Restore streambed and banks, ~4,500 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
This project consisted of replacement of the North wing roof and repair to the load bearing South wall. Deteriorating structural conditions resulted in visible sagging in the roof, bowing, undulating and cracking of the South wall. With a goal to preserve and reuse to the extent possible, the project consisted of removing the roof, reconstructing the south wall with salvaged bricks and matching mortar, and replacing/reusing rafters and slate roof tiles. The historic ornamental ridge crest was stripped of lead paint, repaired, repainted, and re-mounted.
Snakeden Branch at Lake Audubon January 2021Fairfax County
The project stabilized approximately 760 feet of eroding stream utilizing Natural Channel Design methods and protected multiple exposed utilities. This is the first Fairfax County project to make use of pre-cast concrete blocks for imbricated structures.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
The document summarizes a community meeting to discuss the conceptual design for the Huntington Levee project. The meeting covered the project background and flooding issues facing the community. It then reviewed the conceptual design features being considered, including the use of collection drains versus a cutoff wall, different locations for a pump station, options for stormwater diversion, and use of an earthen levee alone or in combination with an I-wall. The design aims to meet FEMA accreditation standards to reduce flooding and received feedback from the community.
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use innovative & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Restore ~1,400 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Stabilize the eroding stream banks
Water quality improvement
Sustainability
Infrastructure protection
Habitat improvement
Coon Branch at Annandale Community Park-Stream Restoration ProjectFairfax County
This document discusses plans to restore 1,900 feet of Coon Branch stream located in Annandale Community Park in Fairfax County, VA. The goals of the project are to stabilize the streambed and banks to reduce sediment and nutrient inputs and improve habitat while protecting infrastructure. The existing conditions show erosion undermining trees and infrastructure like sanitary sewer manholes. Typical restoration structures to be used include cross vanes and root wads. Construction is expected to be completed in phases with monitoring in following years to assess project success.
This project consisted of replacement of the North wing roof and repair to the load bearing South wall. Deteriorating structural conditions resulted in visible sagging in the roof, bowing, undulating and cracking of the South wall. With a goal to preserve and reuse to the extent possible, the project consisted of removing the roof, reconstructing the south wall with salvaged bricks and matching mortar, and replacing/reusing rafters and slate roof tiles. The historic ornamental ridge crest was stripped of lead paint, repaired, repainted, and re-mounted.
Snakeden Branch at Lake Audubon January 2021Fairfax County
The project stabilized approximately 760 feet of eroding stream utilizing Natural Channel Design methods and protected multiple exposed utilities. This is the first Fairfax County project to make use of pre-cast concrete blocks for imbricated structures.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
The document summarizes a community meeting to discuss the conceptual design for the Huntington Levee project. The meeting covered the project background and flooding issues facing the community. It then reviewed the conceptual design features being considered, including the use of collection drains versus a cutoff wall, different locations for a pump station, options for stormwater diversion, and use of an earthen levee alone or in combination with an I-wall. The design aims to meet FEMA accreditation standards to reduce flooding and received feedback from the community.
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use innovative & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Restore ~1,400 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Stabilize the eroding stream banks
Water quality improvement
Sustainability
Infrastructure protection
Habitat improvement
Coon Branch at Annandale Community Park-Stream Restoration ProjectFairfax County
This document discusses plans to restore 1,900 feet of Coon Branch stream located in Annandale Community Park in Fairfax County, VA. The goals of the project are to stabilize the streambed and banks to reduce sediment and nutrient inputs and improve habitat while protecting infrastructure. The existing conditions show erosion undermining trees and infrastructure like sanitary sewer manholes. Typical restoration structures to be used include cross vanes and root wads. Construction is expected to be completed in phases with monitoring in following years to assess project success.
The purpose of this emergency project was to replace approximately 60-ft. segment of 8-inch wastewater sewer pipe that was broken and to retrieve a Closed-Circuit Television Inspection (CCTV) camera that was stuck in the pipe during routine maintenance work. The project was substantially complete on May 14, 2021.
Paul Springs Segment 1 & 2 Stream RestorationFairfax County
Restoration of approximately 1,800 linear feet of headwater tributaries of Paul Spring Branch that flow through Charles Goodman Park and Brickelmaier Park, and adjacent private properties.
Lakevale Sewer Improvements Community MeetingFairfax County
The document summarizes sewer improvement plans for Lakevale, VA following a sewer backup event. Short term plans include installing backflow devices on homes impacted by the backup and maintenance before storms. Mid term plans involve temporary pump station modifications. Long term plans include hydraulic modeling of system alternatives, preliminary engineering and design reports, and construction which may include upsizing pipes and storage. Community input will be gathered during planning, design, and construction through public meetings and an online project website.
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
Design Phase includes:
Finalize sewer alignment
Manhole locations and material selection
Construction phasing plan
Final restoration for former pump station site/access
Existing utility coordination
Easement acquisition (if applicable)
By-pass water & sewer locations
Temporary service outage plan – water/sewer/gas
Traffic control plans
Phasing
Detour and closure plan
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
This document provides information about a stream stabilization project along Pike Branch in Fairfax County, VA. The project aims to stabilize approximately 1,300 feet of stream between Telegraph Road and Wilton Road to improve watershed conditions, reduce flooding and erosion, create wildlife habitat, and enhance water quality. The document discusses regulatory drivers for stormwater management, details the project objectives and timeline, describes existing conditions along the stream, and outlines proposed stabilization structures and retaining wall repairs. Next steps outlined include completing design plans and scheduling construction.
Miller Heights Outfall Rehabilitation Project 2014Fairfax County
The Miller Heights Outfall Rehabilitation Project was completed on time and within budget. The project involved stabilizing over 250 feet of eroded channel near Miller Road and Miller Heights Road. Natural stream channel design was used, including rock cross vanes, weirs, and plantings to reduce erosion and improve water quality. The project addressed safety concerns and stabilized the channel while providing environmental benefits.
The project consists primarily of the interior renovation and reconfiguration of an
existing one story institutional residential care facility with minor site improvements.
The building is approximately 9,500 square feet (SF) previously housing a Boys
Probation House. The renovation will provide for a Crisis Care Program providing
adult crisis stabilization treatment services through the Fairfax County Community
Services Board (CSB). The key elements of the overall project scope include:
Interior renovation with selective demolition and floor plan changes
Interior finish upgrades
New toilet rooms and existing bathroom ADA update
Building system upgrades for MEP, fire protection and security
Roofing and dormer improvements
Parking lot re-striping, new fencing and concrete pads
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
Anticipated Schedule for Construction (estimate 34 weeks)
Restoration schedules can overlap with multiple crews
Plantings occur in spring, fall, and/or winter (live stakes) seasons
Includes 1-year warranty on structures and vegetation
Vegetation warranty starts when planting ends (may be delayed for season)
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
This project included 3,000 linear feet of stormwater improvements that promote infiltration, improve water quality, and safely convey stormwater through the neighborhood to a stream.
The Bradley Acres Pond Retrofit project in Fairfax County, VA converted an existing dry pond into a constructed wetland pond. The project removed the existing trickle ditch, excavated three shallow marshes, constructed a step pool conveyance channel and plunge pool, and installed two stone weir structures. Native plants were seeded and trees/plugs were replanted. The project provides improved downstream water quality by removing nutrients and suspended solids from stormwater runoff.
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
The document outlines plans for the Huntington Levee Project which aims to protect homes from flooding through the construction of an earthen levee and pump station, and discusses the project background, design features, construction process, community amenities, flood modeling results, permitting, schedule, environmental considerations, and community outreach efforts. Construction is scheduled to begin in early 2017 and be completed by spring 2019. The project team is committed to ongoing communication and addressing community concerns throughout construction.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
The Green Hill Estates Sewer Emergency project addressed a broken 8-inch sewer pipe and the erosion of the adjacent stream. The emergency was discovered during routine sewer cleaning and inspection. A break, along with several other defects, were noted in the sewer. In addition, the creek had eroded and had partially exposed the pipe. The stream was diverted and restored, and the broken pipe segment was replaced with a section of PVC pipe. The project was substantially completed August 10, 2021.
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Fairfax County
This Fairfax County project seeks to stabilize excessive, ongoing stream erosion which threatens sanitary sewer pipes, undermines trees, impacts water quality and degrades habitat for aquatic life.
Dead Run Segment One Stream Restoration ProjectFairfax County
The document summarizes a public meeting held by Fairfax County to discuss plans for restoring a segment of Dead Run stream. The project aims to create a stable stream channel that reduces erosion and improves water quality. It will involve regrading the channel, installing structures to reduce erosion, replacing trees lost to the project, and adding two pedestrian bridges and a fording area. Attendees viewed design plans, asked questions, and were invited to provide comments and tour the project site.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018Fairfax County
This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
The purpose of this emergency project was to replace approximately 60-ft. segment of 8-inch wastewater sewer pipe that was broken and to retrieve a Closed-Circuit Television Inspection (CCTV) camera that was stuck in the pipe during routine maintenance work. The project was substantially complete on May 14, 2021.
Paul Springs Segment 1 & 2 Stream RestorationFairfax County
Restoration of approximately 1,800 linear feet of headwater tributaries of Paul Spring Branch that flow through Charles Goodman Park and Brickelmaier Park, and adjacent private properties.
Lakevale Sewer Improvements Community MeetingFairfax County
The document summarizes sewer improvement plans for Lakevale, VA following a sewer backup event. Short term plans include installing backflow devices on homes impacted by the backup and maintenance before storms. Mid term plans involve temporary pump station modifications. Long term plans include hydraulic modeling of system alternatives, preliminary engineering and design reports, and construction which may include upsizing pipes and storage. Community input will be gathered during planning, design, and construction through public meetings and an online project website.
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
Design Phase includes:
Finalize sewer alignment
Manhole locations and material selection
Construction phasing plan
Final restoration for former pump station site/access
Existing utility coordination
Easement acquisition (if applicable)
By-pass water & sewer locations
Temporary service outage plan – water/sewer/gas
Traffic control plans
Phasing
Detour and closure plan
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
This document provides information about a stream stabilization project along Pike Branch in Fairfax County, VA. The project aims to stabilize approximately 1,300 feet of stream between Telegraph Road and Wilton Road to improve watershed conditions, reduce flooding and erosion, create wildlife habitat, and enhance water quality. The document discusses regulatory drivers for stormwater management, details the project objectives and timeline, describes existing conditions along the stream, and outlines proposed stabilization structures and retaining wall repairs. Next steps outlined include completing design plans and scheduling construction.
Miller Heights Outfall Rehabilitation Project 2014Fairfax County
The Miller Heights Outfall Rehabilitation Project was completed on time and within budget. The project involved stabilizing over 250 feet of eroded channel near Miller Road and Miller Heights Road. Natural stream channel design was used, including rock cross vanes, weirs, and plantings to reduce erosion and improve water quality. The project addressed safety concerns and stabilized the channel while providing environmental benefits.
The project consists primarily of the interior renovation and reconfiguration of an
existing one story institutional residential care facility with minor site improvements.
The building is approximately 9,500 square feet (SF) previously housing a Boys
Probation House. The renovation will provide for a Crisis Care Program providing
adult crisis stabilization treatment services through the Fairfax County Community
Services Board (CSB). The key elements of the overall project scope include:
Interior renovation with selective demolition and floor plan changes
Interior finish upgrades
New toilet rooms and existing bathroom ADA update
Building system upgrades for MEP, fire protection and security
Roofing and dormer improvements
Parking lot re-striping, new fencing and concrete pads
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
Anticipated Schedule for Construction (estimate 34 weeks)
Restoration schedules can overlap with multiple crews
Plantings occur in spring, fall, and/or winter (live stakes) seasons
Includes 1-year warranty on structures and vegetation
Vegetation warranty starts when planting ends (may be delayed for season)
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
This project included 3,000 linear feet of stormwater improvements that promote infiltration, improve water quality, and safely convey stormwater through the neighborhood to a stream.
The Bradley Acres Pond Retrofit project in Fairfax County, VA converted an existing dry pond into a constructed wetland pond. The project removed the existing trickle ditch, excavated three shallow marshes, constructed a step pool conveyance channel and plunge pool, and installed two stone weir structures. Native plants were seeded and trees/plugs were replanted. The project provides improved downstream water quality by removing nutrients and suspended solids from stormwater runoff.
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
The document outlines plans for the Huntington Levee Project which aims to protect homes from flooding through the construction of an earthen levee and pump station, and discusses the project background, design features, construction process, community amenities, flood modeling results, permitting, schedule, environmental considerations, and community outreach efforts. Construction is scheduled to begin in early 2017 and be completed by spring 2019. The project team is committed to ongoing communication and addressing community concerns throughout construction.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
The Green Hill Estates Sewer Emergency project addressed a broken 8-inch sewer pipe and the erosion of the adjacent stream. The emergency was discovered during routine sewer cleaning and inspection. A break, along with several other defects, were noted in the sewer. In addition, the creek had eroded and had partially exposed the pipe. The stream was diverted and restored, and the broken pipe segment was replaced with a section of PVC pipe. The project was substantially completed August 10, 2021.
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Fairfax County
This Fairfax County project seeks to stabilize excessive, ongoing stream erosion which threatens sanitary sewer pipes, undermines trees, impacts water quality and degrades habitat for aquatic life.
Dead Run Segment One Stream Restoration ProjectFairfax County
The document summarizes a public meeting held by Fairfax County to discuss plans for restoring a segment of Dead Run stream. The project aims to create a stable stream channel that reduces erosion and improves water quality. It will involve regrading the channel, installing structures to reduce erosion, replacing trees lost to the project, and adding two pedestrian bridges and a fording area. Attendees viewed design plans, asked questions, and were invited to provide comments and tour the project site.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018Fairfax County
This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Long Branch Central Watershed Management Area Project Overview July 2020Fairfax County
Fairfax County overview of the Long Branch Central Watershed Project restoration of eight miles of stream to achieve waste load reduction requirements and provide long term stability with less maintenance.
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
The plan is to return the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor within the constraints of the developed landscape.
Long Branch Central Watershed Management Area 03-03-2021Fairfax County
Project Goals:
Achieve Long Branch Central TMDL waste load reduction requirements.
Provide long-term stability and have low maintenance.
Improve water quality within the Long Branch Central watershed.
Improve habitat and environmental health (ecological lift).
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Fairfax County
This document summarizes a stream restoration project in Fairfax County, VA. The project aims to restore 1,200 feet of streams and improve water quality by reducing sediment and nutrient inputs. It will stabilize streambeds and banks, provide floodplain connectivity, and improve habitat. The presentation provides information on watershed management goals, existing stream conditions, restoration designs including typical structures, construction examples, and landscaping plans. It outlines next steps such as design reviews and permitting before anticipated construction from fall/winter 2018 to fall/winter 2019.
Paul Spring Segment 1 at Hollin Hills Stream Restoration ProjectFairfax County
This document summarizes a stream restoration project along Paul Spring Segment 1 in Fairfax County, VA. The project aims to restore 1,600 feet of stream through stabilizing banks, reducing sediment and improving habitat. It will address issues like erosion, flooding, and loss of recreational areas. The design process involves community input, assessing existing conditions, developing conceptual plans, and securing easements. Construction will use structures like cross vanes and root wads to control flows and velocities. The project goals are to improve watershed conditions while coordinating with stakeholders.
Columbia Road/Randolph Court Stream Restoration July 2015Fairfax County
This document summarizes a proposed stream restoration project in Fairfax County, VA. It describes the existing failing gabion walls and eroding stream banks. The proposed project would replace the gabion walls with more natural stream restoration structures like cross vanes, root wads, and boulder toes to stabilize the banks. It would also add planted buffer zones and benches along the stream. The project requires designing temporary construction access given the steep slopes, and coordinating with other planned restoration work. It outlines the conceptual design, approval, and construction schedule.
Long Branch Central Watershed Management Area Project Overview October 26, 2020Fairfax County
Information about development in Fairfax County, major stormwater management project drivers, a functions-based approach to stream restoration and more information about the project is included in the presentation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Overview of the Fairhill/MLK green infrastructure ambassador project taking shape in Cleveland. Includes details on project history, improvements, Project Clean Lake, traffic patterns and impacts during construction, and more.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
Dead Run Stream Restoration Project Segments 2/3 – Final Concept PlanFairfax County
This document summarizes a community meeting about a stream restoration project on Dead Run in Fairfax County, VA. The project involves restoring 750 linear feet of stream in McLean Central Park (Segment 2) and 1,460 linear feet in Dead Run Stream Valley Park (Segment 3). The meeting outlined existing poor stream conditions, the proposed restoration design which aims to reduce erosion and improve habitat and water quality, and next steps including finalizing the design and beginning construction. Community concerns about tree loss and flooding were also addressed.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Similar to Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and Community Meeting (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
This document summarizes a pedestrian access improvement project along Clarks Crossing Road in Fairfax County, Virginia. The project improved pedestrian and bicycle access by constructing a missing link of sidewalk between Brookside Lane and an existing sidewalk further along Clarks Crossing Road. Work included installing sidewalk, curb ramps, drainage improvements, and milling and overlaying asphalt. The project was substantially completed in March 2022 and provides approximately 200 feet of new pedestrian access along Clarks Crossing Road.
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Sully Community Center Construction ProgressFairfax County
This document provides construction progress photos of the Sully Community Center in Fairfax County, Virginia. The photos show the ongoing construction of the building's exterior, interior spaces like the lobby, corridors, multi-purpose rooms, game room, gym, exercise room, and healthcare suite. The document was published by the Fairfax County Department of Public Works and Environmental Services to share updates on the construction of the new community center, which is scheduled to open in summer 2022.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This document summarizes a meeting about a proposed arts center in Reston, Virginia that would result from a proffer from Boston Properties for development of an area known as Block J. The meeting covered the background and objectives of community outreach efforts to understand needs for the arts venue. Feedback was shared from previous focus group meetings on performing arts, visual arts, and other topics. Key spaces discussed included a 500-seat theater, art studios, galleries, and support spaces. Next steps include further programming, cost estimating, and community input before potential design and construction.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
This document summarizes a focus group meeting to discuss needs and ideas for a proposed new arts center in Reston, Virginia. The meeting covered background on the proposed project, which would result from a development proffer. Attendees provided input through polls and discussion on desired visual arts programming, spaces, and amenities. Key priorities identified included studio space, galleries, classrooms, digital media facilities, and ensuring the center is diverse, equitable and accessible. The project team will take this community feedback into account as they continue planning.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
The project consists of a new 17,400 square feet, two-story, four-bay fire station facility and associated improvements to the one-acre site including stormwater detention, landscaping, and parking. The scope also included the demolition of the existing two and a half bay facility, and construction of a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements include:
Apparatus Bays, Control Room and Offices
Battalion Chief Suite
Kitchen, Dayroom, and Dining Room
Bunk Rooms
Showers and Locker Rooms
Exercise Room
Ready Gear Room
Reston Arts Center Community Meeting 02-28-22Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
The CBC machine is a common diagnostic tool used by doctors to measure a patient's red blood cell count, white blood cell count and platelet count. The machine uses a small sample of the patient's blood, which is then placed into special tubes and analyzed. The results of the analysis are then displayed on a screen for the doctor to review. The CBC machine is an important tool for diagnosing various conditions, such as anemia, infection and leukemia. It can also help to monitor a patient's response to treatment.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...amsjournal
The Fourth Industrial Revolution is transforming industries, including healthcare, by integrating digital,
physical, and biological technologies. This study examines the integration of 4.0 technologies into
healthcare, identifying success factors and challenges through interviews with 70 stakeholders from 33
countries. Healthcare is evolving significantly, with varied objectives across nations aiming to improve
population health. The study explores stakeholders' perceptions on critical success factors, identifying
challenges such as insufficiently trained personnel, organizational silos, and structural barriers to data
exchange. Facilitators for integration include cost reduction initiatives and interoperability policies.
Technologies like IoT, Big Data, AI, Machine Learning, and robotics enhance diagnostics, treatment
precision, and real-time monitoring, reducing errors and optimizing resource utilization. Automation
improves employee satisfaction and patient care, while Blockchain and telemedicine drive cost reductions.
Successful integration requires skilled professionals and supportive policies, promising efficient resource
use, lower error rates, and accelerated processes, leading to optimized global healthcare outcomes.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
Literature Review Basics and Understanding Reference Management.pptxDr Ramhari Poudyal
Three-day training on academic research focuses on analytical tools at United Technical College, supported by the University Grant Commission, Nepal. 24-26 May 2024
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
gray level transformation unit 3(image processing))
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and Community Meeting
1. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Housekeeping and Logistics
PLEASE MUTE YOURSELF ASK QUESTIONS FOR US IN
THE CHAT
SLIDES WILL BE AVAILABLE
ON OUR WEBSITE
Q/A WILL BE AT THE END
2. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Long Branch @ Arlington Boulevard and Robin Ridge Court
Concept Design Community Meeting
December 7, 2021
3. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Who Are We?
3
Department of Public Works and
Environmental Services
Capital
Facilities
Solid Waste Stormwater
Stormwater Planning
Division
Maintenance and
Stormwater
Management
Division
Wastewater
4. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Agenda
4
• Program Drivers
• Vicinity Map
• Project and Social Goals
• Project Background
• Existing Conditions
• Concept Design
• Typical Structures
• Completed Projects
• Next Steps
• Contact Information
5. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Stormwater Program Drivers
5
In response to The Clean Water Act of 1972…
• Municipal Separate Storm Sewer Permit (MS-4)
• Chesapeake Bay Total Maximum Daily Loads (TMDL)
– Regulates amount of pollutants in waterways
• Other Local TMDLs = Local Stream Health
• Maintenance of Existing Stormwater Infrastructure
• Dam Safety Regulations
• Public Safety /Emergency Response
6. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Vicinity map
6
7. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Project Goals
7
• Restore streambed and banks, ~4,500 linear
feet
• Reduce sediment and nutrient inputs into stream system
• Installation of grade control structures, improve/correct
channel dimension and alignment
• Improve floodplain connectivity and ecological
processes
• Reduce force and volume of water within the channel during
storm and flood events
• Naturally process nutrients and sediments on the floodplain
and within the streambed
• Improve habitat for biological community
• Native landscaping
• Floodplain wetlands
• Streambed and flow diversity
• In-stream structures
• Protect Infrastructure – Sanitary Sewer Lines
• Channel Relocation away from sanitary sewer lines when
possible
• Armoring channel banks and bottom where relocation is not
an option
8. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Social Goals
8
1. Maintain open dialog and share
information.
2. Coordinate with all the
stakeholders and the
community.
3. Build partnerships with local
organizations such as
homeowners associations.
9. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Project Background
9
Design Winter 2019 - Fall 2022
Construction - TBD
Inspection
Survey Fall 2018
Revegetation
Design Team:
• Wetland Studies and Solutions, Inc
• Stormwater Planning Division
• Utilities Design and Construction Division
10. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Channel Evolution Model
10
11. Long Branch @ Arlington Boulevard and Robin Ridge Court
Existing Conditions
11
12. Long Branch @ Arlington Boulevard and Robin Ridge Court
Existing Conditions
12
13. Long Branch @ Arlington Boulevard and Robin Ridge Court
Existing Conditions
13
14. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Proposed Design
14
• Concept Design Plan
• Multiple Construction
Access Points
• Tree Inventory
• Optimizing floodplain
connectivity
15. Stormwater Planning Division
Crook Branch @ Mantua Elementary School Stream Restoration
Stream Structures and Bed Reinforcement
15
Reinforced Bed
Step Pools Cross Vanes
16. Stormwater Planning Division
Crook Branch @ Mantua Elementary School Stream Restoration
Stream Reinforcement – Using Wood
16
Toe Wood
Type I Woody Debris
Riffle Log Rollers
In-Stream Habitat Log Sill
17. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Proposed Design
17
• Adding sinuosity to
create a longer
meander path to slow
down water
• Implementing trees
back into the stream
as woody debris
• Utilizing the
floodplain
• Protecting trees of
value
• Building grade control
structures to stabilize
stream banks
18. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Tree Survey
18
• # of Trees Surveyed (> 12”) = 528
• # of Trees to be removed (>12”) =
232
– Poor/Dead Trees = 56
• Trees that are removed are used in
the stream design as woody habitat
• Careful consideration goes into tree
removal, with evaluation from the
County’s Urban Forester on tree
prioritization
• Trees of lesser value are targeted
for removal
19. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Strategies for Successful Revegetation
• Pre-Construction
– Non-Native Invasive Plant Management
• Establish clear zone so that natives can
re-establish
• Final Phase of Construction
– Stabilize with native seed
– Plant native shrubs and trees
– Minimum 1-year warranty
• Minimum 3-year monitoring
– For Native Vegetative Cover
– Less than 20% Invasive
– Zero % Highly Invasive
19
20. Stormwater Planning Division
Long Branch @ Arlington Boulevard and Robin Ridge Court
Completed Restoration Examples – Dead Run Segment 1
20
21. Stormwater Planning Division
Long Branch @ Arlington Boulevard and Robin Ridge Court
Completed Restoration Examples – Dead Run Segment 1
21
22. Stormwater Planning Division
Long Branch @ Arlington Boulevard and Robin Ridge Court
Completed Restoration Examples – Dead Run Segment 1
22
23. Stormwater Planning Division
Long Branch @ Arlington Boulevard and Robin Ridge Court
Completed Restoration Examples – Dead Run Segment 1
23
24. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Temporary Infrastructure to Restore the Stream
24
Access road and tree protection area
Construction staging and stockpile
25. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Large Construction Equipment is Required
25
Track truck Excavator
26. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Schedule
26
• Concept design – May 11, 2021
• Community meeting - Fall 2021
• Final Design – Fall 2022
• “Pardon Our Dust” Community
Meeting – prior to construction
• Construction – Fiscal Year 2024
• pending approval of future funding
27. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Contact Information
27
Vivian Bui– Project Manager
703-324-5609
Vivian.Bui@fairfaxcounty.gov
Stormwater Planning Division
703-324-5500, TTY 711
12000 Government Center Parkway
Suite 449
Fairfax, Virginia 22035
www.fairfaxcounty.gov/publicworks/stormwater
To request this information in an alternate format call 703-324-5500, TTY 711
28. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division
Online Resources
28
• Stormwater Planning Division Website
• https://www.fairfaxcounty.gov/publicworks/stormwater/
• Northern Virginia Soil and Water Conservation District
• http://www.fairfaxcounty.gov/nvswcd/newsletter/planning.htm
• Long Branch North @ Arlington Blvd and Robin Ridge Rd Stream Restoration
• https://www.fairfaxcounty.gov/publicworks/stormwater/plans-projects/long-branch-north-
arlington-blvd-and-robin-ridge-court-stream-restoration-sd-000031-219
29. Long Branch @ Arlington Boulevard and Robin Ridge Court
Stormwater Planning Division 29
Questions?
Editor's Notes
use the raise hand feature if you would like to
We are the Stormwater Planning Division, that takes care of capital improvement projects such as stream restoration and other stormwater improvement projects. Our sister agency, MSMD, handles the maintenance of infrastructure such as pipes, outfalls, and existing ponds, and much more. Together we are one of the four business areas of the department of public works.
Now that we took care of the WHO, I will next go over the WHY, our overarching program drivers that facilitate our work
Next I’ll go over general project information and goals and existing conditions
I’ll take us through the concept plan that has been developed, showing some typical structures that been successful on completed projects and will be used again in this one
I’ll end with example photos of completed projects, and what is to come next, along with my contact information for those who would like to reach me
There are multiple federal, state and local regulations that we must comply with in regards to water quality
In general, they all have different ways of saying we need to reduce pollutants into our waterways, specifically the Chesapeake Bay
Erosion is common in urban streams due to development and the reduction of pervious areas. The ground is a natural sponge, and when we build roads, schools, our homes and other buildings, we remove that sponge effect, and instead of water soaking into the ground, it goes rushing downhill and eventually firehoses into our streams.
That unusually high velocity of water is one cause of erosion, and that sediment dissolves into the water and we start to get an excess amount of nitrogen, phosphorus and total suspended solids into our waterways which suffocates aquatic life and pollutes our water.
Stormwater as a business area of Public Works is relatively new, we just turned 20 last year, and we exist for other reasons such as maintenance of our infrastructure as I had mentioned, and also to regulate local dams and be prepared for emergency response, specifically for major hurricanes or tropical storms
This drainage area that flows into our project area consists of nearly 50% impervious area.
What’s unique about this reach down here is that has a large existing floodplain that is relatively empty of trees, extremely high in non-native invasives and has great potential for stream revitalization.
To note, there are existing storm water and floodplain easements through this entire stream valley which gives the County permission to enter and restore the stream channel
Ultimately, mass erosion, as we often experience in developed communities is bad. If we can reduce this mass erosion, we reduce how much sediment is falling into the water, which is a source of the excess nutrients found in the stream valley/Potomac River and ultimately the Chesapeake Bay, as we saw in that NASA photo
As mentioned, there is 50% impervious area in this drainage area which means half of this area is asphalt, concrete, roofs, buildings, where water cannot infiltrate into the ground and instead rushes through pipe systems and later fire hosing into Long Branch during large storm events.
With that large quantity of fast moving water in mind, a lot of design effort has been made to make sure we design a stream that conveys water efficiently
Allowing water to escape out of the channel and into the floodplain is an extremely important concept of a healthy stream restoration
In a natural, healthy stream valley, there is always an activated floodplain, where water can reside to infiltrate slowly as opposed to be rushed downstream
By doing so, there is less force and volume within the channel which is what often leads to erosion. Also, utilizing the floodplain allows us to design the streams more naturally with less heavy “engineered” solutions such as gabion baskets or massive boulders to protect the stream
The floodplain acts a natural filter for nutrients and sediments that would normally be washed downstream. From a landscaping perspective, the moist nature of the floodplain allows for ecological diversity with wet loving plants.
That then segways to improving the ecological habitat, to introduce back wildlife that have been absent, and remove the invasives that are currently taking over
As we get further into the design, an extensive native landscaping plan will be developed to encourage species diversity, and these native plants will be another source of natural filters for water entering the stream valley
We want to protect our sanitary infrastructure by either relocating the channel away from them, or armoring the banks and bottom when that is not an option
The last thing anybody wants is a broken pipe with sewage spilling into our stream.
We plan on holding more of these community meetings as we continue through the design process, and keep that open dialog going and get feedback
We don’t want to surprise anyone when the project goes under construction and make sure that we set realistic expectations with the community, you all, that will be directly impacted by this project. We understand that this is your home and want to respect that and encourage participation
We have taken this design through review by ecologists, urban foresters, residents, and engineers.
Design Team includes engineers, ecologists, arborists, landscape architect, technicians, and other field staff to help pull this project together.
A TEAM effort with many different backgrounds and expertise
This graphic here is my last “Stream 101” slide, and it is the Channel Evolution Model that most urban streams go through.
In an ideal circumstances, there is a constant base flow within the channel, and it can escape to a small bench or floodplain during larger events
However when there is land use change, whether it is neighborhoods or roads, that bench starts to wash away and is now more incised with shear stresses from lots of water flowing through
Eventually there is this downcutting effecting until the sides start to cave in, or if bedrock is hit, and then we have this widening effect.
Overtime, the stream will heal itself by naturally forming benches again, but at the expense of widening and eating up land, which in this case, is a lot of people’s backyards and in extreme cases, into people’s homes.
That is why we’re here to restore the stream. We are trying to prevent further movement of the stream because of these outside factors and instead design a stream that will convey water in a healthy and natural fashion
Conduct Geomorphic and Watershed (HH assessment).
CEM
Incision (also know as downcutting or headcutting) can occur independently or
simultaneously with meander migration. The bed is eroded and the base level of the
stream is lowered. Downcutting increases bank height, which can eventually lead to
bank failure and channel widening. Widening and downcutting continue until equilibrium
is regained.
Aggradation occurs when sediment supply exceeds transport capacity and the stream
deposits sediment in the channel. Aggradation can be triggered by an increase in
sediment supply due to upstream channel erosion or land development, or by a
decrease in discharge, which reduces the transport capacity of the system. Deposition
continues until a new state of dynamic equilibrium is achieved.
Access path/staging areas are placed in areas of surveyed dead trees