“Construction and Contracts Engineering Professional with more than10 years of hands on experience in Mega Multi-discipline Energy Sector and Building Utilities projects, having key Skills of Supervision, QA/QC, FATs, Erection of; Hydropower Plant, Hydraulic Gates, Cranes, Tunnel Steel Lining, Mechanical Equipment (Static, Rotating, Piping) & Allied Steel Structures, HVAC System and MEP Works. Acquainted with FIDIC, Preparation and Evaluation of Contract / Tender Documents, Claims and Variation Orders.
Worked with renowned lenders including World Bank - WB, Asian Development Bank - ADB, Islamic Development Bank – IDB, International Finance Corporation – IFC and Commonwealth Development Corporation - CDC.”
A Chartered Engineer with decade of experience in Mechanical Maintenance of Drilling Rig Equipment and Reactor Engineering Plant. Competent in Major Maintenance of Drilling Rigs (Onshore & Offshore) through Third Parties including OEMs. Competent in SAP (PM & MM), Windows 7 & 8 and MS Office 2010. Seeking immediate employment, available.
A Chartered Engineer with decade of experience in Mechanical Maintenance of Drilling Rig Equipment and Reactor Engineering Plant. Competent in Major Maintenance of Drilling Rigs (Onshore & Offshore) through Third Parties including OEMs. Competent in SAP (PM & MM), Windows 7 & 8 and MS Office 2010. Seeking immediate employment, available.
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...Qamar Ahmad
• Study of project and drawing as per planning sheet
• Work out of erection time and cost of project
• Site visit to check condition of the site and discuss with client regarding erection of equipment
• Allocate the workmen depending upon the erection schedule
• Allocate the requirement/facilities based upon the requirement.
• Specialized to do the modification at site as per the process requirement
• Knowledge of erection & fabrication drawings & PID drawings
• Provide solutions and fixed Crane or Hoist malfunctioning, modifications and performed replacements and /or new installation
• Assigned personnel and technical support teams to sites requiring erection
• Design and implemented special strategies related to erection procedures
• Inspection of assembled equipment, to ensure proper installation.
• Inspection of all operating parts to ensure proper operation within expected tolerances.
• Clearly and professionally interact with customer, regarding status of erection, on a daily basis
• Interact with internal and external project managers during field projects
• Preparing schedule and planning using MS Office and Word.
• Preparing of project documents such as weekly report, progress report, erection plan, precost and actual cost of projects, bar chart of projects etc
• Site visit for training and troubleshooting to client.
Dear Sir/madam,
I would like to introduce myself as a Mechanical engineer with 7 months of experience in designing & site execution of Mechanical works.
Currently I am on a visit visa seeking an opportunity to secure a challenging and competitive position as a Mechanical Engineer in a reputed organization that enables me to share and enrich my knowledge in all possible dimensions.
Please find my attached CV for your consideration, and if there is any vacancy in your firm kindly let me know. For further details about my profile you can contact me on my below given mobile no. or email.
Best Regards,
HAMID ABDUL SAMI
MOBILE: 0559546542
E-MAIL: hamidasami1606@gmail.com
00 resume of site supervisor (Pipeline & welding)Mohammad Khan
Result-oriented with a fast-learning curve and an ability to take calculated risks, defining business mission and integrating resource strengths to deliver impeccable performances aligned to overall objectives .A dynamic professional offering over 15 years in the field of Site Supervisory position for (Pipeline), Erection in Pipeline, in Oil & Gas, Refinery, Petrochemicals, & Power Plant in Saudi Arabia, U.A.E, Kuwait & India for Various Eng. Construction Projects.
Mechanical Engineer having 5+ years experience in Erection & Commissioning En...Qamar Ahmad
• Study of project and drawing as per planning sheet
• Work out of erection time and cost of project
• Site visit to check condition of the site and discuss with client regarding erection of equipment
• Allocate the workmen depending upon the erection schedule
• Allocate the requirement/facilities based upon the requirement.
• Specialized to do the modification at site as per the process requirement
• Knowledge of erection & fabrication drawings & PID drawings
• Provide solutions and fixed Crane or Hoist malfunctioning, modifications and performed replacements and /or new installation
• Assigned personnel and technical support teams to sites requiring erection
• Design and implemented special strategies related to erection procedures
• Inspection of assembled equipment, to ensure proper installation.
• Inspection of all operating parts to ensure proper operation within expected tolerances.
• Clearly and professionally interact with customer, regarding status of erection, on a daily basis
• Interact with internal and external project managers during field projects
• Preparing schedule and planning using MS Office and Word.
• Preparing of project documents such as weekly report, progress report, erection plan, precost and actual cost of projects, bar chart of projects etc
• Site visit for training and troubleshooting to client.
Dear Sir/madam,
I would like to introduce myself as a Mechanical engineer with 7 months of experience in designing & site execution of Mechanical works.
Currently I am on a visit visa seeking an opportunity to secure a challenging and competitive position as a Mechanical Engineer in a reputed organization that enables me to share and enrich my knowledge in all possible dimensions.
Please find my attached CV for your consideration, and if there is any vacancy in your firm kindly let me know. For further details about my profile you can contact me on my below given mobile no. or email.
Best Regards,
HAMID ABDUL SAMI
MOBILE: 0559546542
E-MAIL: hamidasami1606@gmail.com
00 resume of site supervisor (Pipeline & welding)Mohammad Khan
Result-oriented with a fast-learning curve and an ability to take calculated risks, defining business mission and integrating resource strengths to deliver impeccable performances aligned to overall objectives .A dynamic professional offering over 15 years in the field of Site Supervisory position for (Pipeline), Erection in Pipeline, in Oil & Gas, Refinery, Petrochemicals, & Power Plant in Saudi Arabia, U.A.E, Kuwait & India for Various Eng. Construction Projects.
More than 17 years’ civil engineering experience specializing in construction of Buildings, Bridges, Roads and infrastructure. Have a good experience of construction of structures from piling works to Superstructure including reinforced structure have good analytical, problem solving skills and project management abilities to deliver within time and budget. Experienced working with the world’s leading consultants Halcrow (a CH2M Hill company) Middle East) at prestigious projects including Abu Abyad & Rafiq island development, Zirku , Sarb North & Sarb South Islands Development, Abu Dhabi;. Worked with Nespak (an organization of Govt: of Pakistan)Have ample knowledge of standards and contract documents (AASHTO, BS, ASTM, ACI ) for quality control, contract administration, and resolving valuations and claims disputes with contractor. Have adequate experience of construction of roads, infrastructure and bridges. Have good analytical skill and sufficient design knowledge for reviewing shop drawings and ensuring compliance with contract drawings and design requirements. Extensive construction supervision and contract administration experience including the payment certificates, management of health & safety and management of quality
"While employed as Civil Engineer with Mott MacDonald Abu Dhabi & My previous employers I improved customer relations and developed new clients, which trusted my employers & Industries for a quality product on time and on budget. In addition, I enhanced Mott MacDonald productivity through development and implementation of manpower schedules, which made the team more effective. Furthermore, I streamlined project costs through Quality Aspects by self-performing large portions of the scope of work. Through strong management skills I reduced contract problems through developing solid trust and communication with job owners and sub-contractors, which raised production with less down time. Lastly, with strong work ethics I boosted employee morale though management by example (not being afraid to roll the sleeves up and get dirty and do what it takes to get the job done). Which in effect raised company effectiveness by being reliable and trustworthy."
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
1. Page 1 of 8
CURRICULUM VITAE
NAME : EHSAN ASGHAR
PROFESSION : Consulting Engineer - Mechanical
DATE OF BIRTH : December 20, 1985
NATIONALITY : Pakistani
CONTACT No : +92 346 5317190
EMAIL : ehsan_im@yahoo.com
PASSPORT : CK 1821311
SKYPE : ehsan.asghar3
ADDRESS : House No. 53, Baral Wapda Colony Mangla Cantt,
District Jhelum, Pakistan.
MEMBERSHIP OF Registered Mechanical Engineer with Pakistan Engineering
PROFESSIONAL : Council - Registration No. Mech / 22354
SOCIETIES
KEY QUALIFICATIONS:
Practicing as Professional Mechanical Engineer since 2009
“Construction and Contracts Engineering Professional with more than10 years of hands on experience in
Mega Multi-discipline Energy Sector and Building Utilities projects, having key Skills of Supervision, QA/QC,
FATs, Erection of; Hydropower Plant, Hydraulic Gates, Cranes, Tunnel Steel Lining, Mechanical Equipment
(Static, Rotating, Piping) & Allied Steel Structures, HVAC System and MEP Works. Acquainted with FIDIC,
Preparation and Evaluation of Contract / Tender Documents, Claims and Variation Orders.
Worked with renowned lenders including World Bank - WB, Asian Development Bank - ADB, Islamic
Development Bank – IDB, International Finance Corporation – IFC and Commonwealth Development
Corporation - CDC.”
PROFESSIONAL SUMMARY
Jul. 2018 to date: Working as Owner’s Sr. Hydro Mechanical Engineer representing NESPAK
at GHP Consultants for Construction of 102 MWs Gulpur Hydropower
Project, Kotli, AJ&K.
Nov. 2015 to Jun 2018: Worked as Assistant Resident Engineer – Mechanical represented NESPAK
at Neelum Jhelum Consultants – NJC for Execution of 969 MWs Neelum
Jhelum Hydroelectric Project – NJHEP, Muzaffarabad.
May 2013 to Oct. 2015: Worked as Senior Engineer / Assistant Resident Engineer – ARE
(Mechanical) represented NESPAK at PICs (Project Implementation
Consultants) on Rehabilitation and Modernization of Jinnah Barrage.
Apr 2011 to Apr 2013: Worked as Project Mechanical Engineer with M/s China Machinery
Engineering Corp. CMEC for Execution of 969 MWs Neelum Jhelum
Hydroelectric Project – NJHEP, Muzaffarabad.
Feb 2009 to March 2011: Worked at 1000 MWs Mangla Dam Raising Project – MDRP (WAPDA) as
Assistant Manager Mechanical and Electrical Works with China International
Water and Electric Corp. – CWE.
2. Page 2 of 8
EDUCATION
Bachelors of Mechanical Engineering (2005 – 2009)
Mirpur University of Engineering and Technology – MUST, Pakistan.
COMPUTER SKILLS
• Microsoft Office • AutoCAD • Primavera • Microsoft Project & Visio
INTERPERSONAL SKILLS
• Pleasant Personality • Self-motivated • Leadership • Adoptability & Team Work
TECHNICAL SKILLS
•Technical Report Writing •Estimations, Proposals & Claims •Site Execution & Supervision
•QA / QC & Measurements •Contract Administration •Project Monitoring
•FATs •Workshop Technology •Office Engineering
EMPLOYMENT RECORD
1. Name of Project: 102MWs Gulpur Hydropower Project
Name of Firm: Gulpur Hydropower Consultants – JV 1
Joint Venture of Stantec MWH Inc. and NESPAK
Position Held Sr. Hydro Mechanical Engineer
Contractor Daelim Lotte Joint Venture – DLJV (Andritz Hydro E&M Subcontractor)
Contract Type EPC Contract
Client: Mira Power Limited – MPL
Project Cost: USD $243,500,000
Funded by: K-Exim, CDC, ADB & IFC
Tenure: July, 2018 to date
Project Summary
Gulpur Hydropower Project is owned by Mira Power Limited (Independent Power Produces - IPP) which is
financed by international lenders to construct the project. The Construction award has awarded on Build
Own Operate and Transfer – BOOT basis to a Joint Venture of Daelim and Lotte Engineering Construction
companies – as an EPCC. The gross head is about 60 meters. Bulb Turbines (2 X 51MWs) are being
installed on the discharge of 201m3/sec of Poonch River. Gulpur Hydropower Consultant – JV 1 is hired for
the Design review, to resolve: technical site issues, Contract variations and QA/QC.
Activities Performed:
• Design review and supervision of installation / erection of following Mechanical equipment
in accordance with the technical specifications / contract provisions, approved drawings,
method statements and international standards:
- Cranes - Hydraulic Gates - Turbine Parts - Painting Works
- HVAC - Structure Fabrication - Rail Track - Pumps
• Supervision of QA/QC activities at site which mainly includes inspection of site delivered
Mechanical equipment / parts / sub-assemblies and installed equipment in accordance with
approved Quality Assurance Plan / Technical specifications.
3. Page 3 of 8
• Technical evaluation of Method statements, Reports, Manuals and other Technical
documents submitted by the Contractor.
• Prepare Technical Reports / Letters.
• Prepare Progress Reports.
• Expertise in using international codes & standards
2. Name of Project: 969MWs Neelum Jhelum Hydroelectric Project - NJHEP
Name of Firm: Neelum Jhelum Consultants – NJC
Joint Venture between MWH AMERICAS, NORPLAN, NESPAK, ACE & NDC
Position Held Assistant Resident Engineer – Mechanical
Contractor CGGC – CMEC Consortium
Contract Type EPC Contract
Client: Water and Power Development Authority – WAPDA
Project Cost: Rs. 404 Billion Approx.
Funded by: GOP, EXIM Bank China, IDB & Donor Agencies
Tenure: November, 2015 to June 2018
Project Summary
Neelum Jhelum Hydroelectric Project is the first Pakistan’s Underground Hydroelectric Project under
WAPDA to meet fast – growing energy requirements in Pakistan. Overall project cost is Rs.404 billion (PC-
1, Revision-3). The project utilizes a gross head of about 420 meters, to generate 969 MWs, Four (04)
Vertical Shafts Francis Turbine (VSFT) with the Installed capacity of 242.25 MWs for each Unit by diverting
River Neelum at Nauseri to the lower reach of Jhelum River at Zamianabad through a 47 km long tunnel
system (Avg. 6.5 meter Dia). Neelum Jhelum Consultants – NJC is hired for the construction & management
supervision and design review of the project.
Activities Performed:
SITE EXECUTIONAL WORKS
• Design review and supervision of installation / erection of following Mechanical equipment
in accordance with the technical specifications / contract provisions, approved drawings,
method statements and international standards:
- Cranes - Main Inlet Valves - Hydraulic Gates - Turbine Parts
- HVAC - Structure Fabrication - Rail Track - Pumps
- Piping Network - Painting Works - Welding Works
• Supervision of QA/QC activities at site which mainly includes inspection of site delivered
Mechanical equipment / parts / sub-assemblies and installed equipment in accordance with
approved Quality Assurance Plan / Technical specifications.
• Assisted Resident Engineer / Site Chief in:
- Project Coordination with Client & Contractor
- Technical issues related to Mechanical works at site
• Technical evaluation of Method statements, Reports, Manuals and other Technical
documents submitted by the Contractor.
• Prepare Technical Reports / Letters.
• Prepare Progress Reports.
• Prepared Project Completion Report
• Reviewed as built drawing submissions
• Conducted the PQR and WPS under the supervision of Resident Engineer.
• Member of HSE Committee from Consultants side to audit the HSE compliance at work site
and implemented prescribed code of conduct.
4. Page 4 of 8
• Attended various meeting with the Stakeholders to review the project progress, on risk
management, HSE Implementations etc.
• Expertise in using international codes & standards
• Administrate & manage the duty schedule of Junior Engineers and Inspectors to supervise
the work effectively.
• Briefing the technical / learning site visits / delegations on going site activities.
CONTRACTS AND CLAIM WORKS
• Preparation and evaluation of contract/tender documents, cost estimates, bill of quantities,
specifications, processing and scrutinizing variation orders for Mechanical and Hydraulic
Works
• Design Review and Verification of the quantities
• Scrutiny of Contractor’s Monthly Reports.
• Verification of Interim Payment Certificates.
• Checking the provisions of BOQ Items as per Contract Specifications and related supporting
documents.
• Scrutiny of Rate Analysis and Variation Orders.
• Contract administration including processing of Contractor’s Claims and Variation Orders
with compliance to other contractual matters and submission to Client.
• Monitoring the Contractor’s progress and performance to ensure goods and services
conform to the contract requirements.
• Participating, as necessary, in developing the solicitation and writing the draft documents.
• Working closely with cross functional groups and effectively supporting other Engineers in
order to complete assigned tasks within set timelines & budgetary norms.
Main Achievements:
• Reused the support structure for Steel liners and reutilized the rail track has reduced the
cost incurred on the activity which appreciated by the Client.
• After repatriation of expat Resident Engineer, I served as Resident Incharge and responsible
for the completion of remaining works, variation orders, claims & settlement of disputes.
• Successfully completed all the targeted dates of the fabrication, testing and installation of
major activities at site.
• Awarded Letter of Appreciation on outstanding performance.
3. Name of Project: Rehabilitation and Modernization of Jinnah Barrage
Name of Firm: Project Implementation Consultants – PICs
Joint Venture between NESPAK, ACE & SMEC
Position Held Senior Engineer / Assistant Resident Engineer – Mechanical
Contractor DESCON - CCC Joint Venture
Contract Type EPC Contract
Client: PMO for Punjab Barrages – Irrigation Department, Lahore
Project Cost: USD $155 Million
Funded by: WORLD BANK
Tenure: May 2013 to October 2015
Project Summary:
Jinnah Barrage is located on the Indus River with one off-taking canal (Thal Canal). Scope of Mechanical
works of Jinnah Barrage Project includes replacement of barrage and canal hydraulic gate system (Gate
leaves, hoisting systems, embedded parts and allied assemblies), Installation of new gate system for newly
constructed sub-weir and rehabilitation of old Kalabagh Railway bridge. I joined the project since its inception
and successfully completed all the assigned tasks within scheduled time.
5. Page 5 of 8
Responsibilities:
• Conducted the Joint Condition Survey of existing barrage gates and Thal canal gates
of Jinnah Barrage with Contractor by using Ultrasonic thickness measurement
technique.
• Supervised Installation / erection / replacement activities of Hydraulic Gate equipment
at Barrage and allied structures in accordance with the approved Design and Method
Statements.
• Supervised Welding Works involved in fabrication and installation of hydraulic gate
equipment and superstructures which mainly includes Visual examination, Repair,
procedures, Quality inspection in compliance with Approved welding procedure
(WPS). Conducted Inspection of Welding Works using standard NDT Techniques.
• Conducted condition survey of Old Kalabagh railway bridge and supervised the
rehabilitation and re-modification works of the Bridge to provide alternate vehicular
route before the commencement of dismantling works at Barrage.
• Supervised QA/QC activities at site which mainly includes inspection of site delivered
items/gate equipment from China and installed gate equipment at Main Barrage, Sub
Weir and Canal in accordance with approved Quality Assurance Plan.
• Supervised Rehabilitation activities which include the rehabilitation of superstructure
of Main Barrage and Thal Canal head and cross Regulators.
• Supervised Painting Works at site as per approved / standard coating system.
• Supervised the installation of HVAC system for SCADA Control Room, MEP Works
and FATs & installation of Turbine and Submersible Pumps for Barrage Colony.
• Responsible for preliminary review & evaluation of Contractor’s technical submittals
i.e Method statements, manuals, schedules, progress reports etc.
• Supervised of Fabrication Works carried out by Contractor at site workshop.
• Supervised the Priority Repair Works of existing / old Gates of Main barrage before
the floods of 2013.
• As Estimation Engineer, reviewed the Contractor’s proposal for the rehabilitation of
old / existing Steel Structure of Kalabagh Railway Bridge which was constructed in
1929.
• Assist Resident Engineer in:
- IPC (Payment Certificates) verification of Mechanical Works.
- Project Coordination with Client & Contractor.
- Technical issues related to Mechanical works at site.
• Prepared Technical Reports / Letters.
• Prepared Daily / Weekly / Monthly Progress Reports.
• Prepared Project Completion Report and O&M Manuals for Gate System.
Main Achievements:
• The rehabilitation & re-modification of Old Railway Bridge was first ever milestone of
the project which was completed as per schedule and divert the vehicular traffic from
barrage to this bridge. The rehabilitation of this bridge was a part SDAP. My efforts
were much appreciated by the World Bank representatives visited at site.
• The installation, testing and commissioning of Barrage gates was completed before
the flood season of year 2015 and ensured smooth operation of gates and gate
equipment.
4. Name of Project: 969MWs Neelum Jhelum Hydroelectric Project - NJHEP
Name of Firm: China Machinery Engineering Corporation - CMEC
Position Held Project Engineer – Mechanical
Contractor CGGC – CMEC Consortium
6. Page 6 of 8
Contract Type EPC Contract
Client: Water and Power Development Authority – WAPDA
Project Cost: Rs. 480 Billion Approx.
Funded by: GOP, EXIM Bank China, IDB & Donor Agencies
Tenure: Apr 2011 to Apr 2013
Project Summary
Construction of Neelum Jhelum Hydroelectric Project is the first Pakistan’s Underground Hydroelectric
Project under WAPDA to meet fast – growing energy requirements in Pakistan. Overall project cost is
Rs.404 billion (PC-1, Revision-3). The project utilizes a gross head of about 420 meters, to generate 969
MWs, Four (04) Vertical Shafts Francis Turbine (VSFT) with the Installed capacity of 242.25 MWs for each
Unit by diverting River Neelum at Nauseri to the lower reach of Jhelum River at Zamianabad through a 47
km long tunnel system (Avg. 6.5 meter Dia).
Responsibilities:
• Established the Site Management Office for the execution of EMH Works of the
Project.
• Maintained cordial relationship with clients, ensuring service quality norms to achieve
Client satisfaction & business retention.
• Prepared the method statement for the Mechanical & Hydraulic Steel Structural
works to be executed in Power Complex and Dam / Intake Site.
• Supervision of installation / erection of following Mechanical equipment in
accordance with the technical specifications / contract provisions, approved
drawings, method statements and international standards:
- Draft Tubes - Steel Structures - Hydraulic Gates - Turbine Parts
- Rail Track - Fabrication Works - Painting Works - Piping Network
• Involved in preparation of layout of E&M equipment, HVAC and Piping network.
• Established penstock fabrication workshop at project site.
• Worked as Office Engineer during Site Coordination Meetings between the
Contractor and the Consultant for execution of Electromechanical works of power
house & intake.
• Conducted the site inspection of delivered items including Draft tube, Spiral case,
cones for Power House.
• Hiring of Skilled workers for the execution of works with better quality of
workmanship.
• As a Logistic In charge, prepared the detailed logistic road map for the safe, sound
and in-time shipment of EMH equipment and material from Port Qasim to
Muzaffarabad, AJK
• Worked as Contract Manager involved in the preparation of tender documents,
detail civil drawings, technical specifications and contract document for EMH Staff
dormitories and Offices.
• Prepared and submitted Variation Order and Claims of various mechanical works.
The Claims were prepared according to contract clause, technical specification and
tender drawings for the specific activity.
• Responsible for preparation and submission of Interim Payment Application to
Consultants for certification of executed Mechanical Works as per contract clauses.
• Conducted Factory inspections for under fabricated / manufactured items used at
the Project.
Main Achievements:
7. Page 7 of 8
• Established site management office, started the coordination between the Civil
Contractor and make necessary arrangements to start EMH site activities as per
schedule
• Successfully completed installation, testing and commissioning of Power house
Bridge Crane which was the preliminary equipment used for the installation of
electromechanical equipment in power house.
• Timely completion of Road Survey for the transportation of EMH equipment from
port Qasim to Muzaffarabad project site which appreciated by hi-ups.
• Prepared the claims for the works which were not part of the original contract.
5. Name of Project: Mangla Dam Raising Project - MDRP
Name of Firm: China International Water and Electric Corp. CWE
Position Held Assistant Manager – M&E Works
Contractor CWE-JV
Client: Water and Power Development Authority – WAPDA
Project Cost: Rs. 101.384 billion
Funded by: Government of Pakistan – GoP
Tenure: Feb 2009 to Mar 2011
Project Summary
China International Water & Electric Corp. is a well-recognized one of the world’s largest multinational
construction company working in Pakistan. CWE was involved in Mangla Dam Raising Project. Mangla dam
is one of the biggest dam in Pakistan that includes upraising 30 feet of Main Dam, Sukye Dyke, Main
Spillway, Emergency Spillway, and Gate Equipment Modification & Instrumentation. I joined the project after
my graduation. My responsibilities were as follows:
Responsibilities:
• Responsible for the evaluation, quantitative estimation, technical method
Statements and schedule the M&E Works and get approval from Consultants and
ensure the availability of material/Equipment in time.
• Supervised the fabrication and installation workmanship of Sill Beam and Liner
Plate of Spillway’s Radial Gates and Structural Repairs of Power Intake Gates of
Power House.
• Responsible to check and monitor the Sub-contractor’s works & maintain the
project quality and directed to complete in time.
• Responsible for the installation, testing & commissioning of HVAC systems in
Instrumentation Galleries and Shafts.
• Coordinate with the relative Civil construction company to ensure the execution of
project in time and safe.
• Attended various meetings with Consultant and Client on Critical issues to
complete works with in targeted dates.
• Prepared of monthly Interim Payment Application (IPA) for M&E Works.
• Prepared Technical Reports / Letters.
• Prepared Daily / Weekly / Monthly Progress Reports.
• Performed and prepared condition survey reports of Existing Power Intake Gates
of Mangla Power Station
• Supervised Painting and Sand Blasting of installed Spillway and Power Intake
Gates
• Local and Foreign Procurements of Materials / Equipment as per technical
specifications.
8. Page 8 of 8
• Prepared the as-built Drawing/documentations for the completed works.
• Recorded and Claimed the executed Day Work Activities.
• During Defect Liability Period (DLP) remained as representative of M&E works in
order to hand over the completed project to Client.
• Monitored departmental earthmoving / construction equipment, staff and other
related M&E works.
• Co-ordination with Client/Consultant during execution of the Project
• Prepared Various Claims and Variation orders in accordance with the Technical
Specification of the Project and Contract of Clauses as per FIDIC.
Main Achievements:
• Successfully Installed & Tested the Main Spillway Gates and Handed Over to the
Client - WAPDA.
• Successfully Installed & Tested the Power Intake Gates and Handed Over to the
Client - WAPDA.
• Prepared and submitted cost proposal and claims of works which were not a part
of the Contract but directed / instructed by the Consultants / Client to execute.
15. LANGUAGE
Speaking Reading Writing
English Proficient Proficient Proficient
Urdu Proficient Proficient Proficient
16. INTERNSHIP
Attended 4 weeks practical training at WAPDA Hydel Training Center Mangla, studied about Dams,
Hydraulic turbines & Governors, Generators etc and its Operation and Maintenance.
17. CO-CURRICULAR ACTIVITIES:
I am 6ft-2 inch in height, have healthy, smart and active sportsman physique. I like to play:
- Basket Ball - Swimming - Table Tennis - Badminton
As Captain of College Basketball Team won All Pakistan Basketball Tournament under Directorate Sports
- FBISE in year 2003.
18. REFERENCES
ENGR. JUAN F. MORALES
CHIEF MECHANICAL ENGINEER
Email: jfsalam@gmail.com
jfengineer@yahoo.com
Contact No. +58 4242201087 (Venezuela)
ENGR. JAVAID IQBAL AWAN
CHIEF ENGINEER – MECHANICAL
Associated Consulting Engineers – ACE
Pakistan
Email: jawan356@yahoo.com
Contact No. +92 3455938356 (Pakistan)
(Ehsan Asghar)