmx2400mm glazing
tempered glass with steel frame
unit 2000 6 12000
Doors
17
2500mmx3000mm double leaf
glass door with steel frame
unit 420 3 1260
Washrooms
18 Ceramic Basin unit 200 4 800
19 Ceramic Toilet Bowl unit 500 8 4000
20 Partition Wall unit 200 9 1800
Total 151297
Civil and Structural
Item Description Unit
Unit Price
(RM)
Quantity
Amount
(RM)
Substructure
Excavation
1
Machine excavation remove top
soil
unit 300 16 4800
2
Excavation on trench to receive
raft foundation
unit 78 30 2340
Foundation
3
Precase reinforced concrete
(grade 45) raft
M3
20 75 1500
4
Foundation mild steel high tensile
to raft foundation trench
kg 2 2000 4000
5
Reinforced concrete (grade25) in
substructural works
M3
35 300 10500
6 Asphalt paving, road work M2
110 1200 132000
Superstructure
Structural Steel Work
7
Universal steel beam (4.8m x 8);
(84.5kg/m)
kg 2 3245 6490
8
Universal steel column (3.3m x
12); (84.5kg/m)
kg 2 3346 6692
9 Apply 1 coat of intumescent 1 kg 12 200 2400
102. hour fire-rating paint to hot dipped
galvanized structural steel
PVC coated tensile waterproof
membrane roof
M2
30 60 1800
Joints
10
Stainless steel plate (200mm x
210mm)
unit 11 60 660
Staircase and finishes
11
Stainless Steel Staircase with hot
dipped galvanised finish (overall
size 912mm x 6970mm x 3450mm
high)
unit 3152 3 9456
Total 182638
Mechanical and Electrical
Item Description Unit
Unit Price
(RM)
Quantity
Amount
(RM)
Air Conditioning System
1
LG A5UQ48GFA0 5.0HP Inverter
Outdoor Unit
unit 8840 1 8840
2
LG - 18k BTU - Ceiling Cassette
with Grille
unit 4200 3 12600
3
LIBERO-E 2.5kW Wall Mounted
Inverter Air Conditioner
unit 915 1 915
Electrical System
4 Lighting Timer unit 27 1 27
5 Distribution Box unit 180 1 180
6 Electric Meter unit 106 1 106
Light Fixtures
7 Philips Pendant LED Bulb unit 85 25 2125
8 Patio Light Stringer unit 19.80 15 297
9 PLT LED Edison Bulb unit 21 60 1260
10
ELINKUME Sconce Lighting
Lamp
unit 170 13 2210
Plug points
11 10A One Gang One Way Switch unit 7 6 42
103. 12 10A Two Gang One Way Switch unit 10 3 30
13 10A Three Gang One Way Switch unit 13 2 26
Drainage System
14
32-315mm uPVC Non-Pressure
Soil and Waste pipe
m
0.64-
424.20
80 16000
Rainwater Harvesting System
15
Harvest Rainwater Lightweight
PVC Rain Drain Pipe
m 0.42-7.64 140 1000
Fire Protection System
16 Break Glass Alarm Trigger unit 32 6 192
17 Econlite KELUAR Signage unit 118 5 590
18
Fire Fighter Dry Powder Fire
Extinguisher
unit 115 6 690
19 Heat Detector unit 130 3 390
20 Fire Alarm Bell unit 130 2 260
21 Fire Alarm Control Panel unit 510 1 510
Total 48290
Landscape
Item Description Unit
Unit Price
(RM)
Quantity
Amount
(RM)
Soft scape
1
5mm Polycarbonate Awning
Pergola (including installation)
unit 2000 1 2500
2 Windsor Teak Garden Bench unit 800 4 3200
3
Bamboo furniture garden set (4
chairs + 1 coffee table with glass
top)
set 1200 4 4800
4
Outdoor WPC decking floor wood
plastic composite (including
installation)
M2
150 16 2500
5 White granite gravels ton 600 50 30000
6
Trellis lattice panel (120cm X
250cm)
unit 160 2 320
7 Clay bricks (720pcs/pallet) unit 270 8 2160
Hardscape
8 Red sealing wax palm unit 150 7 1050
104. 9 Red ginger plant unit 35 60 2100
10 Big-sage unit 30 20 600
11 Ashoka unit 200 8 1600
12 Spider plant unit 20 18 360
13 Dwarf Geometry tree unit 250 7 1750
Total 52940
Labour
Item Description Days
Rate/Day
(RM)
Quantity
Amount
(RM)
1 Carpenter 40 90 4 14400
2 Skilled Worker 30 120 8 28800
3 General Worker 60 90 10 54000
4 Electrician 15 120 5 9000
5
Rainwater Harvesting System
Installer
5 120 3 1800
6 Plant and Equipment Operator 40 120 5 24000
Total 132000
Total Construction Cost
Item Description
Amount
(RM)
1 Architectural 151297
2 Civil and Structural 182638
3 Mechanical and Electrical 48290
4 Landscape 52940
5 Labour 132000
Total 567165
105. 8.4 Summary
After the estimations and calculations of the construction cost, the total
construction cost for the Recreation Station is RM565,365. The amount
mentioned excludes the cost and rental of the land as the land has already
been owned by the client, Taylor’s University.
Other Cost
Ite
m
Description
Percentage
(%)
Construction
Cost (RM)
Amount
(RM)
1 Authority Cost 3 565365 16961
2 Preliminary Cost 5 565365 28268
3
Goods and Service Tax
(GST)
6 565365 33922
4 Material Wastage 10 565365 56537
Total 135688
Consultation Fee
Item Description
Percentage
(%)
Construction
Cost (RM)
Amount
(RM)
1 Project Manager 3 565365 16961
2 Architect 2 565365 11307
3 Civil and Structural Engineer 1.5 565365 8481
4
Mechanical and Electrical
Engineer
1.5 565365 8481
5 Landscape Architect 1 565365 5654
6 Quantity Surveyor 1 565365 5654
Total 56537
27%
32%
9%
9%
23%
Total Construction Cost
Architectural
Civil and
Structural
Mechanical and
Electrical
Landscape
Labour
106. Total Project Cost
Item Description Amount (RM)
1 Construction Cost 567165
2 Other Cost 135688
3 Consultation Fees 56537
Total 759390
The Bar Chart shows the cost of each categories of the entire project. Civil
and Structural has the highest cost among the other categories as the main
issue on site is the land, which needs to be paved to allow better accessibility
on site. Architectural cost is lower than C&S cost as using container as the
main building components contributed a lot on reducing the cost of the
construction. The third highest cost of the project is the labour, as skilled
workers and specialists are needed for the construction of containers and
reduction of construction time.
151297
182638
48290
52940
132000
16961
28268
33922
56537
56537
Architectural
Civil and Structural
Mechanical and
Landscape
Labour
Authority Cost
Preliminary Cost
Goods and Service Tax
Material Wastage
Consultation Fees
0 50000 100000 150000 200000
Amount (RM)
Total Project Cost
107. 9.0 Conclusion
In conclusion, the progression of the “Recreational Station” Project is
expected to be completed by August 2018 and project is set to be a carried
out under a period of 1 year. We would like to summarize the project with the
two objectives that we have set in the proposal stage, which will lead to a
successful completion of the project.
The whole project was planned out precisely following the time and job scope
by using Pert chart and Gantt chart to keep every task on schedule. The
consultants values weekly CCM meetings as the meeting aids in keeping
progress on track and also to have time-to-time update from each consultant
to avoid work delay and to discuss on occasional and accidental issues.
Taylor’s SABD School to have more developed and diverse facilities
Beside on being an architectural workshop, the “Recreational Station”
visualizes more public and students to be aware of the architecture school
and its stand on the international platform by showcasing student projects and
models. The workshop is also an alternative space for students to relax,
socialize and interact, providing social hotspot for students especially during
rainy days or traffic peak hours. Students can also enjoy the diverse activities
happening inside the station that has been prepared by Taylor’s University.
Students are now allowed a more feasible and comfortable space to spend
their time.
Project cost control and management
After an intensive discussion and thoughtful consideration among all the
consultants, every costing of materials and resources were sorted out and
planned critically with the coordination and cooperation from all consultants to
prevent wastage and to reduce the budget spent on unnecessary things, the
project is estimated to be completed within the budget quotes. Besides, labor
and resources were also well planned to prevent any off schedule event from
happening while controlling the project costing within budget given by client.
108. 10.0 Appendix
10.1 Meeting agenda and minutes
Week Date Real life situation Stages
Week 2 6/9/2017 August 2017 Pre-design stage
Week 3 13/9/2017 October 2017 Schematic design stage
Week 4 20/9/2017 December 2017
Design development stage and
documentation stage
Week 5 27/9/2017 February 2018
Documentation and approval
stage
Week 6 4/10/2017 April 2018 Tender and construction stage
Week 7 11/10/2017 July 2018
Construction, CPC, CCC and
handling over stage
109. MINUTES OF WEEKLY STAFF MEETING
Date: 6/9/2017
Time: 10.00am
Attendance: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Absent:
Item Description Action Date of
Action
1. Introduction
The meeting commented at 10:00am and
was chaired by project manager. The
minutes of meeting were confirmed by all in
attendance
Project
Manager
1. Delegation of job scope
1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: Ar. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Each memebers identify their role on the project
and what to expect.
Everyone
2. Presentation of company profile (TWY
consultants) and organizational chart and
skateholders
Project
Manager
3. Site visit
Site visit is conducted by the company on
8/6 with client.
Site is located beside Taylor’s University, Zone
Everyone
110. H car park
4. Project Briefing
Project briefing is done by client (Taylor’s
University) . Recreational district of 600m2 to
be designed and built on allocated land
with a budget of RM1.5M
Client
5. Project Manager to draft Gantt Chart and
Pert Chart
Gantt chart is drafted by project manager.
Each member understand their role and
datelines to meet.
Project
Manager
6. Architect to think of design approach and
concept
Client expect a light weight structure with
fast construction. Architect is to come out
with a contemporary, low energy design.
Architect
7. Conclusion
1) Architect to come out with
presentation of concept to client
2) Project manager to come up with risk
analysis
3) C&S to access soil condition
4) Landscape architect
Everyone
8. Adjournment and next meeting
There being no further matters the meeting
was adjourned at 1:30pm. Next meeting shall
be at 16/9/2017 @ 10:00am
Everyone
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
6/9/2017
111. MEETING AGENDA OF WEEKLY STAFF MEETING
Date: 13/9/2017
Time: 10.00am
Facilitators: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Item Description Action Date of Action
1. Debrief of recent site visit and SWOT
analysis
Clear understanding of site condition,
view and vistas and potential risk for
construction site. SWOT presentation
Everyone
2. Concept presentation Architect
3. C&S Engineer to suggest possible
structural solutions in accordance with
appropriacy and costing, landscape
architect to discuss landscape layout in
line with what the architect visualise
C&S
Engineer,
Landscape
Architect &
Architect
4. Quantity surveyor to state out budget
constraint and alternative structural
component for same design.
Quantity
Surveyor
5. Risk Briefing
Project Manager to discuss risk analysis
and prevention
Client
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
13/9/2017
112. MINUTES OF WEEKLY STAFF MEETING
Date: 13/9/2017
Time: 10.00am
Attendance: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Absent:
Item Description Action Date of Action
1. Debrief of recent site visit and SWOT
analysis
Everyone
2. Requirements briefing
Discussion of land zoning, land survey
and DBKL,Bomba and related authorities
requirements of site
Everyone
3. Schematic design presentation
Climaticalism. 600sqm three floors
container stacking with internal
courtyard and rooftop garden
Architect
4. Structural solutions
C&S engineers suggested raft
foundation and CHS column for support
C&S
Engineer
5. Quantity Survey
Containers to use second hand shipping
containers. Price to be confirmed
Quantity
Survey
6. Risk Analysis
a. soil condition – soft sands & stones
b. Inconvinence to car park
condition. Site is blocking the main
assess.
Project
Manager
113. 7. Project Manager to update Gantt Chart
and Pert Chart
Project
Manager
8. Architect to improve design and amend
layout of design based on client’s
comment
Architect
9. Conclusion
5) Finalized version to be shown next
week
2) Site meeting with project team,
client and contractor
Everyone
10. Adjournment and next meeting
There being no further matters the
meeting was adjourned at 1:30pm. Next
meeting shall be at 20/9/2017 @ 10:00am
Everyone
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
13/9/2017
114. MEETING AGENDA OF WEEKLY STAFF MEETING
Date: 20/9/2017
Time: 10.00am
Facilitators: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Item Description Action Date of Action
1.
1.1
Finalised design & spatial layout
presentation
Architect to present final design and
spatial layout
Discussion with fellow parties on each
components
Everyone
2. Possible structural layout and
connections presentation and discussion
C&S
Enginner
3. Budget estimation
First round of budget estimation
according to finalised design. Discussion
with fellow members on balance and
allocatation of budget on different
component of project.
Quantity
Surveyor
4. Landscape design
Discussion of possible plantations and
furnitures (hardscape design) to be used
based on site condition and budget.
Landscape
architect
4. Briefing of latest progress and response
from authorities on site requirements and
human resources.
Project
Manager
115. 5. Risk Briefing
Project Manager to discuss risk analysis
and prevention
Client
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
20/9/2017
116. MINUTES OF WEEKLY STAFF MEETING
Date: 20/9/2017
Time: 10.00am
Attendance: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Absent:
Item Description Action Date of
Action
1.
1.1
1.2
1.3
1.4
Architect’s to present finalized design/ spatial
layout concept after amendment requested
by client.
Landscape architect brainstormed with
relevent parties of initial landscape concept
according to architect’s designintention
Structural concern and suggestion presented
by Structural engineer based on structural
integrity, sustainability and appropriaty on site.
M&E discussion with fellow members on
potential energy saving qualities based on
design and also thermal/lighting feasibility
studies
Feasibility study with team based on design
Everyone
2.
2.1
2.2
2.3
Architect & team
Architect and parties to produced finalised
plans and section and prepare for authorities
submission
Company to produced 1:100 physical model
of site and proposed building
Produce complete 3d model (BIM) to show
further detail of buiding components.
Architect
3. C&S Engineering
To work closely with architect to resolve issues
C&S Engineer
117. on foundation and agreed CHS connetions to
stairs and containers.
4.
4.1
4.2
4.3
Quantity Survey
First round of budget estimation and suggest
alternative for materials with better
performance and appearance with lower
cost.
Budget and finance report, human resources
control
Second hand containers
(40” RM7000, 20” RM5000)
Quantity
surveyor
4. M&E Engineering
Confirmation of size of container and
proposed lighting type. Lighting and Electrical
layout to be discussed next week.
M&E Engineer
5. Project Manager to update Gantt Chart and
human resources report
Project
Manager
6.
6.1
Landscape proposal
Possible plantation and hardscape design based
on architect proposal and budget and quantities
to be aligned with finalised plan and budget.
Possible concrete walkway and gravel flooring at
interior courtyard.
Landscape
Architect
7. Conclusion
1) Each member to proceed with what are
discussed today
2) Site meeting with project team, client and
contractor
Everyone
8. Adjournment and next meeting
There being no further matters the meeting was
adjourned at 1:30pm. Next meeting shall be at
27/9/2017 @ 10:00am
Everyone
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
20/9/2017
118. MEETING AGENDA OF WEEKLY STAFF MEETING
Date: 27/9/2017
Time: 10.00am
Facilitators: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Item Description Action Date of Action
1.
1.1
Drawing submission and review
Architect to discuss amendments on
design and components.
Discussion with fellow parties on each
components
Everyone
2. Confirm with a architect on structural
dimensions and earthwork submission
dateline from DBKL
C&S
Enginner
3. Update on material supply and
selections
To discuss with architect whether the
found source suits architect’s design
Quantity
Surveyor
4. Landscape design
Finalised landscape design and
vegetation selection
Landscape
architect
5. Schematic diagram of M&E system
based on architect’s drawings
M&E
Engineer
6. Progress check
Project Manager to discuss latest
progress and Gantt chart
Project
Manager
7. Client to confirm with architect with final Client
119. design and material selection on
meeting
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
27/9/2017
120. MINUTES OF WEEKLY STAFF MEETING
Date: 27/9/2017
Time: 10.00am
Attendance: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Absent:
Item Description Action Date of
Action
1.
1.1
1.2
1.3
1.4
Architect and team to submit bomba
drawings and door & windows schedule for
submission
Confimation with landscape engineer, C&S
engineer and client on selected materials.
Structural engineer to confirm date of site
clearance after authority submissions
approval next week
Project Manager to confirm with container
supplier and offsite preparation
Quantity survey to look for water resistance
outdoor paint for container to prevent
corrosion
Everyone
2.
2.1
2.2
Architect & team
Authority submission appproval and bomba
approval this week. Prepare for tender
process
3d model (BIM) detailing of piping and M&E
system
Architect
3.
3.1
3.2
C&S Engineering
Foundation padding and CHS connection
revised
Amend dimension and orientation of structure
based on architect’s drawing
C&S Engineer
121. 4.
4.1
4.2
Quantity Survey
Second round budget estimation and
discussion on budget constraint
Finalize cost wih M&E engineer and
landscape architect by next meeting
Estimate laborer needed and contact HR
agency
Quantity
Surveyor
5.
5.1
5.2
5.3
5.4
M&E Engineering
Confimed electrical layout and drainage
system.
Ventilation for toilet- openings (discuss on
design detail)
Air ventilation duct above office and chill
zone to be connected to roof, condenser
units
Bomba submission in lieu with architect
M&E Engineer
5. Project Manager to update Gantt Chart and
human resources report
Project
Manager
6.
6.1
Landscape confirmation
Lndscape architect shown proposed landscape
renderings
Proposed plants for tropical climate such as spider
plant and Daeng Malaysia Ixora
Pathway and vegetation beside drainage to be
confirmed with architect and C&S engineer
Landscape
Architect
7. Conclusion
1) Each member to proceed with what are
discussed today
2) Revised costing on next week
Everyone
8. Adjournment and next meeting
There being no further matters the meeting was
adjourned at 1:30pm. Next meeting shall be at
4/10/2017 @ 10:00am
Everyone
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
27/9/2017
122. MEETING AGENDA OF WEEKLY STAFF MEETING
Date: 4/10/2017
Time: 10.00am
Facilitators: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Item Description Action Date of Action
1. Tender close and award of tender this
week
Everyone
2. Site clearing and hoarding installation
schedule
containers and building materials
delivery schedule next week
Container assembly, floor assembly and
M&E work week after.
Project
Manager,
C&S
Engineer
3. Final expenses quotation & capitalisation
expect second half of remittance from
client and prepare expenses on payday
to members and laborers.
Quantity
Surveyor
4. Vegetation supplier confirmed, finalised
hardscape design with architect
Landscape
architect
5. Air ventilation, stormwater & wastewater
piping installation, water storage on roof,
aircon installation in office and chill zone.
Outdoor and indoor lightings
confirmation with architect and supplier.
M&E
Engineer
6. Excavation
In-charge of site clearing next week,
Project
Manager
123. schedule briefing with workers
7. Remit charges to company and visitation
during site clearing
Client
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
4/10/2017
124. MINUTES OF WEEKLY STAFF MEETING
Date: 4/10/2017
Time: 10.00am
Attendance: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Absent:
Item Description Action Date of
Action
1.
1.1
Award of tender this week
Procurement contract awarded and
construction phase starts next week
Everyone
2.
2.1
2.2
2.3
2.4
2.5
Site clearing
Site clearing on next Monday 9/10/17 and
hoarding installation, and to be supervised by
Project Manager
Structure installation
Pipings and foundation work on Friday
13/10/17
Container delivery and assembly, tensile roof
installation on following week
Project
Manager,
C&S Engineer
3.
3.1
3.2
Tender analysis and agreement of the
contract sum
Revised final detailed bill of quantities,
presented to the team and client.
Whole life cycle costing estimation next week
Quantity
surveyor
4.
4.1
4.2
Hardscape confirmation
Hardscape confirmation with architect,
selection of furnitures and vegetation.
To work with C&S Engineer and project
manager on roadwork schedule, brick paving
and excavation for plants.
Landscape
architect
125. 5.
5.1
5.2
M&E Engineering
water piping and drainage system installation
schedule on 16/10/17 for one week, to work
with C&S engineer
Mechanical ventilation and lightings
instalation on week after (Confirmation on
specs with architect and supplier)
M&E Enginner
6. Project Manager to update Gantt Chart, Per
chart and reallocate time allowance for
installation
To be in-charged of site clearing next week
and schedule briefing with workers and
suppliers. Transportation schedule.
Project
Manager
7. Client to be on site on next Monday 9/10/17 for
groundbreaking ceremony at 8:00am
Client
8. Adjournment and next meeting
There being no further matters the meeting was
adjourned at 1:30pm. Next meeting shall be at
11/10/2017 @ 10:00am
Everyone
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
4/10/2017
126. MEETING AGENDA OF WEEKLY STAFF MEETING
Date: 11/10/2017
Time: 10.00am
Facilitators: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Item Description Action Date of Action
1. Finishing and furniture installation next
week
-Installation schedule
Everyone
2. Landscape work , brick pavement and
roadwork
-Confirmation with team
-Schedule
-Contact with roadwork company
Project
Manager,
Landscape
Architect
3. Complete finance report & M&E
installation expenses
Quantity
Surveyor
4. Site cleanup and authority inspection
-Confirm schedule and demarcation
date
-Bomba inspection
Project
Manager,
Architect,
Client
5. Handling over
-Completion date and CCC
-Visitation with client and company team
Project
Manager,
Architect
6. Opening ceremony
-fix date and last meeting with client
Project
Manager
127. Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
11/10/2017
128. MINUTES OF WEEKLY STAFF MEETING
Date: 11/10/2017
Time: 10.00am
Attendance: 1) Architect: Ar. Jack Too Mun Fai
2) C&S Engineer: Ir. Bryan Yeoh Xiang Ann
3) Project Manager: Ar. James Wong Zhen Fai
4) Landscape Architect: PLA. Tan Wen Hao
5) Quantity Surveyor: Sr. Teo Hong Wei
6) M&E Engineer: Ir. Yan Wai Chun
Absent:
Item Description Action Date of
Action
1.
1.1
Finishing and furniture installation next week
Furniture installation on 12/10/17 Thursday and
artificial turf paving on roof. Tensile fabric
installation on 14/10/17
Everyone
2.
2.1
2.2
2.3
2.4
2.5
Landscape work
Landscape (vegetation plantation and
outdoor furniture (gondola installation, bench)
on next Wednesday 18/10/17 and gravel
laying and on Friday 20/10/17.
Brick pavement and roadwork
Surrounding brick paving on Monday
23/10/17 and roadwork to be tentatively at
Wednesday 25/10/17 until further notice from
road construction company PPMs Asphalt
Project
Manager,
Landscape
Architect
3.
3.1
3.2
Finance report
Finalized finance report
Additional expenses on extra working hours on
M&E installation
Quantity
surveyor
4.
4.1
Site cleanup and authority inspection
Site cleanup at Friday 27/10/2017,with parking
lot, boundary line demarcation and painting
the day after.
Authority inspection on Monday 30/10/2017
Project
Manager,
Architect,
client
129. 4.2 M&E and Bomba inspection by related
authorities
5. Handling over
Construction phase will end at Sunday
29/10/2017. Completion and handling over of
project will be at Wednesday 1/11/2017 after
CCC being awarded.
Project
Manager,
Architect
6. Visitation with client and company team
before opening at 3/11/2017
Client
7. Adjournment and last meeting
There being no further matters the meeting was
adjourned at 1:30pm. Opening ceremony will be
at 6/11/2017 Monday.
Everyone
Minutes taken by:
PLA. Tan Wen Hao
Minutes reviewed by:
Ar. James Wong Zhen Fai
Minutes verified by:
Ar. Jack Too Mun Fai
11/10/2017
130. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
SECOND FLOOR PLAN
SCALE 1:100
Swift
131. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
ROOF PLAN
SCALE 1:100
Swift
132. JackedOff Studio Sdn Bhd
Taylor's University Sdn. Bhd.
SWIFT MECHANICAL & ELECTRICAL SDN. BHD.
BY CIVIL & STRUCTURAL SDN. BHD.
JDSCAPE SDN. BHD.
THW QUANTITY SURVEYOR SDN. BHD.
J.O
SECTION B - B
SCALE 1:100
Swift
SECTION A - A
SCALE 1:100