Design, Supply, Installation, Testing and
Commissioning
of In and Out Arrangement of
500kV Guddu-Multan 3rd Circuit at Rahim Yar Khan
500kV Substation.
Project Report
November 2011
Project Management , Dep.
GAM ARAK Ind.co.
INTRODUCTION
General Introduction of the Project
The facilities to be executed under this project (Package-II) comprise Design, Supply, Installation, Testing
and Commissioning of In and Out Arrangement of 500kV Guddu-Multan 3rd Circuit at Rahim Yar Khan
500kV Substation.
The facilities under the subject Package-II was awarded to Gam Arak Ind. Co. The Notification of Award
(NOA) was issued by General Manager, (GSC) South, NTDC on September 2nd, 2010 and contract was
signed on February 2nd, 2011. The work under this contract comprises Design and Engineering,
Procurement and supply of Materials, Soil Investigation, construction of Foundations, Tower Erection,
Stringing and Testing and Commissioning Transmission line. The construction of the subject project is
being financed by Japanese Bank of International Cooperation (Loan No.PK-P58). The local currency
portion is financed by National Transmission & Dispatch Company Ltd. (NTDC).
Rahim Yar Khan 500/220 kV Grid Station is located in the Penjab Province of Pakistan. The Substation
site is located on main National Highway at a distance of 680 Km from Karachi and 185 Km from Sukkur.
The In and Out Arrangement shall be made at Rahim Yar Khan 500 kV Substation of 500kV Guddu-Multan
3rd Circuit. The salient feature of transmission line is crossing of Indus River between Mithon Kot and
Chachran.
In and Out Arrangement of 500kV Guddu-Multan 3rd Circuit at Rahim Yar Khan 500kV Substation with
Quad Bundle ACSR “Drake” Conductor (about 30+30 Km) of Rahim Yar Khan 500kV Substation and
Associated 500kV transmission line project shall be constructed and completed on design, manufacture,
supply, installation, testing and commissioning basis, in accordance with the contract documents.
Employer has nominated “NESPAK+BARQAAB joint Venture” as their Representative on this project.
Time for completion of all the facilities as a whole is 823 days determined from the effective datem which
is May 4th, 2011.
PLANNING
The contract completion period was 823 days and planning was made to complete the project on time. In
this regard we deputed a team of experienced Engineers & Supervisors as per site Organization Chart.
The Project Time Schedule was initially submitted to Employer’s Representative vide our letter No.90-
425 dated 09.04.2011. Due to delay in receiving the Local Currency Component (LCC) Advance Payment
(May 4th, 2011), nearly 2 months after date of invoice (March 3rd, 2011), the time schedule was revised
and submitted to NESPAK Head Office vide letter No.90-2085 dated 09.05.2011, with May 4th, 2011, as
Effective Date.
Description
Overall Project Progress 10.28%
Rahim Yar Khan 500kV
Substation
Engineering
Tower
Construction
Piling &
Foundation
Procurement
Main
StringingSpare partFounation
Structure list
Miscellaneous
OPGW
Testing &
Commisioning
Installation Tower
Dismantling
Project Description
Project Description
Project Description
Project Description

More Related Content

What's hot

FARID CV
FARID CVFARID CV
Oman sndc eng
Oman sndc engOman sndc eng
Oman sndc eng
Mihai Dragne
 
Resume Wizard of Eng Toni Azar- rev1
Resume Wizard of Eng Toni Azar- rev1Resume Wizard of Eng Toni Azar- rev1
Resume Wizard of Eng Toni Azar- rev1
Toni AZAR
 
Amjad - Planning Manager
Amjad - Planning ManagerAmjad - Planning Manager
Amjad - Planning Manager
Amjad Nawaz
 
Presentation Sample KAAU
Presentation Sample KAAUPresentation Sample KAAU
Presentation Sample KAAU
Abdullah Bakhsh
 
PROJECT INVOLVED 2013
PROJECT INVOLVED 2013PROJECT INVOLVED 2013
PROJECT INVOLVED 2013
MUHD HAFIZUDDIN CHE AZMAN
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
Ali Issa
 
Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018
SanjuBK
 
Holmes Run Weir Diversion Structure No. 417
Holmes Run Weir Diversion Structure No. 417Holmes Run Weir Diversion Structure No. 417
Holmes Run Weir Diversion Structure No. 417
Fairfax County
 
Thai IRPC UHV Project ENG
Thai IRPC UHV Project ENGThai IRPC UHV Project ENG
Thai IRPC UHV Project ENG
Mihai Dragne
 
Project Experience
Project ExperienceProject Experience
Project Experience
Richard Dixon
 
Mason Neck Trail - Segment 2B
Mason Neck Trail - Segment 2BMason Neck Trail - Segment 2B
Mason Neck Trail - Segment 2B
Fairfax County
 
Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County
 
cvPaoloAguzziNov16
cvPaoloAguzziNov16cvPaoloAguzziNov16
cvPaoloAguzziNov16
Paolo Aguzzi
 
Holmes Run Weir Diversion Structure February 2016
Holmes Run Weir Diversion Structure February 2016Holmes Run Weir Diversion Structure February 2016
Holmes Run Weir Diversion Structure February 2016
Fairfax County
 

What's hot (15)

FARID CV
FARID CVFARID CV
FARID CV
 
Oman sndc eng
Oman sndc engOman sndc eng
Oman sndc eng
 
Resume Wizard of Eng Toni Azar- rev1
Resume Wizard of Eng Toni Azar- rev1Resume Wizard of Eng Toni Azar- rev1
Resume Wizard of Eng Toni Azar- rev1
 
Amjad - Planning Manager
Amjad - Planning ManagerAmjad - Planning Manager
Amjad - Planning Manager
 
Presentation Sample KAAU
Presentation Sample KAAUPresentation Sample KAAU
Presentation Sample KAAU
 
PROJECT INVOLVED 2013
PROJECT INVOLVED 2013PROJECT INVOLVED 2013
PROJECT INVOLVED 2013
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018
 
Holmes Run Weir Diversion Structure No. 417
Holmes Run Weir Diversion Structure No. 417Holmes Run Weir Diversion Structure No. 417
Holmes Run Weir Diversion Structure No. 417
 
Thai IRPC UHV Project ENG
Thai IRPC UHV Project ENGThai IRPC UHV Project ENG
Thai IRPC UHV Project ENG
 
Project Experience
Project ExperienceProject Experience
Project Experience
 
Mason Neck Trail - Segment 2B
Mason Neck Trail - Segment 2BMason Neck Trail - Segment 2B
Mason Neck Trail - Segment 2B
 
Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County Fleet Drive Walkway Improvements Sept 2020
Fairfax County Fleet Drive Walkway Improvements Sept 2020
 
cvPaoloAguzziNov16
cvPaoloAguzziNov16cvPaoloAguzziNov16
cvPaoloAguzziNov16
 
Holmes Run Weir Diversion Structure February 2016
Holmes Run Weir Diversion Structure February 2016Holmes Run Weir Diversion Structure February 2016
Holmes Run Weir Diversion Structure February 2016
 

Viewers also liked

Power plant tarrif Stratagies
Power plant tarrif StratagiesPower plant tarrif Stratagies
Power plant tarrif Stratagies
Iftikhar Ahmed
 
Gencos rehabilitation 27.03.2013
Gencos rehabilitation 27.03.2013Gencos rehabilitation 27.03.2013
Gencos rehabilitation 27.03.2013
SULTAN ZAFAR
 
Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013
SULTAN ZAFAR
 
3 SPECIALTY
3 SPECIALTY3 SPECIALTY
3 SPECIALTY
Michelle Robinson
 
Emergencias de salud
Emergencias de saludEmergencias de salud
Emergencias de salud
Ivan Borda Ft
 
Commercial Sales of Cloud, Endpoint Protection and GravityZone Security
Commercial Sales of Cloud, Endpoint Protection and GravityZone SecurityCommercial Sales of Cloud, Endpoint Protection and GravityZone Security
Commercial Sales of Cloud, Endpoint Protection and GravityZone Security
Marcio Amaral
 
AnovusPresentation 2015
AnovusPresentation 2015AnovusPresentation 2015
AnovusPresentation 2015
Anovus Inst. of CR
 
Place-Based Learning Supported by Technology
Place-Based Learning Supported by TechnologyPlace-Based Learning Supported by Technology
Place-Based Learning Supported by Technology
S. Otto Khera
 
Energía inalámbrica
Energía inalámbricaEnergía inalámbrica
Energía inalámbrica
Juan Diego Leon
 
Filming session and shot
Filming session and shotFilming session and shot
Filming session and shot
sbegum8321
 
Trabajar la coherencia en clase
Trabajar la coherencia en claseTrabajar la coherencia en clase
Trabajar la coherencia en clase
Daniel Gracia
 
Brian lopez 11.3
Brian lopez 11.3Brian lopez 11.3
Brian lopez 11.3
brianmanceral
 
Partner Roadmap Webinar: Partner Community (April 3, 2014)
Partner Roadmap Webinar: Partner Community (April 3, 2014)Partner Roadmap Webinar: Partner Community (April 3, 2014)
Partner Roadmap Webinar: Partner Community (April 3, 2014)
Salesforce Partners
 
Como usar métodos de design thinking para validar sua ideia no mercado
Como usar métodos de design thinking para validar sua ideia no mercadoComo usar métodos de design thinking para validar sua ideia no mercado
Como usar métodos de design thinking para validar sua ideia no mercado
Priscilla Albuquerque
 
Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations
abrar younas
 
Analysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel MillsAnalysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel Mills
Danial Sohail
 
Presentation By N.A. Zuberi
Presentation By N.A. ZuberiPresentation By N.A. Zuberi
Presentation By N.A. Zuberi
IEEEP Karachi
 
Power sector of pakistan
Power sector of pakistanPower sector of pakistan
Power sector of pakistan
USMAN TARIQ
 
Energy crises in pakistan butt presentation
Energy crises in pakistan butt presentationEnergy crises in pakistan butt presentation
Energy crises in pakistan butt presentation
goodamazing
 
Ux design/Experiência do Usuário - Conexão KingHost 2015
Ux design/Experiência do Usuário - Conexão KingHost 2015Ux design/Experiência do Usuário - Conexão KingHost 2015
Ux design/Experiência do Usuário - Conexão KingHost 2015
Luisa Ambros
 

Viewers also liked (20)

Power plant tarrif Stratagies
Power plant tarrif StratagiesPower plant tarrif Stratagies
Power plant tarrif Stratagies
 
Gencos rehabilitation 27.03.2013
Gencos rehabilitation 27.03.2013Gencos rehabilitation 27.03.2013
Gencos rehabilitation 27.03.2013
 
Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013
 
3 SPECIALTY
3 SPECIALTY3 SPECIALTY
3 SPECIALTY
 
Emergencias de salud
Emergencias de saludEmergencias de salud
Emergencias de salud
 
Commercial Sales of Cloud, Endpoint Protection and GravityZone Security
Commercial Sales of Cloud, Endpoint Protection and GravityZone SecurityCommercial Sales of Cloud, Endpoint Protection and GravityZone Security
Commercial Sales of Cloud, Endpoint Protection and GravityZone Security
 
AnovusPresentation 2015
AnovusPresentation 2015AnovusPresentation 2015
AnovusPresentation 2015
 
Place-Based Learning Supported by Technology
Place-Based Learning Supported by TechnologyPlace-Based Learning Supported by Technology
Place-Based Learning Supported by Technology
 
Energía inalámbrica
Energía inalámbricaEnergía inalámbrica
Energía inalámbrica
 
Filming session and shot
Filming session and shotFilming session and shot
Filming session and shot
 
Trabajar la coherencia en clase
Trabajar la coherencia en claseTrabajar la coherencia en clase
Trabajar la coherencia en clase
 
Brian lopez 11.3
Brian lopez 11.3Brian lopez 11.3
Brian lopez 11.3
 
Partner Roadmap Webinar: Partner Community (April 3, 2014)
Partner Roadmap Webinar: Partner Community (April 3, 2014)Partner Roadmap Webinar: Partner Community (April 3, 2014)
Partner Roadmap Webinar: Partner Community (April 3, 2014)
 
Como usar métodos de design thinking para validar sua ideia no mercado
Como usar métodos de design thinking para validar sua ideia no mercadoComo usar métodos de design thinking para validar sua ideia no mercado
Como usar métodos de design thinking para validar sua ideia no mercado
 
Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations
 
Analysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel MillsAnalysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel Mills
 
Presentation By N.A. Zuberi
Presentation By N.A. ZuberiPresentation By N.A. Zuberi
Presentation By N.A. Zuberi
 
Power sector of pakistan
Power sector of pakistanPower sector of pakistan
Power sector of pakistan
 
Energy crises in pakistan butt presentation
Energy crises in pakistan butt presentationEnergy crises in pakistan butt presentation
Energy crises in pakistan butt presentation
 
Ux design/Experiência do Usuário - Conexão KingHost 2015
Ux design/Experiência do Usuário - Conexão KingHost 2015Ux design/Experiência do Usuário - Conexão KingHost 2015
Ux design/Experiência do Usuário - Conexão KingHost 2015
 

Similar to Project Description

Resume q.surveyor - amanat ali (updated)
Resume   q.surveyor - amanat ali (updated)Resume   q.surveyor - amanat ali (updated)
Resume q.surveyor - amanat ali (updated)
Amanat ali
 
Updated cv (2)
Updated cv (2)Updated cv (2)
Updated cv (2)
Satyeshwar Sharma
 
ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)
ramakant kushwaha
 
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
Shaukat Mahmood Khan
 
Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL
MUDASSAR AFZAL
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
jamsheer p
 
Muhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo
 
CV
CVCV
MCV
MCVMCV
Ehsan Asghar - Hydromechanical Engineer
Ehsan Asghar - Hydromechanical EngineerEhsan Asghar - Hydromechanical Engineer
Ehsan Asghar - Hydromechanical Engineer
EHSAN ASGHAR, RE
 
CV Latest Rosdi PL381
CV Latest Rosdi PL381CV Latest Rosdi PL381
CV Latest Rosdi PL381
rosdi baharuddin
 
V. SRINIVASA RAO CV
V. SRINIVASA RAO CVV. SRINIVASA RAO CV
V. SRINIVASA RAO CV
VEMPARALA SRINIVASA RAO
 
AjayasankarK M _ Engineer
AjayasankarK M _ EngineerAjayasankarK M _ Engineer
AjayasankarK M _ Engineer
Ajay Sankar
 
CURRICULUM VITAE
CURRICULUM VITAECURRICULUM VITAE
CURRICULUM VITAE
Aneeque Ahmed
 
CV M.Ilyas - 1
CV M.Ilyas - 1CV M.Ilyas - 1
CV M.Ilyas - 1
Muhammad Ilyas Memon
 
Arshad Jan CV
Arshad Jan CVArshad Jan CV
Arshad Jan CV
Arshad Jan
 
Civil Engineer Resume
 Civil Engineer Resume Civil Engineer Resume
Civil Engineer Resume
Ravi Kumar
 
New CV of VRB
New CV of VRBNew CV of VRB
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
Virat Vanijya_  Vishwakarma Industrial Park_r.pptxVirat Vanijya_  Vishwakarma Industrial Park_r.pptx
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
SomSaha1
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
oyepuneeta
 

Similar to Project Description (20)

Resume q.surveyor - amanat ali (updated)
Resume   q.surveyor - amanat ali (updated)Resume   q.surveyor - amanat ali (updated)
Resume q.surveyor - amanat ali (updated)
 
Updated cv (2)
Updated cv (2)Updated cv (2)
Updated cv (2)
 
ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)
 
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
 
Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
 
Muhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTS
 
CV
CVCV
CV
 
MCV
MCVMCV
MCV
 
Ehsan Asghar - Hydromechanical Engineer
Ehsan Asghar - Hydromechanical EngineerEhsan Asghar - Hydromechanical Engineer
Ehsan Asghar - Hydromechanical Engineer
 
CV Latest Rosdi PL381
CV Latest Rosdi PL381CV Latest Rosdi PL381
CV Latest Rosdi PL381
 
V. SRINIVASA RAO CV
V. SRINIVASA RAO CVV. SRINIVASA RAO CV
V. SRINIVASA RAO CV
 
AjayasankarK M _ Engineer
AjayasankarK M _ EngineerAjayasankarK M _ Engineer
AjayasankarK M _ Engineer
 
CURRICULUM VITAE
CURRICULUM VITAECURRICULUM VITAE
CURRICULUM VITAE
 
CV M.Ilyas - 1
CV M.Ilyas - 1CV M.Ilyas - 1
CV M.Ilyas - 1
 
Arshad Jan CV
Arshad Jan CVArshad Jan CV
Arshad Jan CV
 
Civil Engineer Resume
 Civil Engineer Resume Civil Engineer Resume
Civil Engineer Resume
 
New CV of VRB
New CV of VRBNew CV of VRB
New CV of VRB
 
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
Virat Vanijya_  Vishwakarma Industrial Park_r.pptxVirat Vanijya_  Vishwakarma Industrial Park_r.pptx
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
 

Project Description

  • 1. Design, Supply, Installation, Testing and Commissioning of In and Out Arrangement of 500kV Guddu-Multan 3rd Circuit at Rahim Yar Khan 500kV Substation. Project Report November 2011 Project Management , Dep. GAM ARAK Ind.co.
  • 2. INTRODUCTION General Introduction of the Project The facilities to be executed under this project (Package-II) comprise Design, Supply, Installation, Testing and Commissioning of In and Out Arrangement of 500kV Guddu-Multan 3rd Circuit at Rahim Yar Khan 500kV Substation. The facilities under the subject Package-II was awarded to Gam Arak Ind. Co. The Notification of Award (NOA) was issued by General Manager, (GSC) South, NTDC on September 2nd, 2010 and contract was signed on February 2nd, 2011. The work under this contract comprises Design and Engineering, Procurement and supply of Materials, Soil Investigation, construction of Foundations, Tower Erection, Stringing and Testing and Commissioning Transmission line. The construction of the subject project is being financed by Japanese Bank of International Cooperation (Loan No.PK-P58). The local currency portion is financed by National Transmission & Dispatch Company Ltd. (NTDC). Rahim Yar Khan 500/220 kV Grid Station is located in the Penjab Province of Pakistan. The Substation site is located on main National Highway at a distance of 680 Km from Karachi and 185 Km from Sukkur. The In and Out Arrangement shall be made at Rahim Yar Khan 500 kV Substation of 500kV Guddu-Multan 3rd Circuit. The salient feature of transmission line is crossing of Indus River between Mithon Kot and Chachran. In and Out Arrangement of 500kV Guddu-Multan 3rd Circuit at Rahim Yar Khan 500kV Substation with Quad Bundle ACSR “Drake” Conductor (about 30+30 Km) of Rahim Yar Khan 500kV Substation and Associated 500kV transmission line project shall be constructed and completed on design, manufacture, supply, installation, testing and commissioning basis, in accordance with the contract documents. Employer has nominated “NESPAK+BARQAAB joint Venture” as their Representative on this project. Time for completion of all the facilities as a whole is 823 days determined from the effective datem which is May 4th, 2011. PLANNING The contract completion period was 823 days and planning was made to complete the project on time. In this regard we deputed a team of experienced Engineers & Supervisors as per site Organization Chart. The Project Time Schedule was initially submitted to Employer’s Representative vide our letter No.90- 425 dated 09.04.2011. Due to delay in receiving the Local Currency Component (LCC) Advance Payment (May 4th, 2011), nearly 2 months after date of invoice (March 3rd, 2011), the time schedule was revised and submitted to NESPAK Head Office vide letter No.90-2085 dated 09.05.2011, with May 4th, 2011, as Effective Date.
  • 3. Description Overall Project Progress 10.28% Rahim Yar Khan 500kV Substation Engineering Tower Construction Piling & Foundation Procurement Main StringingSpare partFounation Structure list Miscellaneous OPGW Testing & Commisioning Installation Tower Dismantling