SlideShare a Scribd company logo
1 of 46
PLANING,ANALYSIS AND DESIGN OF HI-
TECH SHOPPING MALL
Batch members:
 R. Arshana
 A.S.Aswathi
 A. Lekshmi
 P.Pemila
Reg No:
960515103008
960515103012
960515103025
960515103030
Guided By,
Dr . B.Thanukumari,ME,PhD
HOD,Department of civil .
Cape Institute Of Technology
INTRODUCTION
• In this project, planned to construct a shopping mall in
Anjugramam which is a main town ,situated near the National
Highway .
• In high tech shopping mall we are introducing a new era (shop
with drive ).
• The plinth area of each shop is 54 square meter.
• We are sure about that high tech shopping mall will be useful for
all sectors of people.
ABSTRACT
• Our project deals with the planning,analysis and design of Hi Tech
shopping mall.
• The proposed site of the project is in Anjugramam.
• The structural elements such as slab,beam,column and foundation will
be designed by using IS456-2000 and the materials used for the
design are M20 grade concrete and Fe415 grade steel.
• The plan,section and elevation will be drawn by using Autocad
software and the analysis is done by using STADD.PRO
SCOPE
• Hi Tech shopping mall plays an anchor role in the Indian
shopping centre.
• It can be established in crowded area without any parking
facilities.
• The shopping mall is used as a best entertainment place for
the people.
• Shopping can be done within a fraction of minute.
OBJECTIVES
• In high tech shopping mall digital screen system help to
guide customers in product information and availability
of product.
• Friendly users interface and log in systems makes more
secured.
• ‘Shop and drive facilities with digital collection method
attracts more customers.
• Walk and shop makes the shopping more realistic.
SITE PLAN
ANALYSIS
• Analysis can be done by using stadd.pro
BENDING MOMENT DIAGRAM
20
20
20
20
40
40
40
40
60
60
60
60
10 20 3030.7
9 12
48.4 48.4
-23.7
15.4
Mz(kNm)
20
20
20
20
40
40
40
40
10 20 3030.7
9 12
30.8
-30.8
Fy(kN)
2
2
2
2
4
4
4
4
10 20 3030.7
9 12
-3.15 -3.15
Fx(kN)
FOOTING
COLUMN
DESIGN OF TWO WAY SLAB
(ONE LONG EDGE DISCONTINUOUS)
Datas:
Room size= 6m×9m
Live load= 5kN/m^2
Floor finish load=1kN/m^2
Fck=20 N/mm2
Fy=415N/mm2
Check for span ratio:
Ly/Lx = 9/6 =1.5m<2m
Hence it is a two way slab.
Depth calculation:
D = span / 25 = 6000/25 = 240mm
Say D = 200mm
Cover = 20mm
Effective depth = 180mm
Effective span :
Lx= 6.18 m
Ly = 9000 + 180 = 9180mm
Load calculation:
Dead load = 1m×1m×0.25×25 = 5kN/m2
Live load = 5 kN/m2
Floor finish load = 1 kN/m2
Total load = 11kN/m2
Factored load = 1.5 ×11 = 16.5 kN/m2
Moment calculation :
αx=0.067 ; αx=0.051
αy=0.037 ; αy=0.028
MX = 0.067 × 16.5 × 62 = 39.79 kN m
MX = 0.051 × 16.5 × 62 = 30.29 kN m
MY = 0.037 ×16.5 × 62 = 21.98 kN m
MY = 0.028 × 16.5 × 62 = 16.63 kN m
To find effective depth :
Mu= Mulim
Mu = 2.75 bd2
d = 120.28mm
say d = 120mm<180mm
Hence safe
Ast Calculation:
1) Main Reinforcement (short span ) :
39.79×106 = 0.87×415×Ast×180(1-415Ast/1000×20×180)
Ast=662.92mm2
Provide 16 mm dia bars
Ast prov = π×102/4
=78.53mm2
i)Spacing=1000Astprov /Ast
=1000×78.53/662.92
=118.46mm
Say 110 mm
ii) 3×d = 3× 180 = 540mm
iii) 450 mm
least value to be taken
provide 16mm dia bars @ 110 mm c/c
2) Distribution Reinforcement (shorter span ):
30.29×106= 0.87×415×Ast×180(1-415×Ast/20×1000×180)
Ast=494.23mm2
Provide 10 mm dia rods
Ast (p)=π/4×102= 78.53mm2
Spacing=1000×78053/494.23= 158.89mm
1)say spacing=150mm
2)3d=3×180=540mm
3)450mm
Least value is to be taken
Provide 10mm dia bars at 150mm c/c
3)Main reinforcement(longer span):
29.18×106=0.87×415×Ast×180(1-415×Ast/1000×20×180)
Ast=475mm2
Provide 16 mm dia bars
Ast(p)=π/4×102=78.53mm2
Spacing=1000×78.53/475=165.32mm
1)Say spacing=160mm
2)3d=3×180=540mm
3)450mm
The least value to be taken
Provide 16mm dia bars at 160 mm c/c
4) Distribution reinforcement(longer span):
16.63×106=0.87×415×Ast×180(1-415×Ast/1000×20×180)
Ast=263.92mm2
Provide 10 mm dia bars
Ast(p)=π/4×102=78.53mm2
Spacing=1000×78.53/263.92=297.5mm
1)say spacing=290mm
2)3d=3×180=540mm
3)450mm
Least value to be taken
Provide 10mm dia bars at 290mm c/c
EDGE STRIP
Ast=Astmin=263.92mm2
Spacing=(1000×π/4×82)/263.92=190mm
Provide 8mm dia bars at 190mm c/c where the edge strips
are both longer and shorter span
CHECK FOR SHEAR
τv=Vu/bd
Vu=16.5×6.18/2=50.985KN
τv =50.99×103/1000×180=0.28N/mm2
pt=100×Ast/bd=100×662.92/1000×180=0.37N/mm2
τc=0.417N/mm2
CHECK FOR DEPTH
D=200mm
K=1.20
k ×τc=1.20×0.417=0.5
k ×τc > τv
0.5>0.28N/mm2 Hence ok
DESIGN OF T- BEAM
Datas:
Length of span = 9m
Spacing of beam = 6m
Fy = 415 N/mm2
Fck = 20 N/mm2
Depth of the flange = 200mm
Width of the flange = 9.27m
Cross sectional dimensions
d = span/12 = 9000/12 = 750mm
overall depth = 750 + 50 =800mm
Load calculation
Self weight of beam = 0.2 ×0.75×25=3.75kN/m2
Load from slab = 1×6×0.2×25= 30kN/m2
Floor finish = 1 kN/m2
Live load = 5 kN/m2
Total load = 38.75 kN/m2
Factored load = 1.5 ×38.75 = 58.13 kN/m2
Ultimate load:
Mu = Wu × l2/ 8
=58.13×62 /8
=261.56 kN/m
Shear force :
Vu= Wu ×L /2
=58.13×6/2
=174.39kN
Effective depth of flange:
Bf = L0/6 + bw +6 Df
=9/6 + 0.23 +(6×0.2)
=2.93m
Centre to centre of beam= 6-0.23 = 5.77mm
Take least value bf = 2.93m
Moment capacity of flange:
Mu= 0.36 × fck × bf × df (d-0.42 Df)
=0.36 × 20 × 2930×200×(750-0.42×200)
Mu=1755.18×106 kN m> 261.56 kNm
Hence ok
Reinforcement calculation:
261.56×106= 0.87×415×Ast×750(1-415×Ast/20×1000×750)
Ast=993.22mm2
Provide 16 mm dia rods
Ast (p)=π/4×162= 201.06mm2
No of bars = Ast/ Ast (p) = 4.9
Provide 5 numbers of 16 mm dia bars.
Shear reinforcement:
τv=Vu/bd
=174.39×103/230×750 = 1.01 N/mm2
pt=100×Ast/bd=100×993.22/230×750=0.56N/mm2
τc=0.49N/mm2
0.49<1.01 N/mm2
Vus = Vu- τc×bd
=174.39×103-0.49×230×750
=89.865 kN
Use 8mm dia of 2 legged stirrups
Spacing:
1) Sv = 0.87 × fy ×Asv ×d / Vus
= 150 mm
2) 0.75d = 0.75×750 = 562.5
3) 300mm
Provide 8 mm dia rods @ 150 mm c/c
DESIGN OF L- BEAM
Datas:
Length of span = 9m
Spacing of beam = 6m
Fy = 415 N/mm2
Fck = 20 N/mm2
Depth of the flange = 200mm
Cross sectional dimensions :
d = span/12 = 9000/12 = 750mm
overall depth =780mm
effective span=9+0.3=9.3m
Load calculation:
Self weight of beam = 0.2 ×0.75×25=3.75kN/m2
Load from slab = 1×6×0.2×25= 30kN/m2
Floor finish = 1 kN/m2
Live load = 5 kN/m2
Total load = 39.75 kN/m2
Factored load = 1.5 ×39.75 = 59.63 kN/m2
Effective width of flange:
Bf=lo+bw+3Df=9.3/12+0.23+0.6=1.605m
Say Bf=1.6m
ultimate bending moment :
Mu = Wu × l2/ 12
=195.35 kN/m
Shear force :
Vu= Wu ×L /2
=31.16kN
Torsional moment at the support=20KN/m
Equivalent bending moment and shear force:
Me1=Mu+M
Mu=50.12kNm
Me1=50.12+195.35=245.48kNm
Mu lim=0.36×fck×bd2=0.36×20×230×7502=931.5kNm
Me1 <Mu lim
Ast=930.49mm2
Provide 16 mm dia rods
Ast (p)=π/4×162= 201.06mm2
Area of steel required at the centre with
Mu=50.12kNm
Ast min=0.85bd/Fy=0.85×230×750/415=353.31mm2
Provide 2 rods of 8mm dia bars
Ast (p)=π/4×82= 100.53mm2
Shear reinforcement:
τv=Ve/bd
=170.29×103/230×750 = 0.99N/mm2
p t=100×Ast/bd=100×930.49/230×750=0.54N/mm2
τc =0.49N/mm2
0.49<0.99 N/mm2
Hence safe
DESIGN OF COLUMN
Given data:
Size of column=600×480mm
Mux=48.36kNm
Muy=22.174mm
Fck=20N/mm2
Fy=415N/mm2
Load calculation:
Self weight of column=7.2kNm
Load due to T beam=38.75kNm
Load due to L beam=38.75kNm
Total load=85 kNm
Design load=128.55kN/m
Load Pu=128.55×9/2+128.55×6/2=710Kn/m
Mu=61.18KNm
Provide 4 bars of 25mm dia and 4 bars of 16mm distributed equally on all
faces with 4 bars on each face
P=100×2766/480×600=0.96
p/fck=0.96/20=0.048
Because of symmetry
Mux1=Muy1=221.18kNm
Puz=0.45fckac+0.75fyasc=4076kN
Pu/puz=710/4076=0.17
Check for safety against biaxial bending
(mux/mux1)αn+(muy/muy1)αn greater than or egual to 1.
(48.367/221.18)+(22.174/221018) greater than or equal to 1
=1.32
Hence the section is safe against biaxial bending
DESIGN OF FOOTING
Given data:
Column size=600×480mm
Total load=710Kn
SBC of soil=350Kn/m
Fck =20N/mm2
Fy=415N/mm2
Assume 10 %of column load as self weight of footing
= 107×10/100
=71KN
Total load on footing=710+71=781Kn
Area of footing=781/350=1.5m
Since it’s a rectangular footing
A=B×L
A=1.5B2
B2=2.23/1.5=1.48m
B=1.5m
h=2.5m
size of footing =1.5×2.5m
Fu=710/(1.5×2.5)=189.33KN/m2
Ultimate SBC of soil=1.5×189.33=284KN/m2
Fu<ultimate SBC=284KN/m2
Hence the footing area is adequate
Factored moment:
1)cantilever projection=B-b=1.5-0.25=1.25m
2)bending moment=Ful2/2=189.33×1.252 /2=147.91KNm
Depth of footing:
(a)from moment consideration
Mu=0.138fckbd2
D=230mm
(b)from shear consideration
For Fe 415&M20combination
Pt=0.96%
K=1
k.τc =1×0.61=0.61N/mm2
τv= Vu/bd
=620mm
Overall depth D=620+30=650mm
Reinforcement in footing
Mu=0.87×fy×Ast×d(1-fy×Ast/bd×fck)
147.91×106=0.87×415×Ast×650(1-415Ast/1000×650×20)
Ast=643mm2
Use 16 mm dia bars
Ast(p)=π/4×162 =201.06mm2
Spacing=Ast(p)/Astr×1000
=(π/4×162 ) /643×1000
=313mm
Say310mm
Provide 16mm dia bars at 310mm c/c
Check for shear stress:
Actual shear stress τv=Vu/bd
=0.394N /mm2
Allowable shear stress =ks×τc
τc =0.25√fck
=0.25√20
=1.12N /mm2 Ks=1
Allowable shear stress =ks ×τc
=1.12> τv
Safe against shear
DESIGN OF STAIRCASE
Datas :
Height between the floors = 4m
Rise = 150mm
Tread = 250mm
Landing width = 1.83m
Live load = 5kN/m2
Floor finish load = 1kN/m2
Width of support = 230mm
fck = 20N/mm2
fy = 415N/mm2
Height of each floor = 4/2 = 2m
Number of rise = 2/0.15 = 13 nos
Number of steps = 13-1 = 12 nos
Effective length = 0.23/2 + 1.83 +(12*0.25)+ 1.8+(.23/2)= = 6.89m
Load calculation:
Self weight of stairslab = ws(R^2+T^2)^(1/2)/T
Thickness of waist slab = Leff/20
= 6.89/20
say 350mm
Ws = (1*1*0.35)25 = 8.75kN/m2
Self weight of stairslab = 8.75(0.15^2+0.25^2)^(1/2)/0.25
= 10.204kN/m2
Self weight of steps = R/2*25
= 0.15/2*25 = 1.875 KN/m2
Live load = 5kN/m2
Floor finish = 1kN/m2
Factored load = 1.5*18.579 = 27.86kN/m2
Load on landings:
Assume thickness of landing slab = 200mm
Self weight of landing slab = 0.2*25 = 5kN/m2
Live load = 5kN/m2
Floor finish = 1kN/m2
Total load = 11.5kN/m2
Factored load = 1.5*11.5 =17.25kN/m
Moment @ centre
Taking moment about C
Mc=2.45RB-17.25*1.945(1.5+1.945/2)–27.86*1.5*1.5/2
Mc = 70.28 kNm
Check for depth:
Mulim = 0.138 fckbd^2
D = 159.5mm
say D = 160mm
Assume 12mm dia bars
To find Ast :
Ast = 2577.94mm2 Mu = 0.87fyAstd(1-fyAst/fckbd)
Ast = 2580mm2
Provide 12mm dia bars
Astp = 3.14*12^2/4 = 113.097mm2
Spacing = Astp/ Astr *1000
= 113.097/2580*1000
= 43.83mm ~40mm
Provide 12mm dia bar @40mm c/c
Ast = 0.12% of bD
= 0.12/100*1000*160
= 192mm2
Provide 8mm dia bars
Ast p = 3.14*8^2/4 = 50.26mm2
Spacing = 50.26/192*1000
= 261.7 ~260mm
Provide 8mm dia bar @ 260mm c/c
3D MODEL OF GROUND FLOOR
CONCLUSION
In this project work we have carried out load calculations, analysis and
design of the hi-tech shopping mall. Designs are done by using relevant
codes. We have adopted Limit State Method for the design of slabs, beams,
columns, stairs, etc.
Main purpose for doing this project is to gain a clear idea about
structural design of elements of a framed building. It is to be noted that a
theory cannot be brought to practice completely, a number of amendments
have to be make a design during execution of the work.During this project
we gathered more knowledge about the structural design.
This project is to be submitted to the management of Cape Institute of
Technology for implementation.

More Related Content

What's hot

PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMSagar Shah
 
Session 2 water proofing
Session 2 water proofingSession 2 water proofing
Session 2 water proofingAmol Pawar
 
Advanced Building Materials
Advanced Building MaterialsAdvanced Building Materials
Advanced Building MaterialsSrishti Mehta
 
Bamboo Reinforced Concrete
Bamboo Reinforced ConcreteBamboo Reinforced Concrete
Bamboo Reinforced ConcreteSravan Kumar
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and SteelRithika Ravishankar
 
modular coordination
modular coordinationmodular coordination
modular coordinationShailja km
 
POST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMPOST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMis_web
 
Lacing, battening
Lacing, battening Lacing, battening
Lacing, battening Yash Patel
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREPREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREShivangi Saini
 
Bamboo as construction material
Bamboo as construction materialBamboo as construction material
Bamboo as construction materialsuvendu parida
 
post tensioning slabs
post tensioning slabspost tensioning slabs
post tensioning slabsgopichand's
 

What's hot (20)

PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
Session 2 water proofing
Session 2 water proofingSession 2 water proofing
Session 2 water proofing
 
Advanced Building Materials
Advanced Building MaterialsAdvanced Building Materials
Advanced Building Materials
 
Components of a building
Components of a buildingComponents of a building
Components of a building
 
TRANSLUCENT CONCRETE
TRANSLUCENT CONCRETETRANSLUCENT CONCRETE
TRANSLUCENT CONCRETE
 
Slab
SlabSlab
Slab
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
Bamboo Reinforced Concrete
Bamboo Reinforced ConcreteBamboo Reinforced Concrete
Bamboo Reinforced Concrete
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
modular coordination
modular coordinationmodular coordination
modular coordination
 
POST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMPOST-TENSIONING SYSTEM
POST-TENSIONING SYSTEM
 
Lacing, battening
Lacing, battening Lacing, battening
Lacing, battening
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREPREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
 
Bamboo as construction material
Bamboo as construction materialBamboo as construction material
Bamboo as construction material
 
High rise building
High rise buildingHigh rise building
High rise building
 
post tensioning slabs
post tensioning slabspost tensioning slabs
post tensioning slabs
 
Water tank design ppt
Water tank design pptWater tank design ppt
Water tank design ppt
 
Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
 

Similar to Planing,designing and analysis of HI TECH SHOPPING MALL

Theatre building PPT.pptx
Theatre building PPT.pptxTheatre building PPT.pptx
Theatre building PPT.pptxDivyaprabaN
 
IRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential BuildingIRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential BuildingIRJET Journal
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfAberaMamoJaleta
 
project ppt 2 pdf.pdf
project ppt 2 pdf.pdfproject ppt 2 pdf.pdf
project ppt 2 pdf.pdfKarthikMasky
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxsubhashini214160
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptxKiranKr32
 
Design of Automated Circular Pedestrian Crossing at a Road Intersection
Design of Automated Circular Pedestrian Crossing at a Road IntersectionDesign of Automated Circular Pedestrian Crossing at a Road Intersection
Design of Automated Circular Pedestrian Crossing at a Road IntersectionIRJET Journal
 
IRJET - Design and Analysis of Residential Institute Building
IRJET - Design and Analysis of Residential Institute BuildingIRJET - Design and Analysis of Residential Institute Building
IRJET - Design and Analysis of Residential Institute BuildingIRJET Journal
 
Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school buildingRaghav Sankar
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxRajeshKumar25548
 
presentation_41.pptx
presentation_41.pptxpresentation_41.pptx
presentation_41.pptxShathaTaha2
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDERHarsh Shani
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowAnchit Agrawal
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank designHarish Mahavar
 
onw way slab design
onw way slab designonw way slab design
onw way slab designPalak Patel
 
gantry girders in india
gantry girders in indiagantry girders in india
gantry girders in indiaIJCMESJOURNAL
 

Similar to Planing,designing and analysis of HI TECH SHOPPING MALL (20)

Theatre building PPT.pptx
Theatre building PPT.pptxTheatre building PPT.pptx
Theatre building PPT.pptx
 
IRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential BuildingIRJET- Planning, Analysis and Designing of Cantilever Residential Building
IRJET- Planning, Analysis and Designing of Cantilever Residential Building
 
BATCH 4 PPT.pptx
BATCH 4 PPT.pptxBATCH 4 PPT.pptx
BATCH 4 PPT.pptx
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
 
project ppt 2 pdf.pdf
project ppt 2 pdf.pdfproject ppt 2 pdf.pdf
project ppt 2 pdf.pdf
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptx
 
Design of Automated Circular Pedestrian Crossing at a Road Intersection
Design of Automated Circular Pedestrian Crossing at a Road IntersectionDesign of Automated Circular Pedestrian Crossing at a Road Intersection
Design of Automated Circular Pedestrian Crossing at a Road Intersection
 
SANDIN.pptx
SANDIN.pptxSANDIN.pptx
SANDIN.pptx
 
project design.pptx
project design.pptxproject design.pptx
project design.pptx
 
IRJET - Design and Analysis of Residential Institute Building
IRJET - Design and Analysis of Residential Institute BuildingIRJET - Design and Analysis of Residential Institute Building
IRJET - Design and Analysis of Residential Institute Building
 
6.pptx
6.pptx6.pptx
6.pptx
 
Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school building
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
presentation_41.pptx
presentation_41.pptxpresentation_41.pptx
presentation_41.pptx
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
 
gantry girders in india
gantry girders in indiagantry girders in india
gantry girders in india
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 

Recently uploaded (20)

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Planing,designing and analysis of HI TECH SHOPPING MALL

  • 1. PLANING,ANALYSIS AND DESIGN OF HI- TECH SHOPPING MALL Batch members:  R. Arshana  A.S.Aswathi  A. Lekshmi  P.Pemila Reg No: 960515103008 960515103012 960515103025 960515103030 Guided By, Dr . B.Thanukumari,ME,PhD HOD,Department of civil . Cape Institute Of Technology
  • 2. INTRODUCTION • In this project, planned to construct a shopping mall in Anjugramam which is a main town ,situated near the National Highway . • In high tech shopping mall we are introducing a new era (shop with drive ). • The plinth area of each shop is 54 square meter. • We are sure about that high tech shopping mall will be useful for all sectors of people.
  • 3. ABSTRACT • Our project deals with the planning,analysis and design of Hi Tech shopping mall. • The proposed site of the project is in Anjugramam. • The structural elements such as slab,beam,column and foundation will be designed by using IS456-2000 and the materials used for the design are M20 grade concrete and Fe415 grade steel. • The plan,section and elevation will be drawn by using Autocad software and the analysis is done by using STADD.PRO
  • 4. SCOPE • Hi Tech shopping mall plays an anchor role in the Indian shopping centre. • It can be established in crowded area without any parking facilities. • The shopping mall is used as a best entertainment place for the people. • Shopping can be done within a fraction of minute.
  • 5. OBJECTIVES • In high tech shopping mall digital screen system help to guide customers in product information and availability of product. • Friendly users interface and log in systems makes more secured. • ‘Shop and drive facilities with digital collection method attracts more customers. • Walk and shop makes the shopping more realistic.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13. ANALYSIS • Analysis can be done by using stadd.pro BENDING MOMENT DIAGRAM 20 20 20 20 40 40 40 40 60 60 60 60 10 20 3030.7 9 12 48.4 48.4 -23.7 15.4 Mz(kNm) 20 20 20 20 40 40 40 40 10 20 3030.7 9 12 30.8 -30.8 Fy(kN) 2 2 2 2 4 4 4 4 10 20 3030.7 9 12 -3.15 -3.15 Fx(kN)
  • 16. DESIGN OF TWO WAY SLAB (ONE LONG EDGE DISCONTINUOUS) Datas: Room size= 6m×9m Live load= 5kN/m^2 Floor finish load=1kN/m^2 Fck=20 N/mm2 Fy=415N/mm2 Check for span ratio: Ly/Lx = 9/6 =1.5m<2m Hence it is a two way slab.
  • 17. Depth calculation: D = span / 25 = 6000/25 = 240mm Say D = 200mm Cover = 20mm Effective depth = 180mm Effective span : Lx= 6.18 m Ly = 9000 + 180 = 9180mm Load calculation: Dead load = 1m×1m×0.25×25 = 5kN/m2 Live load = 5 kN/m2 Floor finish load = 1 kN/m2 Total load = 11kN/m2 Factored load = 1.5 ×11 = 16.5 kN/m2
  • 18. Moment calculation : αx=0.067 ; αx=0.051 αy=0.037 ; αy=0.028 MX = 0.067 × 16.5 × 62 = 39.79 kN m MX = 0.051 × 16.5 × 62 = 30.29 kN m MY = 0.037 ×16.5 × 62 = 21.98 kN m MY = 0.028 × 16.5 × 62 = 16.63 kN m To find effective depth : Mu= Mulim Mu = 2.75 bd2 d = 120.28mm say d = 120mm<180mm Hence safe
  • 19. Ast Calculation: 1) Main Reinforcement (short span ) : 39.79×106 = 0.87×415×Ast×180(1-415Ast/1000×20×180) Ast=662.92mm2 Provide 16 mm dia bars Ast prov = π×102/4 =78.53mm2 i)Spacing=1000Astprov /Ast =1000×78.53/662.92 =118.46mm Say 110 mm ii) 3×d = 3× 180 = 540mm iii) 450 mm least value to be taken provide 16mm dia bars @ 110 mm c/c
  • 20. 2) Distribution Reinforcement (shorter span ): 30.29×106= 0.87×415×Ast×180(1-415×Ast/20×1000×180) Ast=494.23mm2 Provide 10 mm dia rods Ast (p)=π/4×102= 78.53mm2 Spacing=1000×78053/494.23= 158.89mm 1)say spacing=150mm 2)3d=3×180=540mm 3)450mm Least value is to be taken Provide 10mm dia bars at 150mm c/c
  • 21. 3)Main reinforcement(longer span): 29.18×106=0.87×415×Ast×180(1-415×Ast/1000×20×180) Ast=475mm2 Provide 16 mm dia bars Ast(p)=π/4×102=78.53mm2 Spacing=1000×78.53/475=165.32mm 1)Say spacing=160mm 2)3d=3×180=540mm 3)450mm The least value to be taken Provide 16mm dia bars at 160 mm c/c
  • 22. 4) Distribution reinforcement(longer span): 16.63×106=0.87×415×Ast×180(1-415×Ast/1000×20×180) Ast=263.92mm2 Provide 10 mm dia bars Ast(p)=π/4×102=78.53mm2 Spacing=1000×78.53/263.92=297.5mm 1)say spacing=290mm 2)3d=3×180=540mm 3)450mm Least value to be taken Provide 10mm dia bars at 290mm c/c
  • 23. EDGE STRIP Ast=Astmin=263.92mm2 Spacing=(1000×π/4×82)/263.92=190mm Provide 8mm dia bars at 190mm c/c where the edge strips are both longer and shorter span CHECK FOR SHEAR τv=Vu/bd Vu=16.5×6.18/2=50.985KN τv =50.99×103/1000×180=0.28N/mm2 pt=100×Ast/bd=100×662.92/1000×180=0.37N/mm2 τc=0.417N/mm2
  • 24. CHECK FOR DEPTH D=200mm K=1.20 k ×τc=1.20×0.417=0.5 k ×τc > τv 0.5>0.28N/mm2 Hence ok
  • 25. DESIGN OF T- BEAM Datas: Length of span = 9m Spacing of beam = 6m Fy = 415 N/mm2 Fck = 20 N/mm2 Depth of the flange = 200mm Width of the flange = 9.27m Cross sectional dimensions d = span/12 = 9000/12 = 750mm overall depth = 750 + 50 =800mm Load calculation Self weight of beam = 0.2 ×0.75×25=3.75kN/m2 Load from slab = 1×6×0.2×25= 30kN/m2 Floor finish = 1 kN/m2 Live load = 5 kN/m2 Total load = 38.75 kN/m2 Factored load = 1.5 ×38.75 = 58.13 kN/m2
  • 26. Ultimate load: Mu = Wu × l2/ 8 =58.13×62 /8 =261.56 kN/m Shear force : Vu= Wu ×L /2 =58.13×6/2 =174.39kN Effective depth of flange: Bf = L0/6 + bw +6 Df =9/6 + 0.23 +(6×0.2) =2.93m Centre to centre of beam= 6-0.23 = 5.77mm Take least value bf = 2.93m Moment capacity of flange: Mu= 0.36 × fck × bf × df (d-0.42 Df) =0.36 × 20 × 2930×200×(750-0.42×200) Mu=1755.18×106 kN m> 261.56 kNm Hence ok
  • 27. Reinforcement calculation: 261.56×106= 0.87×415×Ast×750(1-415×Ast/20×1000×750) Ast=993.22mm2 Provide 16 mm dia rods Ast (p)=π/4×162= 201.06mm2 No of bars = Ast/ Ast (p) = 4.9 Provide 5 numbers of 16 mm dia bars. Shear reinforcement: τv=Vu/bd =174.39×103/230×750 = 1.01 N/mm2 pt=100×Ast/bd=100×993.22/230×750=0.56N/mm2 τc=0.49N/mm2 0.49<1.01 N/mm2 Vus = Vu- τc×bd =174.39×103-0.49×230×750 =89.865 kN Use 8mm dia of 2 legged stirrups
  • 28. Spacing: 1) Sv = 0.87 × fy ×Asv ×d / Vus = 150 mm 2) 0.75d = 0.75×750 = 562.5 3) 300mm Provide 8 mm dia rods @ 150 mm c/c
  • 29. DESIGN OF L- BEAM Datas: Length of span = 9m Spacing of beam = 6m Fy = 415 N/mm2 Fck = 20 N/mm2 Depth of the flange = 200mm Cross sectional dimensions : d = span/12 = 9000/12 = 750mm overall depth =780mm effective span=9+0.3=9.3m Load calculation: Self weight of beam = 0.2 ×0.75×25=3.75kN/m2 Load from slab = 1×6×0.2×25= 30kN/m2 Floor finish = 1 kN/m2
  • 30. Live load = 5 kN/m2 Total load = 39.75 kN/m2 Factored load = 1.5 ×39.75 = 59.63 kN/m2 Effective width of flange: Bf=lo+bw+3Df=9.3/12+0.23+0.6=1.605m Say Bf=1.6m ultimate bending moment : Mu = Wu × l2/ 12 =195.35 kN/m Shear force : Vu= Wu ×L /2 =31.16kN Torsional moment at the support=20KN/m Equivalent bending moment and shear force: Me1=Mu+M
  • 31. Mu=50.12kNm Me1=50.12+195.35=245.48kNm Mu lim=0.36×fck×bd2=0.36×20×230×7502=931.5kNm Me1 <Mu lim Ast=930.49mm2 Provide 16 mm dia rods Ast (p)=π/4×162= 201.06mm2 Area of steel required at the centre with Mu=50.12kNm Ast min=0.85bd/Fy=0.85×230×750/415=353.31mm2 Provide 2 rods of 8mm dia bars Ast (p)=π/4×82= 100.53mm2 Shear reinforcement: τv=Ve/bd
  • 32. =170.29×103/230×750 = 0.99N/mm2 p t=100×Ast/bd=100×930.49/230×750=0.54N/mm2 τc =0.49N/mm2 0.49<0.99 N/mm2 Hence safe
  • 33. DESIGN OF COLUMN Given data: Size of column=600×480mm Mux=48.36kNm Muy=22.174mm Fck=20N/mm2 Fy=415N/mm2 Load calculation: Self weight of column=7.2kNm Load due to T beam=38.75kNm Load due to L beam=38.75kNm Total load=85 kNm Design load=128.55kN/m Load Pu=128.55×9/2+128.55×6/2=710Kn/m Mu=61.18KNm
  • 34. Provide 4 bars of 25mm dia and 4 bars of 16mm distributed equally on all faces with 4 bars on each face P=100×2766/480×600=0.96 p/fck=0.96/20=0.048 Because of symmetry Mux1=Muy1=221.18kNm Puz=0.45fckac+0.75fyasc=4076kN Pu/puz=710/4076=0.17 Check for safety against biaxial bending (mux/mux1)αn+(muy/muy1)αn greater than or egual to 1. (48.367/221.18)+(22.174/221018) greater than or equal to 1 =1.32 Hence the section is safe against biaxial bending
  • 35.
  • 36. DESIGN OF FOOTING Given data: Column size=600×480mm Total load=710Kn SBC of soil=350Kn/m Fck =20N/mm2 Fy=415N/mm2 Assume 10 %of column load as self weight of footing = 107×10/100 =71KN Total load on footing=710+71=781Kn Area of footing=781/350=1.5m Since it’s a rectangular footing A=B×L A=1.5B2 B2=2.23/1.5=1.48m B=1.5m h=2.5m size of footing =1.5×2.5m
  • 37. Fu=710/(1.5×2.5)=189.33KN/m2 Ultimate SBC of soil=1.5×189.33=284KN/m2 Fu<ultimate SBC=284KN/m2 Hence the footing area is adequate Factored moment: 1)cantilever projection=B-b=1.5-0.25=1.25m 2)bending moment=Ful2/2=189.33×1.252 /2=147.91KNm Depth of footing: (a)from moment consideration Mu=0.138fckbd2 D=230mm (b)from shear consideration For Fe 415&M20combination Pt=0.96%
  • 38. K=1 k.τc =1×0.61=0.61N/mm2 τv= Vu/bd =620mm Overall depth D=620+30=650mm Reinforcement in footing Mu=0.87×fy×Ast×d(1-fy×Ast/bd×fck) 147.91×106=0.87×415×Ast×650(1-415Ast/1000×650×20) Ast=643mm2 Use 16 mm dia bars Ast(p)=π/4×162 =201.06mm2 Spacing=Ast(p)/Astr×1000 =(π/4×162 ) /643×1000 =313mm Say310mm Provide 16mm dia bars at 310mm c/c Check for shear stress: Actual shear stress τv=Vu/bd
  • 39. =0.394N /mm2 Allowable shear stress =ks×τc τc =0.25√fck =0.25√20 =1.12N /mm2 Ks=1 Allowable shear stress =ks ×τc =1.12> τv Safe against shear
  • 40. DESIGN OF STAIRCASE Datas : Height between the floors = 4m Rise = 150mm Tread = 250mm Landing width = 1.83m Live load = 5kN/m2 Floor finish load = 1kN/m2 Width of support = 230mm fck = 20N/mm2 fy = 415N/mm2 Height of each floor = 4/2 = 2m Number of rise = 2/0.15 = 13 nos Number of steps = 13-1 = 12 nos Effective length = 0.23/2 + 1.83 +(12*0.25)+ 1.8+(.23/2)= = 6.89m
  • 41. Load calculation: Self weight of stairslab = ws(R^2+T^2)^(1/2)/T Thickness of waist slab = Leff/20 = 6.89/20 say 350mm Ws = (1*1*0.35)25 = 8.75kN/m2 Self weight of stairslab = 8.75(0.15^2+0.25^2)^(1/2)/0.25 = 10.204kN/m2 Self weight of steps = R/2*25 = 0.15/2*25 = 1.875 KN/m2 Live load = 5kN/m2 Floor finish = 1kN/m2 Factored load = 1.5*18.579 = 27.86kN/m2
  • 42. Load on landings: Assume thickness of landing slab = 200mm Self weight of landing slab = 0.2*25 = 5kN/m2 Live load = 5kN/m2 Floor finish = 1kN/m2 Total load = 11.5kN/m2 Factored load = 1.5*11.5 =17.25kN/m Moment @ centre Taking moment about C Mc=2.45RB-17.25*1.945(1.5+1.945/2)–27.86*1.5*1.5/2 Mc = 70.28 kNm
  • 43. Check for depth: Mulim = 0.138 fckbd^2 D = 159.5mm say D = 160mm Assume 12mm dia bars To find Ast : Ast = 2577.94mm2 Mu = 0.87fyAstd(1-fyAst/fckbd) Ast = 2580mm2 Provide 12mm dia bars Astp = 3.14*12^2/4 = 113.097mm2 Spacing = Astp/ Astr *1000 = 113.097/2580*1000 = 43.83mm ~40mm Provide 12mm dia bar @40mm c/c
  • 44. Ast = 0.12% of bD = 0.12/100*1000*160 = 192mm2 Provide 8mm dia bars Ast p = 3.14*8^2/4 = 50.26mm2 Spacing = 50.26/192*1000 = 261.7 ~260mm Provide 8mm dia bar @ 260mm c/c
  • 45. 3D MODEL OF GROUND FLOOR
  • 46. CONCLUSION In this project work we have carried out load calculations, analysis and design of the hi-tech shopping mall. Designs are done by using relevant codes. We have adopted Limit State Method for the design of slabs, beams, columns, stairs, etc. Main purpose for doing this project is to gain a clear idea about structural design of elements of a framed building. It is to be noted that a theory cannot be brought to practice completely, a number of amendments have to be make a design during execution of the work.During this project we gathered more knowledge about the structural design. This project is to be submitted to the management of Cape Institute of Technology for implementation.