SlideShare a Scribd company logo
1 of 101
Construction Aspects of Rigid Pavements’
1
DLC M 10 at 7 days
PQC M 40
Road Crust
Road Composition
Vehicle
450
Sub Grade 9% CBR /Permeability 30 m/day
300mm
Sub Base GSB/DL 27% CBR
Embankment 3% CBR
Ground Level
Agg size 3 time decreases, Permeability 3 times decreases
Stress Diagram
Modulus of Subgrade Reaction ‘k’ value
k value =
Load, kg on 750 mm plate
(area cm2*0.125 cm)
kg/cm2/cm or MPa/m
Soaked
CBR
2 3 4 5 7 10 15 20 50
k Value
MPa/m
21 28 35 42 48 50 62 69 140
Rigid Pavement Flexible pavement
750 mm 200 mm
Deflection 0.2 mm 1 mm
or 200 micron
DESIGN DESIGN
K value/modulus of CBR %
subgrade reaction = (Load/1370kg)100
Load/(Plate area*1.25 mm))
kg/cm2/cm 5
Determines the spring constant “K”
K= F/d ( Total applied load)/ (Deflection)
Slab and beam type bridges
K < 100 kN/mm - flexible
100<K < 250 kN/mm - Semi Rigid
250<K < 400 kN/mm - RP/ stiff
K > 400 kN/mm- - very stiff Air Field/Girder
Choice and Economics
 Built up areas
Poor Drainage
Heavy rain fall & Flood Prone Area
 Water logging
Aggregates are costly
 Poor soil condition
Cost of flexible pavement - 25% less than RP
7
Dowel Bars
NEED OF JOINTS
RIGID PAVEMENT Flexible Pavement Deck Slab
Contraction joint,
longitudinal joint,
expansion joints
No Joints Only Expansion
Joints
Reasons Reasons Reasons
White in colour,
donot absorb heat,
so temperature
gradient
Black in colour, no
temperature gradient
White in Colour
but Reinforced
concrete,
∆ t too less
Warping/curling No warping No warping
Drying shrinkage Not much shrinkage Expansion
contract/RCC
9
Friction between
Sub base and PQC
Each layer bonded No bottom layer
L–Section of Rigid Pavement
Joint Spacing
3 - 6 m
Dowels PQC M40
Sub base, DLC
Granular Sub Base (GSB) OR Drainage Layer
Sub-grade, Compacted Natural Formation camber 2 %
• Jointed Plain with dowels
TABLE6. RECOMMENDEDDIMENSIONSOFDOWELBARS FOR RIGID
PAVEMENTS ( PCA1980)
Slabthickness
mm
Dowelbar details
Diameter, mm Length, mm Spacing, mm
200 25 360 300
230 30 400 300
250 32 450 300
280 36 450 300
300 38 500 300
350 38 500 300
TABLE 7. DETAILS OF TIE BARS FOR LONGITUDINAL JOINT OF
TWO-LANE RIGID PAVEMENTS
Slab
Thickness
(mm)
Tie Bar Details
Diameter
(d) (mm)
Max. Spacing (mm) Minimum length (mm)
Plain Deformed Plain Deformed
150 8
10
330
520
530
830
440
510
480
560
200 10
12
390
560
620
900
510
580
560
640
250 12 450 720 580 640
300 12
16
370
660
600
1060
580
720
640
800
350 12
16
320
570
510
910
580
720
640
800
d2
d1
If d2/d1≤ 0.6, the Transverse joint is damaged
or d2 > 0.6 d1
If d2/d1≤ 0.4, the Longitudinal joint is damaged
or d2 > 0.4 d1
LOA
D
13
Evaluation of Load Transfer Efficiency at
Joints
14
Principle of FWD
Carry out FWD deflection test in outer lane at 500m
Inner lane, if developing cracks should also be tested
Deflections abnormal - Collect data at closer interval
deflectio
n
Distance 17
Evaluation Process
Jointed Reinforced
In steep terrain, Fill up area, super elevation
L/B>1.5
10 - 20 m
Dowels
Slab
Base
Welded Wire Fabric
(0,1 - 0,2 %)
Expansion Joints Construction Joint Longitudinal Joint
19
20
Contraction Joints Placement of dowel bars Crack below
Longitudinal Joints Transverse Joints Contraction Jt.
-Plan Load transverse device
Contraction Joints
Dowel bars Placement
If no dowel bars. Dummy Contraction Joi
21
Expansion Joint/
Contraction Joint Without Gap
Dowel Bars ( ~25 – 38 mm) Plain
IS: 432
Longitudinal/ Construction Joint
Tie Bars ~ 12-16 mm deformed
IS: 1786
Matunga Bombay 1960 200 mm
CCI Established in 1927, Manual 1948
22
Manual 1948
Price Rs 1
First Mechanised Road NH -2, h= 300 mm NHDP G Q
IInd Mechanised Road Yamuna Expressway,
h= 320 mm
Maximum Utilization
Coarse
agg
Type Plain Cement
Concrete
Reinforced
Concrete
Lean Concrete
Less than M 15
Iron Slag 50 25 100
Steel Slag 25 nil 100
RCA 25 20 upto M 25 100
Copper slag 40 35 50
RCA 25 20 upto M 25 100
Chlorides = 0.5%
Sulphates = 0.04 %
Water absorption = 5% upto 10% With precaution
Wrong Right -----MORD 1501 p412
Direction of traffic
Length of panel in direction of traffic) shall not be
less than width of panel
31
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Case 1 = Stress -10,000*450/350*30*30 = 14 kg/cm2
Case 2 = Stress - 10,000*350/450*30*30 = 9 kg/cm2
SLOPE COMPACTOR - Earth Work- Embankment
Embankments ( 95%)
Unsuitable Soil : OI, OL,OH, Pt, > 75 mm
LL >50 %
PI >25 %
FSI > 50 %
Density:
1.52gm/cc upto 3 m
32
Density
S.N
o.
Type of work Maximum laboratory dry
unit weight when tested
as per IS: 2720 (Part 8)
1. Embankments up to 3
metres height, not subjected
to extensive flooding
Not less than 15.2 kN/cu.m
2. Embankments exceeding 3
metres height or
embankments of any height
subject to long periods of
inundation
Not less than 16.0 kN/cu.m
3. Subgrade and earthen
shoulders/verges/backfill
Not less than 17.5 kN/cu.m
Compaction - embankment and subgrade
No Type of
work/material
Relative compaction as
percentage of max. laboratory
dry densiy as per IS: 2720
(Part 8)
1. Subgrade and
earthen
shoulders
Not less than 97
2. Embankment Not less than 95
3. Expansive
clays
(a) Subgrade
and 500
mm
portion
just
below the
subgrade
(b) Remainin
g portion
of
embankm
Not allowed
Not less than 90
35
36
Common
III - VI
100
100
75
60
30
20
6
4
2
Lower sub base
Filter layer
Upper sub base
Drainage layer
EFFECT OF CURING TEMPERATURE ON STRENGTH, IS: 7861
REQUIREMENTS OF PURCHASER
• Variation +/- 10 mm for slump upto 75 mm
• Variation +/- 25 mm for > 75 mm
• Slump of concrete mix for pavements
compacted by vibration using paving trains
• 25 ± 10 mm
Flexural MPa vs Compressive in MPa =
fcr = 0.7 √(fck)
Finished
Road
• Tining (Texture depth ) 3mm Width
4 mm Depth
• Brooming (Texture depth ) 1.0+0.25 mm
• No undulation in form work
• Widening/transition Step/tied
• Density 97% in PQC
• Air < 3%
TWIN SHAFT MIXERS
PAN MIXERS MIXERS
CROSS-SECTION
tied shoulder
Camber not Shown
SUB-GRADE
EMBANKMENT
Dowel bars across transverse Joints not shown for
clarity
SUB-BASE (DLC)
DRAINAGE LAYER
FIGURE 1.4 - RIGID PAVEMENT TYPICAL CROSS-SECTION
LONGITIDINAL JOINT
TIE BAR
BASE (PQC)
DEBONDING/SEPARATION MEMBRANE
WHY DLC M10:
1. Levelling Course/levelled platform
2. To move paver smoothly @ 1m/min
3. Sub base to take some load
4. To modify subgrade CBR indirectly
CONMET BARODA/BRDC/Walia
AB Mumbai/Walia Delhi
Slip Form Paver Wrtgen/
Meckstar/
Gomaco LAYING
46
Thank you
WHERE RCC ?:
1.Steep Terrain
2.L/B>1.5
3.Fill up Areas/ Marshy areas
4.Tool Plazas,
5.Acute angled/ Curved/super elevated
6.Better riding quality
7.High Temperature/Low RH/
8.High wind speed
50
51
• Construction Methodology- Mumbai 1988-
2004
54
CONSTRUCTION
DLC Construction
Acceptance Criteria DLC MORTH
• Longitudinal joint staged by 350 mm
• Construction joint by about 900 mm
• Curing compound gets tackiness spread
hessian.
• 0.2 Litre /sq m
• Six cubes Minimum /day
• 100 m length trial in 2 days
• Insitu density 98% -601.6.5.1
57
MORTH- DLC
• 3 samples /1000 sqm cubes -903.5.1.1
• Square plate 7500-14000 sq. mm compaction
• For 1 min 30-40 kg load. -903.5.1.1
• Thickness not less than 8 mm- 903.5.1.3
• Repaired with lean concrete 10 mm down
58
Laying polythene sheet double at crack
Double
layer as
crack
arresting
layer
Slip Form Pavers of
width 15-16 m
Two layer
construction
61
WHY POLYTHENE SHEET ?
1. Crack arresting layer as
no joints in DLC
2. Water Proof layer
3. Insulating layer
4. Reduce friction
Double ply paper
In Airfield 500 micron thick
Two coat wax based curing compou
Take care- tipper shall not fall on paver
62
Take care- Alignment, location of Do-well bars/Tie bar
Take
care-
Slump
15-40
mm,
M 40
PQC
M 10 DLC
at 7 d
Dowel bars insertion
63
Do not Stop Paver more than 30 minute to avoid cold joint/crack
PQC PAVING
PQC IN PROGRESS
Tent Protection for Paved
surface
67
68
69
Automatic Tie Bars Inserter Automatic Dowel Bars Inserter
Mechanical Broomer
71
72
73
74
IS: 8142 Setting Time of Concrete
• Initial Setting Time - Elapsed time, after
initial contact of cement and water, required
for mortar (sieved from concrete ) to reach a
penetration resistance of
3.43 N/mm2 ( 35 kgf/cm2 ).
• = Load in kg/area of plunger
• Final Setting Time - Elapsed time, after
initial contact of cement and water, required
for mortar ( sieved from concrete ) to reach
a penetration resistance of
26.97 N/mm2 ( 275 kgf/cm2).
Floating, Finishing
Mechanical Floating, Finishing
Texturing – Tinning App.
Texturing by Brooming
Texturing by Tinning
WHY- Contraction Joint - 4.5 m
Drying Shrinkage = 0.06%
So for 100 mm = 0.06 mm
For 1 mm = 0.06/100 mm
= 0.0006 mm
so in 4.5 m or 4500 mm: = 0.0006mm*4500
= 2.7 mm
Required Contraction Joint width = ~3 mm
Expansion Joint say 140 m?
Coefficient of Thermal Expansion, α
= 10*10-6 mm/mm/oC
in 1mm increase in length = 10*10-6 mm/oC
in 140000mm increase =140 000*10*10-6 mm/oC
for Temp gradient /oC = 1.4 mm /oC
So for ∆ t = 15oC change in India
Required Expansion Joint width 1.4 mm *15oC= ~ 20 mm
Joints Cutting, Filling - sealing
How to minimise cracks Over Dowel bars ?
• Tamping device should be attached to finishing
mould to achieve proper consolidation of
concrete around bars.
• In case of high slump when tamper device is
used, there is chance of moving dowel out of
position.
• Speed of the paver 1 m /min,
• Temperature 25-30 oC
81
In continue
• Deposited concrete shall be struck off by means of the
strike off plate /metering gate or a screw auger.
• Spreading Plough extend across whole width of slab.
• Electrical vibrators operate at variable speed from 9000
to 12000 vpm.
82
Two pavers- two lift paving
83
Single Paver- two lift paving
84
Or fck + o.825* Standard
Deviation which ever is greater
30.1 Fail
TYPICAL CORELATION FOR N TYPE REBOUND HAMMER
86
REBOUND HAMMER, IS:
13311, IRC: 112
Crack Depth Measurement using SURFER
In case of doubt -Concrete cores are cut :
Core 85% Av and Individual 75%
Rate of Loading 140 kg/sq cm/ minute
h/d ratio, n 1 1.4 1.8 2
Correction factor, f 0.89 0.93 0.98 1
f= 0.11 n +0.78, n=h/d
Equivalent cube strength = f X crushing strengthX1.25
Acceptable Minimum
Core strength = 85% of Charasteristic
Individual Core = 75% of Charasteristic
9/6/2022 Concrete Pavement -Design &
Applications.
89
As per IS 456
1. Load = full dead load +1.25 times the imposed load -24 hours
2. If in 24 hours of removal of load, structure does not recover
atleast 75% of the deflection under the imposed load
4. Repeated after a lapse of 72 hours, if recovery is <80%-
unacceptable
5. Deflection , mm < 40 ℓ2/D , ℓ - effective span m, D –overall depth in
mm, then it is not necessary to for recovery to be measured and
recovery provision shall not apply
6. Members other than flexural member – analysis
40*20 m*20 m/1000 mm = 16 mm
20 m length 1000 mm depth girder
91
92
Jabalapur L&T
TYRE BURSTING on High Speed Corridors
DOES
• Speed max 100 km/h
• Hardness of top surfac
• Good Tyre/tube quality
• Specified tyre pressure
• Nitrogen
• Never apply break quickly
DONOTS
• Do not have old tyre /Bald
Tyre/ OLD TUBE
• Do not have – Very High or
low tyre pressure
• Do not have sharp
edges/spots in
PQC/Wearing course
• Do not have poor repaired
surface
TYRE BURSTING
1. Flattening of tyres
2. Fill air and petrol early morning
3. Proper removal of welds
4. Round edges of expansion joints
Weld properly grind Sharp edges to be rounde
e 1; Mix Proportion of Very High Strength Durable Concrete
Material Appx. Amount in kg/cubic m of concrete
Cement 780
Slag Fine 180
Silica Fume 180
Sand 370
Coarse aggregate 10 mm 816
Admixture 18
Water 158 95
M 200 Grade (2000kg/cm2) at 28 days
IIT Delhi M 500 at 28 days
Material Amount in
Kg
Density Absolute
Volume
cum
Cement 780 3150 0.2476
Slag Fine 180 2900 0.0620
Silica
Fume
180 2300 0.0783
Sand 370 2700 0.1370
Coarse
aggregate
+ 4.75 mm
816 2700 0.3022
Admixture 18 1210 0.0149
Figure 2 Figure 3 Figures 4 Figure 5.
Mobile Impact Crusher Mobile Cone Crusher Mobile Jaw Crusher Mobile VSI Crusher
MOBILE CRUSHERS
Two Lift Construction MOBILE
CRUSHERS
Automatic plastering
machine
1. Laying Roller Compacted Concrete 2. Compaction Roller Compacted C
3. Thin White Topping Bangalore
4. Laying Cell Filled Concrete Pavem
Fibre Geo Textile
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PVC Backing
CONCRETE CLOTH
(6-14 mm thickness )
IRC: SP: 83 EOT /M
First UTWT 125 mm in Length 20 m
in 2003 Pune
100
• Category Length of crack m/sq m Value of C
• Slightly Cracked 1-2.5 C = 1.0
• Fairly Cracked 2.5-5.5 C = 0.75
• Moderately Cracked 5.5 -8.5 C = 0.55
• Badly Cracked 8.5-12 C= 0.35
• Unbonded Overlay:
Ho = [ h 2 - C. he 2] 1/2
• Partially bonded overlay
Ho = [ h 1.4 - C. he 1.4] 1/1.4
• Fully Bonded Overlay
Ho = [ h - C. he ]
Cell Filled Concrete Pavement
102
Horizontal Shaft Impactor- metal on rock
Impactor- rock on rock
Modern
Impactor
with
recycling
rock is
sprayed on
metal
11/08/2006 NCB/L&T ECCD
Equipment required to test SCC
L box
Shotcrete/Epoxy
resins Low viscosity
IS: 9012
For repair Honey
Combing
Repair Honey Combed Surface
Surface Percentage of Rebound
• Floor or slabs 5-15
• Sloping and vertical walls 15-30
• Overhead work 25-50
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt

More Related Content

Similar to Construction Aspects of Rigid Pavements.ppt

PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxRajeshKumar25548
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowAnchit Agrawal
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank designHarish Mahavar
 
Raise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,liningRaise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,liningSafdar Ali
 
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNCONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNAkshika Mahanama
 
Structural Design
Structural DesignStructural Design
Structural DesignVj NiroSh
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESarnath R
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017ktx500
 
Influence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavementsInfluence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavementsIAEME Publication
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalProSIM R & D Pvt. Ltd.
 
Working with Dragline
Working with DraglineWorking with Dragline
Working with DraglineVR M
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)Utsav Tripathy
 
AS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesAS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesClearCalcs
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumIRJET Journal
 
Clt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveClt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveFWPA
 

Similar to Construction Aspects of Rigid Pavements.ppt (20)

PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
Kellingray
KellingrayKellingray
Kellingray
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
Raise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,liningRaise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,lining
 
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNCONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
 
Structural Design
Structural DesignStructural Design
Structural Design
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAE
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
bridge final ppt.pptx
bridge final ppt.pptxbridge final ppt.pptx
bridge final ppt.pptx
 
Influence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavementsInfluence of subgrade condition on rutting in flexible pavements
Influence of subgrade condition on rutting in flexible pavements
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R Pal
 
Truline Plastic Piling Specifications 2014
Truline Plastic Piling Specifications 2014Truline Plastic Piling Specifications 2014
Truline Plastic Piling Specifications 2014
 
4 Barrier Design 2008
4   Barrier Design 20084   Barrier Design 2008
4 Barrier Design 2008
 
Working with Dragline
Working with DraglineWorking with Dragline
Working with Dragline
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
 
AS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesAS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked Examples
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
 
Stepped footing
Stepped footingStepped footing
Stepped footing
 
Clt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveClt mtb seminar_presentation_five
Clt mtb seminar_presentation_five
 

Recently uploaded

"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfjimielynbastida
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Neo4j
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 

Recently uploaded (20)

"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdf
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 

Construction Aspects of Rigid Pavements.ppt

  • 1. Construction Aspects of Rigid Pavements’ 1
  • 2. DLC M 10 at 7 days PQC M 40 Road Crust Road Composition Vehicle 450 Sub Grade 9% CBR /Permeability 30 m/day 300mm Sub Base GSB/DL 27% CBR Embankment 3% CBR Ground Level Agg size 3 time decreases, Permeability 3 times decreases
  • 4. Modulus of Subgrade Reaction ‘k’ value k value = Load, kg on 750 mm plate (area cm2*0.125 cm) kg/cm2/cm or MPa/m Soaked CBR 2 3 4 5 7 10 15 20 50 k Value MPa/m 21 28 35 42 48 50 62 69 140
  • 5. Rigid Pavement Flexible pavement 750 mm 200 mm Deflection 0.2 mm 1 mm or 200 micron DESIGN DESIGN K value/modulus of CBR % subgrade reaction = (Load/1370kg)100 Load/(Plate area*1.25 mm)) kg/cm2/cm 5
  • 6. Determines the spring constant “K” K= F/d ( Total applied load)/ (Deflection) Slab and beam type bridges K < 100 kN/mm - flexible 100<K < 250 kN/mm - Semi Rigid 250<K < 400 kN/mm - RP/ stiff K > 400 kN/mm- - very stiff Air Field/Girder
  • 7. Choice and Economics  Built up areas Poor Drainage Heavy rain fall & Flood Prone Area  Water logging Aggregates are costly  Poor soil condition Cost of flexible pavement - 25% less than RP 7
  • 9. NEED OF JOINTS RIGID PAVEMENT Flexible Pavement Deck Slab Contraction joint, longitudinal joint, expansion joints No Joints Only Expansion Joints Reasons Reasons Reasons White in colour, donot absorb heat, so temperature gradient Black in colour, no temperature gradient White in Colour but Reinforced concrete, ∆ t too less Warping/curling No warping No warping Drying shrinkage Not much shrinkage Expansion contract/RCC 9 Friction between Sub base and PQC Each layer bonded No bottom layer
  • 10. L–Section of Rigid Pavement Joint Spacing 3 - 6 m Dowels PQC M40 Sub base, DLC Granular Sub Base (GSB) OR Drainage Layer Sub-grade, Compacted Natural Formation camber 2 % • Jointed Plain with dowels
  • 11. TABLE6. RECOMMENDEDDIMENSIONSOFDOWELBARS FOR RIGID PAVEMENTS ( PCA1980) Slabthickness mm Dowelbar details Diameter, mm Length, mm Spacing, mm 200 25 360 300 230 30 400 300 250 32 450 300 280 36 450 300 300 38 500 300 350 38 500 300
  • 12. TABLE 7. DETAILS OF TIE BARS FOR LONGITUDINAL JOINT OF TWO-LANE RIGID PAVEMENTS Slab Thickness (mm) Tie Bar Details Diameter (d) (mm) Max. Spacing (mm) Minimum length (mm) Plain Deformed Plain Deformed 150 8 10 330 520 530 830 440 510 480 560 200 10 12 390 560 620 900 510 580 560 640 250 12 450 720 580 640 300 12 16 370 660 600 1060 580 720 640 800 350 12 16 320 570 510 910 580 720 640 800
  • 13. d2 d1 If d2/d1≤ 0.6, the Transverse joint is damaged or d2 > 0.6 d1 If d2/d1≤ 0.4, the Longitudinal joint is damaged or d2 > 0.4 d1 LOA D 13 Evaluation of Load Transfer Efficiency at Joints
  • 14. 14
  • 15.
  • 17. Carry out FWD deflection test in outer lane at 500m Inner lane, if developing cracks should also be tested Deflections abnormal - Collect data at closer interval deflectio n Distance 17 Evaluation Process
  • 18. Jointed Reinforced In steep terrain, Fill up area, super elevation L/B>1.5 10 - 20 m Dowels Slab Base Welded Wire Fabric (0,1 - 0,2 %)
  • 19. Expansion Joints Construction Joint Longitudinal Joint 19
  • 20. 20 Contraction Joints Placement of dowel bars Crack below Longitudinal Joints Transverse Joints Contraction Jt. -Plan Load transverse device Contraction Joints Dowel bars Placement If no dowel bars. Dummy Contraction Joi
  • 21. 21 Expansion Joint/ Contraction Joint Without Gap Dowel Bars ( ~25 – 38 mm) Plain IS: 432 Longitudinal/ Construction Joint Tie Bars ~ 12-16 mm deformed IS: 1786
  • 22. Matunga Bombay 1960 200 mm CCI Established in 1927, Manual 1948 22
  • 23. Manual 1948 Price Rs 1 First Mechanised Road NH -2, h= 300 mm NHDP G Q IInd Mechanised Road Yamuna Expressway, h= 320 mm
  • 24. Maximum Utilization Coarse agg Type Plain Cement Concrete Reinforced Concrete Lean Concrete Less than M 15 Iron Slag 50 25 100 Steel Slag 25 nil 100 RCA 25 20 upto M 25 100 Copper slag 40 35 50 RCA 25 20 upto M 25 100 Chlorides = 0.5% Sulphates = 0.04 % Water absorption = 5% upto 10% With precaution
  • 25. Wrong Right -----MORD 1501 p412 Direction of traffic Length of panel in direction of traffic) shall not be less than width of panel 31 ---------------------------------------------------------------------------- ---------------------------------------------------------------------------- Case 1 = Stress -10,000*450/350*30*30 = 14 kg/cm2 Case 2 = Stress - 10,000*350/450*30*30 = 9 kg/cm2
  • 26. SLOPE COMPACTOR - Earth Work- Embankment Embankments ( 95%) Unsuitable Soil : OI, OL,OH, Pt, > 75 mm LL >50 % PI >25 % FSI > 50 % Density: 1.52gm/cc upto 3 m 32
  • 27. Density S.N o. Type of work Maximum laboratory dry unit weight when tested as per IS: 2720 (Part 8) 1. Embankments up to 3 metres height, not subjected to extensive flooding Not less than 15.2 kN/cu.m 2. Embankments exceeding 3 metres height or embankments of any height subject to long periods of inundation Not less than 16.0 kN/cu.m 3. Subgrade and earthen shoulders/verges/backfill Not less than 17.5 kN/cu.m
  • 28. Compaction - embankment and subgrade No Type of work/material Relative compaction as percentage of max. laboratory dry densiy as per IS: 2720 (Part 8) 1. Subgrade and earthen shoulders Not less than 97 2. Embankment Not less than 95 3. Expansive clays (a) Subgrade and 500 mm portion just below the subgrade (b) Remainin g portion of embankm Not allowed Not less than 90
  • 29. 35
  • 30. 36 Common III - VI 100 100 75 60 30 20 6 4 2 Lower sub base Filter layer Upper sub base Drainage layer
  • 31. EFFECT OF CURING TEMPERATURE ON STRENGTH, IS: 7861
  • 32. REQUIREMENTS OF PURCHASER • Variation +/- 10 mm for slump upto 75 mm • Variation +/- 25 mm for > 75 mm
  • 33.
  • 34. • Slump of concrete mix for pavements compacted by vibration using paving trains • 25 ± 10 mm Flexural MPa vs Compressive in MPa = fcr = 0.7 √(fck)
  • 35. Finished Road • Tining (Texture depth ) 3mm Width 4 mm Depth • Brooming (Texture depth ) 1.0+0.25 mm • No undulation in form work • Widening/transition Step/tied • Density 97% in PQC • Air < 3%
  • 36.
  • 37. TWIN SHAFT MIXERS PAN MIXERS MIXERS
  • 38.
  • 39. CROSS-SECTION tied shoulder Camber not Shown SUB-GRADE EMBANKMENT Dowel bars across transverse Joints not shown for clarity SUB-BASE (DLC) DRAINAGE LAYER FIGURE 1.4 - RIGID PAVEMENT TYPICAL CROSS-SECTION LONGITIDINAL JOINT TIE BAR BASE (PQC) DEBONDING/SEPARATION MEMBRANE WHY DLC M10: 1. Levelling Course/levelled platform 2. To move paver smoothly @ 1m/min 3. Sub base to take some load 4. To modify subgrade CBR indirectly
  • 40. CONMET BARODA/BRDC/Walia AB Mumbai/Walia Delhi Slip Form Paver Wrtgen/ Meckstar/ Gomaco LAYING 46
  • 42. WHERE RCC ?: 1.Steep Terrain 2.L/B>1.5 3.Fill up Areas/ Marshy areas 4.Tool Plazas, 5.Acute angled/ Curved/super elevated 6.Better riding quality 7.High Temperature/Low RH/ 8.High wind speed
  • 43.
  • 44. 50
  • 45. 51
  • 46.
  • 47. • Construction Methodology- Mumbai 1988- 2004
  • 48. 54
  • 51. Acceptance Criteria DLC MORTH • Longitudinal joint staged by 350 mm • Construction joint by about 900 mm • Curing compound gets tackiness spread hessian. • 0.2 Litre /sq m • Six cubes Minimum /day • 100 m length trial in 2 days • Insitu density 98% -601.6.5.1 57
  • 52. MORTH- DLC • 3 samples /1000 sqm cubes -903.5.1.1 • Square plate 7500-14000 sq. mm compaction • For 1 min 30-40 kg load. -903.5.1.1 • Thickness not less than 8 mm- 903.5.1.3 • Repaired with lean concrete 10 mm down 58
  • 53. Laying polythene sheet double at crack Double layer as crack arresting layer
  • 54.
  • 55. Slip Form Pavers of width 15-16 m Two layer construction 61 WHY POLYTHENE SHEET ? 1. Crack arresting layer as no joints in DLC 2. Water Proof layer 3. Insulating layer 4. Reduce friction Double ply paper In Airfield 500 micron thick Two coat wax based curing compou
  • 56. Take care- tipper shall not fall on paver 62 Take care- Alignment, location of Do-well bars/Tie bar Take care- Slump 15-40 mm, M 40 PQC M 10 DLC at 7 d
  • 58. Do not Stop Paver more than 30 minute to avoid cold joint/crack
  • 61. Tent Protection for Paved surface 67
  • 62. 68
  • 63. 69
  • 64. Automatic Tie Bars Inserter Automatic Dowel Bars Inserter Mechanical Broomer
  • 65. 71
  • 66. 72
  • 67. 73
  • 68. 74
  • 69. IS: 8142 Setting Time of Concrete • Initial Setting Time - Elapsed time, after initial contact of cement and water, required for mortar (sieved from concrete ) to reach a penetration resistance of 3.43 N/mm2 ( 35 kgf/cm2 ). • = Load in kg/area of plunger • Final Setting Time - Elapsed time, after initial contact of cement and water, required for mortar ( sieved from concrete ) to reach a penetration resistance of 26.97 N/mm2 ( 275 kgf/cm2).
  • 70. Floating, Finishing Mechanical Floating, Finishing Texturing – Tinning App. Texturing by Brooming Texturing by Tinning
  • 71. WHY- Contraction Joint - 4.5 m Drying Shrinkage = 0.06% So for 100 mm = 0.06 mm For 1 mm = 0.06/100 mm = 0.0006 mm so in 4.5 m or 4500 mm: = 0.0006mm*4500 = 2.7 mm Required Contraction Joint width = ~3 mm
  • 72. Expansion Joint say 140 m? Coefficient of Thermal Expansion, α = 10*10-6 mm/mm/oC in 1mm increase in length = 10*10-6 mm/oC in 140000mm increase =140 000*10*10-6 mm/oC for Temp gradient /oC = 1.4 mm /oC So for ∆ t = 15oC change in India Required Expansion Joint width 1.4 mm *15oC= ~ 20 mm
  • 73.
  • 75. How to minimise cracks Over Dowel bars ? • Tamping device should be attached to finishing mould to achieve proper consolidation of concrete around bars. • In case of high slump when tamper device is used, there is chance of moving dowel out of position. • Speed of the paver 1 m /min, • Temperature 25-30 oC 81
  • 76. In continue • Deposited concrete shall be struck off by means of the strike off plate /metering gate or a screw auger. • Spreading Plough extend across whole width of slab. • Electrical vibrators operate at variable speed from 9000 to 12000 vpm. 82
  • 77. Two pavers- two lift paving 83
  • 78. Single Paver- two lift paving 84
  • 79. Or fck + o.825* Standard Deviation which ever is greater 30.1 Fail
  • 80. TYPICAL CORELATION FOR N TYPE REBOUND HAMMER 86 REBOUND HAMMER, IS: 13311, IRC: 112
  • 81. Crack Depth Measurement using SURFER
  • 82. In case of doubt -Concrete cores are cut : Core 85% Av and Individual 75% Rate of Loading 140 kg/sq cm/ minute h/d ratio, n 1 1.4 1.8 2 Correction factor, f 0.89 0.93 0.98 1 f= 0.11 n +0.78, n=h/d Equivalent cube strength = f X crushing strengthX1.25
  • 83. Acceptable Minimum Core strength = 85% of Charasteristic Individual Core = 75% of Charasteristic 9/6/2022 Concrete Pavement -Design & Applications. 89
  • 84. As per IS 456 1. Load = full dead load +1.25 times the imposed load -24 hours 2. If in 24 hours of removal of load, structure does not recover atleast 75% of the deflection under the imposed load 4. Repeated after a lapse of 72 hours, if recovery is <80%- unacceptable 5. Deflection , mm < 40 ℓ2/D , ℓ - effective span m, D –overall depth in mm, then it is not necessary to for recovery to be measured and recovery provision shall not apply 6. Members other than flexural member – analysis 40*20 m*20 m/1000 mm = 16 mm 20 m length 1000 mm depth girder
  • 85. 91
  • 87. TYRE BURSTING on High Speed Corridors DOES • Speed max 100 km/h • Hardness of top surfac • Good Tyre/tube quality • Specified tyre pressure • Nitrogen • Never apply break quickly DONOTS • Do not have old tyre /Bald Tyre/ OLD TUBE • Do not have – Very High or low tyre pressure • Do not have sharp edges/spots in PQC/Wearing course • Do not have poor repaired surface
  • 88. TYRE BURSTING 1. Flattening of tyres 2. Fill air and petrol early morning 3. Proper removal of welds 4. Round edges of expansion joints Weld properly grind Sharp edges to be rounde
  • 89. e 1; Mix Proportion of Very High Strength Durable Concrete Material Appx. Amount in kg/cubic m of concrete Cement 780 Slag Fine 180 Silica Fume 180 Sand 370 Coarse aggregate 10 mm 816 Admixture 18 Water 158 95 M 200 Grade (2000kg/cm2) at 28 days IIT Delhi M 500 at 28 days
  • 90. Material Amount in Kg Density Absolute Volume cum Cement 780 3150 0.2476 Slag Fine 180 2900 0.0620 Silica Fume 180 2300 0.0783 Sand 370 2700 0.1370 Coarse aggregate + 4.75 mm 816 2700 0.3022 Admixture 18 1210 0.0149
  • 91. Figure 2 Figure 3 Figures 4 Figure 5. Mobile Impact Crusher Mobile Cone Crusher Mobile Jaw Crusher Mobile VSI Crusher MOBILE CRUSHERS Two Lift Construction MOBILE CRUSHERS Automatic plastering machine
  • 92. 1. Laying Roller Compacted Concrete 2. Compaction Roller Compacted C 3. Thin White Topping Bangalore 4. Laying Cell Filled Concrete Pavem
  • 93. Fibre Geo Textile . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PVC Backing CONCRETE CLOTH (6-14 mm thickness ) IRC: SP: 83 EOT /M
  • 94. First UTWT 125 mm in Length 20 m in 2003 Pune 100
  • 95. • Category Length of crack m/sq m Value of C • Slightly Cracked 1-2.5 C = 1.0 • Fairly Cracked 2.5-5.5 C = 0.75 • Moderately Cracked 5.5 -8.5 C = 0.55 • Badly Cracked 8.5-12 C= 0.35 • Unbonded Overlay: Ho = [ h 2 - C. he 2] 1/2 • Partially bonded overlay Ho = [ h 1.4 - C. he 1.4] 1/1.4 • Fully Bonded Overlay Ho = [ h - C. he ]
  • 96. Cell Filled Concrete Pavement 102
  • 97. Horizontal Shaft Impactor- metal on rock Impactor- rock on rock Modern Impactor with recycling rock is sprayed on metal
  • 98. 11/08/2006 NCB/L&T ECCD Equipment required to test SCC L box
  • 99. Shotcrete/Epoxy resins Low viscosity IS: 9012 For repair Honey Combing Repair Honey Combed Surface Surface Percentage of Rebound • Floor or slabs 5-15 • Sloping and vertical walls 15-30 • Overhead work 25-50