SlideShare a Scribd company logo
DR EMERITA ALIAS
Professor
PROJECT RESEARCH
AND DEVELOPMENT
Reported by
ANGELITO LECCIO ESTRADA
WHERE WE ARE NOW
Clifford F. Gray
Eric W. Larson
Project Audit and Closure
Chapter 14
MAJOR TASKS OF A
PROJECT AUDIT
1. Evaluate if the project delivered the expected benefits to
all stakeholders.
Was the project managed well?
Was the customer satisfied?
2. Assess what was done wrong and what contributed to
successes.
3. Identify changes to improve the delivery of future projects.
PROJECT AUDIT
COMPONENTS
• A review of why the project was selected.
• A reassessment of the project’s role in the
organization’s priorities.
• A check on the organizational culture to ensure it
facilitates the type of project being implemented.
• An assessment of how well the project team is
functioning well and if its is appropriately staffed.
• A check on external factors that might change where
the project is heading or its importance.
• A review of all factors relevant to the project and to
managing future projects.
TYPES OF PROJECT AUDITS
• In-process project audits
• Allow for corrective changes if conditions have changed and
for concentration on project progress and performance.
• Postproject audits
• Take a broader and longer-term view of the project’s role in
the organization and emphasize improving the management
of future projects.
FACTORS INFLUENCING AUDIT
DEPTH AND DETAIL
Table 14.1
Organization size
Project importance
Project type
Project risk
Project size
Project problems
Step1
Initiation and
Staffing
Step 2
Data Collection and
Analysis
Step 3
Reporting
Conducting a Project
Audit
CHARACTERISTICS OF
AUDIT LEADERS
1. No direct involvement or direct interest in the project.
2. Respect (perceived as impartial and fair) of senior
management and other project stakeholders.
3. Willingness to listen.
4. Independence and authority to report audit results
without fear of recriminations from special interests.
5. Perceived as having the best interests of the organization
in making decisions.
6. Broad-based experience in the organization or industry.
STEP 2: DATA COLLECTION
AND ANALYSIS
• Organization View
• Was the organizational culture supportive and correct?
• Was senior management’s support adequate?
• Did the project accomplish its intended purpose?
• Were risks appropriately identified and assessed?
• Were the right people and talents assigned?
• Have staff been fairly reassigned to new projects?
• What does evaluation from contractors suggest?
• Were the project start-up and hand-off successful?
• Is the customer satisfied?
STEP 2: DATA COLLECTION
AND ANALYSIS
• Project Team View
• Were the project planning and control systems appropriate for
this type of project?
• Should all similar projects use these systems?
• Did the project conform to plan for budget and schedule?
• Were interfaces with stakeholders effective?
• Have staff been fairly assigned to new projects?
• Did the team have adequate resources? Were there resource
conflicts?
• Was the team managed well?
• What does evaluation from contractors suggest?
STEP 3: REPORTING
• Audit Report Content Outline
• Classification of project
• Project type
• Size
• Staffing
• Technology level
• Strategic or support
• Analysis of information gathered
• Project mission and objectives
• Procedures and systems used
• Organization resources used
• Recommendations
• Corrective actions
• Lessons learned
• Reminders
• Appendix
• Backup data
• Summary booklet
PROJECT MANAGEMENT
MATURITY MODEL
FIGURE 14.1
PROJECT CLOSURE
• Conditions for Closure
• Normal
• Premature
• Perpetual
• Failed Project
• Changed Priority
• Close-out Plan: Questions
to be Asked
• What tasks are required to
close the project?
• Who will be responsible
for these tasks?
• When will closure begin
and end?
• How will the project be
delivered?
BARRIERS TO PROJECT SUCCESS
Table 14.2
Activity* Barrier Incidence (%)
Planning Unclear definition 16%
32% Poor decision making 9
Bad information 3
Changes 4
Scheduling Tight schedule 4
12% Not meeting schedule 5
Not managing schedule 3
Organizing Lack of responsibility or accountability 5
11% Weak project manager 5
Top management interference 1
Staffing Inadequate personnel 5
12% Incompetent project manager 4
Project member turnover 2
Poor staffing process 1
Directing Poor coordination 9
26% Poor communication 6
Poor leadership 5
Low commitment 6
Controlling Poor follow-up 3
7% Poor monitoring 2
No control system 1
No recognition of problems 1
*To interpret the table, note
that 32 percent of the 1,654
participants reported the
barriers under “Planning,” 12
percent reported the barriers
under “Scheduling,” and so
on.
IMPLEMENTING CLOSEDOWN
1. Getting delivery acceptance from the customer.
2. Shutting down resources and releasing to new uses.
3. Reassigning project team members.
4. Closing accounts and seeing all bills are paid.
5. Evaluating the project team, project team members, and
the project manager.
EUROPEAN
SPACE
LAUNCH, AG—
PROJECT
CLOSURE
CHECKLIST
FIGURE 14.2
PROJECT PERFORMANCE
EVALUATIONS
• Reasons for Poor-Quality Project Performance Evaluations:
• Evaluations of individuals are still left to supervisors of the
team member’s home department.
• Typical measures of team performance center on time, cost,
and specifications.
PROJECT PERFORMANCE
EVALUATION: TEAM
• Are standards and goals for measuring performance Clear,
challenging, and attainable? Lead to positive consequences?
• Are responsibilities and performance standards known by all team
members?
• Are team rewards adequate? Management believes teams are
important?
• Is there a career path for successful project managers
• Does the team have discretionary authority to manage short-term
difficulties?
• Is there a high level of trust within the organization culture?
• Are there criteria beyond time, cost, and specifications?
SAMPLE TEAM EVALUATION
AND FEEDBACK SURVEY
TABLE 14.3
PROJECT PERFORMANCE
EVALUATION: INDIVIDUAL
• Responsibility for assessing performance
• Functional organization or functional matrix: the individual’s
area manager.
• The area manager may solicit the project manager’s opinion of the
individual’s performance on a specific project.
• Balanced matrix: the project manager and the area manager
jointly evaluate an individual’s performance.
• Project matrix and project organizations: the project manager is
responsible for appraising individual performance.
PROJECT PERFORMANCE
EVALUATION: INDIVIDUAL
• Multirater appraisal or the “360-degree feedback
• Involves soliciting feedback concerning team members’
performance from all the people their work affects.
• This includes project managers, area managers, peers,
subordinates, and even customers.
CONDUCTING
PERFORMANCE REVIEWS
• Begin by asking the individual to evaluate his or her
own performance.
• Avoid drawing comparisons with other team members;
rather, assess the individual in terms of established
standards and expectations.
• Focus criticism on specific behaviors rather than on the
individual personally.
• Be consistent and fair in your treatment of all team
members.
• Treat the review as one point in an ongoing process.
KEY POINTS IN
CONDUCTING AUDITS
• Have automatic times or points when audits will take place.
Surprises should be avoided.
• Conduct audits carefully and with sensitivity
• Audit staff must independent from the project.
• Audit reports need to be used and accessible.
• Audits support organizational culture
• Project closures should be planned and orderly.
• Certain “core conditions” must be in place to support team
and individual evaluation.
• Conduct individual and team evaluations separate from pay
or merit reviews.
KEY TERMS
In-process project audit
Maturity model
Performance review
Postproject audit
Project audit report
Project closure
Team evaluation
Three hundred and sixty
degree feedback
Project closure and audit

More Related Content

What's hot

Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
GeorgeKabongah2
 
Project integration management
Project integration managementProject integration management
Project integration management
Prabudh Dhingra
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Mohamed Loey
 
Project management
Project managementProject management
Project management
Al Amin Neaz Ahmed
 
PMP_Project Stakeholder Management
PMP_Project Stakeholder ManagementPMP_Project Stakeholder Management
PMP_Project Stakeholder Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementation
Dr. Saima Baig
 
Project communication management
Project communication managementProject communication management
Project communication management
Takudzwa Chatora
 
Project Closing Process
Project Closing ProcessProject Closing Process
Project Closing Process
Nishant Munjal
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
Abhishek Raj
 
Project management
Project managementProject management
Project management
meena velmurugan
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure ReportCheryl Burcham
 
Project Management
Project ManagementProject Management
Project Management
Mark Roman
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
guest90bddb
 
Project scope management
Project scope managementProject scope management
Project scope management
Jody R Flower
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
Jeremy Jay Lim
 
Project Closing
Project ClosingProject Closing
Project Closing
Martin Sillaots
 
Project scope management
Project scope managementProject scope management
Project scope management
Anit Roy
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Wadhwani Foundation
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6
Agus Suhanto
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
dyaksa hanindito
 

What's hot (20)

Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
 
Project integration management
Project integration managementProject integration management
Project integration management
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Project management
Project managementProject management
Project management
 
PMP_Project Stakeholder Management
PMP_Project Stakeholder ManagementPMP_Project Stakeholder Management
PMP_Project Stakeholder Management
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementation
 
Project communication management
Project communication managementProject communication management
Project communication management
 
Project Closing Process
Project Closing ProcessProject Closing Process
Project Closing Process
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project management
Project managementProject management
Project management
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Project Management
Project ManagementProject Management
Project Management
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Project Closing
Project ClosingProject Closing
Project Closing
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 

Similar to Project closure and audit

Learning_Unit_3
Learning_Unit_3Learning_Unit_3
Learning_Unit_3Jack Ong
 
Lecture 6 Project Audit & Closure.ppt
Lecture 6 Project Audit & Closure.pptLecture 6 Project Audit & Closure.ppt
Lecture 6 Project Audit & Closure.ppt
MehediHasan636262
 
02.pptx
02.pptx02.pptx
02.pptx
Maryam522887
 
How to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer MitterHow to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer Mitter
Sameer Mitter
 
Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10
Hari Krishna Shrestha
 
Project management
Project managementProject management
Project managementobsession56
 
1113 PPT.pptx
1113 PPT.pptx1113 PPT.pptx
1113 PPT.pptx
AVNEETSingh40794
 
The Project Manager
The Project ManagerThe Project Manager
The Project Manager
Robin Surland
 
Unit 1 spm
Unit 1  spmUnit 1  spm
Unit 1 spm
GomathiPrakasham
 
Unit 1 spm
Unit 1  spmUnit 1  spm
Unit 1 spm
GomathiPrakasham
 
Unit 1 PM.pptx
Unit 1 PM.pptxUnit 1 PM.pptx
Unit 1 PM.pptx
YogeshKumar841711
 
Overview of Role of Sponsor in Change
Overview of Role of Sponsor in ChangeOverview of Role of Sponsor in Change
Overview of Role of Sponsor in ChangeRadhia Benalia
 
M & E Presentation DSK.ppt
M & E Presentation DSK.pptM & E Presentation DSK.ppt
M & E Presentation DSK.ppt
ShafayetHossain30
 
Project governance
Project governanceProject governance
Project governance
suraj arvapally
 
Business Analyst vs. Project Manager - Eliminating the Confusion!
Business Analyst vs. Project Manager - Eliminating the Confusion!Business Analyst vs. Project Manager - Eliminating the Confusion!
Business Analyst vs. Project Manager - Eliminating the Confusion!
Corporate Education Group (CEG)
 
Requirements Planning & Management
Requirements Planning & ManagementRequirements Planning & Management
project integration mgmt.pdf
project integration mgmt.pdfproject integration mgmt.pdf
project integration mgmt.pdf
IvarsLinde1
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
Inam Khosa
 
Lecture PLAN MONITORING and EVALUATING.
Lecture PLAN  MONITORING and EVALUATING.Lecture PLAN  MONITORING and EVALUATING.
Lecture PLAN MONITORING and EVALUATING.
Jo Balucanag - Bitonio
 

Similar to Project closure and audit (20)

Learning_Unit_3
Learning_Unit_3Learning_Unit_3
Learning_Unit_3
 
Lecture 6 Project Audit & Closure.ppt
Lecture 6 Project Audit & Closure.pptLecture 6 Project Audit & Closure.ppt
Lecture 6 Project Audit & Closure.ppt
 
02.pptx
02.pptx02.pptx
02.pptx
 
How to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer MitterHow to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer Mitter
 
Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10
 
Project management
Project managementProject management
Project management
 
Chap014
Chap014Chap014
Chap014
 
1113 PPT.pptx
1113 PPT.pptx1113 PPT.pptx
1113 PPT.pptx
 
The Project Manager
The Project ManagerThe Project Manager
The Project Manager
 
Unit 1 spm
Unit 1  spmUnit 1  spm
Unit 1 spm
 
Unit 1 spm
Unit 1  spmUnit 1  spm
Unit 1 spm
 
Unit 1 PM.pptx
Unit 1 PM.pptxUnit 1 PM.pptx
Unit 1 PM.pptx
 
Overview of Role of Sponsor in Change
Overview of Role of Sponsor in ChangeOverview of Role of Sponsor in Change
Overview of Role of Sponsor in Change
 
M & E Presentation DSK.ppt
M & E Presentation DSK.pptM & E Presentation DSK.ppt
M & E Presentation DSK.ppt
 
Project governance
Project governanceProject governance
Project governance
 
Business Analyst vs. Project Manager - Eliminating the Confusion!
Business Analyst vs. Project Manager - Eliminating the Confusion!Business Analyst vs. Project Manager - Eliminating the Confusion!
Business Analyst vs. Project Manager - Eliminating the Confusion!
 
Requirements Planning & Management
Requirements Planning & ManagementRequirements Planning & Management
Requirements Planning & Management
 
project integration mgmt.pdf
project integration mgmt.pdfproject integration mgmt.pdf
project integration mgmt.pdf
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
 
Lecture PLAN MONITORING and EVALUATING.
Lecture PLAN  MONITORING and EVALUATING.Lecture PLAN  MONITORING and EVALUATING.
Lecture PLAN MONITORING and EVALUATING.
 

More from Angelito Estrada, MBA

Transforming organization
Transforming organizationTransforming organization
Transforming organization
Angelito Estrada, MBA
 
Personnel Management in MNE
Personnel Management in MNEPersonnel Management in MNE
Personnel Management in MNE
Angelito Estrada, MBA
 
E government by lito
E government by litoE government by lito
E government by lito
Angelito Estrada, MBA
 
Starting new business venture- Philippine Setting
Starting new business venture- Philippine Setting Starting new business venture- Philippine Setting
Starting new business venture- Philippine Setting Angelito Estrada, MBA
 

More from Angelito Estrada, MBA (6)

Transforming organization
Transforming organizationTransforming organization
Transforming organization
 
Personnel Management in MNE
Personnel Management in MNEPersonnel Management in MNE
Personnel Management in MNE
 
Case Study: Starbucks
Case Study: StarbucksCase Study: Starbucks
Case Study: Starbucks
 
Foreign Direct Investment
Foreign Direct InvestmentForeign Direct Investment
Foreign Direct Investment
 
E government by lito
E government by litoE government by lito
E government by lito
 
Starting new business venture- Philippine Setting
Starting new business venture- Philippine Setting Starting new business venture- Philippine Setting
Starting new business venture- Philippine Setting
 

Recently uploaded

W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
ssuserf63bd7
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
CIOWomenMagazine
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 

Recently uploaded (9)

W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 

Project closure and audit

  • 1. DR EMERITA ALIAS Professor PROJECT RESEARCH AND DEVELOPMENT Reported by ANGELITO LECCIO ESTRADA
  • 3. Clifford F. Gray Eric W. Larson Project Audit and Closure Chapter 14
  • 4. MAJOR TASKS OF A PROJECT AUDIT 1. Evaluate if the project delivered the expected benefits to all stakeholders. Was the project managed well? Was the customer satisfied? 2. Assess what was done wrong and what contributed to successes. 3. Identify changes to improve the delivery of future projects.
  • 5. PROJECT AUDIT COMPONENTS • A review of why the project was selected. • A reassessment of the project’s role in the organization’s priorities. • A check on the organizational culture to ensure it facilitates the type of project being implemented. • An assessment of how well the project team is functioning well and if its is appropriately staffed. • A check on external factors that might change where the project is heading or its importance. • A review of all factors relevant to the project and to managing future projects.
  • 6. TYPES OF PROJECT AUDITS • In-process project audits • Allow for corrective changes if conditions have changed and for concentration on project progress and performance. • Postproject audits • Take a broader and longer-term view of the project’s role in the organization and emphasize improving the management of future projects.
  • 7. FACTORS INFLUENCING AUDIT DEPTH AND DETAIL Table 14.1 Organization size Project importance Project type Project risk Project size Project problems
  • 8. Step1 Initiation and Staffing Step 2 Data Collection and Analysis Step 3 Reporting Conducting a Project Audit
  • 9. CHARACTERISTICS OF AUDIT LEADERS 1. No direct involvement or direct interest in the project. 2. Respect (perceived as impartial and fair) of senior management and other project stakeholders. 3. Willingness to listen. 4. Independence and authority to report audit results without fear of recriminations from special interests. 5. Perceived as having the best interests of the organization in making decisions. 6. Broad-based experience in the organization or industry.
  • 10. STEP 2: DATA COLLECTION AND ANALYSIS • Organization View • Was the organizational culture supportive and correct? • Was senior management’s support adequate? • Did the project accomplish its intended purpose? • Were risks appropriately identified and assessed? • Were the right people and talents assigned? • Have staff been fairly reassigned to new projects? • What does evaluation from contractors suggest? • Were the project start-up and hand-off successful? • Is the customer satisfied?
  • 11. STEP 2: DATA COLLECTION AND ANALYSIS • Project Team View • Were the project planning and control systems appropriate for this type of project? • Should all similar projects use these systems? • Did the project conform to plan for budget and schedule? • Were interfaces with stakeholders effective? • Have staff been fairly assigned to new projects? • Did the team have adequate resources? Were there resource conflicts? • Was the team managed well? • What does evaluation from contractors suggest?
  • 12. STEP 3: REPORTING • Audit Report Content Outline • Classification of project • Project type • Size • Staffing • Technology level • Strategic or support • Analysis of information gathered • Project mission and objectives • Procedures and systems used • Organization resources used • Recommendations • Corrective actions • Lessons learned • Reminders • Appendix • Backup data • Summary booklet
  • 14. PROJECT CLOSURE • Conditions for Closure • Normal • Premature • Perpetual • Failed Project • Changed Priority • Close-out Plan: Questions to be Asked • What tasks are required to close the project? • Who will be responsible for these tasks? • When will closure begin and end? • How will the project be delivered?
  • 15. BARRIERS TO PROJECT SUCCESS Table 14.2 Activity* Barrier Incidence (%) Planning Unclear definition 16% 32% Poor decision making 9 Bad information 3 Changes 4 Scheduling Tight schedule 4 12% Not meeting schedule 5 Not managing schedule 3 Organizing Lack of responsibility or accountability 5 11% Weak project manager 5 Top management interference 1 Staffing Inadequate personnel 5 12% Incompetent project manager 4 Project member turnover 2 Poor staffing process 1 Directing Poor coordination 9 26% Poor communication 6 Poor leadership 5 Low commitment 6 Controlling Poor follow-up 3 7% Poor monitoring 2 No control system 1 No recognition of problems 1 *To interpret the table, note that 32 percent of the 1,654 participants reported the barriers under “Planning,” 12 percent reported the barriers under “Scheduling,” and so on.
  • 16. IMPLEMENTING CLOSEDOWN 1. Getting delivery acceptance from the customer. 2. Shutting down resources and releasing to new uses. 3. Reassigning project team members. 4. Closing accounts and seeing all bills are paid. 5. Evaluating the project team, project team members, and the project manager.
  • 18. PROJECT PERFORMANCE EVALUATIONS • Reasons for Poor-Quality Project Performance Evaluations: • Evaluations of individuals are still left to supervisors of the team member’s home department. • Typical measures of team performance center on time, cost, and specifications.
  • 19. PROJECT PERFORMANCE EVALUATION: TEAM • Are standards and goals for measuring performance Clear, challenging, and attainable? Lead to positive consequences? • Are responsibilities and performance standards known by all team members? • Are team rewards adequate? Management believes teams are important? • Is there a career path for successful project managers • Does the team have discretionary authority to manage short-term difficulties? • Is there a high level of trust within the organization culture? • Are there criteria beyond time, cost, and specifications?
  • 20. SAMPLE TEAM EVALUATION AND FEEDBACK SURVEY TABLE 14.3
  • 21. PROJECT PERFORMANCE EVALUATION: INDIVIDUAL • Responsibility for assessing performance • Functional organization or functional matrix: the individual’s area manager. • The area manager may solicit the project manager’s opinion of the individual’s performance on a specific project. • Balanced matrix: the project manager and the area manager jointly evaluate an individual’s performance. • Project matrix and project organizations: the project manager is responsible for appraising individual performance.
  • 22. PROJECT PERFORMANCE EVALUATION: INDIVIDUAL • Multirater appraisal or the “360-degree feedback • Involves soliciting feedback concerning team members’ performance from all the people their work affects. • This includes project managers, area managers, peers, subordinates, and even customers.
  • 23. CONDUCTING PERFORMANCE REVIEWS • Begin by asking the individual to evaluate his or her own performance. • Avoid drawing comparisons with other team members; rather, assess the individual in terms of established standards and expectations. • Focus criticism on specific behaviors rather than on the individual personally. • Be consistent and fair in your treatment of all team members. • Treat the review as one point in an ongoing process.
  • 24. KEY POINTS IN CONDUCTING AUDITS • Have automatic times or points when audits will take place. Surprises should be avoided. • Conduct audits carefully and with sensitivity • Audit staff must independent from the project. • Audit reports need to be used and accessible. • Audits support organizational culture • Project closures should be planned and orderly. • Certain “core conditions” must be in place to support team and individual evaluation. • Conduct individual and team evaluations separate from pay or merit reviews.
  • 25. KEY TERMS In-process project audit Maturity model Performance review Postproject audit Project audit report Project closure Team evaluation Three hundred and sixty degree feedback

Editor's Notes

  1. Introduction. Initial reaction about the report Ex. Class ends. Basis of Grading
  2. audit
  3. That end the report