PPT Item # 5 - Water Main Installation HDD
1. PUBLIC WORKS
Presented by:
Patrick Sullivan
Director
PROPOSAL FOR WATER MAIN INSTALLATION
VIA HORIZONTAL DIRECTIONAL DRILLING
ITEM # 5
APRIL 10, 2023
2. SUMMARY
Seeking authorization to approve contracted water
main installation via horizontal directional drilling
Improved area is Wildrose, Cloverleaf & Rosemary
From Broadway to N New Braunfels
Miller Brothers selected through Competitive
Sealed Bid Proposal process
Consideration of Ordinance to amend FY 2023
Utility Fund Budget
3. BACKGROUND
Contract for water main installation on Wildrose,
Cloverleaf & Rosemary in preparation of eventual
relocation of water service
Rosemary bid as an add-alternate for budget
consideration
Project area between N. New Braunfels and
Broadway
4. BACKGROUND
Project part of City’s ongoing mandated separation of
sanitary sewer & potable water (4” x 2”)
Water mains to be relocated to the street from current
location in City’s easement at rear of properties
BROADWAY
N.
NEW
BRAUNFELS
5. BACKGROUND
Narrow roadways in project area led to
recommendation of horizontal directional drilling (HDD)
Less intrusive &
disruptive to residents
than open cut installation
Future project will install
piping to connect new
mains to new meters &
then residences
6. PROPOSAL PROCESS
Competitive Sealed Bid Proposals advertised on January
25th & February 1st in San Antonio Express-News
Bid opened on February 24th
Four (4) proposals submitted:
Miller Brothers - $847,811
Guerra Underground LLC. - $1,075,396
Vaca Underground Utilities Inc. - $1,125,530
Rangeline Utility Services LLC. - $1,230,288
7. PROPOSAL PROCESS
Competitive Sealed Bid Proposals reviewed according to
following criteria (100 points total)
Proposed contract price – 40 points
Contractor’s approach – 20 points
Experience & past performance of Bidder – 20 points
Experience & qualifications of proposed key personnel – 20
points
8. PROPOSAL PROCESS
Proposals reviewed Freese & Nichols & Public Works
Found none of submittals provided much history of water main
installation through directional boring
On March 21, Request for Additional Information emailed
to all respondents seeking 2nd opportunity to provide HDD
project history for prime & subcontractors & references
As of March 29th deadline, only one response received –
Miller Brothers
9. BACKGROUND
After extensive review of Competitive Sealed Bid
Proposals & additional information submitted, staff
& Freese & Nichols selects Miller Brothers as most
qualified contractor to perform this work
10. POLICY ANALYSIS
Authorization will allow installation of new water
mains through horizontal directional drilling as part
of City’s continued infrastructure improvements & 4
x 2 compliance with Texas Commission on
Environmental Quality (TCEQ)
12. FISCAL IMPACT
Scenarios Base Bid 5%
Contingency
Engineering
Fee
Total – Not to
Exceed Amount
Wildrose, Cloverleaf &
Rosemary (Preferred)
$874,811.00 $43,741.00 $51,500.00 $970,052.00
Wildrose & Cloverleaf
(Alternate)
$628,000.00 $31,400.00 $51,500.00 $710,900.00
Cost for water main improvement project on all three streets by Miller Brothers is
$874,811.00, plus a 5% contingency, and engineering fee for a total amount not to
exceed $970,052.00
If Rosemary was to be delayed for future consideration, the cost for two streets is
$628,000.00, plus a 5% contingency, and engineering fee for a total amount not to
exceed $710,900.00
13. FISCAL IMPACT
Funds in the amount of $450,000 available in FY
2023 Utility Fund Budget
Swift & volatile fluctuations in cost for construction materials &
high demand for similar projects drove bid costs beyond
budgeted amounts
Funds available in Utility Fund balance to cover
project cost
14. FISCAL IMPACT
If three-street proposal accepted, authorizes
contract with Miller Brothers in an amount not to
exceed $970,052.00 and amends FY 2023 Utility
Fund Budget in amount not to exceed $520,052.00
If two-street proposal (omits Rosemary) accepted,
authorizes contract in amount not to exceed
$710,900.00 & amends FY 2023 Utility Fund Budget in
amount not to exceed $260,900
15. MOTION TO APPROVE
Motion for three-street water main replacement project:
“I make a motion to accept the most qualified bid from Miller
Brothers for the water main installation project on Wildrose
and Cloverleaf, and include the ad-alternate street of
Rosemary, in an amount not to exceed $970,052 and to
amend the FY 2023 Utility Fund Budget in the amount of
$520,052.”