Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 1
Section 1 XRS Consulting Engineers and Project
Managers 1
Section 10 XRS Consulting Engineers and Project
Managers 1
Appendix XRS Consulting Engineers and Project
Managers 1
Section 9
Section 9
Factory Acceptance Tests (FAT)
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 4
Section 1 XRS Consulting Engineers and Project
Managers 4
Section 10 XRS Consulting Engineers and Project
Managers 4
Appendix XRS Consulting Engineers and Project
Managers 4
Section 9
Test Classification and Conditions
Testing procedures and the acceptance criteria must
follow what is stated at the relevant IEC standards.
Tests must be performed at an ambient temperature
between 10°C and 40°C and with cooling water (if
applicable) at a temperature up to 25°C.
When tests results have to be referred to a reference
temperature, for oil-immerse transformers a
temperature of 75°C must be considered, and for dry
type transformers a temperature above 30°K of those
shown on column 3 of the below table must be
considered.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 7
Section 1 XRS Consulting Engineers and Project
Managers 7
Section 10 XRS Consulting Engineers and Project
Managers 7
Appendix XRS Consulting Engineers and Project
Managers 7
Section 9
Test Classification and Conditions
According to IEC standard 60076 FAT for oil-immerse
transformers are classified into three categories:
Type tests
Routine tests
Special testsThis document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 10
Section 1 XRS Consulting Engineers and Project
Managers 10
Section 10 XRS Consulting Engineers and Project
Managers 10
Appendix XRS Consulting Engineers and Project
Managers 10
Section 9
Routine Tests
Routine tests are performed at each transformer, and in
accordance with IEC standard 60076 they comprise:
Measurement of no-load harmonics.
Measurement of impedance voltage drop and resistive
losses.
Measurement of ratio and verification of vector group
(polarity).
Measurement of no-load current and iron (core) losses.
Individual dielectric tests.
Tap changer test (if applicable)
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 13
Section 1 XRS Consulting Engineers and Project
Managers 13
Section 10 XRS Consulting Engineers and Project
Managers 13
Appendix XRS Consulting Engineers and Project
Managers 13
Section 9
Special Tests
These tests, which must be agreed between the client
and the manufacturer, are also defined at IEC standard
60076, and are:
Special dielectric tests
Determination of the capacitances between windings
and between each winding and the earth.
Determination of the characteristics of zero sequence
voltages transmission.
Measurement of zero sequence impedances.
Short-circuit withstand.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 16
Section 1 XRS Consulting Engineers and Project
Managers 16
Section 10 XRS Consulting Engineers and Project
Managers 16
Appendix XRS Consulting Engineers and Project
Managers 16
Section 9
Bushings
Transformer’s bushings failure may be one the main
reasons for a transformer fault.
In transformers with high rated power used in HV and
EHV installations it is recommended to test the bushings
for a rated voltage above 1 kV, in accordance with the
type of bushings and the voltage level, following what is
stated at IEC standard 60137.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 19
Section 1 XRS Consulting Engineers and Project
Managers 19
Section 10 XRS Consulting Engineers and Project
Managers 19
Appendix XRS Consulting Engineers and Project
Managers 19
Section 9
Dry Transformers
According to IEC standard 60726 dry type transformers
must be subjected to the following tests:
Measurement of winding resistance (routine test).
Measurement of voltage ratio and check of voltage
relationship (routine test).
Measurement of impedance voltage (principal taping),
short circuit impedance and load loss (routine test).
Measurement of no-load loss and current (routine
test).
Separate-source voltage withstand test (routine test).
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 22
Section 1 XRS Consulting Engineers and Project
Managers 22
Section 10 XRS Consulting Engineers and Project
Managers 22
Appendix XRS Consulting Engineers and Project
Managers 22
Section 9
Oil Testing
Tests of oil prior to the first fill of the transformer have
the aim to verify the following properties:
Chemical
Physical
ElectricalThis document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 25
Section 1 XRS Consulting Engineers and Project
Managers 25
Section 10 XRS Consulting Engineers and Project
Managers 25
Appendix XRS Consulting Engineers and Project
Managers 25
Section 9
Oil Testing
Interfacial tension (IFT)
Interfacial tension test is used by to determine the
interfacial tension between the oil sample and distilled
water, with the objective to find any contamination in
the oil.This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 28
Section 1 XRS Consulting Engineers and Project
Managers 28
Section 10 XRS Consulting Engineers and Project
Managers 28
Appendix XRS Consulting Engineers and Project
Managers 28
Section 9
Oil Testing
Viscosity
Viscosity that is the resistance of oil to flow, determines
the rate of cooling, and varies with the temperature. A
high viscosity as an obvious disadvantage because of the
sluggish flow through small apertures, which is, entails.
Good oil should have less viscosity so that it offers less
resistance to flow thereby not affecting the cooling of
transformer adversely.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 31
Section 1 XRS Consulting Engineers and Project
Managers 31
Section 10 XRS Consulting Engineers and Project
Managers 31
Appendix XRS Consulting Engineers and Project
Managers 31
Section 9
Oil Testing
If oil is exposed to very high temperatures under fault
conditions for long duration lower molecular weight
hydrocarbons may be produced.
These low molecular weight hydrocarbons cause a
lowering in the flash point of oil.This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 34
Section 1 XRS Consulting Engineers and Project
Managers 34
Section 10 XRS Consulting Engineers and Project
Managers 34
Appendix XRS Consulting Engineers and Project
Managers 34
Section 9
Oil Testing
Moisture
The existence of moisture in the oil decreases
dielectric strength and IFT, degrades cellulose and is
a failure risk.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 37
Section 1 XRS Consulting Engineers and Project
Managers 37
Section 10 XRS Consulting Engineers and Project
Managers 37
Appendix XRS Consulting Engineers and Project
Managers 37
Section 9
Oil Testing
Power factor
The power factor of insulating oil is the ratio of active
power to apparent power.
In a transformer, a high power factor is an indication
of significant dielectric loss in the insulating oil,
usually as a result of polar contaminants such as
water, oxidized oil and cellulose paper degradation.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
Transformer Operation, Maintenance,
Diagnosis & Testing
XRS Consulting Engineers and Project
Managers 40
Section 1 XRS Consulting Engineers and Project
Managers 40
Section 10 XRS Consulting Engineers and Project
Managers 40
Appendix XRS Consulting Engineers and Project
Managers 40
Section 9
End of this
Section
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
1
Flevy (www.flevy.com) is the marketplace
for premium documents. These
documents can range from Business
Frameworks to Financial Models to
PowerPoint Templates.
Flevy was founded under the principle that
companies waste a lot of time and money
recreating the same foundational business
documents. Our vision is for Flevy to
become a comprehensive knowledge base
of business documents. All organizations,
from startups to large enterprises, can use
Flevy— whether it's to jumpstart projects, to
find reference or comparison materials, or
just to learn.
Contact Us
Please contact us with any questions you may have
about our company.
• General Inquiries
support@flevy.com
• Media/PR
press@flevy.com
• Billing
billing@flevy.com

Power Transformers - Factory Acceptance Tests (FAT)

  • 1.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 1 Section 1 XRS Consulting Engineers and Project Managers 1 Section 10 XRS Consulting Engineers and Project Managers 1 Appendix XRS Consulting Engineers and Project Managers 1 Section 9 Section 9 Factory Acceptance Tests (FAT)
  • 2.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 4 Section 1 XRS Consulting Engineers and Project Managers 4 Section 10 XRS Consulting Engineers and Project Managers 4 Appendix XRS Consulting Engineers and Project Managers 4 Section 9 Test Classification and Conditions Testing procedures and the acceptance criteria must follow what is stated at the relevant IEC standards. Tests must be performed at an ambient temperature between 10°C and 40°C and with cooling water (if applicable) at a temperature up to 25°C. When tests results have to be referred to a reference temperature, for oil-immerse transformers a temperature of 75°C must be considered, and for dry type transformers a temperature above 30°K of those shown on column 3 of the below table must be considered. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 3.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 7 Section 1 XRS Consulting Engineers and Project Managers 7 Section 10 XRS Consulting Engineers and Project Managers 7 Appendix XRS Consulting Engineers and Project Managers 7 Section 9 Test Classification and Conditions According to IEC standard 60076 FAT for oil-immerse transformers are classified into three categories: Type tests Routine tests Special testsThis document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 4.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 10 Section 1 XRS Consulting Engineers and Project Managers 10 Section 10 XRS Consulting Engineers and Project Managers 10 Appendix XRS Consulting Engineers and Project Managers 10 Section 9 Routine Tests Routine tests are performed at each transformer, and in accordance with IEC standard 60076 they comprise: Measurement of no-load harmonics. Measurement of impedance voltage drop and resistive losses. Measurement of ratio and verification of vector group (polarity). Measurement of no-load current and iron (core) losses. Individual dielectric tests. Tap changer test (if applicable) This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 5.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 13 Section 1 XRS Consulting Engineers and Project Managers 13 Section 10 XRS Consulting Engineers and Project Managers 13 Appendix XRS Consulting Engineers and Project Managers 13 Section 9 Special Tests These tests, which must be agreed between the client and the manufacturer, are also defined at IEC standard 60076, and are: Special dielectric tests Determination of the capacitances between windings and between each winding and the earth. Determination of the characteristics of zero sequence voltages transmission. Measurement of zero sequence impedances. Short-circuit withstand. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 6.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 16 Section 1 XRS Consulting Engineers and Project Managers 16 Section 10 XRS Consulting Engineers and Project Managers 16 Appendix XRS Consulting Engineers and Project Managers 16 Section 9 Bushings Transformer’s bushings failure may be one the main reasons for a transformer fault. In transformers with high rated power used in HV and EHV installations it is recommended to test the bushings for a rated voltage above 1 kV, in accordance with the type of bushings and the voltage level, following what is stated at IEC standard 60137. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 7.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 19 Section 1 XRS Consulting Engineers and Project Managers 19 Section 10 XRS Consulting Engineers and Project Managers 19 Appendix XRS Consulting Engineers and Project Managers 19 Section 9 Dry Transformers According to IEC standard 60726 dry type transformers must be subjected to the following tests: Measurement of winding resistance (routine test). Measurement of voltage ratio and check of voltage relationship (routine test). Measurement of impedance voltage (principal taping), short circuit impedance and load loss (routine test). Measurement of no-load loss and current (routine test). Separate-source voltage withstand test (routine test). This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 8.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 22 Section 1 XRS Consulting Engineers and Project Managers 22 Section 10 XRS Consulting Engineers and Project Managers 22 Appendix XRS Consulting Engineers and Project Managers 22 Section 9 Oil Testing Tests of oil prior to the first fill of the transformer have the aim to verify the following properties: Chemical Physical ElectricalThis document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 9.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 25 Section 1 XRS Consulting Engineers and Project Managers 25 Section 10 XRS Consulting Engineers and Project Managers 25 Appendix XRS Consulting Engineers and Project Managers 25 Section 9 Oil Testing Interfacial tension (IFT) Interfacial tension test is used by to determine the interfacial tension between the oil sample and distilled water, with the objective to find any contamination in the oil.This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 10.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 28 Section 1 XRS Consulting Engineers and Project Managers 28 Section 10 XRS Consulting Engineers and Project Managers 28 Appendix XRS Consulting Engineers and Project Managers 28 Section 9 Oil Testing Viscosity Viscosity that is the resistance of oil to flow, determines the rate of cooling, and varies with the temperature. A high viscosity as an obvious disadvantage because of the sluggish flow through small apertures, which is, entails. Good oil should have less viscosity so that it offers less resistance to flow thereby not affecting the cooling of transformer adversely. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 11.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 31 Section 1 XRS Consulting Engineers and Project Managers 31 Section 10 XRS Consulting Engineers and Project Managers 31 Appendix XRS Consulting Engineers and Project Managers 31 Section 9 Oil Testing If oil is exposed to very high temperatures under fault conditions for long duration lower molecular weight hydrocarbons may be produced. These low molecular weight hydrocarbons cause a lowering in the flash point of oil.This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 12.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 34 Section 1 XRS Consulting Engineers and Project Managers 34 Section 10 XRS Consulting Engineers and Project Managers 34 Appendix XRS Consulting Engineers and Project Managers 34 Section 9 Oil Testing Moisture The existence of moisture in the oil decreases dielectric strength and IFT, degrades cellulose and is a failure risk. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 13.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 37 Section 1 XRS Consulting Engineers and Project Managers 37 Section 10 XRS Consulting Engineers and Project Managers 37 Appendix XRS Consulting Engineers and Project Managers 37 Section 9 Oil Testing Power factor The power factor of insulating oil is the ratio of active power to apparent power. In a transformer, a high power factor is an indication of significant dielectric loss in the insulating oil, usually as a result of polar contaminants such as water, oxidized oil and cellulose paper degradation. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 14.
    Transformer Operation, Maintenance, Diagnosis& Testing XRS Consulting Engineers and Project Managers 40 Section 1 XRS Consulting Engineers and Project Managers 40 Section 10 XRS Consulting Engineers and Project Managers 40 Appendix XRS Consulting Engineers and Project Managers 40 Section 9 End of this Section This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/power-transformers--factory-acceptance-tests-fat-3509
  • 15.
    1 Flevy (www.flevy.com) isthe marketplace for premium documents. These documents can range from Business Frameworks to Financial Models to PowerPoint Templates. Flevy was founded under the principle that companies waste a lot of time and money recreating the same foundational business documents. Our vision is for Flevy to become a comprehensive knowledge base of business documents. All organizations, from startups to large enterprises, can use Flevy— whether it's to jumpstart projects, to find reference or comparison materials, or just to learn. Contact Us Please contact us with any questions you may have about our company. • General Inquiries support@flevy.com • Media/PR press@flevy.com • Billing billing@flevy.com