SlideShare a Scribd company logo
1 of 15
DEPARTMENT OF CIVIL ENGINEERING
PROJECT PLANNING AND MANAGEMENT
EVALUATON TENDER
Punit Sharnagat
October 2, 2017 NURUL ASRA ABD RAHMAN 2
COURSE OUTCOME
• Enable to understand the tender evaluation process.
• Knowledge on tender evaluation stages and the criteria involved.
• Enable to know all information needed during tender.
• Enable to strategize work during tender stages.
To determine and to recommend to the Board of Procurement
a tender which offers the most profit to the GOVERNMENT.
Only contractor which has the financial and technical
capabilities is eligible for Award and Acceptance.
OBJECTIVES
October 2, 2017 NURUL ASRA ABD RAHMAN 3
EVALUATION PROCESS
6.
Issuing of
tender
Acceptance
letter
5.
Determine
budget
4.
Treasury
(if applicable)
3.
Procurement
board
2.
Processing
tender
1.
Tender opening
committee
In validity
Tender
period
Tender evaluation must be done in validity of tender period
(minimum 90 days) from tender closing date.
October 2, 2017 NURUL ASRA ABD RAHMAN 4
EVALUATION PROCESS
FIRST STAGE
Tender price adjustment
Arrange the tender price
(from low to high)
Price reasonableness based
on budget or “cut-off”
Determine the number of
tenderers to be evaluated
SECOND STAGE
Tender compliance
Tender compliance analysis
Completeness of document analysis
Adequacy of minimum capital
analsys
THIRD STAGE
Experience and capability
Tenderer experience analysis
Technical personnel analysis
qualify
qualify
Rejected Contractor
Not Fulfill requirement
Not Fulfill requirement
Not Fulfill requirement
October 2, 2017 NURUL ASRA ABD RAHMAN 5
CRITERIA
• PWD practice tender evaluation has been divided into
3 categories, namely:
i. Large projects (more than RM10.0 million)
ii. Medium projects (RM2.0 million to RM10.0 million)
iii. Small projects (less than RM2.0 million)
CRITERIA
- INFORMATION REQUIRED
OTHERS DOCUMENT
i. Audited account copy for last 2 years
ii. Account bank statement copy for last 3 months
iii. Bank report / financial institution (sealed)
iv. Copy of the certificate / confirmation of completion for each
project listed in Form D and G
v. EPF statement and a copy of Form A or copy service
agreement for contract staff
vi. Copy of the certificate of approval of technical staff
vii. Copy of Grant / hire-purchase agreement plant / equipment
viii. Copies of the final interim payment certificate for the current
project
ix. Project report (sealed)
October 2, 2017 NURUL ASRA ABD RAHMAN 6
• Number of tenderer should be assessed is
between 15-20 tenderer to produce between 3-
5 tenderer who will pass.
• "Range" of tenderer can be selected is between
+ / - 20% (+ / - 25% for Civil Engineering) from
the Mean Price.
• For the tenderers who are below the "cut-off"
will be checked the compulsory document first.
Select tenderer with special criteria to be
evaluated.
• For tenderers who are outside the “cut-off” to be
referred to tender committee for consideration.
EVALUATION STAGES
- FIRST STAGE
October 2, 2017 NURUL ASRA ABD RAHMAN 7
• A system of evaluation based on predetermined
conditions to ascertain whether tenderers are
eligible for further evaluation.
• Evaluation Criteria:
i. Analysis on Compliance to Tender
ii. Analysis on Completeness of tender
documents.
iii. Analysis on Adequacy of Capital
iv. Analysis on performance of current work.
• Objectives:
To ensure tenders under consideration are
reasonable, in compliance, complete, have
adequate capital and have good current work
performance free from sick project,
EVALUATION STAGES
- SECOND STAGE
October 2, 2017 NURUL ASRA ABD RAHMAN 8
i. Analysis on Compliance to Tender
EVALUATION STAGES
- SECOND STAGE
• Only Tenderers which comply and free from any
imperfection in term of legal and contractual which may
jeopardize their qualification based on current practice are
to be considered.
– To check if form of tender has been signed by
tenderers
– The signing person has been given the power to sign.
– To check if tender price is stated in the form of tender.
– Are PKK/CIDB registration still valid.
– Has tenderer returned all the basic tender documents,
– Check proposed construction period is stated in the
form of tender.
– Failure to submit any of the forms of tender may effect
the ranking of tenderer,
October 2, 2017 NURUL ASRA ABD RAHMAN 9
ii. Analysis on Completeness of Tender
a) Tender which is complete and comply to the
requirement of tender/regulation/Authority.
b) Mandatory Tender Documents includes:
i. Forms of Tender
ii. List of Quantity/ Summary of Tender
iii. Addendum (if any)
iv. Schedule of rates
v. Design proposal, specification, pricing by
contractor etc. (where applicable) as
required
to enable design work by tenderer to be
evaluated.
EVALUATION STAGES
- SECOND STAGE
October 2, 2017 NURUL ASRA ABD RAHMAN 10
ii. Analysis on Completeness of Tender
EVALUATION STAGES
- SECOND STAGE
MANDATORY DOCUMENTS
a) Audited account copy for last 2 years, or
Account bank statement copy for last 3 months, or
Bank report / financial institution (sealed)
b) Project report by project superintendence officer
Without mandatory documents
(especially regarding financial)
evaluation of tenders can not be made
and therefore tender will be rejected.
October 2, 2017 NURUL ASRA ABD RAHMAN 11
EVALUATION STAGES
- SECOND STAGE
iii. Analysis on Adequacy of Minimum Capital
Method of calculation
i. Rolling capital = asset liability – current liability
ii. Bank account = average of latest 3 months
iii. Make comparison between rolling capital and bank
account. Select the higher amount
iv. Include credit facilities report
v. Add (+) iii and iv = total liquidated capital (>3%)
October 2, 2017 NURUL ASRA ABD RAHMAN 12
• Work still on progress during the tendering
process (Form D, G and GA)
• No sick project – below 30% of work schedule
• No termination record
• Checking will carry out through;
i. PKK / CIDB / JKR scale
ii. Superintendence project report
iii. T.K.S. if no project on hand.
EVALUATION STAGES
- SECOND STAGE
iii. Analysis on performance of current work
October 2, 2017 NURUL ASRA ABD RAHMAN 13
EVALUATION STAGES
- THIRD STAGE
FINANCIAL CAPABILITY (Financial Bid Capacity)
= Working capital
Yearly project value
i. Financial Capability
October 2, 2017 NURUL ASRA ABD RAHMAN 14
• Working experiences
• Technical staff
• Machineries / plant
EVALUATION STAGES
- THIRD STAGE
ii. Technical
• Working experience
Evaluation criteria
-. Completed total work value past 5 years
- Largest work value done in past 5 years
- Type of work is limited to recognized work
Comparable or similar (follow by head / sub-head
October 2, 2017 NURUL ASRA ABD RAHMAN 15
• Machineries / plants
EVALUATION STAGES
- THIRD STAGE
Plant and equipment that could be accounted is limited to:
• As listed in the Estimated Minimum Requirement. Plants / machineries
can be considered if function equivalently
• Owned / hire-purchase before the closing of tender
• Useful life not exceeding 150 years
• If rent-mortgage, the agreement should cover the contract period.

More Related Content

What's hot

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Construction management
Construction managementConstruction management
Construction managementRahul
 
Tender & bidding in construction projects
Tender  & bidding in construction projectsTender  & bidding in construction projects
Tender & bidding in construction projectsTEJAS2011
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentationnipuna_bopage
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract Venuri Lakshani
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
Kriteria penilaian tender untuk kontraktor
Kriteria penilaian tender untuk kontraktorKriteria penilaian tender untuk kontraktor
Kriteria penilaian tender untuk kontraktorkubigs
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tendersgayu pandian
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and ArbitrationJIT KUMAR GUPTA
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Pang Khai Shuen
 
Tender processing
Tender processingTender processing
Tender processingdnyandev_d
 

What's hot (20)

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
ECA form
ECA formECA form
ECA form
 
Construction management
Construction managementConstruction management
Construction management
 
Tender & bidding in construction projects
Tender  & bidding in construction projectsTender  & bidding in construction projects
Tender & bidding in construction projects
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
PP1 report
PP1 reportPP1 report
PP1 report
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Kriteria penilaian tender untuk kontraktor
Kriteria penilaian tender untuk kontraktorKriteria penilaian tender untuk kontraktor
Kriteria penilaian tender untuk kontraktor
 
Highway Projects
Highway Projects Highway Projects
Highway Projects
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Tender processing
Tender processingTender processing
Tender processing
 

Similar to Evaluating Tenders for Civil Engineering Projects

A Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction IndustryA Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction IndustryIRJET Journal
 
Furrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingAditya Sanyal
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptxssuser4ae21a
 
Quantycosts consultants Profile
Quantycosts consultants ProfileQuantycosts consultants Profile
Quantycosts consultants ProfileMaina Wanjama
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningJB Nartey
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lin Hui
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slidesashleyyeap
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)Js Cheok
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)Jy Chong
 
3. Project Procurement Planning..pptx
3. Project Procurement Planning..pptx3. Project Procurement Planning..pptx
3. Project Procurement Planning..pptxDoctorOkelloBen
 
Project tender
Project tenderProject tender
Project tenderFarah Sham
 

Similar to Evaluating Tenders for Civil Engineering Projects (20)

Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
A Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction IndustryA Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction Industry
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
Furrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity Surveyor
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Quantycosts consultants Profile
Quantycosts consultants ProfileQuantycosts consultants Profile
Quantycosts consultants Profile
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project Planning
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
 
Bid document reverse tendering
Bid document reverse tenderingBid document reverse tendering
Bid document reverse tendering
 
QSS
QSSQSS
QSS
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
3. Project Procurement Planning..pptx
3. Project Procurement Planning..pptx3. Project Procurement Planning..pptx
3. Project Procurement Planning..pptx
 
Qsx
QsxQsx
Qsx
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Project tender
Project tenderProject tender
Project tender
 

Recently uploaded

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Evaluating Tenders for Civil Engineering Projects

  • 1. DEPARTMENT OF CIVIL ENGINEERING PROJECT PLANNING AND MANAGEMENT EVALUATON TENDER Punit Sharnagat
  • 2. October 2, 2017 NURUL ASRA ABD RAHMAN 2 COURSE OUTCOME • Enable to understand the tender evaluation process. • Knowledge on tender evaluation stages and the criteria involved. • Enable to know all information needed during tender. • Enable to strategize work during tender stages. To determine and to recommend to the Board of Procurement a tender which offers the most profit to the GOVERNMENT. Only contractor which has the financial and technical capabilities is eligible for Award and Acceptance. OBJECTIVES
  • 3. October 2, 2017 NURUL ASRA ABD RAHMAN 3 EVALUATION PROCESS 6. Issuing of tender Acceptance letter 5. Determine budget 4. Treasury (if applicable) 3. Procurement board 2. Processing tender 1. Tender opening committee In validity Tender period Tender evaluation must be done in validity of tender period (minimum 90 days) from tender closing date.
  • 4. October 2, 2017 NURUL ASRA ABD RAHMAN 4 EVALUATION PROCESS FIRST STAGE Tender price adjustment Arrange the tender price (from low to high) Price reasonableness based on budget or “cut-off” Determine the number of tenderers to be evaluated SECOND STAGE Tender compliance Tender compliance analysis Completeness of document analysis Adequacy of minimum capital analsys THIRD STAGE Experience and capability Tenderer experience analysis Technical personnel analysis qualify qualify Rejected Contractor Not Fulfill requirement Not Fulfill requirement Not Fulfill requirement
  • 5. October 2, 2017 NURUL ASRA ABD RAHMAN 5 CRITERIA • PWD practice tender evaluation has been divided into 3 categories, namely: i. Large projects (more than RM10.0 million) ii. Medium projects (RM2.0 million to RM10.0 million) iii. Small projects (less than RM2.0 million) CRITERIA - INFORMATION REQUIRED OTHERS DOCUMENT i. Audited account copy for last 2 years ii. Account bank statement copy for last 3 months iii. Bank report / financial institution (sealed) iv. Copy of the certificate / confirmation of completion for each project listed in Form D and G v. EPF statement and a copy of Form A or copy service agreement for contract staff vi. Copy of the certificate of approval of technical staff vii. Copy of Grant / hire-purchase agreement plant / equipment viii. Copies of the final interim payment certificate for the current project ix. Project report (sealed)
  • 6. October 2, 2017 NURUL ASRA ABD RAHMAN 6 • Number of tenderer should be assessed is between 15-20 tenderer to produce between 3- 5 tenderer who will pass. • "Range" of tenderer can be selected is between + / - 20% (+ / - 25% for Civil Engineering) from the Mean Price. • For the tenderers who are below the "cut-off" will be checked the compulsory document first. Select tenderer with special criteria to be evaluated. • For tenderers who are outside the “cut-off” to be referred to tender committee for consideration. EVALUATION STAGES - FIRST STAGE
  • 7. October 2, 2017 NURUL ASRA ABD RAHMAN 7 • A system of evaluation based on predetermined conditions to ascertain whether tenderers are eligible for further evaluation. • Evaluation Criteria: i. Analysis on Compliance to Tender ii. Analysis on Completeness of tender documents. iii. Analysis on Adequacy of Capital iv. Analysis on performance of current work. • Objectives: To ensure tenders under consideration are reasonable, in compliance, complete, have adequate capital and have good current work performance free from sick project, EVALUATION STAGES - SECOND STAGE
  • 8. October 2, 2017 NURUL ASRA ABD RAHMAN 8 i. Analysis on Compliance to Tender EVALUATION STAGES - SECOND STAGE • Only Tenderers which comply and free from any imperfection in term of legal and contractual which may jeopardize their qualification based on current practice are to be considered. – To check if form of tender has been signed by tenderers – The signing person has been given the power to sign. – To check if tender price is stated in the form of tender. – Are PKK/CIDB registration still valid. – Has tenderer returned all the basic tender documents, – Check proposed construction period is stated in the form of tender. – Failure to submit any of the forms of tender may effect the ranking of tenderer,
  • 9. October 2, 2017 NURUL ASRA ABD RAHMAN 9 ii. Analysis on Completeness of Tender a) Tender which is complete and comply to the requirement of tender/regulation/Authority. b) Mandatory Tender Documents includes: i. Forms of Tender ii. List of Quantity/ Summary of Tender iii. Addendum (if any) iv. Schedule of rates v. Design proposal, specification, pricing by contractor etc. (where applicable) as required to enable design work by tenderer to be evaluated. EVALUATION STAGES - SECOND STAGE
  • 10. October 2, 2017 NURUL ASRA ABD RAHMAN 10 ii. Analysis on Completeness of Tender EVALUATION STAGES - SECOND STAGE MANDATORY DOCUMENTS a) Audited account copy for last 2 years, or Account bank statement copy for last 3 months, or Bank report / financial institution (sealed) b) Project report by project superintendence officer Without mandatory documents (especially regarding financial) evaluation of tenders can not be made and therefore tender will be rejected.
  • 11. October 2, 2017 NURUL ASRA ABD RAHMAN 11 EVALUATION STAGES - SECOND STAGE iii. Analysis on Adequacy of Minimum Capital Method of calculation i. Rolling capital = asset liability – current liability ii. Bank account = average of latest 3 months iii. Make comparison between rolling capital and bank account. Select the higher amount iv. Include credit facilities report v. Add (+) iii and iv = total liquidated capital (>3%)
  • 12. October 2, 2017 NURUL ASRA ABD RAHMAN 12 • Work still on progress during the tendering process (Form D, G and GA) • No sick project – below 30% of work schedule • No termination record • Checking will carry out through; i. PKK / CIDB / JKR scale ii. Superintendence project report iii. T.K.S. if no project on hand. EVALUATION STAGES - SECOND STAGE iii. Analysis on performance of current work
  • 13. October 2, 2017 NURUL ASRA ABD RAHMAN 13 EVALUATION STAGES - THIRD STAGE FINANCIAL CAPABILITY (Financial Bid Capacity) = Working capital Yearly project value i. Financial Capability
  • 14. October 2, 2017 NURUL ASRA ABD RAHMAN 14 • Working experiences • Technical staff • Machineries / plant EVALUATION STAGES - THIRD STAGE ii. Technical • Working experience Evaluation criteria -. Completed total work value past 5 years - Largest work value done in past 5 years - Type of work is limited to recognized work Comparable or similar (follow by head / sub-head
  • 15. October 2, 2017 NURUL ASRA ABD RAHMAN 15 • Machineries / plants EVALUATION STAGES - THIRD STAGE Plant and equipment that could be accounted is limited to: • As listed in the Estimated Minimum Requirement. Plants / machineries can be considered if function equivalently • Owned / hire-purchase before the closing of tender • Useful life not exceeding 150 years • If rent-mortgage, the agreement should cover the contract period.