SlideShare a Scribd company logo
1 of 29
PRECAST TECHNOLOGY
DEFINITION: Precast Technology is Technological innovation suitable for manufacturing process

Structural elements
are standardized and
cast in factory

STANDARDIZATION OF ELEMENTS

Transported to site on
trailers

Erected on site by
Cranes

ELEMENTS ASSEMBLED TOGETHER WITH APPROPRIATE JOINTS
PROJECT DESCRIPTION
 G+23 Storey fully Precast Residential Building
 Total BUA = 1.2 M. Sq.ft.
 Divided in to 2 phases viz.,
Phase 1 – Tower A, B, C (Completed)
Phase 2 – Tower D, E, F (Ongoing)
 Challenge of Building 24 storied residential towers using Precast in seismic zone 3 in Mumbai.

PROJECT BRIEF:
Total BUA

1.2 M Sq.ft.

Unit Configuration

14-16 Units/ Floor

Sub Structure

Pile foundation

Ground & Terrace Floor

Conventional Construction

1st to 23rd Floor

Precast Large Wall Panel System
SITE LAYOUT

Phase - 1
Phase - 2
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS

1. DESIGN
2. PRODUCTIVITY ENHANCEMENT

3. SPEED OF CONSTRUCTION
4. STANDARDIZATION
5. QUALITY CONTROL
6. SAFETY
7. SUSTAINABILITY
8. ENVIRONMENTAL BENEFITS
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS

BEST DESIGN PRACTICES
IN ASIA

BEST DESIGN PRACTICES
IN EUROPE

DUCTILITY
REQUIREMENTS IN
SEISMIC ZONE

INDIAN CODAL
PROVISIONS

DESIGN OF PRAGATI TOWERS

IN CONFORMANCE
WITH

DESIGN

PUT TOGETHER TO
COMPLETE

1.
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS
2.

PRODUCTIVITY ENHANCEMENT

CONSTRUCTION
INDUSTRY

FACING SHORTAGE
OF SKILLED
MANPOWER

ADOPTING
MECHANIZATION IN
CONSTRUCTION

L&T ENVISAGED THE
SOLUTION IS TO BE
MORE DEPENDENT
ON MACHINES

LEAD TO INCREASE
IN PRODUCTIVITY IN
PRAGATI TOWERS

MANPOWER
REQUIREMENT REDUCED
BY AROUND 30% AT
PRAGATI TOWERS
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS
3.
Formwork
•Stage 1

SPEED OF CONSTRUCTION
Reinforcement
•Stage 2

Concreting
•Stage 3

Blockwork
•Stage 4

Plastering
•Stage 5

POP works
•Stage 6

Painting
•Stage 7

Conventional Construction
Activities – on site
Reduction in the number of
activities

Precast Construction
Casting at yard
•Stage 1

Transportation
•Stage 2

Erection
•Stage 3

Jointing
•Stage 4

Painting
•Stage 5

Reduction in the number of activities & materials along
with reliability on mechanized production lead to
increase in speed of construction at Pragati Towers.

Reducing the dependency
on labour.

Savings in Precious Project
Time & thereby costs.
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS
4.

STANDARDIZATION

WALL
PANELS

SLABS

PRAGATI
TOWERS
PODS

WALL PANELS

SOLID SLAB PANELS

POD ELEMENTS

BEAMS

ENTIRE TOWER WAS BROKEN UP INTO
STANDARDIZED ELEMENTS TO GAIN
MAXIMUM REPETITION OF MOULDS

SPANDREL
PARAPET BEAMS

COLUMNS

COLUMNS

STAIRCASE

SPANDREL

STAIRCASE

ALL ELEMENTS WERE STANDARDIZED FOR ECONOMISING CONSTRUCTION AT PRAGATI TOWERS
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS
5. QUALITY CONTROL
 Precast Elements of Pragati Towers were cast in strictly controlled factory conditions

 Rigorous inspection at all stages ensures smooth and high quality finish.
ELIGIBILITY FOR ENGINEERING EXCELLENCE
PRAGATI TOWERS – HIGH QUALITY INTERIORS
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS
6. SAFETY
 All Casting activities of Pragati Towers were carried out at ground level
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS
7.

SUSTAINABILITY

 Pragati Towers demonstrated ‘Elimination of activities like brickwork, block work,
plastering’ etc at site.
Savings in Sand, labour, formwork material, scaffolding material such as wood,
timber, plywood etc.
Reduction in wastage of materials as casting processes are carried out in stringent
quality controlled factory environment.
Savings of construction material will not only result in savings of our construction
materials but also natural resources from which these materials are derived.
ELIGIBILITY FOR ENGINEERING EXCELLENCE
– PRAGATI TOWERS
8.

ENVIRONMENTAL BENEFITS

 Frequent Transportation of construction materials in conventional construction creates congestion in the
city and nuisance to the public.

ADVANTAGES: Transportation of all precast elements
at Pragati site was done during night / off peak
hours.
 Relief to public as traffic congestion was reduced
in jam-packed area of South Mumbai (Parel).
 Reduction in nuisances to nearby population like
dust, noise, air pollution.
 Relief to Motorist.
ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION
– PRAGATI TOWERS
1.

TECHNOLOGY

 Potential offered by precast technology was limited to infrastructure
projects such as airports, stadiums, bridges, dome roofs, metro projects etc.
 Pragati towers demonstrated technical feasibility of using ‘Precast
Technology’ for 24 storeyed towers & paved the way of using Precast
Technology in Indian Residential Building Construction.

First time in India, 24 storied residential building structures are
constructed by using Precast Technology

KANTEERAVA STADIUM

CHENNAI METRO RAIL

INFRASTRUCTURE PROJECTS

PUTTAPARTHY
ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION
– PRAGATI TOWERS
2.

DESIGN

 G+23 Storey ‘Total Precast System’ in Seismic Zone-3,
Mumbai.
 Designed in conformance to all ‘I.S. codal requirements’.

 Structural connections designed to comply with design codes.
 Innovative combination of ‘Modular units’ and ‘Large Panel
system’ to suit the construction needs of the project.
 Designed & Detailed in conformance to I.S. Codal
requirements to prevent progressive collapse in Precast system.
ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION
– PRAGATI TOWERS
3.

PRECAST PANEL FABRICATION – ‘INDIGENEOUSLY DEVELOPED MODULAR UNITS’

MOULD - MODULAR BLOCKS

MODULAR BLOCKS ( 3D POD)

EXPLODED VIEW

REAR VIEW

INTERIOR CORE

TRANSPORTATION
ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION
– PRAGATI TOWERS
3.

PRECAST PANEL FABRICATION – ‘INDIGENEOUSLY BATTERY MOULDS’

MOULD – BATTERY MOULD

TOP VIEW

• DESIGNED FOR CASTING WALL PANEL ELEMENTS.
ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION
– PRAGATI TOWERS
4.

WATER PROOFING

Joint detail
should ensure
water
tightness

Monolithic casting of
WC & Bathrooms in
Pragati Towers ensures
water tightness
ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION
– PRAGATI TOWERS
5.

SPEED & SAFETY

 Reduction in number of construction activities & Labour requirement helped in achieving
higher speed of construction.

 Precast Staircases and Slabs offered rapid installation and early safe access to subsequent
floors.
 Zero accidents at Pragati Towers demonstrates the safety standards.
ELIGIBILITY FOR OPERATIONAL EXCELLENCE OF PROJECT

– PRAGATI TOWERS
1.

RECORD ERECTION TIME

 Superstructure (1st Floor to 23rd Floor) of Tower A,B & C completed in a record time of 12 months.
 Planned erection = 3 Dwelling Units/day
 Peak erection achieved at Pragati Towers = 10 Dwelling Units/day
 Precast Technology @ Pragati Towers has addressed the ‘DEMAND & SUPPLY’ issue faced by our construction
industry.
 Speedy completion reduced time for construction and thereby reducing costs associated with the lifecycle of
the project.

EXECUTION OF LOGISTIC PLANNING IN CONGESTED AREAS

NOISE FREE ERECTION EVEN DURING NIGHT
ELIGIBILITY FOR OPERATIONAL EXCELLENCE OF PROJECT

– PRAGATI TOWERS
2.

REDUCTION IN NUMBER OF ACTIVITIES AT SITE

 Elimination of activities like block work, plastering & brickwork reduced
the turn around time of the project.

3.

LESS LABOUR INTENSIVE

 Labour requirement at Pragati site was found to be 30% lesser
when compared to a similar conventional construction project
(similar magnitude).

4.

MOULDS

 Battery Moulds – Specialized for high speed of

production of Precast Wall Panels without offsets
 Flat Bed Moulds – Specialized moulds for Precast Wall
Panels with offsets.
 Maximum Utilization of Moulds was planned for
achieving savings in cost of moulds.

INSIDE A BATTERY MOULD
FLAT BED MOULD
ELIGIBILITY FOR OPERATIONAL EXCELLENCE OF PROJECT

– PRAGATI TOWERS
5.

RELIEVING TRAFFIC CONGESTION

 Reduction in number of repeated trips of materials ( debris, workers, equipment, materials)
during day time.
 Finished product was transported to site during night/off-peak hours for erection.
 Relief to Motorist and nearby population.
ELIGIBILITY FOR ADDING SELF RELIANCE OF INDIA IN
CONSTRUCTION SECTOR
– PRAGATI TOWERS
1.

CONVICTION IN CONSTRUCTION TECHNOLOGY

 Proved that Precast Technology is feasible for Indian Residential Construction Industry.

2.

SERVICEABILITY OF STRUCTURE

 Longer Life Span of Structure free from plaster spalls & Wall Cracks

3.

INHOUSE DEVELOPMENT FOR PRODUCTION YARD, MOULD FABRICATION

 Methods of Mould Fabrication & Yard set up was suitably modified to cater to Indian Construction Industry.
 These methods can be used in future to lend cost competitiveness to the future precast projects.
ELIGIBILITY FOR ADDING SELF RELIANCE OF INDIA IN
CONSTRUCTION SECTOR
– PRAGATI TOWERS
4.

PROGRESSION IN DESIGN & JOINT DETAILING

 Entire ‘DESIGN & JOINT DETAILING’ in accordance to codal provision was developed.

5.

WASTE REDUCTION & SUSTAINABLE DEVELOPMENT

 Stringent controls in factory based production helped in reducing wastage of materials.
ELIGIBILITY FOR KEY IMPACTS THIS PROJECT HAS MADE
– PRAGATI TOWERS
1.

Proved ‘PRECAST TECHNOLOGY’ is feasible for high rise in seismic conditions.

2.

Successfully Addressed ‘The DEMAND & SUPPLY’ gap faced by Construction Industry.

3.

Immaculate finishes without compromising cost competitiveness of the Project.

4.

‘AMAZEMENT OF PEOPLE’ to view massive structures erected with great ease.

5.

Timely Project Completion
ELIGIBILITY FOR FUTURE READINESS OF THE PROJECT
– PRAGATI TOWERS
1.

‘FEASIBILITY & ACCEPTABILITY’ of Technology.

2.

‘BRISK PACE’ of Erection of 24 storey towers in a period of 12 months in congested area.

3.

‘ CUSTOMIZATION OF ARCHITECTURAL FINISHES’ as per the requirement of client.

4.

‘INDIGENEOUS DEVELOPMENT IN MOULD DESIGN’ to increase cost effectiveness.

5.

‘REDUCING THE DEPENDENCY OF LABOUR BY INVOLVING TECHNOLOGY OR MECHANIZED
CONSTRUCTION.’

6.

MULTIFOLD INCREASE in ‘Quality, Durability, cost effectiveness, speed with high quality
end products.’
CURRENT STATUS
- PRAGATI TOWERS
THANK YOU

More Related Content

What's hot

Low Cost Housing India
Low Cost Housing IndiaLow Cost Housing India
Low Cost Housing IndiaRohan Zagade
 
Rural of kashmir architecture
Rural of kashmir architectureRural of kashmir architecture
Rural of kashmir architecturerazarizwanraza
 
Case study Housing (Sem-VIth)
Case study Housing (Sem-VIth)Case study Housing (Sem-VIth)
Case study Housing (Sem-VIth)Amir Azhar
 
Folded plates case study (theory of structures)
Folded plates case study (theory of structures)Folded plates case study (theory of structures)
Folded plates case study (theory of structures)NIKITA SHARMA
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Prateek Srivastava
 
Group housing case study
Group housing case studyGroup housing case study
Group housing case studyVishwas Sahni
 
Mix use building case Study
Mix use building case Study Mix use building case Study
Mix use building case Study Nitesh Parmar
 
Beijing national stadium
Beijing national stadiumBeijing national stadium
Beijing national stadiumSHIFA SHAIKH
 
High-rise case study in Seagram Building & John Hancock Center
High-rise case study in Seagram Building & John Hancock CenterHigh-rise case study in Seagram Building & John Hancock Center
High-rise case study in Seagram Building & John Hancock CenterNuruzzamanpeash
 
Case study on steel structure Shrikant
Case study on steel structure  ShrikantCase study on steel structure  Shrikant
Case study on steel structure ShrikantShriKant49
 
Case study- ATS Group housing
Case study- ATS Group housingCase study- ATS Group housing
Case study- ATS Group housingAyushi Agrawal
 
World one (Lodha Tower)
World one (Lodha Tower)World one (Lodha Tower)
World one (Lodha Tower)Nikunj Rathod
 
Vernacular Architecture in Himachal Pradesh
Vernacular Architecture in Himachal PradeshVernacular Architecture in Himachal Pradesh
Vernacular Architecture in Himachal PradeshMansi Pushpakar
 
Degree College and Hill Complex, Leh, Himachal Pradesh
Degree College and Hill Complex, Leh, Himachal PradeshDegree College and Hill Complex, Leh, Himachal Pradesh
Degree College and Hill Complex, Leh, Himachal PradeshGAURAVnK
 
DISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHAN
DISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHANDISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHAN
DISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHANDipesh Jain
 

What's hot (20)

Low Cost Housing India
Low Cost Housing IndiaLow Cost Housing India
Low Cost Housing India
 
presentation ON TALL BUILDING
 presentation ON TALL BUILDING presentation ON TALL BUILDING
presentation ON TALL BUILDING
 
L&T
L&TL&T
L&T
 
Rural of kashmir architecture
Rural of kashmir architectureRural of kashmir architecture
Rural of kashmir architecture
 
Case study Housing (Sem-VIth)
Case study Housing (Sem-VIth)Case study Housing (Sem-VIth)
Case study Housing (Sem-VIth)
 
Folded plates case study (theory of structures)
Folded plates case study (theory of structures)Folded plates case study (theory of structures)
Folded plates case study (theory of structures)
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
 
Group housing case study
Group housing case studyGroup housing case study
Group housing case study
 
Mix use building case Study
Mix use building case Study Mix use building case Study
Mix use building case Study
 
Beijing national stadium
Beijing national stadiumBeijing national stadium
Beijing national stadium
 
High-rise case study in Seagram Building & John Hancock Center
High-rise case study in Seagram Building & John Hancock CenterHigh-rise case study in Seagram Building & John Hancock Center
High-rise case study in Seagram Building & John Hancock Center
 
Case study on steel structure Shrikant
Case study on steel structure  ShrikantCase study on steel structure  Shrikant
Case study on steel structure Shrikant
 
Shanghai tower
Shanghai towerShanghai tower
Shanghai tower
 
Case study- ATS Group housing
Case study- ATS Group housingCase study- ATS Group housing
Case study- ATS Group housing
 
World one (Lodha Tower)
World one (Lodha Tower)World one (Lodha Tower)
World one (Lodha Tower)
 
KATH-KUNI HOUSING
KATH-KUNI HOUSINGKATH-KUNI HOUSING
KATH-KUNI HOUSING
 
Vernacular Architecture in Himachal Pradesh
Vernacular Architecture in Himachal PradeshVernacular Architecture in Himachal Pradesh
Vernacular Architecture in Himachal Pradesh
 
Commerzbank headquarters
Commerzbank headquartersCommerzbank headquarters
Commerzbank headquarters
 
Degree College and Hill Complex, Leh, Himachal Pradesh
Degree College and Hill Complex, Leh, Himachal PradeshDegree College and Hill Complex, Leh, Himachal Pradesh
Degree College and Hill Complex, Leh, Himachal Pradesh
 
DISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHAN
DISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHANDISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHAN
DISSERTATION- TRADITIONAL CONSTRUCTION MATERIALS OF RAJASTHAN
 

Viewers also liked

PRECAST CONSTRUCTION MAKE IN INDIA
PRECAST CONSTRUCTION MAKE IN INDIAPRECAST CONSTRUCTION MAKE IN INDIA
PRECAST CONSTRUCTION MAKE IN INDIADevender Kumar
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frameSatish Kambaliya
 
Jai Prakash Associates Pvt Ltd.
Jai Prakash Associates Pvt Ltd.Jai Prakash Associates Pvt Ltd.
Jai Prakash Associates Pvt Ltd.Sujata Verma
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technologyAnjith Augustine
 
G+20 Corporate House Construction & Project Management.
G+20 Corporate House Construction & Project Management.G+20 Corporate House Construction & Project Management.
G+20 Corporate House Construction & Project Management.Neelay Khese
 
Partially Industrialized Construction
Partially Industrialized ConstructionPartially Industrialized Construction
Partially Industrialized Constructionturbi
 
David Smith 2016 CV
David Smith 2016 CVDavid Smith 2016 CV
David Smith 2016 CVDavid Smith
 
Designing Better Applications, Websites and Intranets
Designing Better Applications, Websites and IntranetsDesigning Better Applications, Websites and Intranets
Designing Better Applications, Websites and IntranetsnForm User Experience
 
Fau Innovation 6 2010 Progress
Fau Innovation  6 2010 ProgressFau Innovation  6 2010 Progress
Fau Innovation 6 2010 Progressfzollo
 
nForm better intranets | PCL construction case study
nForm better intranets | PCL construction case studynForm better intranets | PCL construction case study
nForm better intranets | PCL construction case studynForm User Experience
 
Silvapen Industrialized Cons.
Silvapen Industrialized Cons.Silvapen Industrialized Cons.
Silvapen Industrialized Cons.Silvapen
 
Ush company case study
Ush company case studyUsh company case study
Ush company case studystartguru
 

Viewers also liked (20)

PRECAST CONSTRUCTION MAKE IN INDIA
PRECAST CONSTRUCTION MAKE IN INDIAPRECAST CONSTRUCTION MAKE IN INDIA
PRECAST CONSTRUCTION MAKE IN INDIA
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frame
 
Brochure ug
Brochure ugBrochure ug
Brochure ug
 
Prathibha profile
Prathibha profile Prathibha profile
Prathibha profile
 
Larsen & toubro ltd
Larsen & toubro ltdLarsen & toubro ltd
Larsen & toubro ltd
 
L&T Solar
L&T SolarL&T Solar
L&T Solar
 
Jai Prakash Associates Pvt Ltd.
Jai Prakash Associates Pvt Ltd.Jai Prakash Associates Pvt Ltd.
Jai Prakash Associates Pvt Ltd.
 
Era infra engineering
Era infra engineeringEra infra engineering
Era infra engineering
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
G+20 Corporate House Construction & Project Management.
G+20 Corporate House Construction & Project Management.G+20 Corporate House Construction & Project Management.
G+20 Corporate House Construction & Project Management.
 
Partially Industrialized Construction
Partially Industrialized ConstructionPartially Industrialized Construction
Partially Industrialized Construction
 
David Smith 2016 CV
David Smith 2016 CVDavid Smith 2016 CV
David Smith 2016 CV
 
Designing Better Applications, Websites and Intranets
Designing Better Applications, Websites and IntranetsDesigning Better Applications, Websites and Intranets
Designing Better Applications, Websites and Intranets
 
Fau Innovation 6 2010 Progress
Fau Innovation  6 2010 ProgressFau Innovation  6 2010 Progress
Fau Innovation 6 2010 Progress
 
nForm better intranets | PCL construction case study
nForm better intranets | PCL construction case studynForm better intranets | PCL construction case study
nForm better intranets | PCL construction case study
 
Silvapen Industrialized Cons.
Silvapen Industrialized Cons.Silvapen Industrialized Cons.
Silvapen Industrialized Cons.
 
Ush company case study
Ush company case studyUsh company case study
Ush company case study
 
green building
green buildinggreen building
green building
 
Indonesia - adaptation in South East Asia
Indonesia - adaptation in South East AsiaIndonesia - adaptation in South East Asia
Indonesia - adaptation in South East Asia
 

Similar to Larsen & toubro constructions

412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdfRenukaChalikwar2
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsIRJET Journal
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure pptAbhishekM45
 
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...IRJET Journal
 
RESUME_of_manish-New
RESUME_of_manish-NewRESUME_of_manish-New
RESUME_of_manish-NewManish Sabane
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISIRJET Journal
 
IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...
IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...
IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...IRJET Journal
 
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTIONEDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTIONEduardo H. Pare
 
Final Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 PageFinal Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 PageGirish Damle
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Precast Concrete Structure
Precast Concrete StructurePrecast Concrete Structure
Precast Concrete StructureArchit Ahmad
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for constPradeepPandya1
 
internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdfPAYALINAMDAR
 
EDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDING
EDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDINGEDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDING
EDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDINGEduardo H. Pare
 
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...IRJET Journal
 
Cost and Quality Management in Buildings
Cost and Quality Management in BuildingsCost and Quality Management in Buildings
Cost and Quality Management in BuildingsIRJET Journal
 
Muhammad Aamir Javed
Muhammad Aamir JavedMuhammad Aamir Javed
Muhammad Aamir JavedAamir Javed
 

Similar to Larsen & toubro constructions (20)

412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf
 
Presentation 2016
Presentation  2016Presentation  2016
Presentation 2016
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
 
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
 
RESUME_of_manish-New
RESUME_of_manish-NewRESUME_of_manish-New
RESUME_of_manish-New
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
 
IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...
IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...
IRJET- Review Paper on Comparative Study of an Industrial Pre – Engineered Bu...
 
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTIONEDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
 
Final Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 PageFinal Hi Tech Broucher New 12 Page
Final Hi Tech Broucher New 12 Page
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Precast Concrete Structure
Precast Concrete StructurePrecast Concrete Structure
Precast Concrete Structure
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for const
 
internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdf
 
EDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDING
EDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDINGEDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDING
EDUARDO H. PARE DESIGN CONSIDERATIONS TO AVOID WATER LEAKAGES ON BUILDING
 
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
 
Resume - Raveendra S
Resume - Raveendra SResume - Raveendra S
Resume - Raveendra S
 
Cost and Quality Management in Buildings
Cost and Quality Management in BuildingsCost and Quality Management in Buildings
Cost and Quality Management in Buildings
 
Muhammad Aamir Javed
Muhammad Aamir JavedMuhammad Aamir Javed
Muhammad Aamir Javed
 

More from engineeringwatch

Engineering Watch Fellowship Portfolio
Engineering Watch Fellowship PortfolioEngineering Watch Fellowship Portfolio
Engineering Watch Fellowship Portfolioengineeringwatch
 
Engineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire BookletEngineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire Bookletengineeringwatch
 
Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 engineeringwatch
 
A novel drip irrigation system
A novel drip irrigation systemA novel drip irrigation system
A novel drip irrigation systemengineeringwatch
 
Wankhede nomination 31-08-2013
Wankhede nomination   31-08-2013Wankhede nomination   31-08-2013
Wankhede nomination 31-08-2013engineeringwatch
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013engineeringwatch
 
Ongc tripura power company limited
Ongc tripura power company limitedOngc tripura power company limited
Ongc tripura power company limitedengineeringwatch
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)engineeringwatch
 
Airports authority of india,kolkata
Airports authority of india,kolkataAirports authority of india,kolkata
Airports authority of india,kolkataengineeringwatch
 
Braithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkataBraithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkataengineeringwatch
 

More from engineeringwatch (20)

Eduindia UPTU Portfolio
Eduindia UPTU PortfolioEduindia UPTU Portfolio
Eduindia UPTU Portfolio
 
Engineering Watch Fellowship Portfolio
Engineering Watch Fellowship PortfolioEngineering Watch Fellowship Portfolio
Engineering Watch Fellowship Portfolio
 
Eduindia Portfolio
Eduindia PortfolioEduindia Portfolio
Eduindia Portfolio
 
Engineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire BookletEngineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire Booklet
 
Edu india presentation
Edu india presentationEdu india presentation
Edu india presentation
 
Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014
 
A novel drip irrigation system
A novel drip irrigation systemA novel drip irrigation system
A novel drip irrigation system
 
Wankhede nomination 31-08-2013
Wankhede nomination   31-08-2013Wankhede nomination   31-08-2013
Wankhede nomination 31-08-2013
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
 
Globus infocom limited
Globus infocom limitedGlobus infocom limited
Globus infocom limited
 
Ongc tripura power company limited
Ongc tripura power company limitedOngc tripura power company limited
Ongc tripura power company limited
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)
 
Hll lifecare ltd.
Hll lifecare ltd.Hll lifecare ltd.
Hll lifecare ltd.
 
Csir cftri
Csir cftriCsir cftri
Csir cftri
 
Hll lifecare ltd.
Hll lifecare ltd.Hll lifecare ltd.
Hll lifecare ltd.
 
Beml limited
Beml limitedBeml limited
Beml limited
 
Beml limited
Beml limitedBeml limited
Beml limited
 
Hscc (india) ltd
Hscc (india) ltdHscc (india) ltd
Hscc (india) ltd
 
Airports authority of india,kolkata
Airports authority of india,kolkataAirports authority of india,kolkata
Airports authority of india,kolkata
 
Braithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkataBraithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkata
 

Recently uploaded

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...lizamodels9
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 

Recently uploaded (20)

Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 

Larsen & toubro constructions

  • 1.
  • 2. PRECAST TECHNOLOGY DEFINITION: Precast Technology is Technological innovation suitable for manufacturing process Structural elements are standardized and cast in factory STANDARDIZATION OF ELEMENTS Transported to site on trailers Erected on site by Cranes ELEMENTS ASSEMBLED TOGETHER WITH APPROPRIATE JOINTS
  • 3. PROJECT DESCRIPTION  G+23 Storey fully Precast Residential Building  Total BUA = 1.2 M. Sq.ft.  Divided in to 2 phases viz., Phase 1 – Tower A, B, C (Completed) Phase 2 – Tower D, E, F (Ongoing)  Challenge of Building 24 storied residential towers using Precast in seismic zone 3 in Mumbai. PROJECT BRIEF: Total BUA 1.2 M Sq.ft. Unit Configuration 14-16 Units/ Floor Sub Structure Pile foundation Ground & Terrace Floor Conventional Construction 1st to 23rd Floor Precast Large Wall Panel System
  • 4. SITE LAYOUT Phase - 1 Phase - 2
  • 5. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 1. DESIGN 2. PRODUCTIVITY ENHANCEMENT 3. SPEED OF CONSTRUCTION 4. STANDARDIZATION 5. QUALITY CONTROL 6. SAFETY 7. SUSTAINABILITY 8. ENVIRONMENTAL BENEFITS
  • 6. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS BEST DESIGN PRACTICES IN ASIA BEST DESIGN PRACTICES IN EUROPE DUCTILITY REQUIREMENTS IN SEISMIC ZONE INDIAN CODAL PROVISIONS DESIGN OF PRAGATI TOWERS IN CONFORMANCE WITH DESIGN PUT TOGETHER TO COMPLETE 1.
  • 7. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 2. PRODUCTIVITY ENHANCEMENT CONSTRUCTION INDUSTRY FACING SHORTAGE OF SKILLED MANPOWER ADOPTING MECHANIZATION IN CONSTRUCTION L&T ENVISAGED THE SOLUTION IS TO BE MORE DEPENDENT ON MACHINES LEAD TO INCREASE IN PRODUCTIVITY IN PRAGATI TOWERS MANPOWER REQUIREMENT REDUCED BY AROUND 30% AT PRAGATI TOWERS
  • 8. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 3. Formwork •Stage 1 SPEED OF CONSTRUCTION Reinforcement •Stage 2 Concreting •Stage 3 Blockwork •Stage 4 Plastering •Stage 5 POP works •Stage 6 Painting •Stage 7 Conventional Construction Activities – on site Reduction in the number of activities Precast Construction Casting at yard •Stage 1 Transportation •Stage 2 Erection •Stage 3 Jointing •Stage 4 Painting •Stage 5 Reduction in the number of activities & materials along with reliability on mechanized production lead to increase in speed of construction at Pragati Towers. Reducing the dependency on labour. Savings in Precious Project Time & thereby costs.
  • 9. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 4. STANDARDIZATION WALL PANELS SLABS PRAGATI TOWERS PODS WALL PANELS SOLID SLAB PANELS POD ELEMENTS BEAMS ENTIRE TOWER WAS BROKEN UP INTO STANDARDIZED ELEMENTS TO GAIN MAXIMUM REPETITION OF MOULDS SPANDREL PARAPET BEAMS COLUMNS COLUMNS STAIRCASE SPANDREL STAIRCASE ALL ELEMENTS WERE STANDARDIZED FOR ECONOMISING CONSTRUCTION AT PRAGATI TOWERS
  • 10. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 5. QUALITY CONTROL  Precast Elements of Pragati Towers were cast in strictly controlled factory conditions  Rigorous inspection at all stages ensures smooth and high quality finish.
  • 11. ELIGIBILITY FOR ENGINEERING EXCELLENCE PRAGATI TOWERS – HIGH QUALITY INTERIORS
  • 12. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 6. SAFETY  All Casting activities of Pragati Towers were carried out at ground level
  • 13. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 7. SUSTAINABILITY  Pragati Towers demonstrated ‘Elimination of activities like brickwork, block work, plastering’ etc at site. Savings in Sand, labour, formwork material, scaffolding material such as wood, timber, plywood etc. Reduction in wastage of materials as casting processes are carried out in stringent quality controlled factory environment. Savings of construction material will not only result in savings of our construction materials but also natural resources from which these materials are derived.
  • 14. ELIGIBILITY FOR ENGINEERING EXCELLENCE – PRAGATI TOWERS 8. ENVIRONMENTAL BENEFITS  Frequent Transportation of construction materials in conventional construction creates congestion in the city and nuisance to the public. ADVANTAGES: Transportation of all precast elements at Pragati site was done during night / off peak hours.  Relief to public as traffic congestion was reduced in jam-packed area of South Mumbai (Parel).  Reduction in nuisances to nearby population like dust, noise, air pollution.  Relief to Motorist.
  • 15. ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION – PRAGATI TOWERS 1. TECHNOLOGY  Potential offered by precast technology was limited to infrastructure projects such as airports, stadiums, bridges, dome roofs, metro projects etc.  Pragati towers demonstrated technical feasibility of using ‘Precast Technology’ for 24 storeyed towers & paved the way of using Precast Technology in Indian Residential Building Construction. First time in India, 24 storied residential building structures are constructed by using Precast Technology KANTEERAVA STADIUM CHENNAI METRO RAIL INFRASTRUCTURE PROJECTS PUTTAPARTHY
  • 16. ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION – PRAGATI TOWERS 2. DESIGN  G+23 Storey ‘Total Precast System’ in Seismic Zone-3, Mumbai.  Designed in conformance to all ‘I.S. codal requirements’.  Structural connections designed to comply with design codes.  Innovative combination of ‘Modular units’ and ‘Large Panel system’ to suit the construction needs of the project.  Designed & Detailed in conformance to I.S. Codal requirements to prevent progressive collapse in Precast system.
  • 17. ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION – PRAGATI TOWERS 3. PRECAST PANEL FABRICATION – ‘INDIGENEOUSLY DEVELOPED MODULAR UNITS’ MOULD - MODULAR BLOCKS MODULAR BLOCKS ( 3D POD) EXPLODED VIEW REAR VIEW INTERIOR CORE TRANSPORTATION
  • 18. ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION – PRAGATI TOWERS 3. PRECAST PANEL FABRICATION – ‘INDIGENEOUSLY BATTERY MOULDS’ MOULD – BATTERY MOULD TOP VIEW • DESIGNED FOR CASTING WALL PANEL ELEMENTS.
  • 19. ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION – PRAGATI TOWERS 4. WATER PROOFING Joint detail should ensure water tightness Monolithic casting of WC & Bathrooms in Pragati Towers ensures water tightness
  • 20. ELIGIBILITY FOR INNOVATIVENESS IN CONSTRUCTION – PRAGATI TOWERS 5. SPEED & SAFETY  Reduction in number of construction activities & Labour requirement helped in achieving higher speed of construction.  Precast Staircases and Slabs offered rapid installation and early safe access to subsequent floors.  Zero accidents at Pragati Towers demonstrates the safety standards.
  • 21. ELIGIBILITY FOR OPERATIONAL EXCELLENCE OF PROJECT – PRAGATI TOWERS 1. RECORD ERECTION TIME  Superstructure (1st Floor to 23rd Floor) of Tower A,B & C completed in a record time of 12 months.  Planned erection = 3 Dwelling Units/day  Peak erection achieved at Pragati Towers = 10 Dwelling Units/day  Precast Technology @ Pragati Towers has addressed the ‘DEMAND & SUPPLY’ issue faced by our construction industry.  Speedy completion reduced time for construction and thereby reducing costs associated with the lifecycle of the project. EXECUTION OF LOGISTIC PLANNING IN CONGESTED AREAS NOISE FREE ERECTION EVEN DURING NIGHT
  • 22. ELIGIBILITY FOR OPERATIONAL EXCELLENCE OF PROJECT – PRAGATI TOWERS 2. REDUCTION IN NUMBER OF ACTIVITIES AT SITE  Elimination of activities like block work, plastering & brickwork reduced the turn around time of the project. 3. LESS LABOUR INTENSIVE  Labour requirement at Pragati site was found to be 30% lesser when compared to a similar conventional construction project (similar magnitude). 4. MOULDS  Battery Moulds – Specialized for high speed of production of Precast Wall Panels without offsets  Flat Bed Moulds – Specialized moulds for Precast Wall Panels with offsets.  Maximum Utilization of Moulds was planned for achieving savings in cost of moulds. INSIDE A BATTERY MOULD FLAT BED MOULD
  • 23. ELIGIBILITY FOR OPERATIONAL EXCELLENCE OF PROJECT – PRAGATI TOWERS 5. RELIEVING TRAFFIC CONGESTION  Reduction in number of repeated trips of materials ( debris, workers, equipment, materials) during day time.  Finished product was transported to site during night/off-peak hours for erection.  Relief to Motorist and nearby population.
  • 24. ELIGIBILITY FOR ADDING SELF RELIANCE OF INDIA IN CONSTRUCTION SECTOR – PRAGATI TOWERS 1. CONVICTION IN CONSTRUCTION TECHNOLOGY  Proved that Precast Technology is feasible for Indian Residential Construction Industry. 2. SERVICEABILITY OF STRUCTURE  Longer Life Span of Structure free from plaster spalls & Wall Cracks 3. INHOUSE DEVELOPMENT FOR PRODUCTION YARD, MOULD FABRICATION  Methods of Mould Fabrication & Yard set up was suitably modified to cater to Indian Construction Industry.  These methods can be used in future to lend cost competitiveness to the future precast projects.
  • 25. ELIGIBILITY FOR ADDING SELF RELIANCE OF INDIA IN CONSTRUCTION SECTOR – PRAGATI TOWERS 4. PROGRESSION IN DESIGN & JOINT DETAILING  Entire ‘DESIGN & JOINT DETAILING’ in accordance to codal provision was developed. 5. WASTE REDUCTION & SUSTAINABLE DEVELOPMENT  Stringent controls in factory based production helped in reducing wastage of materials.
  • 26. ELIGIBILITY FOR KEY IMPACTS THIS PROJECT HAS MADE – PRAGATI TOWERS 1. Proved ‘PRECAST TECHNOLOGY’ is feasible for high rise in seismic conditions. 2. Successfully Addressed ‘The DEMAND & SUPPLY’ gap faced by Construction Industry. 3. Immaculate finishes without compromising cost competitiveness of the Project. 4. ‘AMAZEMENT OF PEOPLE’ to view massive structures erected with great ease. 5. Timely Project Completion
  • 27. ELIGIBILITY FOR FUTURE READINESS OF THE PROJECT – PRAGATI TOWERS 1. ‘FEASIBILITY & ACCEPTABILITY’ of Technology. 2. ‘BRISK PACE’ of Erection of 24 storey towers in a period of 12 months in congested area. 3. ‘ CUSTOMIZATION OF ARCHITECTURAL FINISHES’ as per the requirement of client. 4. ‘INDIGENEOUS DEVELOPMENT IN MOULD DESIGN’ to increase cost effectiveness. 5. ‘REDUCING THE DEPENDENCY OF LABOUR BY INVOLVING TECHNOLOGY OR MECHANIZED CONSTRUCTION.’ 6. MULTIFOLD INCREASE in ‘Quality, Durability, cost effectiveness, speed with high quality end products.’