CONSTRUCTION TECHNOLOGY
COSTING OF COLUMN
GROUP N0 01
CONTENT
INTRODUCTION
SITE VISIT
CALCULATION
DISCUSSION
SUMMARY
2
INTRODUCTION
Column.
 A column or pillar in architecture and structural engineering is a
structural element that transmits, through compression, the weight
of the structure above to other structural elements below.
3
INTRODUCTION
Types of Columns
 Based on slenderness ratio (critical buckling length), Long
column, Short column, Intermediate column.
 Based on shape, Rectangular, Square, Circular, Polygon
 Based on type of loading, Axially loaded columns, Axial load
and un-axial bending column, Axial load and biaxial bending
column
4
INTRODUCTION
RCC column (reinforced concrete column)
 Structural member designed to carry compressive loads with
steel frame composed with concrete.
 Columns especially slender columns may be subjected to lateral
loads and moment's.
 At times tensile stress may also develop especially in columns
at outer periphery of the building.
 Steel can take care of this tensile stress.
5
SITE VISIT
SITE DETAIL
 Project name BMW
 Project Details
 Client Prime Homes
 Consultant Aruth Badaraji
 Contractor Nikko Construction (pvt) Ltd
 Date of commence 23/July/2016
 Date of completion April 2018
 Project Value 150 Millions
6
SITE VISIT
 Current status of project
 Progress Structural 6th Floor
 Masonry 3rd Floor completed
 No of stories 6 story
 Type of Construction Apartment
 Location Bauddaloka
Mawatha
 Land Area 4000 sqft
 Architect Anil Kumara
 Structural Engineer Laksin Cooray
 Site Engineer Ashen Udara
 Procurement Method Traditional
7
SITE VISIT
Selected column – C37 located in 5th floor – Grid D-E / 3
8
Length of column : 3000mm
T12 T12
T16
T12
T12
T16
T12T12
T16
T12
T12
T16
CALCULATION
 BAR SCHEDULE AND REINFORCEMENT WEIGHT
Cost Calculation
• Number of bars
No. of 12mm bars: 8
No. of 16mm bars: 4
Total no. of bars: 12
• Number of stirrups
Length of column: 3000mm
Spacing of stirrups: 150mm
3000/150 = 20
20 +1 = 21 , two stirrups used in combination , 21 *2 = 42
9
Rate of steel per 1Kg = Rs. 130.00 ( Lanva )
Labor rate for reinforcement Per 1Kg = Rs 25.00
CALCULATION
 Total length of a stirrups
162.5mm * 4 = 650mm
70mm * 2 = 140mm
Total length = 0.79m
10
CALCULATION
Weight of dia 12mm bar
= 7800kg/m3 * 22/7 * (12/2mm * 10-3)3 * 3000mm
= 2.73kg
Total weight
2.73 * 8 = 21.86 kg
11
CALCULATION
Weight of 16mm bar
= 7800kg/m3 * 22/7 * (16/2mm * 10-3)3 * 3000mm
= 4.85 kg
Total weight
4.85 kg * 4 = 19.43kg
12
CALCULATION
Weight of stirrups
= 7800kg/m3 * 22/7 * (6mm * 10-3)3 * 790mm
=0.17 kg
Total weight
0.17kg * 40 = 7.41kg
13
CALCULATION
 Total weight of reinforcement in a column
12mm bar = 21.86 kg
16mm bar = 19.43 kg
Stirrups = 7.41 kg
TOTAL WEIGHT = 48.1 kg
14
CALCULATION
Labor Rate for steel reinforcement - Rs 25000/= per 1ton
- Rs 25/= per 1kg
Rate for 48.1 kg = 48.1kg * 25/=
= Rs 1202 /=
15
CALCULATION
Bar name Number of
bar
Length Diameter of
a bar
Volume of a
bar
Total volume
bar
Mass of
bars
Rate
T16 4 10' 16 mm 603429 mm³ 2413714mm³ 19.43 Kg Rs 2525.90
T12 8 10' 12 mm 339429 mm³ 2715428mm³ 21.86 Kg Rs 2841.80
Stirrups 42 31.3" 6 mm 22487.1mm³ 944458.2mm³ 7.41 Kg Rs 963.30
Total - - - - 6073600.2mm³ 48.7 Kg Rs 6331.00
16
Therefore total cost for reinforcement the column =Rs.6331+Rs.1202
=Rs.7533.00
CALCULATION
 FOAM WORK ARRANGEMENT
COST CALCULATION
8’X 4’ PLYWOOD COST = RS 2200.00
2’X 2’ BATTEN 1FT = RS 30.00
TREAD BAR 20FT = RS 720.00
TREAD BAR 1FT COST = 720/20 = 36.00
17
9”
15”
CALCULATION
18
FOAM WORK ARRANGEMENT
CALCULATION
19
48”
15” 15” 18”
Height of the column = 8 ft
Gap between two tread bars = 600mm
How many tread bars need = 2400 mm/600 mm
= 4
= 4+1
= 5 x 2
= 10
Column size = 2x0.75x8 = 12
= 2x1.75x8 = 28
= 12 + 28 = 40ft2
Plywood 1ft2 cost = 2200/32 = Rs 68.75
CALCULATION
20
For plywood 40ft2 cost = 68.75 x 40 = Rs 2750.00
2’x 2’ battens need = 0.381mm x 10 x 3.28
Horizontal = 12.5 Ft
= 0.254 mm x 10 x 3.28
= 8.3 Ft
2’x 2’ battens need Vertical = 8 x 2438mm x 3.28
= 63.981 Ft
Cost for 2’x 2’ battens = (12.5+8.3 + 63.981) x 30 = Rs
2543.43.00
CALCULATION
Length of useable tread bar = 400 x 10 = 4000mm
= 4000mm/10 = 400cm
= 400/30 = 13.3ft
Cost for 13.3ft tread bar = 13.3 x 36 = rs 478.8
Labor cost for 1ft2 = rs 80.00
For 40ft2 labour cost = 80 x 40 = rs 3200.00
Final cost for column form work = 2750 + 2543.43 + 478.8 + 3200
= Rs 8972.23
21
CALCULATION
FOAM WORK ARRANGEMENT
22
CALCULATION
cement sand Coarse
aggregate
Grade(N/mm
2)
1 3 6 10/15
1 2 4 20
1 1 ½ 3 25
1 1 2 30
23
► Concreting the column
Grade of concrete
Definition
The grade of concrete refers to the ratio by which the ingredients of concrete
e.g. cement, fine aggregate (sand) and coarse aggregate is mixed.
Few commonly used nominal mix ratios for volume batching are
CALCULATION
 Recommended steps for concreting
 Concrete is not a single step of mixing materials and it is a process of few
important steps.
 Material selection
 Material measuring
 Mixing
 Transporting
 Placing
 Compacting
 Finishing
 Curing
24
CALCULATION
Hardening state
After final setting time of the concrete, hardening process is started and
continue for long period of time. Concrete gains strength due to this
hardening process.
25
CALCULATION
 Concrete pouring method of the column
Equipment’s & tools required for concrete pouring
Hand saw, Wire cutter, Brush, Shovel
Steel Brush
Air compressor
Plumb bob
Line dory
Concrete Pump
Vibrator
Trowel
Spirit Level
26
CALCULATION
 Concrete finishing and Curing
27
CALCULATION
 Evaluation cost for concreting
Find the volume of column:
Length = 15" (15×25=375mm)
Width = 09" (9×25=225mm)
Height = 10' (10×300=3000mm)
Therefore total volume of column = 375mm×225mm×3000mm
= 253,125,000 mm³
= 0.253125 m³
= 0.25 m³
28
CALCULATION
Item Number of
labours
Rate per date Total cost
Skills Non
skills
Skills Non
skills
Pouring 2 3 Rs.2000 Rs.1800 Rs.8100+Rs 8000
To poker - 1 - Rs.500 Rs.500
Other works - 1 - Rs.800 Rs.800
Rs.17400.00
29
Therefore total cost for concreting the column is =Rs.3416+Rs 85.20 +Rs.17400
=Rs.20901.20
CALCULATION
 TOTAL COST FOR THE COLUMN
Reinforcement = Rs 7533.00
Concreting = Rs 20 901.20
Foam work = Rs 8972.23
Total = Rs 37 406.23
Profit and contingencies 25% = Rs 37 406.23 * 25 %
= Rs 9351.55
Total cost for the column = Rs 46757.78
30
Discussion
 Link Spacing and link size of the column
 Link size should be > ¼ of largest diameter of bar or 6 mm. In
our column the largest diameter was 16mm and the link size
the 16/4 = 4 mm. Therefore it is taken as 6 mm
 Link spacing should be < 12 times of smallest diameter of the
bar. Then 12 x12 = 144 mm , but the column we chosen had
the link spacing 150 mm. 125mm can be use according to ( CL
3.12.7 )
31
Discussion
 Concrete Protection Cover
 Weight of a 1m in steel bar.
32
Diameter Weight
6mm 0.22kg
8mm 0.39kg
10mm 0.62kg
12mm 0.88kg
16mm 1.58kg
20mm 2.47kg
Standard weight is calculated
by: [DxD/162
Cost for concrete
 1:1:2 proportion. Grade 30
 Cement amount used
 Density = 1420 and mass for cement
 d = m / V
1 Cube = 2.83 m3
Sand and gravel cube cost can be calculate by
(1 / 2.83) x V = amount in cubes.
33
Cement : Sand : Gravel
1 : 1 : 2 ( volume)
¼ : ¼ : ½ ( 1 m3)
For the compaction when mixing 50%
Then the volume increased to 1.5 m3
¼ x 1.5 : ¼ x 1.5 : ½ x1.5
0.375 : 0.375 : 0.75
Discussion
 Ties used in columns.
34
Discussion
 Rate of steel
Rate of steel changes according to the manufacture. In
Sanstha the rate per ton is Rs 130000/=, In melva the rate is Rs
125000/= pre ton and in GTB 123000/=.
 Formwork in columns.
35
Discussion
 Column with footing
36
Volume selected
for cost
evaluation
Height of 10 Ft
Discussion
 Anchorage, laps and joints of column Bar
 Anchorage
 Laps and Joints
 When both bars at a laps exists size 20 and the cover is less than (1.5
x size of the smaller bar ,transfer link should be provided throughout
the lap length. At the lap the link bar should be not less than ( ½ x
size of the smaller bar ) and the spacing should not exceeding
200mm.
37
Summary
 What is a Column
 What is a RCC Column
 Site Visit details
 How to identify Bar schedule
 How to calculate bar weight
38
Summary
 How to Arranged the form work for column
 How to calculate form work cost
 What are the concreting methods
 How to pouring concrete
 Grades of concrete
 Finalize the cost of building a column
39
Questions
40
THANK YOU
41

More Related Content

What's hot

Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Anne Allan
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshulAnshul Shakya
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Hamza Waheed
 
Glass fiber reinforced concrete
Glass fiber reinforced concreteGlass fiber reinforced concrete
Glass fiber reinforced concretebhavin shah
 
Ultra High Performance Concrete(UHPC)
Ultra High Performance Concrete(UHPC)Ultra High Performance Concrete(UHPC)
Ultra High Performance Concrete(UHPC)Abdul Majid
 
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONS
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONSCELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONS
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONSIjripublishers Ijri
 
Properties of concrete 1
Properties of concrete 1Properties of concrete 1
Properties of concrete 1TaseerBaloch1
 
EVALUATON TENDER project planning and management ppt
EVALUATON TENDER project planning and management pptEVALUATON TENDER project planning and management ppt
EVALUATON TENDER project planning and management pptPunit Sharnagat
 
Penetration resistance test
Penetration resistance testPenetration resistance test
Penetration resistance testAyaz khan
 
Concrete basicss for gem
Concrete basicss for gemConcrete basicss for gem
Concrete basicss for gemAbdel Zayed
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Anne Allan
 

What's hot (20)

Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Long wall and short wall method 4
Long wall and short wall method 4Long wall and short wall method 4
Long wall and short wall method 4
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
Glass fiber reinforced concrete
Glass fiber reinforced concreteGlass fiber reinforced concrete
Glass fiber reinforced concrete
 
Ultra High Performance Concrete(UHPC)
Ultra High Performance Concrete(UHPC)Ultra High Performance Concrete(UHPC)
Ultra High Performance Concrete(UHPC)
 
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONS
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONSCELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONS
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONS
 
READY MIX CONCRETE
READY MIX CONCRETEREADY MIX CONCRETE
READY MIX CONCRETE
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Properties of concrete 1
Properties of concrete 1Properties of concrete 1
Properties of concrete 1
 
Concrete cloth
Concrete cloth Concrete cloth
Concrete cloth
 
EVALUATON TENDER project planning and management ppt
EVALUATON TENDER project planning and management pptEVALUATON TENDER project planning and management ppt
EVALUATON TENDER project planning and management ppt
 
Penetration resistance test
Penetration resistance testPenetration resistance test
Penetration resistance test
 
Concrete basicss for gem
Concrete basicss for gemConcrete basicss for gem
Concrete basicss for gem
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
 

Similar to CONSTRUCTION TECHNOLOGY COSTING OF COLUMN

INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDERHarsh Shani
 
CIVE 801 - Course Project Report (Teal)
CIVE 801 - Course Project Report (Teal)CIVE 801 - Course Project Report (Teal)
CIVE 801 - Course Project Report (Teal)Cyle Teal
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET Journal
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfAberaMamoJaleta
 
Design ppt
Design pptDesign ppt
Design ppttishu001
 
Lec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rLec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rCivil Zone
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptbala506586
 
design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyoverPeer Mohideen
 
DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...
DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...
DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...p shivashanker
 
Lec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rLec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rMUST,Mirpur AJK,Pakistan
 
Planing,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALLPlaning,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALLArshana Anu
 
Flexural behaviour of fibre reinforced ferrocement concrete
Flexural behaviour of fibre reinforced ferrocement concreteFlexural behaviour of fibre reinforced ferrocement concrete
Flexural behaviour of fibre reinforced ferrocement concreteSanthosh Jayaraman
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowAnchit Agrawal
 
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxRajeshKumar25548
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank designHarish Mahavar
 
Design and Construction of a Connecting rod
Design and Construction of a Connecting rodDesign and Construction of a Connecting rod
Design and Construction of a Connecting rodFaisal Niloy
 

Similar to CONSTRUCTION TECHNOLOGY COSTING OF COLUMN (20)

INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
 
CIVE 801 - Course Project Report (Teal)
CIVE 801 - Course Project Report (Teal)CIVE 801 - Course Project Report (Teal)
CIVE 801 - Course Project Report (Teal)
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line System
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
 
Design ppt
Design pptDesign ppt
Design ppt
 
Lec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rLec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-r
 
Lec 13-14-15
Lec 13-14-15Lec 13-14-15
Lec 13-14-15
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
 
design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
 
DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...
DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...
DESIGN OF PARTIAL MAGNETIC REPULSION FOUNDATION BUILDING BY USING U-BOOTS AND...
 
PROJECT DEMO final
PROJECT DEMO finalPROJECT DEMO final
PROJECT DEMO final
 
Lec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rLec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-r
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
 
Planing,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALLPlaning,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALL
 
Flexural behaviour of fibre reinforced ferrocement concrete
Flexural behaviour of fibre reinforced ferrocement concreteFlexural behaviour of fibre reinforced ferrocement concrete
Flexural behaviour of fibre reinforced ferrocement concrete
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
connecting rod
connecting rodconnecting rod
connecting rod
 
Design and Construction of a Connecting rod
Design and Construction of a Connecting rodDesign and Construction of a Connecting rod
Design and Construction of a Connecting rod
 

Recently uploaded

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

CONSTRUCTION TECHNOLOGY COSTING OF COLUMN

  • 3. INTRODUCTION Column.  A column or pillar in architecture and structural engineering is a structural element that transmits, through compression, the weight of the structure above to other structural elements below. 3
  • 4. INTRODUCTION Types of Columns  Based on slenderness ratio (critical buckling length), Long column, Short column, Intermediate column.  Based on shape, Rectangular, Square, Circular, Polygon  Based on type of loading, Axially loaded columns, Axial load and un-axial bending column, Axial load and biaxial bending column 4
  • 5. INTRODUCTION RCC column (reinforced concrete column)  Structural member designed to carry compressive loads with steel frame composed with concrete.  Columns especially slender columns may be subjected to lateral loads and moment's.  At times tensile stress may also develop especially in columns at outer periphery of the building.  Steel can take care of this tensile stress. 5
  • 6. SITE VISIT SITE DETAIL  Project name BMW  Project Details  Client Prime Homes  Consultant Aruth Badaraji  Contractor Nikko Construction (pvt) Ltd  Date of commence 23/July/2016  Date of completion April 2018  Project Value 150 Millions 6
  • 7. SITE VISIT  Current status of project  Progress Structural 6th Floor  Masonry 3rd Floor completed  No of stories 6 story  Type of Construction Apartment  Location Bauddaloka Mawatha  Land Area 4000 sqft  Architect Anil Kumara  Structural Engineer Laksin Cooray  Site Engineer Ashen Udara  Procurement Method Traditional 7
  • 8. SITE VISIT Selected column – C37 located in 5th floor – Grid D-E / 3 8 Length of column : 3000mm T12 T12 T16 T12 T12 T16 T12T12 T16 T12 T12 T16
  • 9. CALCULATION  BAR SCHEDULE AND REINFORCEMENT WEIGHT Cost Calculation • Number of bars No. of 12mm bars: 8 No. of 16mm bars: 4 Total no. of bars: 12 • Number of stirrups Length of column: 3000mm Spacing of stirrups: 150mm 3000/150 = 20 20 +1 = 21 , two stirrups used in combination , 21 *2 = 42 9 Rate of steel per 1Kg = Rs. 130.00 ( Lanva ) Labor rate for reinforcement Per 1Kg = Rs 25.00
  • 10. CALCULATION  Total length of a stirrups 162.5mm * 4 = 650mm 70mm * 2 = 140mm Total length = 0.79m 10
  • 11. CALCULATION Weight of dia 12mm bar = 7800kg/m3 * 22/7 * (12/2mm * 10-3)3 * 3000mm = 2.73kg Total weight 2.73 * 8 = 21.86 kg 11
  • 12. CALCULATION Weight of 16mm bar = 7800kg/m3 * 22/7 * (16/2mm * 10-3)3 * 3000mm = 4.85 kg Total weight 4.85 kg * 4 = 19.43kg 12
  • 13. CALCULATION Weight of stirrups = 7800kg/m3 * 22/7 * (6mm * 10-3)3 * 790mm =0.17 kg Total weight 0.17kg * 40 = 7.41kg 13
  • 14. CALCULATION  Total weight of reinforcement in a column 12mm bar = 21.86 kg 16mm bar = 19.43 kg Stirrups = 7.41 kg TOTAL WEIGHT = 48.1 kg 14
  • 15. CALCULATION Labor Rate for steel reinforcement - Rs 25000/= per 1ton - Rs 25/= per 1kg Rate for 48.1 kg = 48.1kg * 25/= = Rs 1202 /= 15
  • 16. CALCULATION Bar name Number of bar Length Diameter of a bar Volume of a bar Total volume bar Mass of bars Rate T16 4 10' 16 mm 603429 mm³ 2413714mm³ 19.43 Kg Rs 2525.90 T12 8 10' 12 mm 339429 mm³ 2715428mm³ 21.86 Kg Rs 2841.80 Stirrups 42 31.3" 6 mm 22487.1mm³ 944458.2mm³ 7.41 Kg Rs 963.30 Total - - - - 6073600.2mm³ 48.7 Kg Rs 6331.00 16 Therefore total cost for reinforcement the column =Rs.6331+Rs.1202 =Rs.7533.00
  • 17. CALCULATION  FOAM WORK ARRANGEMENT COST CALCULATION 8’X 4’ PLYWOOD COST = RS 2200.00 2’X 2’ BATTEN 1FT = RS 30.00 TREAD BAR 20FT = RS 720.00 TREAD BAR 1FT COST = 720/20 = 36.00 17 9” 15”
  • 19. CALCULATION 19 48” 15” 15” 18” Height of the column = 8 ft Gap between two tread bars = 600mm How many tread bars need = 2400 mm/600 mm = 4 = 4+1 = 5 x 2 = 10 Column size = 2x0.75x8 = 12 = 2x1.75x8 = 28 = 12 + 28 = 40ft2 Plywood 1ft2 cost = 2200/32 = Rs 68.75
  • 20. CALCULATION 20 For plywood 40ft2 cost = 68.75 x 40 = Rs 2750.00 2’x 2’ battens need = 0.381mm x 10 x 3.28 Horizontal = 12.5 Ft = 0.254 mm x 10 x 3.28 = 8.3 Ft 2’x 2’ battens need Vertical = 8 x 2438mm x 3.28 = 63.981 Ft Cost for 2’x 2’ battens = (12.5+8.3 + 63.981) x 30 = Rs 2543.43.00
  • 21. CALCULATION Length of useable tread bar = 400 x 10 = 4000mm = 4000mm/10 = 400cm = 400/30 = 13.3ft Cost for 13.3ft tread bar = 13.3 x 36 = rs 478.8 Labor cost for 1ft2 = rs 80.00 For 40ft2 labour cost = 80 x 40 = rs 3200.00 Final cost for column form work = 2750 + 2543.43 + 478.8 + 3200 = Rs 8972.23 21
  • 23. CALCULATION cement sand Coarse aggregate Grade(N/mm 2) 1 3 6 10/15 1 2 4 20 1 1 ½ 3 25 1 1 2 30 23 ► Concreting the column Grade of concrete Definition The grade of concrete refers to the ratio by which the ingredients of concrete e.g. cement, fine aggregate (sand) and coarse aggregate is mixed. Few commonly used nominal mix ratios for volume batching are
  • 24. CALCULATION  Recommended steps for concreting  Concrete is not a single step of mixing materials and it is a process of few important steps.  Material selection  Material measuring  Mixing  Transporting  Placing  Compacting  Finishing  Curing 24
  • 25. CALCULATION Hardening state After final setting time of the concrete, hardening process is started and continue for long period of time. Concrete gains strength due to this hardening process. 25
  • 26. CALCULATION  Concrete pouring method of the column Equipment’s & tools required for concrete pouring Hand saw, Wire cutter, Brush, Shovel Steel Brush Air compressor Plumb bob Line dory Concrete Pump Vibrator Trowel Spirit Level 26
  • 28. CALCULATION  Evaluation cost for concreting Find the volume of column: Length = 15" (15×25=375mm) Width = 09" (9×25=225mm) Height = 10' (10×300=3000mm) Therefore total volume of column = 375mm×225mm×3000mm = 253,125,000 mm³ = 0.253125 m³ = 0.25 m³ 28
  • 29. CALCULATION Item Number of labours Rate per date Total cost Skills Non skills Skills Non skills Pouring 2 3 Rs.2000 Rs.1800 Rs.8100+Rs 8000 To poker - 1 - Rs.500 Rs.500 Other works - 1 - Rs.800 Rs.800 Rs.17400.00 29 Therefore total cost for concreting the column is =Rs.3416+Rs 85.20 +Rs.17400 =Rs.20901.20
  • 30. CALCULATION  TOTAL COST FOR THE COLUMN Reinforcement = Rs 7533.00 Concreting = Rs 20 901.20 Foam work = Rs 8972.23 Total = Rs 37 406.23 Profit and contingencies 25% = Rs 37 406.23 * 25 % = Rs 9351.55 Total cost for the column = Rs 46757.78 30
  • 31. Discussion  Link Spacing and link size of the column  Link size should be > ¼ of largest diameter of bar or 6 mm. In our column the largest diameter was 16mm and the link size the 16/4 = 4 mm. Therefore it is taken as 6 mm  Link spacing should be < 12 times of smallest diameter of the bar. Then 12 x12 = 144 mm , but the column we chosen had the link spacing 150 mm. 125mm can be use according to ( CL 3.12.7 ) 31
  • 32. Discussion  Concrete Protection Cover  Weight of a 1m in steel bar. 32 Diameter Weight 6mm 0.22kg 8mm 0.39kg 10mm 0.62kg 12mm 0.88kg 16mm 1.58kg 20mm 2.47kg Standard weight is calculated by: [DxD/162
  • 33. Cost for concrete  1:1:2 proportion. Grade 30  Cement amount used  Density = 1420 and mass for cement  d = m / V 1 Cube = 2.83 m3 Sand and gravel cube cost can be calculate by (1 / 2.83) x V = amount in cubes. 33 Cement : Sand : Gravel 1 : 1 : 2 ( volume) ¼ : ¼ : ½ ( 1 m3) For the compaction when mixing 50% Then the volume increased to 1.5 m3 ¼ x 1.5 : ¼ x 1.5 : ½ x1.5 0.375 : 0.375 : 0.75
  • 34. Discussion  Ties used in columns. 34
  • 35. Discussion  Rate of steel Rate of steel changes according to the manufacture. In Sanstha the rate per ton is Rs 130000/=, In melva the rate is Rs 125000/= pre ton and in GTB 123000/=.  Formwork in columns. 35
  • 36. Discussion  Column with footing 36 Volume selected for cost evaluation Height of 10 Ft
  • 37. Discussion  Anchorage, laps and joints of column Bar  Anchorage  Laps and Joints  When both bars at a laps exists size 20 and the cover is less than (1.5 x size of the smaller bar ,transfer link should be provided throughout the lap length. At the lap the link bar should be not less than ( ½ x size of the smaller bar ) and the spacing should not exceeding 200mm. 37
  • 38. Summary  What is a Column  What is a RCC Column  Site Visit details  How to identify Bar schedule  How to calculate bar weight 38
  • 39. Summary  How to Arranged the form work for column  How to calculate form work cost  What are the concreting methods  How to pouring concrete  Grades of concrete  Finalize the cost of building a column 39