Location:- Ranihati Amta Road, Subhoara, P.O. Gabberia, Howrah 711 322
VIRATVANIJYAPRIVATELIMITED
Department of MSME&T, Govt. of West Bengal
Nodal Organization:WBSIDCL
State Approved Industrial Park (SAIP)
Background of Project / Park
• Contact : +91 9330 924 553;
• e-mail : rbefin2008@gmail.com
The Company proposed to create
world class MSME Industrial Park
similar to plug & play module. The
Park is meant for Light Engineering
and MSME Park which growing up
with employment and economically in
the rural area of our twin city of
Howrah and Kolkata.
Company / SPV details
• 1. Name : VIRAT VANIJYA PVT. LTD.
• 2. Registered Office : 153/2B, A. P. C. Road, 1st Floor, Kolkata – 700 006.
• 3. Works/Plant : Suvoara, Ranihati Amta Road, P.O. Gabberia, Howrah – 711 322, W.B., India
• 4. Directors : i) MR. RITESH AGARWAL
• ii) MR. BALARAM AGARWAL
• 5. Nature of Business : Service
• 6. CIN : U51909WB2011PTC158901
• 7. PAN : AADCV6212B
• 8. TAN : CALV03556A
• 9. GSTIN : 19AADCV6212B1ZN
About SPV
We are a Kolkata based group, established in 1983 by Shri Balaram Agarwal. In the past 37 years the group has
diversified into total solutions in agriculture and irrigation. Mr. Ritesh Agarwal son of Shri Balaram Agarwal has also
ventured into manufacturing of hardware components and fittings for Electrification.
Location with area / land details
Location:-
Mouza - Subhoara, Vill. Bada, P.O. Gabberia, P.S. & Block Panchla, Sub-Div. Uluberia, Dist. Howrah,
West Bengal, PIN – 711 322.
The park is located in Gabberia on the Ranihati—Amta Road, State Highway connecting with National Highway 16,
just 4 Km away and Nearest Railway Station is Amta (14 Km).
Lattitude :- 22°33'58.7"N ; Longitude :- 88°07'09.8"E
Land status:- Industrial uses.
Project details
 Situated on State Highway Ranihati Amta Road (SH 117) 4.2 km
away from NH 16 Connecting to NH 2 & 60 (within 20 km & 60 km
respectively).
 Amta Railway Station within 14 Km and Howrah Rly Station,
Shalimar & Dankuni Goods Yard within 30 km distance.
 The park used for Light Engineering MSME Park, Making of
Engineering Goods and Others.
Project Master Plan
Area statement for AIP
Project Cost summary
LAND & LAND DEVELOPMENT COST
PROPOSED LAND 8.76ACRE 58.75L/ACRE 514.65
PLANT & SHED 536.55
DEVELOPMENT 46.00L/ACRE 402.96
BOUNDARY WALL & ROAD (including Drainage) 25.00L/ACRE 219.00
1,673.16
COMMON INFRASTRUCTURE FACILITIES
FIRE FIGHTING EQUIPMENT 5.00L/ACRE 43.80
TRANSFORMER & OTHERS 15.00 131.40
ELECTRICITY INSTALLATION 9.50 83.22
SECUIRTY COTTAGE 1.50 13.14
271.56
OTHERS (Conversion, Mutation, Taxes) 7.75L/ACRE 67.89
Employment Generation
Expected to generate employment in the park around : 500 – 700 personal
 Technical, Managing and Skilled Labour will be directly involved with the
park.
 Casual and unskilled Labour will be indirectly involved with the park.
Land / Plot allotment status and numbers of allotted plot
Total Number of Units : 8 (Eight)
 Allotted Units : 2 (Two) MSME
Engineering Goods Manufacturer.
 Allot Units : 1 (One) MSME Company.
 Under Process : Shed II
 Vacant : 6 (Six)
Status of Statutory Clearances
 Local Authority Clearance Received
 Fire – Licence taken by unit.
 Pollution – Green Category
clearance received by Unit.
 Electricity – Connected through
WBSEDCL.
Note : Due to under process of the park, Primary visit
done by Fire & PCB. Final applicable after competition of
the project.
Status of Basic and Essential Common Infrastructure & its Progress
1. Land Development
2. Boundary Wall
3. Internal Road
4. Drainage Work
5. Electrical Infrastructure, Street Light etc.
6. Security Room
7. Fire Fighting Infrastructure
8. Water Supply arrangement
Status of approvals of Virat Vanijya Industrial Park
under SAIP
‘Final Approval’ in favour of Virat Vanijya / Vishwakarma Industrial Park
was accorded on 20.04.2022.
Now he has requested for for the release of ‘1st installment of Incentives’ of
the said Industrial Park.
Checklist according to parameter for 1st Incentive payment
Sl
No
Criteria as per guideline Comments of PMU, WBSIDCL
1 Mutation, conversion & registration of
the land in SPV’s name
Total land has been in possession of the SPV and already 23.21
acres have been converted by ADM (LR) & DLLRO, Hooghly. Other
lands are in process for conversion.
2 Formation of the SPV and obtaining
final approval of the AIP from the
SLEC
All components have been submitted in DPR.
This Park has been visited on 02nd December, 2022 by the PMU Team of WBSIDCL in presence of Mr.
Sanjay Saha, Executive Officer, Virat Vanijya Pvt. Ltd. along with his team and after inspection &
checking of the project it has been found that according to criteria as specified in SAIP 2020
Guideline for the 1st installment, Virat Vanijya Pvt. Ltd. has fulfilled all the parameters (except
remaining portion of Internal Road) and may be recommended for the release of 1st installment
under SAIP subject to completion of construction of the balance portion Internal Road.
Accordingly WBSIDCL has been recommended for release of ‘1st incentive’ in favour of Virat
Vanijya / Vishwakarma Industrial Park on 29.12.2022.
….cont’d
Sl Criteria as per
guideline
Comments of PMU, WBSIDCL
3 Completion of
construction of Boundary
Wall, Land filling and
Internal Roads
Land Development Work has been completed.
The total length of Boundary Wall executed at site is 909m (approx). So the
Construction of Boundary Wall has been completed and along with 2(two) nos gate.
Construction of Security Room has been completed.
Internal Road Work has been partially completed by paver block from the
entrance gate to the main office building and remaining portion has been filled up
by moorum & brick bats. The total length of internal road is 2211.58m (approx).
Drainage System (one side) is done through the site comprises with RCC Wall &
construction of pit is under process and the total length of about 231.72m
executed at site.
Regarding Electric Connection WBSEDCL has provided power infrastructure
throughout the site and individual unit got power as per their requirement and
installed transformer room.
Water through deep tubewell, security room & electric arrangement is done at
proposed site.
Work for street light (10 nos flood light) has been completed.
….cont’d
RECOMMENDATIONS BY WBSIDCL
According to criteria as specified in SAIP 2020 Guideline for the 1st installment, concerned Park Developers /
SPV has fulfilled all the parameters and may be recommended for the release of 1st installment of Incentives
under SAIP against Development of ‘Vishwakarma Industrial Park’ at Ranihati, Amta, Howrah.
Site Photographs
Operational of Project and Ways ahead
Thank
You

More Related Content

Similar to Virat Vanijya_ Vishwakarma Industrial Park_r.pptx

AjayasankarK M _ Engineer
AjayasankarK M _ EngineerAjayasankarK M _ Engineer
AjayasankarK M _ Engineer
Ajay Sankar
 
Presentation 1
Presentation 1Presentation 1
Presentation 1
Baig Ali
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
jamsheer p
 
VK-Resume
VK-ResumeVK-Resume
VK-Resume
vinod krishnan
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
Nikhil Jaipurkar
 
Ashutosh Mishra DOC
Ashutosh Mishra DOCAshutosh Mishra DOC
Ashutosh Mishra DOC
Ashutosh Mishra
 
THOWFIC AHAMED CV
THOWFIC AHAMED CVTHOWFIC AHAMED CV
THOWFIC AHAMED CV
Thowfic Ahamed
 
Updated resume.pdf
Updated resume.pdfUpdated resume.pdf
Updated resume.pdf
Afzal Ahamed
 
Vignesh_Sr.Elec Designer
Vignesh_Sr.Elec DesignerVignesh_Sr.Elec Designer
Vignesh_Sr.Elec Designer
Vignesh V
 
Design Status.pptx
Design Status.pptxDesign Status.pptx
Design Status.pptx
ssuser73884b
 
RCPRESUMEOCT2016
RCPRESUMEOCT2016RCPRESUMEOCT2016
RCPRESUMEOCT2016
Robert Pagulayan
 
Ranjith cv
Ranjith cvRanjith cv
Ranjith cv
Ranjith koyili
 
Abhilash CV
Abhilash CVAbhilash CV
1 Engr. Mohammad Faizal CV (1) - Copy
1 Engr. Mohammad Faizal CV (1) - Copy1 Engr. Mohammad Faizal CV (1) - Copy
1 Engr. Mohammad Faizal CV (1) - Copy
Mohammad Faizal Molok
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
Sumit Singh
 
NEMER- CV - 16
NEMER- CV - 16NEMER- CV - 16
NEMER- CV - 16
Nemer Abuhajar
 
Offshore wind energy Development in India, MNRE, Government of India
Offshore wind energy Development in India, MNRE, Government of IndiaOffshore wind energy Development in India, MNRE, Government of India
Offshore wind energy Development in India, MNRE, Government of India
OECD Environment
 
Basil Resume
Basil Resume Basil Resume
Basil Resume
Basil T Mathai
 
2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking Management2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking Management
TOD India
 
05. PPT for EAC (BPCL).ppt
05. PPT for EAC (BPCL).ppt05. PPT for EAC (BPCL).ppt
05. PPT for EAC (BPCL).ppt
NMnam
 

Similar to Virat Vanijya_ Vishwakarma Industrial Park_r.pptx (20)

AjayasankarK M _ Engineer
AjayasankarK M _ EngineerAjayasankarK M _ Engineer
AjayasankarK M _ Engineer
 
Presentation 1
Presentation 1Presentation 1
Presentation 1
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
 
VK-Resume
VK-ResumeVK-Resume
VK-Resume
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
 
Ashutosh Mishra DOC
Ashutosh Mishra DOCAshutosh Mishra DOC
Ashutosh Mishra DOC
 
THOWFIC AHAMED CV
THOWFIC AHAMED CVTHOWFIC AHAMED CV
THOWFIC AHAMED CV
 
Updated resume.pdf
Updated resume.pdfUpdated resume.pdf
Updated resume.pdf
 
Vignesh_Sr.Elec Designer
Vignesh_Sr.Elec DesignerVignesh_Sr.Elec Designer
Vignesh_Sr.Elec Designer
 
Design Status.pptx
Design Status.pptxDesign Status.pptx
Design Status.pptx
 
RCPRESUMEOCT2016
RCPRESUMEOCT2016RCPRESUMEOCT2016
RCPRESUMEOCT2016
 
Ranjith cv
Ranjith cvRanjith cv
Ranjith cv
 
Abhilash CV
Abhilash CVAbhilash CV
Abhilash CV
 
1 Engr. Mohammad Faizal CV (1) - Copy
1 Engr. Mohammad Faizal CV (1) - Copy1 Engr. Mohammad Faizal CV (1) - Copy
1 Engr. Mohammad Faizal CV (1) - Copy
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
 
NEMER- CV - 16
NEMER- CV - 16NEMER- CV - 16
NEMER- CV - 16
 
Offshore wind energy Development in India, MNRE, Government of India
Offshore wind energy Development in India, MNRE, Government of IndiaOffshore wind energy Development in India, MNRE, Government of India
Offshore wind energy Development in India, MNRE, Government of India
 
Basil Resume
Basil Resume Basil Resume
Basil Resume
 
2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking Management2020 Karol Bagh Pedestrianization & Parking Management
2020 Karol Bagh Pedestrianization & Parking Management
 
05. PPT for EAC (BPCL).ppt
05. PPT for EAC (BPCL).ppt05. PPT for EAC (BPCL).ppt
05. PPT for EAC (BPCL).ppt
 

Recently uploaded

A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024
Intelisync
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Safe Software
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Tosin Akinosho
 
Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!
GDSC PJATK
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
ssuserfac0301
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Jeffrey Haguewood
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
Zilliz
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
fredae14
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
Wouter Lemaire
 
Nunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdf
Nunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdfNunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdf
Nunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdf
flufftailshop
 
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStrDeep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
saastr
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
alexjohnson7307
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
tolgahangng
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
MichaelKnudsen27
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
Jason Packer
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
Postman
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
Jakub Marek
 
Azure API Management to expose backend services securely
Azure API Management to expose backend services securelyAzure API Management to expose backend services securely
Azure API Management to expose backend services securely
Dinusha Kumarasiri
 
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying AheadDigital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Wask
 

Recently uploaded (20)

A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
 
Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
 
Nunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdf
Nunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdfNunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdf
Nunit vs XUnit vs MSTest Differences Between These Unit Testing Frameworks.pdf
 
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStrDeep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
Deep Dive: Getting Funded with Jason Jason Lemkin Founder & CEO @ SaaStr
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
 
Azure API Management to expose backend services securely
Azure API Management to expose backend services securelyAzure API Management to expose backend services securely
Azure API Management to expose backend services securely
 
Digital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying AheadDigital Marketing Trends in 2024 | Guide for Staying Ahead
Digital Marketing Trends in 2024 | Guide for Staying Ahead
 

Virat Vanijya_ Vishwakarma Industrial Park_r.pptx

  • 1. developed by Location:- Ranihati Amta Road, Subhoara, P.O. Gabberia, Howrah 711 322 VIRATVANIJYAPRIVATELIMITED Department of MSME&T, Govt. of West Bengal Nodal Organization:WBSIDCL State Approved Industrial Park (SAIP)
  • 2. Background of Project / Park • Contact : +91 9330 924 553; • e-mail : rbefin2008@gmail.com The Company proposed to create world class MSME Industrial Park similar to plug & play module. The Park is meant for Light Engineering and MSME Park which growing up with employment and economically in the rural area of our twin city of Howrah and Kolkata.
  • 3. Company / SPV details • 1. Name : VIRAT VANIJYA PVT. LTD. • 2. Registered Office : 153/2B, A. P. C. Road, 1st Floor, Kolkata – 700 006. • 3. Works/Plant : Suvoara, Ranihati Amta Road, P.O. Gabberia, Howrah – 711 322, W.B., India • 4. Directors : i) MR. RITESH AGARWAL • ii) MR. BALARAM AGARWAL • 5. Nature of Business : Service • 6. CIN : U51909WB2011PTC158901 • 7. PAN : AADCV6212B • 8. TAN : CALV03556A • 9. GSTIN : 19AADCV6212B1ZN About SPV We are a Kolkata based group, established in 1983 by Shri Balaram Agarwal. In the past 37 years the group has diversified into total solutions in agriculture and irrigation. Mr. Ritesh Agarwal son of Shri Balaram Agarwal has also ventured into manufacturing of hardware components and fittings for Electrification.
  • 4. Location with area / land details Location:- Mouza - Subhoara, Vill. Bada, P.O. Gabberia, P.S. & Block Panchla, Sub-Div. Uluberia, Dist. Howrah, West Bengal, PIN – 711 322. The park is located in Gabberia on the Ranihati—Amta Road, State Highway connecting with National Highway 16, just 4 Km away and Nearest Railway Station is Amta (14 Km). Lattitude :- 22°33'58.7"N ; Longitude :- 88°07'09.8"E Land status:- Industrial uses.
  • 5. Project details  Situated on State Highway Ranihati Amta Road (SH 117) 4.2 km away from NH 16 Connecting to NH 2 & 60 (within 20 km & 60 km respectively).  Amta Railway Station within 14 Km and Howrah Rly Station, Shalimar & Dankuni Goods Yard within 30 km distance.  The park used for Light Engineering MSME Park, Making of Engineering Goods and Others.
  • 8. Project Cost summary LAND & LAND DEVELOPMENT COST PROPOSED LAND 8.76ACRE 58.75L/ACRE 514.65 PLANT & SHED 536.55 DEVELOPMENT 46.00L/ACRE 402.96 BOUNDARY WALL & ROAD (including Drainage) 25.00L/ACRE 219.00 1,673.16 COMMON INFRASTRUCTURE FACILITIES FIRE FIGHTING EQUIPMENT 5.00L/ACRE 43.80 TRANSFORMER & OTHERS 15.00 131.40 ELECTRICITY INSTALLATION 9.50 83.22 SECUIRTY COTTAGE 1.50 13.14 271.56 OTHERS (Conversion, Mutation, Taxes) 7.75L/ACRE 67.89
  • 9. Employment Generation Expected to generate employment in the park around : 500 – 700 personal  Technical, Managing and Skilled Labour will be directly involved with the park.  Casual and unskilled Labour will be indirectly involved with the park.
  • 10. Land / Plot allotment status and numbers of allotted plot Total Number of Units : 8 (Eight)  Allotted Units : 2 (Two) MSME Engineering Goods Manufacturer.  Allot Units : 1 (One) MSME Company.  Under Process : Shed II  Vacant : 6 (Six)
  • 11. Status of Statutory Clearances  Local Authority Clearance Received  Fire – Licence taken by unit.  Pollution – Green Category clearance received by Unit.  Electricity – Connected through WBSEDCL. Note : Due to under process of the park, Primary visit done by Fire & PCB. Final applicable after competition of the project.
  • 12. Status of Basic and Essential Common Infrastructure & its Progress 1. Land Development 2. Boundary Wall 3. Internal Road 4. Drainage Work 5. Electrical Infrastructure, Street Light etc. 6. Security Room 7. Fire Fighting Infrastructure 8. Water Supply arrangement
  • 13. Status of approvals of Virat Vanijya Industrial Park under SAIP ‘Final Approval’ in favour of Virat Vanijya / Vishwakarma Industrial Park was accorded on 20.04.2022. Now he has requested for for the release of ‘1st installment of Incentives’ of the said Industrial Park.
  • 14. Checklist according to parameter for 1st Incentive payment Sl No Criteria as per guideline Comments of PMU, WBSIDCL 1 Mutation, conversion & registration of the land in SPV’s name Total land has been in possession of the SPV and already 23.21 acres have been converted by ADM (LR) & DLLRO, Hooghly. Other lands are in process for conversion. 2 Formation of the SPV and obtaining final approval of the AIP from the SLEC All components have been submitted in DPR. This Park has been visited on 02nd December, 2022 by the PMU Team of WBSIDCL in presence of Mr. Sanjay Saha, Executive Officer, Virat Vanijya Pvt. Ltd. along with his team and after inspection & checking of the project it has been found that according to criteria as specified in SAIP 2020 Guideline for the 1st installment, Virat Vanijya Pvt. Ltd. has fulfilled all the parameters (except remaining portion of Internal Road) and may be recommended for the release of 1st installment under SAIP subject to completion of construction of the balance portion Internal Road. Accordingly WBSIDCL has been recommended for release of ‘1st incentive’ in favour of Virat Vanijya / Vishwakarma Industrial Park on 29.12.2022.
  • 15. ….cont’d Sl Criteria as per guideline Comments of PMU, WBSIDCL 3 Completion of construction of Boundary Wall, Land filling and Internal Roads Land Development Work has been completed. The total length of Boundary Wall executed at site is 909m (approx). So the Construction of Boundary Wall has been completed and along with 2(two) nos gate. Construction of Security Room has been completed. Internal Road Work has been partially completed by paver block from the entrance gate to the main office building and remaining portion has been filled up by moorum & brick bats. The total length of internal road is 2211.58m (approx). Drainage System (one side) is done through the site comprises with RCC Wall & construction of pit is under process and the total length of about 231.72m executed at site. Regarding Electric Connection WBSEDCL has provided power infrastructure throughout the site and individual unit got power as per their requirement and installed transformer room. Water through deep tubewell, security room & electric arrangement is done at proposed site. Work for street light (10 nos flood light) has been completed.
  • 16. ….cont’d RECOMMENDATIONS BY WBSIDCL According to criteria as specified in SAIP 2020 Guideline for the 1st installment, concerned Park Developers / SPV has fulfilled all the parameters and may be recommended for the release of 1st installment of Incentives under SAIP against Development of ‘Vishwakarma Industrial Park’ at Ranihati, Amta, Howrah.
  • 18. Operational of Project and Ways ahead