PRESENT STATUS OF APARTMENT BUILDING
     APPROVAL AND CONSTRUCTION IN
               KATHMANDU VALLEY


                         Study Report




                      SUBMITTED TO

          NEPAL ADMINISTRATIVE STAFF COLLEGE
             JAWALAKHEL, LALITPUR, NEPAL


In partial fulfillment of “Advanced Course on Management and
 Development” for Class II Officers of the Government of Nepal

                 (Paush 23 – Falgun 10, 2069)



                      SUBMITTED BY:

                 Binay Charan Shrestha (DUDBC)

                 Dilip Kumar Sadaula (DSCWM)

                   Kamaldeo Prasad Shah (DoR)

                Mahendra Dhose Adhikari (MoHP)

                   Rudra Nath Devkota (MoHA)

                    Sanjaya Dhungel (WECS)



                         FALGUN 2069
ACKNOWLEDGEMENT


We would like to extend our sincere gratitude to respective Ministries for providing
opportunity to take part in the training program and Nepal Administrative Staff
College for providing the training.



We are grateful to Division Chief Mr. Shiv Hari Sharma, Engineer Mr. Himal KC and
Architect Mr. Rajendra Khatiwada of Department of Urban Development and
Building Construction, Division office Kathmandu, for providing data / information
on the topic and also for extending continued support to complete the study.



We are very much thankful to Mr. Ishwari Prasad Ghimire and his team members Mr.
Santosh Koirala, Mr. Hari Lal Gyawali and Ms. Achala Dahal for their kind
cooperation during the whole training period.



We would also like to convey our sincere thanks to the respondents from the Kalash
Apartment, Tahachal, Kathmandu for providing the insight of the apartment living.



Finally, the study team would like to express their sincere gratitude to all who directly
or indirectly helped in bringing this report in the present form.




The Study Team
Abstract



The study entitled “Present Status of Apartment Building Approval and Construction
in Kathmandu Valley” has been undertaken as a project work in the context of
completing “Advanced Course on Management and Development” for class II
officers of Government of Nepal conducted by Nepal Administrative Staff College
during the period of Paush 23 to Falgun 10, 2069.

Job opportunities and availability of physical facilities causes rapid increase in
population in the urban areas. The increase in population demands the housing
facilities and accordingly the construction of multi-story buildings/apartments are
taking place. Apartment construction is providing the business opportunities for the
builders, financial institutions and manufacturers of construction materials.

Realizing the need to provide safe as well as quality living standard housing facilities,
government has designed the procedures and mandated different agencies as a
regulators. This study is focused mainly in examining the apartment buildings
approval procedures as well as monitoring and supervision process currently practiced
by DOK.

The relevant primary data are collected from residents of Kalash Apartment through
questionnaire survey and secondary data are collected from DUDBC, DOK. The
collected data were analyzed and inferences were drawn. Till Paush 2069, sixty-four
apartments have obtained approval from DOK in the Kathmandu Valley out of which
thirteen apartments are in operation with completion certificate and 15 are on
operation without obtaining completion certificate. 28 are under construction and 8
apartments have yet to start construction. There are many agencies (at least 6)
involved in apartment approval process. DOK lies at the core, but is working under
the condition of resource constraint.

Many issues have emerged as pertinent and challenging in this sector. Some of them
are related to project management while other is ethical.
The apartment construction processes have been found to be streamlined gradually.
However, enhancements of capacity of regulating agencies are yet to be in place to
provide safe and quality apartments to the residents.
i




TABLE OF CONTENT


	
TABLE OF CONTENT .................................................................................................. i 

LIST OF TABLES ....................................................................................................... iii 

LIST OF FIGURES ..................................................................................................... iii 

LIST OF ABBREVIATIONS ....................................................................................... iv 

1. INTRODUCTION ..................................................................................................... 1 

    1.1      Background ..................................................................................................... 1 

    1.2      Objectives ........................................................................................................ 3 

    1.3   Methodology ................................................................................................... 4 

    1.4   Limitations ...................................................................................................... 4 

2. INTRODUCTION OF THE ORGANIZATION ....................................................... 5 

    2.1      Introduction ..................................................................................................... 5 

    2.2      Vision .............................................................................................................. 7 

    2.3      Objectives & Strategies ................................................................................... 7 

3. DATA PRESENTATION & ANALYSIS ................................................................. 9 

    3.1      Early Initiatives ............................................................................................... 9 

    3.2      Approved Apartments ..................................................................................... 9 

    3.3      Apartments Locations and Unit Details ........................................................ 10 

    3.4      Apartments on Approval Process .................................................................. 11 

    3.5      Apartment Approval Procedure .................................................................... 12 

       3.5.1        Planning Permit ...................................................................................... 13 

       3.5.2        Environmental Approval ........................................................................ 14 

       3.5.3        Apartment Approval .............................................................................. 14 
ii




   3.6       Monitoring and Supervision .......................................................................... 16 

   3.7       Issuance of Completion Certificate ............................................................... 17 

   3.8       APARTMENT LIVING CONDITION ........................................................ 17 

   3.8       KEY ISSUES ................................................................................................ 18 

       3.8.1        Time Taken for Approval Process ......................................................... 18 

       3.8.2        Project Management Issues.................................................................... 19 

       3.8.3        Insufficient Resources ............................................................................ 19 

       3.8.4        `Unethical Practices ............................................................................... 20 

4. MAJOR FINDINGS, CONCLUSION & RECOMMENDATIONS ....................... 21 

   4.1       Major Findings .............................................................................................. 21 

   4.2       Conclusion ..................................................................................................... 22 

   4.3       Recommendation ........................................................................................... 22 

Bibliography ................................................................................................................ 24 

APPENDICES ............................................................................................................. 25 

Appendix 1 ................................................................................................................... 26 

Appendix 2 ................................................................................................................... 31 

Appendix 3 ................................................................................................................... 34 

Appendix 4 ................................................................................................................... 41 

Appendix 5 ................................................................................................................... 45 
iii




LIST OF TABLES

Table 1: Status of the 64 Apartments having apartment approval ................................. 9 

Table 2 Number of apartments inside and outside the ring road ................................. 10 

Table 3: Status of apartment proposals on approval process ....................................... 11 

Table 4: Screening Criteria .......................................................................................... 14 



LIST OF FIGURES

Figure 1: Location of apartments within the Kathmandu valley ................................. 10 

Figure 2: District wise distribution of approved apartments ....................................... 11 

Figure 3: Apartment Approval Procedure.................................................................... 13 

Figure 4: Kalash Apartment ......................................................................................... 35 

Figure 5: Fire Escape in Kalash ................................................................................... 35 

Figure 6: Fire Hose in Kalash ...................................................................................... 35 

Figure 7: Questionnaire survey .................................................................................... 35 

Figure 8:Violation of Planning Permit ......................................................................... 36 

Figure 9: Change in Approved Design ........................................................................ 37 

Figure 10: Inadequate Safety Measure ........................................................................ 38 

Figure 11: Partial Dismantling of Major Structural Member ...................................... 39 

Figure 12: Use Change Without Prior Approval ......................................................... 40 

Figure 13: Organization Chart of DUDBC .................................................................. 46 

Figure 14: Jurisdiction of DUDBC division office (source DUDBC) ......................... 47 

Figure 15: Organization Chart of DOK ....................................................................... 48 
iv




LIST OF ABBREVIATIONS



CANN           Civil Aviation authority of Nepal

DOK            Division Office Kathmandu

DUDBC          Department        of   Urban      Development   and
               Building Construction

EIA            Environmental Impact Assessment

IEE            Initial Environmental Examination

KVDA           Kathmandu Valley Development Authority

KVWSMB         Kathmandu Valley water supply Management
               Board

MoPPW          Ministry of Physical Planning & Works

MoUD           Ministry of Urban Development

MoSTE          Ministry     of        Science,    Technology    &
               Environment

NNBC           Nepal National Building Code

NRRC           Nepal Risk Reduction Consortium

OJHA           Ownership of Joint Housing Act

OJHR           Ownership of Joint Housing Regulation
1


                                    CHAPTER 1

1. INTRODUCTION

1.1    BACKGROUND
The study entitled “Present Status of Apartment Building Approval and Construction
in Kathmandu Valley “has been undertaken as a project work in the context of
completing “Advanced Course on Management and Development” conducted by
Nepal Administrative Staff College from Paush 23 to Falgun 10, 2069.

The National Census (2068 B.S.) revealed that the total population in Nepal is
26,494,504. Out of which the male and female population are 48.50% and 51.50%
respectively. The populations settling in the urban areas are 17.07%.The density of
population in the urban area is 1381 compared to 153 persons per square kilometer in
rural area. Though Nepal has the lowest urbanization rate in south Asia at 14 per cent
its urban growth rate is 6.4 per cent which is the highest in south-Asia. In the last
decade population growth in the urban areas was 3 times that of the country as a
whole. Kathmandu has high population density (4416 person per square kilometer)
compared to other part of the country. Nepal has a total of 5,423,297 households, of
which 85.26% and 12.81% families are residing in their own house and rented houses
respectively. The total number of houses/buildings or residential structures until 2068
are 4,768,196.

The development pace between rural and urban parts of the country resulted people
migrating to urban areas for better opportunities and quality life. Opportunities for
self-employment in enterprises have attracted people in urban areas. Health, education
and other facilities are well developed in urban areas compared to rural. The
migration of the large rural population from the countryside and the influx of
foreigner for business and other purposes have created a need for additional housing
facilities. The available land in the urban areas is limited to provide housing facilities
to the growing population. In order to cater the housing needs of increasing
population, multi-story buildings in the forms of collective and apartment housings
are being developed. People residing in urban areas have less time to arrange the
various physical facilities and security measures on their own. Further, those residing
2


in the individual houses also prefer to move into the apartments for availing better
security and physical facilities. The good earning populations, who are unable to
spend time for building their house are also seeking for the readymade
apartments/buildings. These factors necessitate the need for the apartment buildings.
Increase in demand of housing will continue as the new generation prefers nuclear
families.

The growing demand of the apartments has provided the opportunities for business
communities to diverse the investment in the multi-story building sector. Likewise,
the commercial banks, financial institutions and cooperatives also took this as an
opportunity to diversify the loan portfolio. The construction materials manufacturers
and suppliers are also attracted in this sector. The skilled and unskilled construction
workers also prefer to work in multi-story building construction as it provides long
term employment with assured wages. Thus, the builders, financial institutions and
manufacturers are putting collaborative efforts to get cash benefits from the housing
business.

Building construction around a decade ago was completely a personal matter. There is
a tradition of constructing houses through self-effort and utilizing own resources and
means. The local municipalities were the only authority to give approval to construct
a house after examining the drawings and inspecting the construction site. The limited
technical and financial resources in the municipalities has posed a problem to examine
the overall aspects of construction that includes environmental assessment, structural
design, sanitary, water supply and plumbing system, firefighting system, electrical
system and design etc. in details. These factors are of utmost importance to maintain
safe and quality living.

Considering these aspects, government has formulated 'National Shelter Policy, 2012'
with the vision of providing housing, which is safe, adequate and as per living
standard to all. Change in attitude and working style of both regulating authorities and
construction entrepreneurs are the prime factors for translating the vision into reality.

Multiple agencies are involved in providing clearance to the builder for apartment
construction. Ministry of Science, Technology and Environment (MoSTE) is
responsible for Environmental assessment, Kathmandu Valley Development
3


Authority (KVDA) is for providing planning permit, Civil Aviation Authority
(CAAN) is for clearing safe flying zone, Kathmandu Valley Water Supply and
Management Board (KVWSMB) for groundwater use and Department of Urban
Development and Building Construction (DUDBC) granting approval for apartment
construction. After the clearance from these agencies, final approval is given by the
concerned       local   government      (Municipalities    /   Village    Development
Committee(VDC)).

In the construction of apartments, on the one hand multiple regulatory agencies and
on the other several builders/companies from different background are involved. The
objective of regulatory agencies is to ensure compliance of specified design as well as
quality construction and safety measures whereas, the objective of the
builders/companies is to complete the construction at earliest with minimum cost
ensuring higher profit. The regulating agencies should sincerely adhere to the stated
policy and procedure to approve, monitor and supervise the construction process.
Likewise, the honest effort of the builders is required for timely completion and
quality of construction.

In this context, the team has identified the apartment construction process including
monitoring and supervision as a pertinent issue and decided to undertake as a study
project.

1.2      OBJECTIVES

The general objective of the study is to review the present status of apartment
construction industry in Kathmandu valley.

The specific objectives are:

     To assess the apartment construction approval procedures.
     To examine the monitoring and supervision process currently adopted by
      DUDBC, DOK.
     To access the present apartment living condition in a sample apartment.
4


1.3    METHODOLOGY
The information on the apartment construction approval process was gathered from
presentation made by officials from DUDBC, DOK. The unpublished materials
provided during the presentation were reviewed and studied in detail. Legal
provisions relating to apartments were also studied from different acts, regulations
and building bylaws.

The study group visited the Kalash apartment, Tahachal and interacted with the
apartment dwellers and collected necessary information and verified them through
observation at the site. The inference has been derived based on the available data.

1.4    LIMITATIONS
      The present study is mainly based on secondary data / information collected
       from DUDBC, DOK.

      Review of apartment construction approval procedure is mainly focused on the
       role of DUDBC, DOK.

      The primary information collected is from one apartment (10 residential units)
       only and may not represent the case of all the apartments. It is of qualitative
       type and only subjective inferences have been made.
5


                                  CHAPTER 2

2. INTRODUCTION OF THE ORGANIZATION

2.1    INTRODUCTION
The first public entity office established in Nepal for construction sector was named
as “Banaune Adda” in 1970 BS during the Rana Regime. Its main objectives were to
maintain the royal palace, existing government buildings and construction of new
project. This office was then renamed as the Department of Building (DoB) in 2020
BS under the then Ministry of Works and Transportation (MoWT) and was mandated
to design and construct the government buildings. From the fiscal year 2027/28 the
department was reformed as Department of Housing, Building and Physical Planning
(DHBUP) and was also mandated to address the growing need of housing and Urban
Planning in Nepal.

In 2044 BS the government of Nepal gave priority to planned urban growth as well as
safe shelter and formed a new Housing and Physical Planning Ministry. In 2045 BS
under this new ministry DHBUP was reconstituted into two separate entities namely;
Department of Buildings(DOB) and The Department of Housing & Urban
Development(DHUD) at the central level; whereas as the regional and district level,
both the departments have the same offices. The district chiefs of these offices were
deputed as the member secretary of the concerned Town Development Committees.

Again in 2058 the government of Nepal reorganized the two departments into one
single unit under the Ministry of Physical Planning & Works (MPPW) and named the
newly formed entity as Department of Urban Development and Building construction
(DUDBC) to avoid duplications in works carried out by the then two departments.
Recently in 2069 BS this department has been put under the newly formed Ministry of
Urban Development (MoUD).

At present DUDBC have three divisions, twenty-four division offices and one training
center (Appendix 5,Figure 13) The main task of the Department of Urban
Development and Building Construction (DUDBC) lies in the sphere of planning.
Since 2002, the office assisted in the preparation of Periodic Plans following the
6


participatory and consultative process for municipalities. The department was also the
focal point for the Integrated Action Planning exercise which commenced in 1992.
More than 30 municipalities have prepared their own integrated action plan, which
was later replaced by Periodic Plans as provisioned in the Local Self-Governance
Regulations.

There is no history of the department being directly involved in the housing sector.
Yet in recent years the Department of Urban Development and Building Construction,
has been increasingly committed to the urban housing problem and acknowledged the
issue of squatter settlements. The department took exemplary action by signing MOU
with the NGOs to upgrade slums and squatters. The department has set a target to
upgrade 25 slums and squatter communities in their three year interim plan beginning
July 2007. There are several ministries involved in the land tenure issue. Yet in
absence of a clear policy on addressing the urban squatter problem, the fund allocated
for squatter settlement could not be used as intended. Instead the fund was utilized to
buy land for resettlement of squatters.

Besides these the department has been an important partner for disaster risk
management (DRM) initiatives specifically regarding building codes, technical
assistance, orientations, enforcement and trainings. Based on the mandated work, the
DUDBC has provided significant support for the Nepal Risk Reduction Consortium
(NRRC). The following lists the various activities DUDBC has contributed for DRM
in Nepal:

Flagship 1: School and hospital safety

    Structural and non-structural aspects of making schools and hospitals
       earthquake resilient

Flagship 2: Emergency preparedness and response capacity

    Prepare site inventory of major open spaces to enhance preparedness of GoN
       & international agencies & reduce adverse consequences that might happen
       after disaster. This includes camp management plan, water supply and
       sanitations, primary health and school buildings, security posts and
       improvement of infrastructure services
7


       Municipal Profiles in terms of Earthquake Risk and Vulnerability,
          Vulnerability Assessment and Damage Assessment.

Flagship 5: Policy/institutional support for disaster risk management

       Preparation of Risk Hazard Map, GIS map of municipalities.
       Study of Existing Practices in High Rise Building & Recommendation for
          safety.
       Support to municipalities on Building code implimentation & Update of Nepal
          National Building Code
       Seismic Vulnerability Evaluation Guideline for Private and Public Building /
          Training Manual / Training on Damage Assessment, Vulnerability
          Assessment, Demonstrative Retrofitting works

2.2       VISION
The main vision of the Department is:

         Urban Development Sector: Achieve a balanced national urban structure,
          Promote safe and economically vibrant urban environment and Promote
          effective urban management.

         Housing Sector: Promote Planned Development through providing affordable,
          adequate and safe shelter to all income group people.

         Building: Promote safe, economical and Environment friendly buildings that
          can display indigenous architecture

2.3       OBJECTIVES & STRATEGIES
Objectives

Urban Development

To invest in urban infrastructure and other services through inter-agency coordination,
to legally empower and institutionally strengthen local bodies in order to build a
clean, safe and prosperous urban environment, and to progressively guide rural
settlements towards urbanization by expanding rural urban inter-relationship under
the overall notion that urban development promotes rural development.
8


Housing

To provide safe and economical housing facility by developing organized habitats
under the notion of “shelter for all”.

Building

To construct and develop buildings which portray Nepalese architecture to the extent
possible, and are safe, affordable and environmental friendly.

Strategies

• To develop large urban centers in the country as regional economic centers, and to
 link them with medium and small centers through roads and other infrastructures,
 and thereby strengthen the rural urban inter-relationship.

• To guide urban development by establishing urban infrastructure through physical
 development planning with an aim to preserve and conserve the existing cultural,
 historical and tourist areas. To develop suburbs at the periphery of the city and to
 prepare a base for planned development of urbanizing VDCs.

• To develop local bodies as the major agency to implement urban plans, and also
 strengthen institutional capability of concerned central agencies involved in urban
 planning and policy formulation, and monitoring.

• To develop urban housing with the participation and involvement of the
 government, cooperatives and the private sector.

• To develop market centers in the urbanizing settlements and develop requisite
 infrastructure in the scattered settlements in rural areas, while regulating
 development in urban and rural settlements to preserve historical and cultural
 heritage.

• To update and implement the Building Code and byelaws in the government and
 private sectors as well.

• To promote and develop the capability of national consultants and contractors.

• To develop appropriate building construction technology and materials.
9


                                    CHAPTER 3

3. DATA PRESENTATION & ANALYSIS

3.1    EARLY INITIATIVES
The need of "Joint housing" was felt during early 2050BS due to the sudden increase
of population pressure on urban areas and the subsequent increase in the land price.
Nepal enacted the Ownership of Joint Housing Act (OJHA), in 2054 (authentication
and publication date: 2054.9.7). However, the actual apartment building began after
the approval of Ownership of Joint Housing Regulation (OJHR) by the then HMG/N
in 2060/04/12 B.S. Indreni Apartment - 1 (having 32 units), located at Kathmandu
municipality - 4, Bhatbhateni, Kathmandu and owned by Subhakamana Housing
company Pvt. Ltd, was the first to obtain the apartment construction approval from
DUDBC, DOK.

3.2    APPROVED APARTMENTS
In total 64 apartments have obtained apartment construction approval from the
division till paush 2069. Status of these 64 apartments has been summarized in Table
1 below.

Table 1: Status of the 64 Apartments having apartment approval

      S.     Status                                        No of apartments
      No

      1      On operation with completion certificate              13

      2      On operation without completion certificate           15

      3      On construction phase and others*                     28

      4      Construction not started                              8

             Total                                                 64

Source: DUDBC, Division office, Babarmahal, Kathmandu

*On construction phase and others
10


           Revised approval (3)
           Completion certificate processing (3)
           On completion (regular/irregular)
           Halt construction

3.3         APARTMENTS LOCATIONS AND UNIT DETAILS
Out of 64 approved apartments 51 are located inside the ring road while the reaming
13 are located in outside areas (Table 2,Figure 1)

Table 2 Number of apartments inside and outside the ring road

          Location              Nos                 Apartment Units

Inside Ring road                51                       2862

Outside Ring                    13                       3465
road

Total                           64                       6327

(Source: DUDBC,DOK)




                Figure 1: Location of apartments within the Kathmandu valley
11


Among these 64 apartments 46 are located in Kathmandu district while the remaining
18 are located in Lalitpur district. No apartment is located in Bhaktapur district. The
district wide distribution of approved apartments in Kathmandu valley in given in
Figure 2 below.




             Figure 2: District wise distribution of approved apartments

                                    (source DOK)

3.4    APARTMENTS ON APPROVAL PROCESS
Right now, there are 14 apartment proposals in the division at different stages of the
overall approval process. Out of these 14 proposals 6 are in regular follow up. Besides
this, 7 other apartments have taken planning permit but not applied for design
approval yet. The status of apartment on approval process is given in Table 3 below

Table 3: Status of apartment proposals on approval process

 S.N status of proposal                                            No    of   apartment
                                                                   proposed

 1     Apartment proposal with regular follow up                              6

 2     Apartment proposal without regular follow up                           8

 3     Apartment proposal yet to apply for design approval                    7

       Total Proposals                                                        21

Source: DOK
12


3.5       APARTMENT APPROVAL PROCEDURE
The entire apartment approval procedure can be discussed under the following three
stages.

Stage 1: Planning Permit Stage

         Developer produce project proposal with design and drawings for planning
          permit
         Developer applies for planning permit from KVDA
         Developer undertakes environmental screening
Stage 2: Apartment Approval Stage

         Developer applies for apartment approval from DOK, DUDBC
         Developer undertakes EIA/IEE study as required
         Developer applies for clearance from civil aviation authority for safe flying
          zone
         Developer applies for approval from KVWSMB for groundwater use
Stage 3: Local Body Approval Stage

         Applies for approval from municipality/VDC concerned
13


The overall apartment approval procedure has been summarized in Figure 3 below.




    Figure 3: Apartment Approval Procedure

    (Source DOK, modified)

3.5.1 Planning Permit

As mention above, the developer has to apply to Kathmandu Valley Development
Authority (KVDA) with required planning permit design and drawing for planning
permit. KVDA reviews the documents within the broad framework of:

      Town Development Act, 2045
      Gazette published on BS 2062/11/22 and
      Building by-laws 2064
The key elements covered by planning permit include:

      Construction area, approach road, Set back, FAR, light plane
      Ground coverage, greenery (open surface) and other open spaces
      Distance between blocks
      Parking facilities
      Planning related issues like sewer, electrical systems, GLD lines, HT line,
       water supply plan
14


         Waste water and solid waste management

3.5.2 Environmental Approval

The project developer has to undertake the environmental assessment as per the
guidance of Environment Protection Act, 2053 and Environment Protection
Regulation 2055. The first task to undertake this process is to carry out the
environmental screening so as to determine whether the project requires IEE or EIA,
or it does not require any assessment at all. The screening criteria as mentioned in
EPR, 2055 is shown below in Table 4:

Table 4: Screening Criteria

SN       Criteria                        No EA          IEE               EIA

1        Build Up Area                   <5000 sqm      5000-10000 sqm    >10000 sqm

2        No of Story                     <10            10-16             >16

3        Height of the Building          <25 m          25-50 m           >50 m

4        NO of Inflow and Outflow at a   <1000 person   1000-2000         >2000 persons
         time                                           persons

Source DOK

The developer conducts either IEE or EIA and submits the report to competent
authority MoUD in case of IEE and MoSTE in case of EIA) for approval. The key
aspects/areas covered by IEE/EIA document include:

         Project description covering construction planning
         Review of relevant policies in relation to the project implementation
         Alternative analysis
         Major adverse environmental impacts and their mitigation measures
         Major beneficial environmental impacts and their enhancement measures
         Environmental management plan ( environmental monitoring plan covered)

3.5.3 Apartment Approval

The developer applies to the DUDBC, DOK for design approval and construction and
operation permit with all required documents. The Division office reviews the
15


proposal in line with the broad framework provided by the following policy
instruments.

      OJHA 2054 & OJHR 2060
      Building act 2055
      Nepal National building code 2060
      Work procedure 2060
The key elements covered by Apartment Approval are:

Architectural Design

      Light and ventilation system
      Staircase, exit
      Lobby, lift, disable ramp, parapet height
      Glazing system
Structural Design

      Geo-technical investigation
      Structural analysis/model as per NNBC 2060
      Structural drawing with respect to output of structural design and ductile
       detailing code
Sanitary, water supply and planning system

   •   Water supply/Treatment Plant/Pumping System
   •   Toilet Bath fixtures and installation systems.
   •   Liquid waste and solid waste management system.
   •   Rain water Harvesting Systems.
Firefighting system

   •   Fire Detector, Fire extinguisher, Firefighting Hose reels, Hose pipes, Water
       tank, Hydrant stations.
   •   Fire escape staircase, Exit, Lobby, Escape route.
Electrical system and design

   •   Electrical Points, load calculation, Cable sizes.
   •   Earthing, Lightning arrestor.
16


      •   Safety against electrical hazards.
      •   Transformer, Generator and Panel Boards.
Operation and management plan (including safety management plan)

      •   Electrical, Sanitary services operation and management plan.
      •   Fire safety management and earthquake safety management plan.
      •   Evacuation area, Exit, Use of Open Spaces during Disaster
The division office may ask for presentation from designer for complex structures.
There is also the provision for "review" by "expert panel" for such complex
structures. The documents to be submitted to DOK along with the proposal are:

      •   Application form.
      •   Provision of details of Services/Facilities.
      •   Sample of Contract agreement paper. (As per clause 15 of OJHA2054)
      •   Land and Company related ownership documents.
      •   Proprietor, Developers Representatives.
      •   Quality assurance documents and designer’s affidavit papers.
      •   Project brief reports, design reports and soil test reports.
      •   Insurance letter.

3.6       MONITORING AND SUPERVISION
Monitoring and supervision            from DOK is mainly focused on checking of
reinforcement detailing before/during casting of important structural components e.g.
foundation, column, slab and beam. Monitoring from DOK also involves reviewing of
the periodic progress reports and lab test reports. The main constraint on monitoring
and supervision from the DOK prospective is the lack of adequate resources, mainly
the human resources (Shown in Appendix 5, Figure 15).

The task of conducting environmental monitoring lies within the concerned line
ministry, MoUD in this case. However, no regular and systematic environmental
monitoring has been conducted so far. Monitoring from other agencies like KVDA
and local bodies (Municipality/VDC) have been reported to be weak as well.

Monitoring of the DOK has reported the following diversified observations:
17


          Violations of planning permit and building by-laws(Appendix 3, Figure 8)
          Change in approved design/drawings. (Appendix 3, Figure 9)
          Major construction work without presence of technical team (Project
           manager, engineer, architects)
          Approved drawing/detailing not available at site.
          Project manager/site engineer unknown about approved drawings
          Inadequate safety measures (Appendix 3,Figure 10)
          Approved design followed strictly and safety tools used properly
          Partial dismantling of major structural elements (Appendix 3, Figure 11)
          Use change without prior approval (Appendix 3, Figure 12)

3.7       ISSUANCE OF COMPLETION CERTIFICATE
The project developer submits the project completion report (with as built drawings),
quality control reports and environmental compliance report to DOK. The DOK
engineers undertake site visits for final checking including the firefighting system. In
case, where the regular quality test reports were not submitted to the DOK, the third
party consultant is hired for post construction quality test and structural design
verification.

The Division office issues the completion certificates when all the reports and
observations comply with the design requirements.

3.8       APARTMENT LIVING CONDITION
The aim of the study team was to visit at least one apartment in Kathmandu valley to
access the existing situations. The study team decided to visit Kalash Apartment
which is situated at Tahachal, Kathmandu. It is centrally located. It is a multi-story
(nine stories) apartment. It has been functioning since two years. There are altogether
75 units out of which only 50 units are found to be occupied. Developer has already
obtained construction completion certificate from DOK.

A sample questionnaire was prepared which was mostly related with the extent of
satisfactions of the unit owner, major problems faced by unit owners in smooth
operation and their opinion for its improvement. The interaction was two way and
18


conducted in an open environment. They inquired us about existing policies, acts and
regulation. Most of them were not aware with OJHA and OJHR. After interaction the
team walked around and had a look on facilities provided. Apartment has been found
to be furnished with most required facilities like parking space, exits for emergency,
sauna, health club, fire extinguisher etc.

The assessment from the interaction was very much interesting to us. Apartment is
completely dependent on ground water supply for bathing, utensils cleaning, cloth
washing etc. and unit owners uses aqua guards for drinking purpose. It has a generator
for electricity backup during load shedding, but it faces fuel shortage and improper
management. The unit owners have themselves arranged security personnel and they
are quite satisfied with securities arrangements made by them. There were several
issues opined from most of them. Unit owners are still without ownership certificate
(LALPURJA) of their units. Ownership transfer must have completed by December,
2011 but still they are in hands of developer. Most of the unit owners are
businessman. They need PAN numbers urgently but in absence of ownership
document they are unable to get it. Developers still have not yet transferred
apartments operation and management to existing society. The open space for
children is not available. There is a temporary arrangement for garbage disposal
which is altogether managed by dwellers themselves. There is not sufficient space
available after exit which is must in the case of emergency.

3.8    KEY ISSUES
3.8.1 Time Taken for Approval Process

Organization structure of the Kathmandu Division (Appendix5, Figure 15) depicts
inadequacy of technical manpower for the evaluation of structural and non-structural
designs along with monitoring of mushrooming apartments of Kathmandu valley.
Developer’s unwillingness to obtain design approval due to uncertainty in the market
behavior either from government’s inconsistent decisions or from economic recession
also becomes the cause of some delay in approval process. IEE/EIA processes
(though necessary and mandatory) were identified as being cumbersome and time
consuming due to its unclear (non-standardized) processes and guidelines. Apartment
19


construction approval process seeks approval from as many as nine (6) agencies. All
those agencies have their own working norms. It is natural that delay occurs due to
several agency involvements.

3.8.2 Project Management Issues

There are some smaller but significant issues relating to project management. Some of
important issues that have emerged during the past years of apartment housing in
Nepal are:

   1. Frequent change of technical personnel leading to a gap between old and new
       and between the business and the regulating authority.

   2. Weaker coordination between developer, consultant and the contractor's
       technical personnel hindering the smooth, timely and orderly implementation
       of the activities.

   3. Improper and inadequate safety consideration during construction.

   4. Weak progress reporting.

   5. Construction without prior checking by DOK.

   6. Use change without prior approval.

3.8.3 Insufficient Resources

In Kathmandu valley, urbanization is in rapid expansion and a large number of
apartments are under construction. Giving permission of building construction,
supervision and monitoring during construction and issuing completion certificate to
the developer are the major responsibilities of the DOK in the apartment sector.
Within the division, having no separate section for apartment, the available human
resources (technical as well as administrative) are insufficient in relation to its work-
load. Still the division is working under the old organogram. It is realized that due to
insufficient human resource, division has felt difficulty in delivering its services
smoothly. The issue is not related to human resource only, other resources like budget
and vehicles for supervision and monitoring are also felt inadequate. On the other
hand, the office management/operational cost are same as in the past despite increased
20


work load. In totality all the factors discussed above are hindering the apartment
construction business as a whole.

3.8.4 `Unethical Practices

It has been reported that designer change (one person designs and the other signs the
drawings and affidavit) is prevailing in practice. Such unethical practices are indeed
one of the serious concerns for the DOK and are yet to be checked.
21


                                 CHAPTER 4

4. MAJOR FINDINGS, CONCLUSION & RECOMMENDATIONS

4.1   MAJOR FINDINGS
1.    There are at least 6 agencies directly involved in the apartment approval
      process. In this sense it can be regarded as a multi stakeholder task. The DOK,
      has a key role and is focused mainly on safety criteria by ensuring adoption of
      National Building Code.

2.    It has been noticed that the time taken for the apartment approval process
      (from planning permit to approval from local body) was found to be varying
      widely (6 months to 3 years). It is not only the regulatory body's role which is
      responsible for such wide variation; equally important factors are the market
      condition and the promoter's management skill.

3.    The Kathmandu Division Office is handling the entire task of apartment
      approval, monitoring and supervision on top of its regular job. The
      organization structure of the division has remained the same since 2058 B.S.
      No arrangements have been made to accomplish the additional task on
      "apartment" which was assigned to the division by the gazette dated
      2060/01/02 B.S. In addition to this, the division office is also facing serious
      resource constraints.

4.    Some apartments have been reported to be operating without completion
      certificate from DOK. Furthermore few cases of even ownership transfer
      (without completion certificate from DOK) have also been reported.

5.    During the period of last 8/9 years some issues has been emerged as pertinent
      and challenging. Some are ethical (designer change) while other are related to
      project management (weak progress reporting, safety during construction,
      construction without prior checking by DOK etc.) . Use change has emerged
      as another major issue.

6.    The residents (apartment owner) of the surveyed apartment are found to be
      unaware of the concerning laws and regulations. They doubt whether the
22


       firefighting system works properly. The developer has not provided the
       "ownership certificate" (LALPURJA) yet.

4.2    CONCLUSION
In general, apartment approval and construction has been found to be streamlined in
the right direction. However the pertinent issues emerged so far have to be
systematically and promptly addressed by the concerned authority(ies). DOK has to
be strengthened. Safety considerations have to be given the first priority by all
stakeholders concerned.

4.3    RECOMMENDATION
1.      DOK should be strengthened by allocating adequate resources and providing
        additional responsibilities and authorities so that it can function as a strong
        and competent "one door" of the government in apartment housing sector.

2.      DOK and the concerning local authority (municipality/VDC) should organize
        regular safety awareness campaign (including drilling) in the occupied
        apartments. Safety related systems/equipment should be checked on a regular
        basis.

3.      Third party monitoring can be introduced after required preparations. This
        will help in ensuring better adoption of safety requirements while keeping the
        DOK size appropriately slim.
23
24


BIBLIOGRAPHY

Government of Nepal Building Bye Law. - 2064.

Government of Nepal Environment Protection Act. - 2053.

Government of Nepal Environment Protection Regulations. - 2055.

Government of Nepal Ownership of Joint Housing Act, 2054. - 1997.

Government of Nepal Ownership of Joint Housing Regulations. - 2060.

http:www.dudbc.gov.np [Online]. - Department of Urban Development & Building
Construction.

National Census: A Brief Report [Report]. - [s.l.] : Bureau of Statistic,Government of
Nepal, 2012.

National Shelter Police [Report]. - [s.l.] : Ministry of Urban Development,
Government of Nepal, 2012.

Nepal Urban Housing sector Profile [Report]. - [s.l.] : UN-HABITAT, 2010.
25




APPENDICES
26




APPENDIX 1

             Detail of Approval of Apartments
27
28
29
30
31




APPENDIX 2

             Apartments under Approval Procedure
32
33
34




APPENDIX 3

             Photographs
35




Figure 4: Kalash Apartment      Figure 5: Fire Escape in Kalash




                                Figure 7: Questionnaire survey


Figure 6: Fire Hose in Kalash
36




Figure 8:Violation of Planning Permit

Photo Courtesy: DOK
37




Figure 9: Change in Approved Design

Photo Courtesy: DOK
38




Figure 10: Inadequate Safety Measure

Source DOK
39




Figure 11: Partial Dismantling of Major Structural Member

Source DOK
40




Figure 12: Use Change Without Prior Approval

Source DOK
41




APPENDIX 4

             Sample Questionnaire
42




                    ckf6{d]G6sf OsfO{ wgLx?sf] nflu k|ZgfjnL
ckf6{d]G6sf] gfd M                                             :yfg M
O{sfO{ wgLsf] gfd M                                   Joj;fo M
cjwL M      jif{
!_ vfg]kfgL, lah'nL tyf ;'/Iff cj:yf s:tf] 5 <
      s_ vfg]kfgL M
      v_ lah'nL M
      u_ ;'/Iff M
@_cfunfuL, e'sDk cflbsf] j]nfdf s;/L ;'/IfLt x'g] jf/]df pknAw ;'/Iff
   lalwx? jf/]df oxf+ egfO{ s] 5 <


$_ ckf6{d]G6sf] a;fO{ b]lv ;Gt'i6 x'g' x'G5 t<


#_ ckf6{d]G6 a;fO{sf] d'Vo –d'Vo ;d:ofx? s] s] 5g <




%_ ckf6{d]G6sf] a;fO{ k|efjsf/L agfpg s] s] ug{' knf{ <
43




                                                                                                                                                                                                                                                                                                           snz Pkf6{d]G6, tfxfrn, sf7df08f}df ePsf] k|zgf]Q/sf] ;f/f+z

OsfO{ wgLsf] gfd,        vfg]kfgLsf]                                                                              ljh'nLsf]                                                                                        ;'/Iffsf]                                                                cfunfuL,     e'sDksf]       ;dodf   ckf6{d]G6 a;fO{sf] d'Vo d'Vo ;:ofx?            ckf6{d]G6sf] a;fO{ b]lv slt           ckf6{d]G6sf] a;fO{ k|efsf/L jgfpg s] ug{
o'lg6 g+=, Joj;fo        cj:yf jf/]                                                                               cj:yf jf/]                                                                                       cj:yf jf/]                                                               ;'/lIft x'g] pknAw k|jGwx?                                                         ;Gt'i6 x'g' x'G5                      knf{
tyf       ckf6{d]G6df
a;]sf] cjlw

dx]z cu|jfn, O2,                                                                                                                                                                                                                                                                            ;'/lIft :yfg 5}g . k|ofKt :yfg      kmf]x/ kmfNg] k|jGw /fd|f] 5}g . Parking sf]   @)!!            l8;]Dj/        ;Dd    aRrfxx?sf] nflu Play ground sf]
                         vfgsf] nfllu Acqua Guard, cfKmg} Joj:yf 5 . cGosfdsf] nflu af]l/Ësf] kfgL



                                                                                                                  Backup sf] nflu h]g]/]6/ eP klg, Diesel gePsf] j]nf tyf break down sf]



                                                                                                                                                                                                                   Society sf] nflu cfkmg} security team agfPsf] n] ;'/Iff Joj:yf l7s 5 .

Jofkf/, !=% jif{                                                                                                                                                                                                                                                                            5}g .                               ;d:of 5 . Unit handover gubf{                  ownership                 x:tfGt/0f   Joj:yf x'g' kg]{ . kmf]x/d}nf Joj:yfkg x'g' kg]{
                                                                                                                                                                                                                                                                                                                                ;femf ;d:of 5 . Generator /fVg]                x'g'kg]{ t/ ePsf] 5}g . l7s} 5 .      . hUufsf] dfkb08 cg';f/ Building
                                                                                                                                                                                                                                                                                                                                proper :yfg 5}g .                                                                    construction sf] :jLs[tL lbg' kg]{ .

/fhg        ltldN;]gf,                                                                                                                                                                                                                                                                      @ j6f Fire Exit 5g . GF             Socity btf{ eP klg unit sf] nfnk'hf{           ;Gt'i6g} 5' .                         Society bQf{ ;DjGwL tyf handover
D9, Jofkf/,!=% jif{                                                                                                                                                                                                                                                                         df fire extingusher sf]             kfPsf] 5}g h;n] ubf{ PAN g+= lng                                                     ug]{ ;DjGwL sfg'gdf ;'wf/ x'g' kg]{ . t'?Gt
                                                                                                                                                                                                                                                                                            Joj:yf 5 .                          ;lsPsf] 5}g .                                                                        nfnk'hf{ kfpg' kg]{ .

ls/0f cu|jfn, E7,                                                                                                                                                                                                                                                                           e'sDk k|'km 5 . @ j6f Fire          k|ofKt v'nf 7f+p 5}g .                         ;Gt'i6g} 5' . kmfobf a9L 5 .          k};f p7fP/ yk sfdx? ug]{ u/]sf 5f}+
Jofkf/,!=% jif{                                                                                                                                                                                                                                                                             Exit 5g .                                                                                                                .Pkf6{d]G6 cuf8Lsf] ;8sdf ;'wf/ x'g' kg]{ .

k|eft s'df/ ;/f{km,                                                                                                                                                                                                                                                                         Emergency sIf k|To]s                ;j} l7s 5 .                                    ;Gt'i6g} 5' .                         ;j} /fd|} 5 s]xL ug{ kb}{g .
F7, Jofkf/, ! jif{                                                                                                                                                                                                                                                                          tNnfdf 5 .
                                                                                                                                                                                           j]nf light off x'G5 .




;lGhj zfSo, D6,                                                                                                                                                                                                                                                                             Emergency             sIf     tyf   ;d:of vf;} s]xL 5}g .                          ;Gt'i6 5' .                           Society bQf{ ;DjGwL tyf handover
Jofkf/,!=% jif{                                                                                                                                                                                                                                                                             k|To]s       tNnfdf          Fire                                                                                        ug]{ ;DjGwL sfg'gdf ;'wf/ x'g' kg]{ .
                                                                                                     Joj:yf 5 .




                                                                                                                                                                                                                                                                                            exetinguisher sf] Joj:yf
                                                                                                                                                                                                                                                                                            5.
44




OsfO{ wgLsf] gfd,       vfg]kfgLsf]                                                                            ljh'nLsf]                                                                                        ;'/Iffsf]                                                                cfunfuL,     e'sDksf]    ;dodf      ckf6{d]G6 a;fO{sf] d'Vo d'Vo ;:ofx?        ckf6{d]G6sf] a;fO{ b]lv slt   ckf6{d]G6sf] a;fO{ k|efsf/L jgfpg s] ug{
o'lg6 g+=, Joj;fo       cj:yf jf/]                                                                             cj:yf jf/]                                                                                       cj:yf jf/]                                                               ;'/lIft x'g] pknAw k|jGwx?                                                     ;Gt'i6 x'g' x'G5              knf{
tyf       ckf6{d]G6df
a;]sf] cjlw

cdg s'df/ cu|jfn,                                                                                                                                                                                                                                                                        Emergency sIf tyf k|To]s            ;j}nfO{ ldnfP/ lx8g ufx««f] 5 . cGo ;j}    ;Gt'i6 5' .                   ;'ljwf Joj:yfkgdf ;j}sf] cfly{s ;xof]u
                                                                                                               Backup sf] nflu h]g]/]6/ eP klg, Diesel gePsf] j]nf tyf break down sf] j]nf light
                        vfgsf] nfllu Acqua Guard, cfKmg} Joj:yf 5 . cGosfdsf] nflu af]l/Ësf] kfgL Joj:yf 5 .




G7, Jofkf/, @ jif{                                                                                                                                                                                                                                                                       tNnfdf Fire exetinguisher           /fd|f] . ;d:of sd kmfobf a9L 5 .                                         cfjZos 5 .
                                                                                                                                                                                                                Society sf] nflu cfkmg} security team agfPsf] n] ;'/Iff Joj:yf l7s 5 .

                                                                                                                                                                                                                                                                                         sf] Joj:yf 5 .

;'lw/ s'df/ cu|jfn,                                                                                                                                                                                                                                                                      Emergency sIf tyf k|To]s            Vff;} ;d:of 5}g .                          ;Gt'i6 5' .                   Society btf{df PAN g+= lbg grfx]sf] .
H5, Jofkf/, @ jif{                                                                                                                                                                                                                                                                       tNnfdf Fire exetinguisher                                                                                    t'?Gt nfnk'hf{ kfpg' kg]{ .
                                                                                                                                                                                                                                                                                         sf] Joj:yf 5 .

;~ho cu|jfn, C7,                                                                                                                                                                                                                                                                         Emergency sIf tyf k|To]s            Vff;} ;d:of 5}g .                          ;Gt'i6 5' .                   Society btf{df PAN g+= lbg grfx]sf] .
Jofkf/, !=% jif{                                                                                                                                                                                                                                                                         tNnfdf Fire exetinguisher                                                                                    t'?Gt nfnk'hf{ kfpg' kg]{ .
                                                                                                                                                                                                   off x'G5 .




                                                                                                                                                                                                                                                                                         sf] Joj:yf 5 .

;~ho cu|jfn, C3,                                                                                                                                                                                                                                                                         a}sNkLs     jf6f]   5,       Fire   Socity btf{ eP klg unit sf] nfnk'hf{       l7s} 5 .                      Apartment maintenance sf] lhDdf
Jofkf/, !=% jif{                                                                                                                                                                                                                                                                         exetinguisher sf] Joj:yf 5          kfPsf] 5}g h;n] ubf{ PAN g+= lng                                         society nfO{ lbg' kb{5 . t'?Gt nfnk'hf{
                                                                                                                                                                                                                                                                                         .                                   ;lsPsf] 5}g .                                                            kfpg' kg]{ .

of]u]z uf]on, Jofkf/                                                                                                                                                                                                                                                                     a}sNkLs     jf6f]   5,       Fire   laN8/n] tf]s]sf] ;do leq lgdf{0f gug]{,    ;Gt'i6 5' .                   Apartment maintenance sf] lhDdf
                                                                                                                                                                                                                                                                                         exetinguisher sf] Joj:yf 5          jfrf u/]sf] ;'ljwfx? Glbg] / d'Vodf                                      society nfO{ lbg' kb{5 .
                                                                                                                                                                                                                                                                                         .                                   kfls{Ë, ;'/Iff, v]ns'bsf] ;'ljwf / cGodf
                                                                                                                                                                                                                                                                                                                             maintenance society nfO{ lhDdf
                                                                                                                                                                                                                                                                                                                             nufO{ lbg' kb{5 .
45




APPENDIX 5

             Organization Charts
46




                                                               Director General




           DDG                                DDG                       DDG
         Urban Dev                       Building Divison
                                                                   Housing Divison
          Divison

          Physical Planning &                Building                  Housing        Division Office       Building
          Urban Dev                          Construction
                                                                                         (24 Nos.)       construction &
                                             Building Code                                                maintenance
          Urban Environment                                            Planning                             Divison
                                             Building
           Small Town
                                                                       Monitoring
                                             Maintenance &
          Municipality                       Evaluation                                                  Class II
                                                                                      Class I
                                             Standardization           Foreign Aid    Division Chief     Division
          Stastical &                                                  Coordination                      Chief
          GIS

Building                  General               Fiscal                                                  Procuremen        Legal
Technology              Administration                                                                  t Unit
                                             Administration
Research &                 & HR
Training Center
47




Figure 14: Jurisdiction of DUDBC division office (source DUDBC)
48




Figure 15: Organization Chart of DOK

           (source DOK)
49

More Related Content

What's hot

Aranya Low Cost Housing
Aranya Low Cost HousingAranya Low Cost Housing
Aranya Low Cost Housing
Ankita Kolamkar
 
Development control rules and regulation
Development control rules and regulationDevelopment control rules and regulation
Development control rules and regulation
MANINANDANSAHU
 
F.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye LawsF.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye LawsAr. Md Shahroz Alam
 
Masters Thesis Report _ Skyscraper _ High rise Mixed use Development
Masters Thesis Report _ Skyscraper _ High rise Mixed use DevelopmentMasters Thesis Report _ Skyscraper _ High rise Mixed use Development
Masters Thesis Report _ Skyscraper _ High rise Mixed use Development
Ar. M. Senthil [ senthilmani ]
 
Neighbourhood planning
Neighbourhood planningNeighbourhood planning
Neighbourhood planning
College Of Engineering, Pune
 
Housing Presentation
Housing Presentation Housing Presentation
Housing Presentation
Dhanya Pravin
 
Cidco- NAVI MUMBAI
Cidco- NAVI MUMBAICidco- NAVI MUMBAI
Cidco- NAVI MUMBAI
Dhawal Kataria
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuation
Kavin Raval
 
Affordable Housing
Affordable HousingAffordable Housing
Affordable Housing
Dr K M SONI
 
Stanlee's presentation on affordable housing
Stanlee's presentation on affordable housingStanlee's presentation on affordable housing
Stanlee's presentation on affordable housing
StanLee GeorGe
 
Low Cost Housing India
Low Cost Housing IndiaLow Cost Housing India
Low Cost Housing India
Rohan Zagade
 
Charles Correa
Charles CorreaCharles Correa
Charles Correa
Mohamed Faseehun
 
Planning concepts
Planning conceptsPlanning concepts
Planning conceptsctlachu
 
Incremental housing
Incremental housingIncremental housing
Incremental housing
Rajat Nainwal
 
GARDEN CITY(garden city concept)
GARDEN CITY(garden city concept)GARDEN CITY(garden city concept)
GARDEN CITY(garden city concept)
ARCHITECTURE SCHOOL
 
Commonwealth Games Village
Commonwealth Games VillageCommonwealth Games Village
Commonwealth Games Village
Roushan Gupta
 
Architecture- easements and valuations
Architecture- easements and valuationsArchitecture- easements and valuations
Architecture- easements and valuations
Aditi Garg
 
Case study on Apartment
Case study on ApartmentCase study on Apartment
Case study on Apartment
Asmit Kiran Bhattarai
 
Belapur Incremental housing - A case study
Belapur Incremental housing - A case studyBelapur Incremental housing - A case study
Belapur Incremental housing - A case study
Rithika Ravishankar
 
HOUSING LITERATURE STUDY M.ARCH CCA
HOUSING LITERATURE STUDY M.ARCH CCAHOUSING LITERATURE STUDY M.ARCH CCA
HOUSING LITERATURE STUDY M.ARCH CCA
Ar. Prerna Chouhan
 

What's hot (20)

Aranya Low Cost Housing
Aranya Low Cost HousingAranya Low Cost Housing
Aranya Low Cost Housing
 
Development control rules and regulation
Development control rules and regulationDevelopment control rules and regulation
Development control rules and regulation
 
F.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye LawsF.A.R., Ground Coverage and Height Permissible as per Bye Laws
F.A.R., Ground Coverage and Height Permissible as per Bye Laws
 
Masters Thesis Report _ Skyscraper _ High rise Mixed use Development
Masters Thesis Report _ Skyscraper _ High rise Mixed use DevelopmentMasters Thesis Report _ Skyscraper _ High rise Mixed use Development
Masters Thesis Report _ Skyscraper _ High rise Mixed use Development
 
Neighbourhood planning
Neighbourhood planningNeighbourhood planning
Neighbourhood planning
 
Housing Presentation
Housing Presentation Housing Presentation
Housing Presentation
 
Cidco- NAVI MUMBAI
Cidco- NAVI MUMBAICidco- NAVI MUMBAI
Cidco- NAVI MUMBAI
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuation
 
Affordable Housing
Affordable HousingAffordable Housing
Affordable Housing
 
Stanlee's presentation on affordable housing
Stanlee's presentation on affordable housingStanlee's presentation on affordable housing
Stanlee's presentation on affordable housing
 
Low Cost Housing India
Low Cost Housing IndiaLow Cost Housing India
Low Cost Housing India
 
Charles Correa
Charles CorreaCharles Correa
Charles Correa
 
Planning concepts
Planning conceptsPlanning concepts
Planning concepts
 
Incremental housing
Incremental housingIncremental housing
Incremental housing
 
GARDEN CITY(garden city concept)
GARDEN CITY(garden city concept)GARDEN CITY(garden city concept)
GARDEN CITY(garden city concept)
 
Commonwealth Games Village
Commonwealth Games VillageCommonwealth Games Village
Commonwealth Games Village
 
Architecture- easements and valuations
Architecture- easements and valuationsArchitecture- easements and valuations
Architecture- easements and valuations
 
Case study on Apartment
Case study on ApartmentCase study on Apartment
Case study on Apartment
 
Belapur Incremental housing - A case study
Belapur Incremental housing - A case studyBelapur Incremental housing - A case study
Belapur Incremental housing - A case study
 
HOUSING LITERATURE STUDY M.ARCH CCA
HOUSING LITERATURE STUDY M.ARCH CCAHOUSING LITERATURE STUDY M.ARCH CCA
HOUSING LITERATURE STUDY M.ARCH CCA
 

Viewers also liked

10. Nepal standard formulation process
10. Nepal standard formulation process10. Nepal standard formulation process
10. Nepal standard formulation process
Centre For Rural Technology, Nepal
 
Municipal periodic plan in nepalese context [compatibility mode]
Municipal periodic plan in nepalese context [compatibility mode]Municipal periodic plan in nepalese context [compatibility mode]
Municipal periodic plan in nepalese context [compatibility mode]
Freelancing - Urban development and Planning
 
Kanchanjunga apartment. Passive sustainable design. Case study
Kanchanjunga apartment. Passive sustainable design. Case studyKanchanjunga apartment. Passive sustainable design. Case study
Kanchanjunga apartment. Passive sustainable design. Case study
AlHosn University
 
Present status of apartment building approval and construction
Present status of apartment building approval and constructionPresent status of apartment building approval and construction
Present status of apartment building approval and constructionBinay Shrestha
 
Construction Entrepreneurs in Nepal
 Construction Entrepreneurs in Nepal Construction Entrepreneurs in Nepal
Construction Entrepreneurs in Nepal
Suresh Adhikari
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
Binay Shrestha
 
site analysis
site analysis site analysis
site analysis Arch Mgaya
 
2013 - Mon Tresor master plan
2013 - Mon Tresor master plan 2013 - Mon Tresor master plan
2013 - Mon Tresor master plan
Jacques Van Dinteren
 
McQuinn case study
McQuinn case studyMcQuinn case study
McQuinn case studywkmcquinn
 
Renovia Apartment Case study 7-15
Renovia Apartment Case study  7-15Renovia Apartment Case study  7-15
Renovia Apartment Case study 7-15Brian Johnson
 
Seismic evaluation of rc frame with brick masonry infill walls
Seismic evaluation of rc frame with brick masonry infill wallsSeismic evaluation of rc frame with brick masonry infill walls
Seismic evaluation of rc frame with brick masonry infill walls
eSAT Journals
 
Project 4 - Pre cast concrete 10 storey Building design
Project 4 - Pre cast concrete 10 storey Building designProject 4 - Pre cast concrete 10 storey Building design
Project 4 - Pre cast concrete 10 storey Building designDinesha Kuruppuarachchi
 
Code approaches to seismic design of masonry infiled rc frames
Code approaches to seismic design of masonry infiled rc framesCode approaches to seismic design of masonry infiled rc frames
Code approaches to seismic design of masonry infiled rc frames
Binay Shrestha
 
Behavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loadingBehavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loading
Binay Shrestha
 
056 Labour Productivity
056 Labour Productivity056 Labour Productivity
056 Labour Productivity
Dr Fereidoun Dejahang
 
021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)
Dr Fereidoun Dejahang
 
Nepal's Urban Planning and Dvelopment
Nepal's Urban Planning and DvelopmentNepal's Urban Planning and Dvelopment
Nepal's Urban Planning and Dvelopment
Freelancing - Urban development and Planning
 
RIBA World Cities Saadiyat
RIBA World Cities SaadiyatRIBA World Cities Saadiyat
RIBA World Cities Saadiyat
guybriggs
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
Essam Lotffy, PMP®, CCP®
 

Viewers also liked (20)

10. Nepal standard formulation process
10. Nepal standard formulation process10. Nepal standard formulation process
10. Nepal standard formulation process
 
Municipal periodic plan in nepalese context [compatibility mode]
Municipal periodic plan in nepalese context [compatibility mode]Municipal periodic plan in nepalese context [compatibility mode]
Municipal periodic plan in nepalese context [compatibility mode]
 
Kanchanjunga apartment. Passive sustainable design. Case study
Kanchanjunga apartment. Passive sustainable design. Case studyKanchanjunga apartment. Passive sustainable design. Case study
Kanchanjunga apartment. Passive sustainable design. Case study
 
Present status of apartment building approval and construction
Present status of apartment building approval and constructionPresent status of apartment building approval and construction
Present status of apartment building approval and construction
 
Construction Entrepreneurs in Nepal
 Construction Entrepreneurs in Nepal Construction Entrepreneurs in Nepal
Construction Entrepreneurs in Nepal
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
 
site analysis
site analysis site analysis
site analysis
 
2013 - Mon Tresor master plan
2013 - Mon Tresor master plan 2013 - Mon Tresor master plan
2013 - Mon Tresor master plan
 
McQuinn case study
McQuinn case studyMcQuinn case study
McQuinn case study
 
Renovia Apartment Case study 7-15
Renovia Apartment Case study  7-15Renovia Apartment Case study  7-15
Renovia Apartment Case study 7-15
 
Seismic evaluation of rc frame with brick masonry infill walls
Seismic evaluation of rc frame with brick masonry infill wallsSeismic evaluation of rc frame with brick masonry infill walls
Seismic evaluation of rc frame with brick masonry infill walls
 
Project 4 - Pre cast concrete 10 storey Building design
Project 4 - Pre cast concrete 10 storey Building designProject 4 - Pre cast concrete 10 storey Building design
Project 4 - Pre cast concrete 10 storey Building design
 
Code approaches to seismic design of masonry infiled rc frames
Code approaches to seismic design of masonry infiled rc framesCode approaches to seismic design of masonry infiled rc frames
Code approaches to seismic design of masonry infiled rc frames
 
Behavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loadingBehavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loading
 
056 Labour Productivity
056 Labour Productivity056 Labour Productivity
056 Labour Productivity
 
Thesis proposal
Thesis proposalThesis proposal
Thesis proposal
 
021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)
 
Nepal's Urban Planning and Dvelopment
Nepal's Urban Planning and DvelopmentNepal's Urban Planning and Dvelopment
Nepal's Urban Planning and Dvelopment
 
RIBA World Cities Saadiyat
RIBA World Cities SaadiyatRIBA World Cities Saadiyat
RIBA World Cities Saadiyat
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 

Similar to Present status of apartment building approval and construction

jain university Project Report
jain university Project Reportjain university Project Report
jain university Project ReportSukesh Shetty
 
Watershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdfWatershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdf
ravi936752
 
20090104 oecd china country note second draft -2_
20090104 oecd china country note second draft -2_20090104 oecd china country note second draft -2_
20090104 oecd china country note second draft -2_Lichia Saner-Yiu
 
Satya final project
Satya final projectSatya final project
Satya final project
EY
 
Impact assessment-study-dit
Impact assessment-study-ditImpact assessment-study-dit
Impact assessment-study-dit
Girma Biresaw
 
Developing and Implementing Competency-based ICT Training for Teachers: A Cas...
Developing and Implementing Competency-based ICT Training for Teachers: A Cas...Developing and Implementing Competency-based ICT Training for Teachers: A Cas...
Developing and Implementing Competency-based ICT Training for Teachers: A Cas...
eraser Juan José Calderón
 
Fulltext01
Fulltext01Fulltext01
Fulltext01
Farhin Kazi
 
Fet business studies gr 10 12 - we_b#c0fc
Fet   business studies gr 10 12 - we_b#c0fcFet   business studies gr 10 12 - we_b#c0fc
Fet business studies gr 10 12 - we_b#c0fc
Celtia Tladi
 
THE DIGITAL TURN Pathways for higher education in the digital age
THE DIGITAL TURN Pathways for higher education in the digital ageTHE DIGITAL TURN Pathways for higher education in the digital age
THE DIGITAL TURN Pathways for higher education in the digital age
eraser Juan José Calderón
 
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Chris Delepierre
 
Clancy95barriers geetal
Clancy95barriers geetalClancy95barriers geetal
Clancy95barriers geetal
Shridhar Wangikar
 
Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...
Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...
Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...
Ihsan Nadir
 
Report
ReportReport
QP_PRACTICAL_GUIDE_08062018_online (1).pdf
QP_PRACTICAL_GUIDE_08062018_online (1).pdfQP_PRACTICAL_GUIDE_08062018_online (1).pdf
QP_PRACTICAL_GUIDE_08062018_online (1).pdf
albeetar11
 
“Bank Finance in Real Estate – Significance and Impact” (India)
“Bank Finance in Real Estate – Significance and  Impact” (India)“Bank Finance in Real Estate – Significance and  Impact” (India)
“Bank Finance in Real Estate – Significance and Impact” (India)
RITESH BAFNA
 
Hidoe student transportation study report
Hidoe student transportation study reportHidoe student transportation study report
Hidoe student transportation study report
Honolulu Civil Beat
 
Flow And Throughput Improvement
Flow And Throughput ImprovementFlow And Throughput Improvement
Flow And Throughput Improvement
Ramon Saviñon
 
Contoh Report Latihan Industri
Contoh Report Latihan IndustriContoh Report Latihan Industri
Contoh Report Latihan Industri
Dhom Nawhki
 

Similar to Present status of apartment building approval and construction (20)

jain university Project Report
jain university Project Reportjain university Project Report
jain university Project Report
 
Watershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdfWatershed Development in India An Approach Evolving through Experience_0.pdf
Watershed Development in India An Approach Evolving through Experience_0.pdf
 
20090104 oecd china country note second draft -2_
20090104 oecd china country note second draft -2_20090104 oecd china country note second draft -2_
20090104 oecd china country note second draft -2_
 
Satya final project
Satya final projectSatya final project
Satya final project
 
Impact assessment-study-dit
Impact assessment-study-ditImpact assessment-study-dit
Impact assessment-study-dit
 
Developing and Implementing Competency-based ICT Training for Teachers: A Cas...
Developing and Implementing Competency-based ICT Training for Teachers: A Cas...Developing and Implementing Competency-based ICT Training for Teachers: A Cas...
Developing and Implementing Competency-based ICT Training for Teachers: A Cas...
 
Fulltext01
Fulltext01Fulltext01
Fulltext01
 
caps document
caps documentcaps document
caps document
 
Fet business studies gr 10 12 - we_b#c0fc
Fet   business studies gr 10 12 - we_b#c0fcFet   business studies gr 10 12 - we_b#c0fc
Fet business studies gr 10 12 - we_b#c0fc
 
Tn vision 2023
Tn vision 2023Tn vision 2023
Tn vision 2023
 
THE DIGITAL TURN Pathways for higher education in the digital age
THE DIGITAL TURN Pathways for higher education in the digital ageTHE DIGITAL TURN Pathways for higher education in the digital age
THE DIGITAL TURN Pathways for higher education in the digital age
 
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...
 
Clancy95barriers geetal
Clancy95barriers geetalClancy95barriers geetal
Clancy95barriers geetal
 
Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...
Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...
Elimination of Bonded Labour due to Bondage in the Brick Kilns in 4 Districts...
 
Report
ReportReport
Report
 
QP_PRACTICAL_GUIDE_08062018_online (1).pdf
QP_PRACTICAL_GUIDE_08062018_online (1).pdfQP_PRACTICAL_GUIDE_08062018_online (1).pdf
QP_PRACTICAL_GUIDE_08062018_online (1).pdf
 
“Bank Finance in Real Estate – Significance and Impact” (India)
“Bank Finance in Real Estate – Significance and  Impact” (India)“Bank Finance in Real Estate – Significance and  Impact” (India)
“Bank Finance in Real Estate – Significance and Impact” (India)
 
Hidoe student transportation study report
Hidoe student transportation study reportHidoe student transportation study report
Hidoe student transportation study report
 
Flow And Throughput Improvement
Flow And Throughput ImprovementFlow And Throughput Improvement
Flow And Throughput Improvement
 
Contoh Report Latihan Industri
Contoh Report Latihan IndustriContoh Report Latihan Industri
Contoh Report Latihan Industri
 

Present status of apartment building approval and construction

  • 1. PRESENT STATUS OF APARTMENT BUILDING APPROVAL AND CONSTRUCTION IN KATHMANDU VALLEY Study Report SUBMITTED TO NEPAL ADMINISTRATIVE STAFF COLLEGE JAWALAKHEL, LALITPUR, NEPAL In partial fulfillment of “Advanced Course on Management and Development” for Class II Officers of the Government of Nepal (Paush 23 – Falgun 10, 2069) SUBMITTED BY: Binay Charan Shrestha (DUDBC) Dilip Kumar Sadaula (DSCWM) Kamaldeo Prasad Shah (DoR) Mahendra Dhose Adhikari (MoHP) Rudra Nath Devkota (MoHA) Sanjaya Dhungel (WECS) FALGUN 2069
  • 2. ACKNOWLEDGEMENT We would like to extend our sincere gratitude to respective Ministries for providing opportunity to take part in the training program and Nepal Administrative Staff College for providing the training. We are grateful to Division Chief Mr. Shiv Hari Sharma, Engineer Mr. Himal KC and Architect Mr. Rajendra Khatiwada of Department of Urban Development and Building Construction, Division office Kathmandu, for providing data / information on the topic and also for extending continued support to complete the study. We are very much thankful to Mr. Ishwari Prasad Ghimire and his team members Mr. Santosh Koirala, Mr. Hari Lal Gyawali and Ms. Achala Dahal for their kind cooperation during the whole training period. We would also like to convey our sincere thanks to the respondents from the Kalash Apartment, Tahachal, Kathmandu for providing the insight of the apartment living. Finally, the study team would like to express their sincere gratitude to all who directly or indirectly helped in bringing this report in the present form. The Study Team
  • 3. Abstract The study entitled “Present Status of Apartment Building Approval and Construction in Kathmandu Valley” has been undertaken as a project work in the context of completing “Advanced Course on Management and Development” for class II officers of Government of Nepal conducted by Nepal Administrative Staff College during the period of Paush 23 to Falgun 10, 2069. Job opportunities and availability of physical facilities causes rapid increase in population in the urban areas. The increase in population demands the housing facilities and accordingly the construction of multi-story buildings/apartments are taking place. Apartment construction is providing the business opportunities for the builders, financial institutions and manufacturers of construction materials. Realizing the need to provide safe as well as quality living standard housing facilities, government has designed the procedures and mandated different agencies as a regulators. This study is focused mainly in examining the apartment buildings approval procedures as well as monitoring and supervision process currently practiced by DOK. The relevant primary data are collected from residents of Kalash Apartment through questionnaire survey and secondary data are collected from DUDBC, DOK. The collected data were analyzed and inferences were drawn. Till Paush 2069, sixty-four apartments have obtained approval from DOK in the Kathmandu Valley out of which thirteen apartments are in operation with completion certificate and 15 are on operation without obtaining completion certificate. 28 are under construction and 8 apartments have yet to start construction. There are many agencies (at least 6) involved in apartment approval process. DOK lies at the core, but is working under the condition of resource constraint. Many issues have emerged as pertinent and challenging in this sector. Some of them are related to project management while other is ethical.
  • 4. The apartment construction processes have been found to be streamlined gradually. However, enhancements of capacity of regulating agencies are yet to be in place to provide safe and quality apartments to the residents.
  • 5. i TABLE OF CONTENT TABLE OF CONTENT .................................................................................................. i  LIST OF TABLES ....................................................................................................... iii  LIST OF FIGURES ..................................................................................................... iii  LIST OF ABBREVIATIONS ....................................................................................... iv  1. INTRODUCTION ..................................................................................................... 1  1.1  Background ..................................................................................................... 1  1.2  Objectives ........................................................................................................ 3  1.3   Methodology ................................................................................................... 4  1.4   Limitations ...................................................................................................... 4  2. INTRODUCTION OF THE ORGANIZATION ....................................................... 5  2.1  Introduction ..................................................................................................... 5  2.2  Vision .............................................................................................................. 7  2.3  Objectives & Strategies ................................................................................... 7  3. DATA PRESENTATION & ANALYSIS ................................................................. 9  3.1  Early Initiatives ............................................................................................... 9  3.2  Approved Apartments ..................................................................................... 9  3.3  Apartments Locations and Unit Details ........................................................ 10  3.4  Apartments on Approval Process .................................................................. 11  3.5  Apartment Approval Procedure .................................................................... 12  3.5.1  Planning Permit ...................................................................................... 13  3.5.2  Environmental Approval ........................................................................ 14  3.5.3  Apartment Approval .............................................................................. 14 
  • 6. ii 3.6  Monitoring and Supervision .......................................................................... 16  3.7  Issuance of Completion Certificate ............................................................... 17  3.8  APARTMENT LIVING CONDITION ........................................................ 17  3.8  KEY ISSUES ................................................................................................ 18  3.8.1  Time Taken for Approval Process ......................................................... 18  3.8.2  Project Management Issues.................................................................... 19  3.8.3  Insufficient Resources ............................................................................ 19  3.8.4  `Unethical Practices ............................................................................... 20  4. MAJOR FINDINGS, CONCLUSION & RECOMMENDATIONS ....................... 21  4.1  Major Findings .............................................................................................. 21  4.2  Conclusion ..................................................................................................... 22  4.3  Recommendation ........................................................................................... 22  Bibliography ................................................................................................................ 24  APPENDICES ............................................................................................................. 25  Appendix 1 ................................................................................................................... 26  Appendix 2 ................................................................................................................... 31  Appendix 3 ................................................................................................................... 34  Appendix 4 ................................................................................................................... 41  Appendix 5 ................................................................................................................... 45 
  • 7. iii LIST OF TABLES Table 1: Status of the 64 Apartments having apartment approval ................................. 9  Table 2 Number of apartments inside and outside the ring road ................................. 10  Table 3: Status of apartment proposals on approval process ....................................... 11  Table 4: Screening Criteria .......................................................................................... 14  LIST OF FIGURES Figure 1: Location of apartments within the Kathmandu valley ................................. 10  Figure 2: District wise distribution of approved apartments ....................................... 11  Figure 3: Apartment Approval Procedure.................................................................... 13  Figure 4: Kalash Apartment ......................................................................................... 35  Figure 5: Fire Escape in Kalash ................................................................................... 35  Figure 6: Fire Hose in Kalash ...................................................................................... 35  Figure 7: Questionnaire survey .................................................................................... 35  Figure 8:Violation of Planning Permit ......................................................................... 36  Figure 9: Change in Approved Design ........................................................................ 37  Figure 10: Inadequate Safety Measure ........................................................................ 38  Figure 11: Partial Dismantling of Major Structural Member ...................................... 39  Figure 12: Use Change Without Prior Approval ......................................................... 40  Figure 13: Organization Chart of DUDBC .................................................................. 46  Figure 14: Jurisdiction of DUDBC division office (source DUDBC) ......................... 47  Figure 15: Organization Chart of DOK ....................................................................... 48 
  • 8. iv LIST OF ABBREVIATIONS CANN Civil Aviation authority of Nepal DOK Division Office Kathmandu DUDBC Department of Urban Development and Building Construction EIA Environmental Impact Assessment IEE Initial Environmental Examination KVDA Kathmandu Valley Development Authority KVWSMB Kathmandu Valley water supply Management Board MoPPW Ministry of Physical Planning & Works MoUD Ministry of Urban Development MoSTE Ministry of Science, Technology & Environment NNBC Nepal National Building Code NRRC Nepal Risk Reduction Consortium OJHA Ownership of Joint Housing Act OJHR Ownership of Joint Housing Regulation
  • 9. 1 CHAPTER 1 1. INTRODUCTION 1.1 BACKGROUND The study entitled “Present Status of Apartment Building Approval and Construction in Kathmandu Valley “has been undertaken as a project work in the context of completing “Advanced Course on Management and Development” conducted by Nepal Administrative Staff College from Paush 23 to Falgun 10, 2069. The National Census (2068 B.S.) revealed that the total population in Nepal is 26,494,504. Out of which the male and female population are 48.50% and 51.50% respectively. The populations settling in the urban areas are 17.07%.The density of population in the urban area is 1381 compared to 153 persons per square kilometer in rural area. Though Nepal has the lowest urbanization rate in south Asia at 14 per cent its urban growth rate is 6.4 per cent which is the highest in south-Asia. In the last decade population growth in the urban areas was 3 times that of the country as a whole. Kathmandu has high population density (4416 person per square kilometer) compared to other part of the country. Nepal has a total of 5,423,297 households, of which 85.26% and 12.81% families are residing in their own house and rented houses respectively. The total number of houses/buildings or residential structures until 2068 are 4,768,196. The development pace between rural and urban parts of the country resulted people migrating to urban areas for better opportunities and quality life. Opportunities for self-employment in enterprises have attracted people in urban areas. Health, education and other facilities are well developed in urban areas compared to rural. The migration of the large rural population from the countryside and the influx of foreigner for business and other purposes have created a need for additional housing facilities. The available land in the urban areas is limited to provide housing facilities to the growing population. In order to cater the housing needs of increasing population, multi-story buildings in the forms of collective and apartment housings are being developed. People residing in urban areas have less time to arrange the various physical facilities and security measures on their own. Further, those residing
  • 10. 2 in the individual houses also prefer to move into the apartments for availing better security and physical facilities. The good earning populations, who are unable to spend time for building their house are also seeking for the readymade apartments/buildings. These factors necessitate the need for the apartment buildings. Increase in demand of housing will continue as the new generation prefers nuclear families. The growing demand of the apartments has provided the opportunities for business communities to diverse the investment in the multi-story building sector. Likewise, the commercial banks, financial institutions and cooperatives also took this as an opportunity to diversify the loan portfolio. The construction materials manufacturers and suppliers are also attracted in this sector. The skilled and unskilled construction workers also prefer to work in multi-story building construction as it provides long term employment with assured wages. Thus, the builders, financial institutions and manufacturers are putting collaborative efforts to get cash benefits from the housing business. Building construction around a decade ago was completely a personal matter. There is a tradition of constructing houses through self-effort and utilizing own resources and means. The local municipalities were the only authority to give approval to construct a house after examining the drawings and inspecting the construction site. The limited technical and financial resources in the municipalities has posed a problem to examine the overall aspects of construction that includes environmental assessment, structural design, sanitary, water supply and plumbing system, firefighting system, electrical system and design etc. in details. These factors are of utmost importance to maintain safe and quality living. Considering these aspects, government has formulated 'National Shelter Policy, 2012' with the vision of providing housing, which is safe, adequate and as per living standard to all. Change in attitude and working style of both regulating authorities and construction entrepreneurs are the prime factors for translating the vision into reality. Multiple agencies are involved in providing clearance to the builder for apartment construction. Ministry of Science, Technology and Environment (MoSTE) is responsible for Environmental assessment, Kathmandu Valley Development
  • 11. 3 Authority (KVDA) is for providing planning permit, Civil Aviation Authority (CAAN) is for clearing safe flying zone, Kathmandu Valley Water Supply and Management Board (KVWSMB) for groundwater use and Department of Urban Development and Building Construction (DUDBC) granting approval for apartment construction. After the clearance from these agencies, final approval is given by the concerned local government (Municipalities / Village Development Committee(VDC)). In the construction of apartments, on the one hand multiple regulatory agencies and on the other several builders/companies from different background are involved. The objective of regulatory agencies is to ensure compliance of specified design as well as quality construction and safety measures whereas, the objective of the builders/companies is to complete the construction at earliest with minimum cost ensuring higher profit. The regulating agencies should sincerely adhere to the stated policy and procedure to approve, monitor and supervise the construction process. Likewise, the honest effort of the builders is required for timely completion and quality of construction. In this context, the team has identified the apartment construction process including monitoring and supervision as a pertinent issue and decided to undertake as a study project. 1.2 OBJECTIVES The general objective of the study is to review the present status of apartment construction industry in Kathmandu valley. The specific objectives are:  To assess the apartment construction approval procedures.  To examine the monitoring and supervision process currently adopted by DUDBC, DOK.  To access the present apartment living condition in a sample apartment.
  • 12. 4 1.3 METHODOLOGY The information on the apartment construction approval process was gathered from presentation made by officials from DUDBC, DOK. The unpublished materials provided during the presentation were reviewed and studied in detail. Legal provisions relating to apartments were also studied from different acts, regulations and building bylaws. The study group visited the Kalash apartment, Tahachal and interacted with the apartment dwellers and collected necessary information and verified them through observation at the site. The inference has been derived based on the available data. 1.4 LIMITATIONS  The present study is mainly based on secondary data / information collected from DUDBC, DOK.  Review of apartment construction approval procedure is mainly focused on the role of DUDBC, DOK.  The primary information collected is from one apartment (10 residential units) only and may not represent the case of all the apartments. It is of qualitative type and only subjective inferences have been made.
  • 13. 5 CHAPTER 2 2. INTRODUCTION OF THE ORGANIZATION 2.1 INTRODUCTION The first public entity office established in Nepal for construction sector was named as “Banaune Adda” in 1970 BS during the Rana Regime. Its main objectives were to maintain the royal palace, existing government buildings and construction of new project. This office was then renamed as the Department of Building (DoB) in 2020 BS under the then Ministry of Works and Transportation (MoWT) and was mandated to design and construct the government buildings. From the fiscal year 2027/28 the department was reformed as Department of Housing, Building and Physical Planning (DHBUP) and was also mandated to address the growing need of housing and Urban Planning in Nepal. In 2044 BS the government of Nepal gave priority to planned urban growth as well as safe shelter and formed a new Housing and Physical Planning Ministry. In 2045 BS under this new ministry DHBUP was reconstituted into two separate entities namely; Department of Buildings(DOB) and The Department of Housing & Urban Development(DHUD) at the central level; whereas as the regional and district level, both the departments have the same offices. The district chiefs of these offices were deputed as the member secretary of the concerned Town Development Committees. Again in 2058 the government of Nepal reorganized the two departments into one single unit under the Ministry of Physical Planning & Works (MPPW) and named the newly formed entity as Department of Urban Development and Building construction (DUDBC) to avoid duplications in works carried out by the then two departments. Recently in 2069 BS this department has been put under the newly formed Ministry of Urban Development (MoUD). At present DUDBC have three divisions, twenty-four division offices and one training center (Appendix 5,Figure 13) The main task of the Department of Urban Development and Building Construction (DUDBC) lies in the sphere of planning. Since 2002, the office assisted in the preparation of Periodic Plans following the
  • 14. 6 participatory and consultative process for municipalities. The department was also the focal point for the Integrated Action Planning exercise which commenced in 1992. More than 30 municipalities have prepared their own integrated action plan, which was later replaced by Periodic Plans as provisioned in the Local Self-Governance Regulations. There is no history of the department being directly involved in the housing sector. Yet in recent years the Department of Urban Development and Building Construction, has been increasingly committed to the urban housing problem and acknowledged the issue of squatter settlements. The department took exemplary action by signing MOU with the NGOs to upgrade slums and squatters. The department has set a target to upgrade 25 slums and squatter communities in their three year interim plan beginning July 2007. There are several ministries involved in the land tenure issue. Yet in absence of a clear policy on addressing the urban squatter problem, the fund allocated for squatter settlement could not be used as intended. Instead the fund was utilized to buy land for resettlement of squatters. Besides these the department has been an important partner for disaster risk management (DRM) initiatives specifically regarding building codes, technical assistance, orientations, enforcement and trainings. Based on the mandated work, the DUDBC has provided significant support for the Nepal Risk Reduction Consortium (NRRC). The following lists the various activities DUDBC has contributed for DRM in Nepal: Flagship 1: School and hospital safety  Structural and non-structural aspects of making schools and hospitals earthquake resilient Flagship 2: Emergency preparedness and response capacity  Prepare site inventory of major open spaces to enhance preparedness of GoN & international agencies & reduce adverse consequences that might happen after disaster. This includes camp management plan, water supply and sanitations, primary health and school buildings, security posts and improvement of infrastructure services
  • 15. 7  Municipal Profiles in terms of Earthquake Risk and Vulnerability, Vulnerability Assessment and Damage Assessment. Flagship 5: Policy/institutional support for disaster risk management  Preparation of Risk Hazard Map, GIS map of municipalities.  Study of Existing Practices in High Rise Building & Recommendation for safety.  Support to municipalities on Building code implimentation & Update of Nepal National Building Code  Seismic Vulnerability Evaluation Guideline for Private and Public Building / Training Manual / Training on Damage Assessment, Vulnerability Assessment, Demonstrative Retrofitting works 2.2 VISION The main vision of the Department is:  Urban Development Sector: Achieve a balanced national urban structure, Promote safe and economically vibrant urban environment and Promote effective urban management.  Housing Sector: Promote Planned Development through providing affordable, adequate and safe shelter to all income group people.  Building: Promote safe, economical and Environment friendly buildings that can display indigenous architecture 2.3 OBJECTIVES & STRATEGIES Objectives Urban Development To invest in urban infrastructure and other services through inter-agency coordination, to legally empower and institutionally strengthen local bodies in order to build a clean, safe and prosperous urban environment, and to progressively guide rural settlements towards urbanization by expanding rural urban inter-relationship under the overall notion that urban development promotes rural development.
  • 16. 8 Housing To provide safe and economical housing facility by developing organized habitats under the notion of “shelter for all”. Building To construct and develop buildings which portray Nepalese architecture to the extent possible, and are safe, affordable and environmental friendly. Strategies • To develop large urban centers in the country as regional economic centers, and to link them with medium and small centers through roads and other infrastructures, and thereby strengthen the rural urban inter-relationship. • To guide urban development by establishing urban infrastructure through physical development planning with an aim to preserve and conserve the existing cultural, historical and tourist areas. To develop suburbs at the periphery of the city and to prepare a base for planned development of urbanizing VDCs. • To develop local bodies as the major agency to implement urban plans, and also strengthen institutional capability of concerned central agencies involved in urban planning and policy formulation, and monitoring. • To develop urban housing with the participation and involvement of the government, cooperatives and the private sector. • To develop market centers in the urbanizing settlements and develop requisite infrastructure in the scattered settlements in rural areas, while regulating development in urban and rural settlements to preserve historical and cultural heritage. • To update and implement the Building Code and byelaws in the government and private sectors as well. • To promote and develop the capability of national consultants and contractors. • To develop appropriate building construction technology and materials.
  • 17. 9 CHAPTER 3 3. DATA PRESENTATION & ANALYSIS 3.1 EARLY INITIATIVES The need of "Joint housing" was felt during early 2050BS due to the sudden increase of population pressure on urban areas and the subsequent increase in the land price. Nepal enacted the Ownership of Joint Housing Act (OJHA), in 2054 (authentication and publication date: 2054.9.7). However, the actual apartment building began after the approval of Ownership of Joint Housing Regulation (OJHR) by the then HMG/N in 2060/04/12 B.S. Indreni Apartment - 1 (having 32 units), located at Kathmandu municipality - 4, Bhatbhateni, Kathmandu and owned by Subhakamana Housing company Pvt. Ltd, was the first to obtain the apartment construction approval from DUDBC, DOK. 3.2 APPROVED APARTMENTS In total 64 apartments have obtained apartment construction approval from the division till paush 2069. Status of these 64 apartments has been summarized in Table 1 below. Table 1: Status of the 64 Apartments having apartment approval S. Status No of apartments No 1 On operation with completion certificate 13 2 On operation without completion certificate 15 3 On construction phase and others* 28 4 Construction not started 8 Total 64 Source: DUDBC, Division office, Babarmahal, Kathmandu *On construction phase and others
  • 18. 10  Revised approval (3)  Completion certificate processing (3)  On completion (regular/irregular)  Halt construction 3.3 APARTMENTS LOCATIONS AND UNIT DETAILS Out of 64 approved apartments 51 are located inside the ring road while the reaming 13 are located in outside areas (Table 2,Figure 1) Table 2 Number of apartments inside and outside the ring road Location Nos Apartment Units Inside Ring road 51 2862 Outside Ring 13 3465 road Total 64 6327 (Source: DUDBC,DOK) Figure 1: Location of apartments within the Kathmandu valley
  • 19. 11 Among these 64 apartments 46 are located in Kathmandu district while the remaining 18 are located in Lalitpur district. No apartment is located in Bhaktapur district. The district wide distribution of approved apartments in Kathmandu valley in given in Figure 2 below. Figure 2: District wise distribution of approved apartments (source DOK) 3.4 APARTMENTS ON APPROVAL PROCESS Right now, there are 14 apartment proposals in the division at different stages of the overall approval process. Out of these 14 proposals 6 are in regular follow up. Besides this, 7 other apartments have taken planning permit but not applied for design approval yet. The status of apartment on approval process is given in Table 3 below Table 3: Status of apartment proposals on approval process S.N status of proposal No of apartment proposed 1 Apartment proposal with regular follow up 6 2 Apartment proposal without regular follow up 8 3 Apartment proposal yet to apply for design approval 7 Total Proposals 21 Source: DOK
  • 20. 12 3.5 APARTMENT APPROVAL PROCEDURE The entire apartment approval procedure can be discussed under the following three stages. Stage 1: Planning Permit Stage  Developer produce project proposal with design and drawings for planning permit  Developer applies for planning permit from KVDA  Developer undertakes environmental screening Stage 2: Apartment Approval Stage  Developer applies for apartment approval from DOK, DUDBC  Developer undertakes EIA/IEE study as required  Developer applies for clearance from civil aviation authority for safe flying zone  Developer applies for approval from KVWSMB for groundwater use Stage 3: Local Body Approval Stage  Applies for approval from municipality/VDC concerned
  • 21. 13 The overall apartment approval procedure has been summarized in Figure 3 below. Figure 3: Apartment Approval Procedure (Source DOK, modified) 3.5.1 Planning Permit As mention above, the developer has to apply to Kathmandu Valley Development Authority (KVDA) with required planning permit design and drawing for planning permit. KVDA reviews the documents within the broad framework of:  Town Development Act, 2045  Gazette published on BS 2062/11/22 and  Building by-laws 2064 The key elements covered by planning permit include:  Construction area, approach road, Set back, FAR, light plane  Ground coverage, greenery (open surface) and other open spaces  Distance between blocks  Parking facilities  Planning related issues like sewer, electrical systems, GLD lines, HT line, water supply plan
  • 22. 14  Waste water and solid waste management 3.5.2 Environmental Approval The project developer has to undertake the environmental assessment as per the guidance of Environment Protection Act, 2053 and Environment Protection Regulation 2055. The first task to undertake this process is to carry out the environmental screening so as to determine whether the project requires IEE or EIA, or it does not require any assessment at all. The screening criteria as mentioned in EPR, 2055 is shown below in Table 4: Table 4: Screening Criteria SN Criteria No EA IEE EIA 1 Build Up Area <5000 sqm 5000-10000 sqm >10000 sqm 2 No of Story <10 10-16 >16 3 Height of the Building <25 m 25-50 m >50 m 4 NO of Inflow and Outflow at a <1000 person 1000-2000 >2000 persons time persons Source DOK The developer conducts either IEE or EIA and submits the report to competent authority MoUD in case of IEE and MoSTE in case of EIA) for approval. The key aspects/areas covered by IEE/EIA document include:  Project description covering construction planning  Review of relevant policies in relation to the project implementation  Alternative analysis  Major adverse environmental impacts and their mitigation measures  Major beneficial environmental impacts and their enhancement measures  Environmental management plan ( environmental monitoring plan covered) 3.5.3 Apartment Approval The developer applies to the DUDBC, DOK for design approval and construction and operation permit with all required documents. The Division office reviews the
  • 23. 15 proposal in line with the broad framework provided by the following policy instruments.  OJHA 2054 & OJHR 2060  Building act 2055  Nepal National building code 2060  Work procedure 2060 The key elements covered by Apartment Approval are: Architectural Design  Light and ventilation system  Staircase, exit  Lobby, lift, disable ramp, parapet height  Glazing system Structural Design  Geo-technical investigation  Structural analysis/model as per NNBC 2060  Structural drawing with respect to output of structural design and ductile detailing code Sanitary, water supply and planning system • Water supply/Treatment Plant/Pumping System • Toilet Bath fixtures and installation systems. • Liquid waste and solid waste management system. • Rain water Harvesting Systems. Firefighting system • Fire Detector, Fire extinguisher, Firefighting Hose reels, Hose pipes, Water tank, Hydrant stations. • Fire escape staircase, Exit, Lobby, Escape route. Electrical system and design • Electrical Points, load calculation, Cable sizes. • Earthing, Lightning arrestor.
  • 24. 16 • Safety against electrical hazards. • Transformer, Generator and Panel Boards. Operation and management plan (including safety management plan) • Electrical, Sanitary services operation and management plan. • Fire safety management and earthquake safety management plan. • Evacuation area, Exit, Use of Open Spaces during Disaster The division office may ask for presentation from designer for complex structures. There is also the provision for "review" by "expert panel" for such complex structures. The documents to be submitted to DOK along with the proposal are: • Application form. • Provision of details of Services/Facilities. • Sample of Contract agreement paper. (As per clause 15 of OJHA2054) • Land and Company related ownership documents. • Proprietor, Developers Representatives. • Quality assurance documents and designer’s affidavit papers. • Project brief reports, design reports and soil test reports. • Insurance letter. 3.6 MONITORING AND SUPERVISION Monitoring and supervision from DOK is mainly focused on checking of reinforcement detailing before/during casting of important structural components e.g. foundation, column, slab and beam. Monitoring from DOK also involves reviewing of the periodic progress reports and lab test reports. The main constraint on monitoring and supervision from the DOK prospective is the lack of adequate resources, mainly the human resources (Shown in Appendix 5, Figure 15). The task of conducting environmental monitoring lies within the concerned line ministry, MoUD in this case. However, no regular and systematic environmental monitoring has been conducted so far. Monitoring from other agencies like KVDA and local bodies (Municipality/VDC) have been reported to be weak as well. Monitoring of the DOK has reported the following diversified observations:
  • 25. 17  Violations of planning permit and building by-laws(Appendix 3, Figure 8)  Change in approved design/drawings. (Appendix 3, Figure 9)  Major construction work without presence of technical team (Project manager, engineer, architects)  Approved drawing/detailing not available at site.  Project manager/site engineer unknown about approved drawings  Inadequate safety measures (Appendix 3,Figure 10)  Approved design followed strictly and safety tools used properly  Partial dismantling of major structural elements (Appendix 3, Figure 11)  Use change without prior approval (Appendix 3, Figure 12) 3.7 ISSUANCE OF COMPLETION CERTIFICATE The project developer submits the project completion report (with as built drawings), quality control reports and environmental compliance report to DOK. The DOK engineers undertake site visits for final checking including the firefighting system. In case, where the regular quality test reports were not submitted to the DOK, the third party consultant is hired for post construction quality test and structural design verification. The Division office issues the completion certificates when all the reports and observations comply with the design requirements. 3.8 APARTMENT LIVING CONDITION The aim of the study team was to visit at least one apartment in Kathmandu valley to access the existing situations. The study team decided to visit Kalash Apartment which is situated at Tahachal, Kathmandu. It is centrally located. It is a multi-story (nine stories) apartment. It has been functioning since two years. There are altogether 75 units out of which only 50 units are found to be occupied. Developer has already obtained construction completion certificate from DOK. A sample questionnaire was prepared which was mostly related with the extent of satisfactions of the unit owner, major problems faced by unit owners in smooth operation and their opinion for its improvement. The interaction was two way and
  • 26. 18 conducted in an open environment. They inquired us about existing policies, acts and regulation. Most of them were not aware with OJHA and OJHR. After interaction the team walked around and had a look on facilities provided. Apartment has been found to be furnished with most required facilities like parking space, exits for emergency, sauna, health club, fire extinguisher etc. The assessment from the interaction was very much interesting to us. Apartment is completely dependent on ground water supply for bathing, utensils cleaning, cloth washing etc. and unit owners uses aqua guards for drinking purpose. It has a generator for electricity backup during load shedding, but it faces fuel shortage and improper management. The unit owners have themselves arranged security personnel and they are quite satisfied with securities arrangements made by them. There were several issues opined from most of them. Unit owners are still without ownership certificate (LALPURJA) of their units. Ownership transfer must have completed by December, 2011 but still they are in hands of developer. Most of the unit owners are businessman. They need PAN numbers urgently but in absence of ownership document they are unable to get it. Developers still have not yet transferred apartments operation and management to existing society. The open space for children is not available. There is a temporary arrangement for garbage disposal which is altogether managed by dwellers themselves. There is not sufficient space available after exit which is must in the case of emergency. 3.8 KEY ISSUES 3.8.1 Time Taken for Approval Process Organization structure of the Kathmandu Division (Appendix5, Figure 15) depicts inadequacy of technical manpower for the evaluation of structural and non-structural designs along with monitoring of mushrooming apartments of Kathmandu valley. Developer’s unwillingness to obtain design approval due to uncertainty in the market behavior either from government’s inconsistent decisions or from economic recession also becomes the cause of some delay in approval process. IEE/EIA processes (though necessary and mandatory) were identified as being cumbersome and time consuming due to its unclear (non-standardized) processes and guidelines. Apartment
  • 27. 19 construction approval process seeks approval from as many as nine (6) agencies. All those agencies have their own working norms. It is natural that delay occurs due to several agency involvements. 3.8.2 Project Management Issues There are some smaller but significant issues relating to project management. Some of important issues that have emerged during the past years of apartment housing in Nepal are: 1. Frequent change of technical personnel leading to a gap between old and new and between the business and the regulating authority. 2. Weaker coordination between developer, consultant and the contractor's technical personnel hindering the smooth, timely and orderly implementation of the activities. 3. Improper and inadequate safety consideration during construction. 4. Weak progress reporting. 5. Construction without prior checking by DOK. 6. Use change without prior approval. 3.8.3 Insufficient Resources In Kathmandu valley, urbanization is in rapid expansion and a large number of apartments are under construction. Giving permission of building construction, supervision and monitoring during construction and issuing completion certificate to the developer are the major responsibilities of the DOK in the apartment sector. Within the division, having no separate section for apartment, the available human resources (technical as well as administrative) are insufficient in relation to its work- load. Still the division is working under the old organogram. It is realized that due to insufficient human resource, division has felt difficulty in delivering its services smoothly. The issue is not related to human resource only, other resources like budget and vehicles for supervision and monitoring are also felt inadequate. On the other hand, the office management/operational cost are same as in the past despite increased
  • 28. 20 work load. In totality all the factors discussed above are hindering the apartment construction business as a whole. 3.8.4 `Unethical Practices It has been reported that designer change (one person designs and the other signs the drawings and affidavit) is prevailing in practice. Such unethical practices are indeed one of the serious concerns for the DOK and are yet to be checked.
  • 29. 21 CHAPTER 4 4. MAJOR FINDINGS, CONCLUSION & RECOMMENDATIONS 4.1 MAJOR FINDINGS 1. There are at least 6 agencies directly involved in the apartment approval process. In this sense it can be regarded as a multi stakeholder task. The DOK, has a key role and is focused mainly on safety criteria by ensuring adoption of National Building Code. 2. It has been noticed that the time taken for the apartment approval process (from planning permit to approval from local body) was found to be varying widely (6 months to 3 years). It is not only the regulatory body's role which is responsible for such wide variation; equally important factors are the market condition and the promoter's management skill. 3. The Kathmandu Division Office is handling the entire task of apartment approval, monitoring and supervision on top of its regular job. The organization structure of the division has remained the same since 2058 B.S. No arrangements have been made to accomplish the additional task on "apartment" which was assigned to the division by the gazette dated 2060/01/02 B.S. In addition to this, the division office is also facing serious resource constraints. 4. Some apartments have been reported to be operating without completion certificate from DOK. Furthermore few cases of even ownership transfer (without completion certificate from DOK) have also been reported. 5. During the period of last 8/9 years some issues has been emerged as pertinent and challenging. Some are ethical (designer change) while other are related to project management (weak progress reporting, safety during construction, construction without prior checking by DOK etc.) . Use change has emerged as another major issue. 6. The residents (apartment owner) of the surveyed apartment are found to be unaware of the concerning laws and regulations. They doubt whether the
  • 30. 22 firefighting system works properly. The developer has not provided the "ownership certificate" (LALPURJA) yet. 4.2 CONCLUSION In general, apartment approval and construction has been found to be streamlined in the right direction. However the pertinent issues emerged so far have to be systematically and promptly addressed by the concerned authority(ies). DOK has to be strengthened. Safety considerations have to be given the first priority by all stakeholders concerned. 4.3 RECOMMENDATION 1. DOK should be strengthened by allocating adequate resources and providing additional responsibilities and authorities so that it can function as a strong and competent "one door" of the government in apartment housing sector. 2. DOK and the concerning local authority (municipality/VDC) should organize regular safety awareness campaign (including drilling) in the occupied apartments. Safety related systems/equipment should be checked on a regular basis. 3. Third party monitoring can be introduced after required preparations. This will help in ensuring better adoption of safety requirements while keeping the DOK size appropriately slim.
  • 31. 23
  • 32. 24 BIBLIOGRAPHY Government of Nepal Building Bye Law. - 2064. Government of Nepal Environment Protection Act. - 2053. Government of Nepal Environment Protection Regulations. - 2055. Government of Nepal Ownership of Joint Housing Act, 2054. - 1997. Government of Nepal Ownership of Joint Housing Regulations. - 2060. http:www.dudbc.gov.np [Online]. - Department of Urban Development & Building Construction. National Census: A Brief Report [Report]. - [s.l.] : Bureau of Statistic,Government of Nepal, 2012. National Shelter Police [Report]. - [s.l.] : Ministry of Urban Development, Government of Nepal, 2012. Nepal Urban Housing sector Profile [Report]. - [s.l.] : UN-HABITAT, 2010.
  • 34. 26 APPENDIX 1 Detail of Approval of Apartments
  • 35. 27
  • 36. 28
  • 37. 29
  • 38. 30
  • 39. 31 APPENDIX 2 Apartments under Approval Procedure
  • 40. 32
  • 41. 33
  • 42. 34 APPENDIX 3 Photographs
  • 43. 35 Figure 4: Kalash Apartment Figure 5: Fire Escape in Kalash Figure 7: Questionnaire survey Figure 6: Fire Hose in Kalash
  • 44. 36 Figure 8:Violation of Planning Permit Photo Courtesy: DOK
  • 45. 37 Figure 9: Change in Approved Design Photo Courtesy: DOK
  • 46. 38 Figure 10: Inadequate Safety Measure Source DOK
  • 47. 39 Figure 11: Partial Dismantling of Major Structural Member Source DOK
  • 48. 40 Figure 12: Use Change Without Prior Approval Source DOK
  • 49. 41 APPENDIX 4 Sample Questionnaire
  • 50. 42 ckf6{d]G6sf OsfO{ wgLx?sf] nflu k|ZgfjnL ckf6{d]G6sf] gfd M :yfg M O{sfO{ wgLsf] gfd M Joj;fo M cjwL M jif{ !_ vfg]kfgL, lah'nL tyf ;'/Iff cj:yf s:tf] 5 < s_ vfg]kfgL M v_ lah'nL M u_ ;'/Iff M @_cfunfuL, e'sDk cflbsf] j]nfdf s;/L ;'/IfLt x'g] jf/]df pknAw ;'/Iff lalwx? jf/]df oxf+ egfO{ s] 5 < $_ ckf6{d]G6sf] a;fO{ b]lv ;Gt'i6 x'g' x'G5 t< #_ ckf6{d]G6 a;fO{sf] d'Vo –d'Vo ;d:ofx? s] s] 5g < %_ ckf6{d]G6sf] a;fO{ k|efjsf/L agfpg s] s] ug{' knf{ <
  • 51. 43 snz Pkf6{d]G6, tfxfrn, sf7df08f}df ePsf] k|zgf]Q/sf] ;f/f+z OsfO{ wgLsf] gfd, vfg]kfgLsf] ljh'nLsf] ;'/Iffsf] cfunfuL, e'sDksf] ;dodf ckf6{d]G6 a;fO{sf] d'Vo d'Vo ;:ofx? ckf6{d]G6sf] a;fO{ b]lv slt ckf6{d]G6sf] a;fO{ k|efsf/L jgfpg s] ug{ o'lg6 g+=, Joj;fo cj:yf jf/] cj:yf jf/] cj:yf jf/] ;'/lIft x'g] pknAw k|jGwx? ;Gt'i6 x'g' x'G5 knf{ tyf ckf6{d]G6df a;]sf] cjlw dx]z cu|jfn, O2, ;'/lIft :yfg 5}g . k|ofKt :yfg kmf]x/ kmfNg] k|jGw /fd|f] 5}g . Parking sf] @)!! l8;]Dj/ ;Dd aRrfxx?sf] nflu Play ground sf] vfgsf] nfllu Acqua Guard, cfKmg} Joj:yf 5 . cGosfdsf] nflu af]l/Ësf] kfgL Backup sf] nflu h]g]/]6/ eP klg, Diesel gePsf] j]nf tyf break down sf] Society sf] nflu cfkmg} security team agfPsf] n] ;'/Iff Joj:yf l7s 5 . Jofkf/, !=% jif{ 5}g . ;d:of 5 . Unit handover gubf{ ownership x:tfGt/0f Joj:yf x'g' kg]{ . kmf]x/d}nf Joj:yfkg x'g' kg]{ ;femf ;d:of 5 . Generator /fVg] x'g'kg]{ t/ ePsf] 5}g . l7s} 5 . . hUufsf] dfkb08 cg';f/ Building proper :yfg 5}g . construction sf] :jLs[tL lbg' kg]{ . /fhg ltldN;]gf, @ j6f Fire Exit 5g . GF Socity btf{ eP klg unit sf] nfnk'hf{ ;Gt'i6g} 5' . Society bQf{ ;DjGwL tyf handover D9, Jofkf/,!=% jif{ df fire extingusher sf] kfPsf] 5}g h;n] ubf{ PAN g+= lng ug]{ ;DjGwL sfg'gdf ;'wf/ x'g' kg]{ . t'?Gt Joj:yf 5 . ;lsPsf] 5}g . nfnk'hf{ kfpg' kg]{ . ls/0f cu|jfn, E7, e'sDk k|'km 5 . @ j6f Fire k|ofKt v'nf 7f+p 5}g . ;Gt'i6g} 5' . kmfobf a9L 5 . k};f p7fP/ yk sfdx? ug]{ u/]sf 5f}+ Jofkf/,!=% jif{ Exit 5g . .Pkf6{d]G6 cuf8Lsf] ;8sdf ;'wf/ x'g' kg]{ . k|eft s'df/ ;/f{km, Emergency sIf k|To]s ;j} l7s 5 . ;Gt'i6g} 5' . ;j} /fd|} 5 s]xL ug{ kb}{g . F7, Jofkf/, ! jif{ tNnfdf 5 . j]nf light off x'G5 . ;lGhj zfSo, D6, Emergency sIf tyf ;d:of vf;} s]xL 5}g . ;Gt'i6 5' . Society bQf{ ;DjGwL tyf handover Jofkf/,!=% jif{ k|To]s tNnfdf Fire ug]{ ;DjGwL sfg'gdf ;'wf/ x'g' kg]{ . Joj:yf 5 . exetinguisher sf] Joj:yf 5.
  • 52. 44 OsfO{ wgLsf] gfd, vfg]kfgLsf] ljh'nLsf] ;'/Iffsf] cfunfuL, e'sDksf] ;dodf ckf6{d]G6 a;fO{sf] d'Vo d'Vo ;:ofx? ckf6{d]G6sf] a;fO{ b]lv slt ckf6{d]G6sf] a;fO{ k|efsf/L jgfpg s] ug{ o'lg6 g+=, Joj;fo cj:yf jf/] cj:yf jf/] cj:yf jf/] ;'/lIft x'g] pknAw k|jGwx? ;Gt'i6 x'g' x'G5 knf{ tyf ckf6{d]G6df a;]sf] cjlw cdg s'df/ cu|jfn, Emergency sIf tyf k|To]s ;j}nfO{ ldnfP/ lx8g ufx««f] 5 . cGo ;j} ;Gt'i6 5' . ;'ljwf Joj:yfkgdf ;j}sf] cfly{s ;xof]u Backup sf] nflu h]g]/]6/ eP klg, Diesel gePsf] j]nf tyf break down sf] j]nf light vfgsf] nfllu Acqua Guard, cfKmg} Joj:yf 5 . cGosfdsf] nflu af]l/Ësf] kfgL Joj:yf 5 . G7, Jofkf/, @ jif{ tNnfdf Fire exetinguisher /fd|f] . ;d:of sd kmfobf a9L 5 . cfjZos 5 . Society sf] nflu cfkmg} security team agfPsf] n] ;'/Iff Joj:yf l7s 5 . sf] Joj:yf 5 . ;'lw/ s'df/ cu|jfn, Emergency sIf tyf k|To]s Vff;} ;d:of 5}g . ;Gt'i6 5' . Society btf{df PAN g+= lbg grfx]sf] . H5, Jofkf/, @ jif{ tNnfdf Fire exetinguisher t'?Gt nfnk'hf{ kfpg' kg]{ . sf] Joj:yf 5 . ;~ho cu|jfn, C7, Emergency sIf tyf k|To]s Vff;} ;d:of 5}g . ;Gt'i6 5' . Society btf{df PAN g+= lbg grfx]sf] . Jofkf/, !=% jif{ tNnfdf Fire exetinguisher t'?Gt nfnk'hf{ kfpg' kg]{ . off x'G5 . sf] Joj:yf 5 . ;~ho cu|jfn, C3, a}sNkLs jf6f] 5, Fire Socity btf{ eP klg unit sf] nfnk'hf{ l7s} 5 . Apartment maintenance sf] lhDdf Jofkf/, !=% jif{ exetinguisher sf] Joj:yf 5 kfPsf] 5}g h;n] ubf{ PAN g+= lng society nfO{ lbg' kb{5 . t'?Gt nfnk'hf{ . ;lsPsf] 5}g . kfpg' kg]{ . of]u]z uf]on, Jofkf/ a}sNkLs jf6f] 5, Fire laN8/n] tf]s]sf] ;do leq lgdf{0f gug]{, ;Gt'i6 5' . Apartment maintenance sf] lhDdf exetinguisher sf] Joj:yf 5 jfrf u/]sf] ;'ljwfx? Glbg] / d'Vodf society nfO{ lbg' kb{5 . . kfls{Ë, ;'/Iff, v]ns'bsf] ;'ljwf / cGodf maintenance society nfO{ lhDdf nufO{ lbg' kb{5 .
  • 53. 45 APPENDIX 5 Organization Charts
  • 54. 46 Director General DDG DDG DDG Urban Dev Building Divison Housing Divison Divison Physical Planning & Building Housing Division Office Building Urban Dev Construction (24 Nos.) construction & Building Code maintenance Urban Environment Planning Divison Building Small Town Monitoring Maintenance & Municipality Evaluation Class II Class I Standardization Foreign Aid Division Chief Division Stastical & Coordination Chief GIS Building General Fiscal Procuremen Legal Technology Administration t Unit Administration Research & & HR Training Center
  • 55. 47 Figure 14: Jurisdiction of DUDBC division office (source DUDBC)
  • 56. 48 Figure 15: Organization Chart of DOK (source DOK)
  • 57. 49