The Project Controls Group Mission Analyze the organization structure and information needs and configure UNIFIERTMto suit that organization and meet those needs
UNIFIERTM deployment involved defining: 1) Business Processes:   Workflow Processes (reviews/approvals)   Information capture (forms/fields) 2) Reporting Requirements
CityCenter Business Processes(Pre-Construction)
CityCenter Business Processes(Project Management)
CityCenter Business Processes (Construction Management)
Business Processes (in a typical) Project Management Information Systemmay include….
Budget Management ,[object Object]
 Budget Transfers
 Budget ChangesDesign Management ,[object Object]
 Collaborative Design Reviews
 Estimating Process
 VE Process Management
 BIM StandardsProcurement ,[object Object]
 On-Line Bidding
 Contract Approval processing
 Contract Awards/Commitment Processing
 Vendor Authorizations ,[object Object]
 Change Order Processing
 Cost ReportingAdministration ,[object Object]
 Meeting Minutes
 Correspondence
 RFIs/Submittals
 Close-Out ProcessProject Accounting ,[object Object]
 On-Line A/E InvoicingCost/Schedule Management ,[object Object]
 Cash-flow Analysis/EVProject Management ,[object Object]
 Submittals
 Daily Reporting
 Quality Management  ,[object Object]
CityCenter PMIS adoption required:   Contractual language requiring it’s use   Stakeholder buy-in of Business Process workflows   Output/Reports   Executive Level (Dashboards)   Project Management (Summary/Detailed/Logs/Queries) Reports Identify: Current Status Management Action Items Critical Decisions Required   Documentation  Built-in, deployment specific Help Files  Standard Operating Procedures  Deployment/Configuration Documents   Training   Communications (change notifications)
Output/Reports
Project Executive Dashboards Project metrics that highlight information for: ,[object Object]
 Management action
 Critical decisions,[object Object]
Project Management Reports Comprehensive Anticipated Cost Reports to pro-actively manage cost to meet budget Real-time queries of the system’s database to respond to issues and actions “real-time” Logs to track the status of records and locate bottlenecks (Ball-in-Court reporting)

More Related Content

What's hot

Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
a23ccb
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
Josephine Claire
 
How to Implement a Project Management Information System
How to Implement a Project Management Information SystemHow to Implement a Project Management Information System
How to Implement a Project Management Information System
PMA Consultants
 
03ch
03ch03ch
PMS Project Management System | CONSYSA
PMS Project Management System | CONSYSAPMS Project Management System | CONSYSA
PMS Project Management System | CONSYSA
Accutech Services LLC
 
Project Management of Project-Blood Information Management System
 Project Management of Project-Blood Information Management System  Project Management of Project-Blood Information Management System
Project Management of Project-Blood Information Management System
Saban Kumar K.C.
 
Project Management System
Project Management SystemProject Management System
Project Management System
.AIR UNIVERSITY ISLAMABAD
 
Program Management Office Services
Program Management Office ServicesProgram Management Office Services
Program Management Office Services
Glen Alleman
 
KI_res_24_yrs_exp_big_6
KI_res_24_yrs_exp_big_6KI_res_24_yrs_exp_big_6
KI_res_24_yrs_exp_big_6
keith inman
 
Flyer ProTrack
Flyer ProTrackFlyer ProTrack
Flyer ProTrack
Sven Hankemeier
 
Foursite brochure
Foursite brochureFoursite brochure
Foursite brochure
Matt Cayton
 
Template Plano de disponibilidade dos serviços
Template Plano de disponibilidade dos serviçosTemplate Plano de disponibilidade dos serviços
Template Plano de disponibilidade dos serviços
Fernando Palma
 
Computing Project
Computing Project Computing Project
Computing Project
Er. Nawaraj Bhandari
 
Shruti ppt
Shruti pptShruti ppt
Shruti ppt
SHRUTI SAGAR
 
Ipma Paper 264 For Presentation V1.2
Ipma Paper 264 For Presentation V1.2Ipma Paper 264 For Presentation V1.2
Ipma Paper 264 For Presentation V1.2
dalenott
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
andyburghardt
 
Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00
Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00
Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00
dalenott
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
Craig Brown
 

What's hot (18)

Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
How to Implement a Project Management Information System
How to Implement a Project Management Information SystemHow to Implement a Project Management Information System
How to Implement a Project Management Information System
 
03ch
03ch03ch
03ch
 
PMS Project Management System | CONSYSA
PMS Project Management System | CONSYSAPMS Project Management System | CONSYSA
PMS Project Management System | CONSYSA
 
Project Management of Project-Blood Information Management System
 Project Management of Project-Blood Information Management System  Project Management of Project-Blood Information Management System
Project Management of Project-Blood Information Management System
 
Project Management System
Project Management SystemProject Management System
Project Management System
 
Program Management Office Services
Program Management Office ServicesProgram Management Office Services
Program Management Office Services
 
KI_res_24_yrs_exp_big_6
KI_res_24_yrs_exp_big_6KI_res_24_yrs_exp_big_6
KI_res_24_yrs_exp_big_6
 
Flyer ProTrack
Flyer ProTrackFlyer ProTrack
Flyer ProTrack
 
Foursite brochure
Foursite brochureFoursite brochure
Foursite brochure
 
Template Plano de disponibilidade dos serviços
Template Plano de disponibilidade dos serviçosTemplate Plano de disponibilidade dos serviços
Template Plano de disponibilidade dos serviços
 
Computing Project
Computing Project Computing Project
Computing Project
 
Shruti ppt
Shruti pptShruti ppt
Shruti ppt
 
Ipma Paper 264 For Presentation V1.2
Ipma Paper 264 For Presentation V1.2Ipma Paper 264 For Presentation V1.2
Ipma Paper 264 For Presentation V1.2
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00
Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00
Pmi Met Sig Congress 2007 Presentation Dale Nott V1.00
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 

Similar to PMIS at City Center - a Unifier Deployment

Enabling The Service-Oriented Enterprise
Enabling The Service-Oriented EnterpriseEnabling The Service-Oriented Enterprise
Enabling The Service-Oriented Enterprise
Nathaniel Palmer
 
New Charts Architectures (2)
New Charts Architectures (2)New Charts Architectures (2)
New Charts Architectures (2)
guestf73e68
 
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
Project Plan ERP Sample by ijaz haider malik weboriez@hotmailProject Plan ERP Sample by ijaz haider malik weboriez@hotmail
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
Ijaz Haider Malik TOGAF, Harvard MM,Siebel, PRINCE2
 
Intelligent Process Management & Visualization Technologies
Intelligent Process Management & Visualization TechnologiesIntelligent Process Management & Visualization Technologies
Intelligent Process Management & Visualization Technologies
Dafna Levy
 
Bpm nuts & bolts
Bpm nuts & boltsBpm nuts & bolts
Bpm nuts & bolts
Incessant Technologies
 
FINAL-SAP-Group5-1
FINAL-SAP-Group5-1FINAL-SAP-Group5-1
FINAL-SAP-Group5-1
Panagiotis Markidis
 
Managing Contracts with SharePoint
Managing Contracts with SharePointManaging Contracts with SharePoint
Managing Contracts with SharePoint
Ram Prabhala
 
Business Process Modeling
Business Process ModelingBusiness Process Modeling
Business Process Modeling
Sandy Kemsley
 
Erp pavan ppt
Erp pavan pptErp pavan ppt
Erp pavan ppt
pavan gupta
 
Dmn Org Aligment Essentials
Dmn Org Aligment EssentialsDmn Org Aligment Essentials
Dmn Org Aligment Essentials
Jørgen Brøndum
 
Vivek C CV
Vivek C CVVivek C CV
Vivek C CV
Vivek Cholera
 
XIT_ERPbyNet_Brochure
XIT_ERPbyNet_BrochureXIT_ERPbyNet_Brochure
XIT_ERPbyNet_Brochure
Ganesh Limaye
 
ch01-Design.ppt
ch01-Design.pptch01-Design.ppt
ch01-Design.ppt
LuckySaigon1
 
1. Introduction to Business Process Analysys
1. Introduction to Business Process Analysys1. Introduction to Business Process Analysys
1. Introduction to Business Process Analysys
GentaSahuri2
 
1Introduction To Business Process Design2Overvie.docx
1Introduction To Business Process Design2Overvie.docx1Introduction To Business Process Design2Overvie.docx
1Introduction To Business Process Design2Overvie.docx
felicidaddinwoodie
 
Vendor Management
Vendor ManagementVendor Management
Vendor Management
mikecarey491
 
Presentation to the AEA (June 23)
Presentation to the AEA (June 23) Presentation to the AEA (June 23)
Presentation to the AEA (June 23)
Daljit Banger
 
CobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced ScorecardsCobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced Scorecards
Michael Sim
 
MuraliShankar
MuraliShankarMuraliShankar
The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...
The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...
The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...
SAP Ariba
 

Similar to PMIS at City Center - a Unifier Deployment (20)

Enabling The Service-Oriented Enterprise
Enabling The Service-Oriented EnterpriseEnabling The Service-Oriented Enterprise
Enabling The Service-Oriented Enterprise
 
New Charts Architectures (2)
New Charts Architectures (2)New Charts Architectures (2)
New Charts Architectures (2)
 
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
Project Plan ERP Sample by ijaz haider malik weboriez@hotmailProject Plan ERP Sample by ijaz haider malik weboriez@hotmail
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
 
Intelligent Process Management & Visualization Technologies
Intelligent Process Management & Visualization TechnologiesIntelligent Process Management & Visualization Technologies
Intelligent Process Management & Visualization Technologies
 
Bpm nuts & bolts
Bpm nuts & boltsBpm nuts & bolts
Bpm nuts & bolts
 
FINAL-SAP-Group5-1
FINAL-SAP-Group5-1FINAL-SAP-Group5-1
FINAL-SAP-Group5-1
 
Managing Contracts with SharePoint
Managing Contracts with SharePointManaging Contracts with SharePoint
Managing Contracts with SharePoint
 
Business Process Modeling
Business Process ModelingBusiness Process Modeling
Business Process Modeling
 
Erp pavan ppt
Erp pavan pptErp pavan ppt
Erp pavan ppt
 
Dmn Org Aligment Essentials
Dmn Org Aligment EssentialsDmn Org Aligment Essentials
Dmn Org Aligment Essentials
 
Vivek C CV
Vivek C CVVivek C CV
Vivek C CV
 
XIT_ERPbyNet_Brochure
XIT_ERPbyNet_BrochureXIT_ERPbyNet_Brochure
XIT_ERPbyNet_Brochure
 
ch01-Design.ppt
ch01-Design.pptch01-Design.ppt
ch01-Design.ppt
 
1. Introduction to Business Process Analysys
1. Introduction to Business Process Analysys1. Introduction to Business Process Analysys
1. Introduction to Business Process Analysys
 
1Introduction To Business Process Design2Overvie.docx
1Introduction To Business Process Design2Overvie.docx1Introduction To Business Process Design2Overvie.docx
1Introduction To Business Process Design2Overvie.docx
 
Vendor Management
Vendor ManagementVendor Management
Vendor Management
 
Presentation to the AEA (June 23)
Presentation to the AEA (June 23) Presentation to the AEA (June 23)
Presentation to the AEA (June 23)
 
CobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced ScorecardsCobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced Scorecards
 
MuraliShankar
MuraliShankarMuraliShankar
MuraliShankar
 
The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...
The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...
The Hartford's Michael Knipper on Blueprint for Rapid and Sustainable Spend M...
 

PMIS at City Center - a Unifier Deployment