Fairfax County overview of the Long Branch Central Watershed Project restoration of eight miles of stream to achieve waste load reduction requirements and provide long term stability with less maintenance.
Long Branch Central Watershed Management Area Project Overview October 26, 2020Fairfax County
Information about development in Fairfax County, major stormwater management project drivers, a functions-based approach to stream restoration and more information about the project is included in the presentation.
Long Branch Central Watershed Management Area 03-03-2021Fairfax County
Project Goals:
Achieve Long Branch Central TMDL waste load reduction requirements.
Provide long-term stability and have low maintenance.
Improve water quality within the Long Branch Central watershed.
Improve habitat and environmental health (ecological lift).
Introduction to Biohabitats presentation public meeting number one 02 11-21Fairfax County
Phase I.A – Field Assessment Work Plan Development
Existing watershed information, data and mapping
Public outreach and participation plan
Restoration goals
Field assessment plan (streams, outfalls, riparian areas and County-maintained stormwater facilities)
Preliminary approach to monitoring and identify early-action items
Preliminary design and permitting approaches
Long Branch Central Watershed Field Assessment Work Plan
Phase I.B – Watershed Field Assessment and Opportunity Identification
Field assessment and opportunity identification (streams, outfalls, riparian areas and County-maintained stormwater facilities)
Inventory and condition assessment data
Preliminary Project Identification and Prioritization
Phase I.C – Restoration Implementation Work Plan
Piney Run Public Meeting 1 October 17, 2018Fairfax County
This project will restore 4,300 feet of stream on Lake Werowance Inc. and privately owned properties. Goals are stabilized stream banks and bed, reduced sediment and nutrients, improved habitat, and enhanced water quality.
Powerpoint tripps run at barrett road presentation websiteFairfax County
This document summarizes a study of flood mitigation scenarios for Tripps Run at Barrett Road in Fairfax County, VA. Four scenarios were analyzed: 1) raising a bridge, 2) stream enhancements without property acquisition, 3) acquiring 9 properties for floodplain restoration, and 4) acquiring 16 properties for restoration. Scenario 3 provided the best balance of benefits, reducing flood levels by up to 4.6 feet, removing 13 structures from the floodplain, and costing an estimated $12.7 million. The consultants recommended pursuing additional information to support a decision on implementing Scenario 3.
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Fairfax County
The goal of the stream restoration project is to build an ecologically sound restoration that balances water quality benefits with riparian function and park user experience.
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021Fairfax County
The Rocky Run Tributary at Hickory Hollow Lane project goals are to stabilize the stream, reduce excess sediment from flowing downstream; improve aesthetics, reduce hazards, reconnect the stream to the floodplain, improve the riparian buffer and reduce road flooding, among other goals.
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Fairfax County
This Fairfax County project seeks to stabilize excessive, ongoing stream erosion which threatens sanitary sewer pipes, undermines trees, impacts water quality and degrades habitat for aquatic life.
Long Branch Central Watershed Management Area Project Overview October 26, 2020Fairfax County
Information about development in Fairfax County, major stormwater management project drivers, a functions-based approach to stream restoration and more information about the project is included in the presentation.
Long Branch Central Watershed Management Area 03-03-2021Fairfax County
Project Goals:
Achieve Long Branch Central TMDL waste load reduction requirements.
Provide long-term stability and have low maintenance.
Improve water quality within the Long Branch Central watershed.
Improve habitat and environmental health (ecological lift).
Introduction to Biohabitats presentation public meeting number one 02 11-21Fairfax County
Phase I.A – Field Assessment Work Plan Development
Existing watershed information, data and mapping
Public outreach and participation plan
Restoration goals
Field assessment plan (streams, outfalls, riparian areas and County-maintained stormwater facilities)
Preliminary approach to monitoring and identify early-action items
Preliminary design and permitting approaches
Long Branch Central Watershed Field Assessment Work Plan
Phase I.B – Watershed Field Assessment and Opportunity Identification
Field assessment and opportunity identification (streams, outfalls, riparian areas and County-maintained stormwater facilities)
Inventory and condition assessment data
Preliminary Project Identification and Prioritization
Phase I.C – Restoration Implementation Work Plan
Piney Run Public Meeting 1 October 17, 2018Fairfax County
This project will restore 4,300 feet of stream on Lake Werowance Inc. and privately owned properties. Goals are stabilized stream banks and bed, reduced sediment and nutrients, improved habitat, and enhanced water quality.
Powerpoint tripps run at barrett road presentation websiteFairfax County
This document summarizes a study of flood mitigation scenarios for Tripps Run at Barrett Road in Fairfax County, VA. Four scenarios were analyzed: 1) raising a bridge, 2) stream enhancements without property acquisition, 3) acquiring 9 properties for floodplain restoration, and 4) acquiring 16 properties for restoration. Scenario 3 provided the best balance of benefits, reducing flood levels by up to 4.6 feet, removing 13 structures from the floodplain, and costing an estimated $12.7 million. The consultants recommended pursuing additional information to support a decision on implementing Scenario 3.
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Fairfax County
The goal of the stream restoration project is to build an ecologically sound restoration that balances water quality benefits with riparian function and park user experience.
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021Fairfax County
The Rocky Run Tributary at Hickory Hollow Lane project goals are to stabilize the stream, reduce excess sediment from flowing downstream; improve aesthetics, reduce hazards, reconnect the stream to the floodplain, improve the riparian buffer and reduce road flooding, among other goals.
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Fairfax County
This Fairfax County project seeks to stabilize excessive, ongoing stream erosion which threatens sanitary sewer pipes, undermines trees, impacts water quality and degrades habitat for aquatic life.
Rocky Run Tributary at Dulles Access Road Stream Restoration ProjectFairfax County
Restore up to 1,200 feet of stream within the wooded dry pond footprint.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream
Improve habitat
Reduce long-term maintenance of pond
Consider water quality enhancements and a litter collection system in the open pond area
Maintain close coordination with stakeholders
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Fairfax County
Restore approximately 3,500 feet of stream on Lake Werowance Inc. and privately owned properties.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream system
Improve habitat
Maintain close coordination with stakeholders
Enhance water quality and biological diversity through the enhancements of existing wetland features within the former lakebed
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
The plan is to return the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor within the constraints of the developed landscape.
Piney Run at Lake Werowance Stream Restoration ProjectFairfax County
Improve watershed conditions and reduce downstream impacts through….
Stabilize the channel
Reduce erosion
Protect vegetation
Restore native vegetation & riparian buffer
Connect and enhance wetlands within former lakebed
Improve water quality
Paul Springs Segment 1 & 2 Stream RestorationFairfax County
Restoration of approximately 1,800 linear feet of headwater tributaries of Paul Spring Branch that flow through Charles Goodman Park and Brickelmaier Park, and adjacent private properties.
This document provides details about a pond retrofit project in Fairfax County, VA called Towlston Meadows Sec 3 Pond 1. The purpose of the project was to increase water quality and add an access road for maintenance. Work included regrading the pond, adding micro pools, increasing storage volume, and constructing an all-weather access road. Native plants were also installed to restore the landscape. The project was completed on time and on budget in April 2014.
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public MeetingFairfax County
This document summarizes a public meeting to discuss draft action plans for sediment, bacteria, and PCBs total maximum daily loads (TMDLs) in Fairfax County, Virginia. It provides an overview of the county's municipal separate storm sewer system permit requirements and TMDL development process. The draft action plans address approved TMDLs for sediment impairment in Bull Run, Difficult Run, and Popes Head Creek, and bacteria impairment in several waterbodies. The sediment plan focuses on retrofit and stream restoration projects to meet load reduction targets. The bacteria plan emphasizes identifying and eliminating illicit discharges through inspection and monitoring programs.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
The Wakefield Park South Stream Restoration project in Fairfax County, VA was completed ahead of schedule and on budget. The project restored 2,700 linear feet of streams that feed into Accotink Creek using natural channel design techniques. This included establishing stable channels and floodplains, installing structures to reduce erosion and improve habitat, and reducing nitrogen, phosphorus, and sediment runoff into Accotink Creek. The project was a collaboration between Fairfax County agencies and private contractors.
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Fairfax County
This document summarizes a public meeting to discuss a stream restoration project on Bull Neck Run at the Spring Hill Recreation Center. The meeting outlined Fairfax County's watershed planning efforts, presented the project objectives and existing conditions, and proposed improvements and example projects. Attendees were invited to ask questions. The project aims to provide water quality controls and protect channel capacity as required for a recreation center expansion. Next steps include design, permitting, public feedback, construction, and long-term maintenance.
Oakton Swim and Racquet Water Quality RetrofitFairfax County
The Oakton Swim & Racquet Water Quality Retrofit Project in Fairfax County, VA involved retrofitting three stormwater inlet areas with rain gardens to improve water quality. The project was completed in April 2015. It installed rain gardens to remove sediment and pollutants from stormwater runoff, reducing nitrogen, phosphorus, and sediment levels in nearby waterways. The project team included members from the county's Stormwater Planning Division, Urban Forest Management Division, and Utilities Design and Construction Division.
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020Fairfax County
The virtual community meeting held on Sept 29, 2020 advised residents about the proposed stream restoration in a Pimmit Run tributary at the George Marshall High School in Fairfax County, VA.
Non-regulatory and Advisory:
Administer programs that conserve natural resources at the local level, based on local needs.
Provide technical assistance and work with cooperators to implement beneficial practices on their lands.
Support and complement Fairfax County programs to address issues of common concern.
Dead Run Stream Restoration Public Meeting April 23, 2014Fairfax County
This document summarizes a public meeting about a stream restoration project along Dead Run in Fairfax County, Virginia. The meeting outlined Fairfax County's stormwater management program and watershed planning efforts. It then provided details on the existing conditions of Dead Run, several restoration options being considered, and examples of previous similar projects. Attendees were invited to ask questions about the Dead Run Stream Restoration Project and next steps in the planning and implementation process.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
Restore streambed and banks, ~4,500 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Rocky Run Tributary at Dulles Access Road Stream Restoration ProjectFairfax County
Restore up to 1,200 feet of stream within the wooded dry pond footprint.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream
Improve habitat
Reduce long-term maintenance of pond
Consider water quality enhancements and a litter collection system in the open pond area
Maintain close coordination with stakeholders
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Fairfax County
Restore approximately 3,500 feet of stream on Lake Werowance Inc. and privately owned properties.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream system
Improve habitat
Maintain close coordination with stakeholders
Enhance water quality and biological diversity through the enhancements of existing wetland features within the former lakebed
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
The plan is to return the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor within the constraints of the developed landscape.
Piney Run at Lake Werowance Stream Restoration ProjectFairfax County
Improve watershed conditions and reduce downstream impacts through….
Stabilize the channel
Reduce erosion
Protect vegetation
Restore native vegetation & riparian buffer
Connect and enhance wetlands within former lakebed
Improve water quality
Paul Springs Segment 1 & 2 Stream RestorationFairfax County
Restoration of approximately 1,800 linear feet of headwater tributaries of Paul Spring Branch that flow through Charles Goodman Park and Brickelmaier Park, and adjacent private properties.
This document provides details about a pond retrofit project in Fairfax County, VA called Towlston Meadows Sec 3 Pond 1. The purpose of the project was to increase water quality and add an access road for maintenance. Work included regrading the pond, adding micro pools, increasing storage volume, and constructing an all-weather access road. Native plants were also installed to restore the landscape. The project was completed on time and on budget in April 2014.
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public MeetingFairfax County
This document summarizes a public meeting to discuss draft action plans for sediment, bacteria, and PCBs total maximum daily loads (TMDLs) in Fairfax County, Virginia. It provides an overview of the county's municipal separate storm sewer system permit requirements and TMDL development process. The draft action plans address approved TMDLs for sediment impairment in Bull Run, Difficult Run, and Popes Head Creek, and bacteria impairment in several waterbodies. The sediment plan focuses on retrofit and stream restoration projects to meet load reduction targets. The bacteria plan emphasizes identifying and eliminating illicit discharges through inspection and monitoring programs.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
The Wakefield Park South Stream Restoration project in Fairfax County, VA was completed ahead of schedule and on budget. The project restored 2,700 linear feet of streams that feed into Accotink Creek using natural channel design techniques. This included establishing stable channels and floodplains, installing structures to reduce erosion and improve habitat, and reducing nitrogen, phosphorus, and sediment runoff into Accotink Creek. The project was a collaboration between Fairfax County agencies and private contractors.
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Fairfax County
This document summarizes a public meeting to discuss a stream restoration project on Bull Neck Run at the Spring Hill Recreation Center. The meeting outlined Fairfax County's watershed planning efforts, presented the project objectives and existing conditions, and proposed improvements and example projects. Attendees were invited to ask questions. The project aims to provide water quality controls and protect channel capacity as required for a recreation center expansion. Next steps include design, permitting, public feedback, construction, and long-term maintenance.
Oakton Swim and Racquet Water Quality RetrofitFairfax County
The Oakton Swim & Racquet Water Quality Retrofit Project in Fairfax County, VA involved retrofitting three stormwater inlet areas with rain gardens to improve water quality. The project was completed in April 2015. It installed rain gardens to remove sediment and pollutants from stormwater runoff, reducing nitrogen, phosphorus, and sediment levels in nearby waterways. The project team included members from the county's Stormwater Planning Division, Urban Forest Management Division, and Utilities Design and Construction Division.
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020Fairfax County
The virtual community meeting held on Sept 29, 2020 advised residents about the proposed stream restoration in a Pimmit Run tributary at the George Marshall High School in Fairfax County, VA.
Non-regulatory and Advisory:
Administer programs that conserve natural resources at the local level, based on local needs.
Provide technical assistance and work with cooperators to implement beneficial practices on their lands.
Support and complement Fairfax County programs to address issues of common concern.
Dead Run Stream Restoration Public Meeting April 23, 2014Fairfax County
This document summarizes a public meeting about a stream restoration project along Dead Run in Fairfax County, Virginia. The meeting outlined Fairfax County's stormwater management program and watershed planning efforts. It then provided details on the existing conditions of Dead Run, several restoration options being considered, and examples of previous similar projects. Attendees were invited to ask questions about the Dead Run Stream Restoration Project and next steps in the planning and implementation process.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
Restore streambed and banks, ~4,500 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Fairfax County
This document summarizes a stream restoration project in Fairfax County, VA. The project aims to restore 1,200 feet of streams and improve water quality by reducing sediment and nutrient inputs. It will stabilize streambeds and banks, provide floodplain connectivity, and improve habitat. The presentation provides information on watershed management goals, existing stream conditions, restoration designs including typical structures, construction examples, and landscaping plans. It outlines next steps such as design reviews and permitting before anticipated construction from fall/winter 2018 to fall/winter 2019.
Difficult Run at Brittenford Drive Information Meeting May 17, 2017Fairfax County
This document provides information about a proposed stream restoration project along Difficult Run in Fairfax County, VA. The project aims to restore about 3000 feet of the main channel and 1500 feet of tributaries to stabilize the streambed and banks, reduce sediment and nutrient inputs, and improve habitat. The document discusses the existing poor conditions of erosion and instability. It also outlines the proposed restoration approaches, including designs for cross sections, alignments, structures, grading plans and profiles. Timeline details are provided, with construction dependent on future funding. The overall goal is to improve watershed conditions and reduce downstream impacts.
Paul Spring Segment 1 at Hollin Hills Stream Restoration ProjectFairfax County
This document summarizes a stream restoration project along Paul Spring Segment 1 in Fairfax County, VA. The project aims to restore 1,600 feet of stream through stabilizing banks, reducing sediment and improving habitat. It will address issues like erosion, flooding, and loss of recreational areas. The design process involves community input, assessing existing conditions, developing conceptual plans, and securing easements. Construction will use structures like cross vanes and root wads to control flows and velocities. The project goals are to improve watershed conditions while coordinating with stakeholders.
Banks Property Stream Restoration (DC9218)Fairfax County
The Banks Property Stream Restoration project restored 1,150 linear feet of degraded stream tributary. The project established a stable channel geometry, reconnected the stream to its floodplain, stabilized the stream bed and banks with structures like rock sills and cross-vanes, daylighted piped sections, and replanted the site with native vegetation. The restoration is estimated to reduce nitrogen, phosphorus, and sediment loads to the stream. The project involved several Fairfax County departments and private organizations and was substantially completed in November 2014.
The Bradley Acres Pond Retrofit project in Fairfax County, VA converted an existing dry pond into a constructed wetland pond. The project removed the existing trickle ditch, excavated three shallow marshes, constructed a step pool conveyance channel and plunge pool, and installed two stone weir structures. Native plants were seeded and trees/plugs were replanted. The project provides improved downstream water quality by removing nutrients and suspended solids from stormwater runoff.
Rabbit Branch Tributary Restoration ProjectFairfax County
The Rabbit Branch Tributary project restored over 1,500 linear feet of degraded stream channel using natural channel design techniques. The project established a stable channel geometry, reconnected the stream to its floodplain, installed in-stream structures to reduce erosion and improve habitat, and planted native vegetation. The restoration is expected to reduce nitrogen, phosphorus, and sediment pollution entering Pohick Creek on an annual basis. The project involved teams from Fairfax County and private environmental firms.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018Fairfax County
This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Dead Run Segments 2/3 Stream Restoration Project Public MeetingFairfax County
This document summarizes a public meeting held on June 9, 2015 regarding a stream restoration project along Dead Run in Fairfax County, VA. The project involves restoring 800 linear feet of stream in McLean Central Park (Segment 2) and 1,500 linear feet extending to Churchill Road (Segment 3). Concerns were raised about tree loss and impacts to the park. Alternatives for reducing impacts were discussed, such as adjusting the channel size and alignments. A citizen task force was recommended to provide input on revising the design.
Crook Branch at Mantua Elementary School Stream Restoration ProjectFairfax County
The document discusses a planned stream restoration project along Crook Branch in Fairfax County, VA. It provides background on Fairfax County's stormwater management program and watershed planning efforts. It then discusses the Accotink Creek Watershed Management Plan and identifies Crook Branch as a priority restoration project. The document reviews the existing degraded conditions along Crook Branch and outlines the planned design process to reconnect the stream to its floodplain and stabilize eroding areas using natural channel design approaches and stream reinforcement structures.
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...Fairfax County
This document summarizes a community meeting held by the Fairfax County Department of Public Works and Environmental Services to discuss plans for restoring a section of stream in the Hollin Hills area. The project aims to stabilize eroding streambanks, reduce sediment and nutrient pollution, and improve habitat. The design goals and proposed restoration techniques were presented, including reconnecting the stream to its floodplain and replanting native vegetation. Attendees were invited to provide comments on the preliminary design by May 28th. Construction is planned to begin once final permits are obtained.
Long Branch Tributary at Long Branch Falls ParkFairfax County
The Long Branch Tributary at Long Branch Falls Park project restored approximately 670 linear feet of stream within the Accotink Creek watershed. The stream channel was enhanced and stabilized using natural channel design elements. Existing erosion damage was repaired and future water quality has been improved. The project included channel realignment, in-stream rock structures, log structures, constructed wetlands, wood habitat clusters, deer exclusion fence, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
This document summarizes a pedestrian access improvement project along Clarks Crossing Road in Fairfax County, Virginia. The project improved pedestrian and bicycle access by constructing a missing link of sidewalk between Brookside Lane and an existing sidewalk further along Clarks Crossing Road. Work included installing sidewalk, curb ramps, drainage improvements, and milling and overlaying asphalt. The project was substantially completed in March 2022 and provides approximately 200 feet of new pedestrian access along Clarks Crossing Road.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Sully Community Center Construction ProgressFairfax County
This document provides construction progress photos of the Sully Community Center in Fairfax County, Virginia. The photos show the ongoing construction of the building's exterior, interior spaces like the lobby, corridors, multi-purpose rooms, game room, gym, exercise room, and healthcare suite. The document was published by the Fairfax County Department of Public Works and Environmental Services to share updates on the construction of the new community center, which is scheduled to open in summer 2022.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This document summarizes a meeting about a proposed arts center in Reston, Virginia that would result from a proffer from Boston Properties for development of an area known as Block J. The meeting covered the background and objectives of community outreach efforts to understand needs for the arts venue. Feedback was shared from previous focus group meetings on performing arts, visual arts, and other topics. Key spaces discussed included a 500-seat theater, art studios, galleries, and support spaces. Next steps include further programming, cost estimating, and community input before potential design and construction.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
This document summarizes a focus group meeting to discuss needs and ideas for a proposed new arts center in Reston, Virginia. The meeting covered background on the proposed project, which would result from a development proffer. Attendees provided input through polls and discussion on desired visual arts programming, spaces, and amenities. Key priorities identified included studio space, galleries, classrooms, digital media facilities, and ensuring the center is diverse, equitable and accessible. The project team will take this community feedback into account as they continue planning.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
The project consists of a new 17,400 square feet, two-story, four-bay fire station facility and associated improvements to the one-acre site including stormwater detention, landscaping, and parking. The scope also included the demolition of the existing two and a half bay facility, and construction of a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements include:
Apparatus Bays, Control Room and Offices
Battalion Chief Suite
Kitchen, Dayroom, and Dining Room
Bunk Rooms
Showers and Locker Rooms
Exercise Room
Ready Gear Room
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
Advanced control scheme of doubly fed induction generator for wind turbine us...IJECEIAES
This paper describes a speed control device for generating electrical energy on an electricity network based on the doubly fed induction generator (DFIG) used for wind power conversion systems. At first, a double-fed induction generator model was constructed. A control law is formulated to govern the flow of energy between the stator of a DFIG and the energy network using three types of controllers: proportional integral (PI), sliding mode controller (SMC) and second order sliding mode controller (SOSMC). Their different results in terms of power reference tracking, reaction to unexpected speed fluctuations, sensitivity to perturbations, and resilience against machine parameter alterations are compared. MATLAB/Simulink was used to conduct the simulations for the preceding study. Multiple simulations have shown very satisfying results, and the investigations demonstrate the efficacy and power-enhancing capabilities of the suggested control system.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELgerogepatton
As digital technology becomes more deeply embedded in power systems, protecting the communication
networks of Smart Grids (SG) has emerged as a critical concern. Distributed Network Protocol 3 (DNP3)
represents a multi-tiered application layer protocol extensively utilized in Supervisory Control and Data
Acquisition (SCADA)-based smart grids to facilitate real-time data gathering and control functionalities.
Robust Intrusion Detection Systems (IDS) are necessary for early threat detection and mitigation because
of the interconnection of these networks, which makes them vulnerable to a variety of cyberattacks. To
solve this issue, this paper develops a hybrid Deep Learning (DL) model specifically designed for intrusion
detection in smart grids. The proposed approach is a combination of the Convolutional Neural Network
(CNN) and the Long-Short-Term Memory algorithms (LSTM). We employed a recent intrusion detection
dataset (DNP3), which focuses on unauthorized commands and Denial of Service (DoS) cyberattacks, to
train and test our model. The results of our experiments show that our CNN-LSTM method is much better
at finding smart grid intrusions than other deep learning algorithms used for classification. In addition,
our proposed approach improves accuracy, precision, recall, and F1 score, achieving a high detection
accuracy rate of 99.50%.
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
Long Branch Central Watershed Management Area Project Overview July 2020
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
July 21, 2020
Project Overview
Braddock District
Long Branch Central
Watershed Management Area
2. DPWES Stormwater Planning Division
Project Location
2
Long Branch Central Watershed Management Area
Long Branch Central Watershed
3.71 Square Miles - 8 Miles of Streams
Braddock Road
Little River Turnpike (236)
Capital Betway
(495)
Burke Station Road
3. DPWES Stormwater Planning Division
Project Overview
Project Goals:
• Achieve Long Branch Central TMDL
waste load reduction requirements.
• Provide long-term stability and have
low maintenance.
• Improve water quality within the
Long Branch Central watershed.
• Improve habitat and environmental
health (ecological lift).
3
Long Branch Central Watershed Management Area
Failed Stream Bank: Long Branch near
Olde Creek Elementary School
Degraded Outfall: Long
Branch at Laurel Street
4. DPWES Stormwater Planning Division
Project Scope
Assess:
• ~8 miles of stream
• ~100 outfall
• County maintained SW facilities
(optional task)
Restore:
• ~6 miles of stream
• ~75 outfalls
• Renovate county SW facilities
(optional)
4
Long Branch Central Watershed Management Area
Undermined Concrete Ditch: Long Branch in Smokewood
Park Downstream of Whiteacre Dr
5. DPWES Stormwater Planning Division
Project Schedule
• Begin Assessment – Summer 2020
• Complete Restoration Work Plan –
Winter 2021
• Complete First Construction Plans –
Winter 2022
• Begin Construction – Summer 2022
• Construction Ongoing – Through
2027
• Warranty, Monitoring and
Maintenance – 2023 through 2030
5
Long Branch Central Watershed Management Area
Massive Bank Erosion: Long Branch Tributary in Old Forge Park
6. DPWES Stormwater Planning Division
Who’s Involved
• County Agencies
– DPWES
– FCPA
– NVSWCD
– FCPS
• Design Consultant: Biohabitats, Inc.
• Braddock District Supervisor’s Office
• Identified Stakeholder Groups:
– Friends of Long Branch
– Friends of Accotink Creek
– Earth Sangha
– Stone Haven Civic Association (Canterbury
Woods area)
– Red Fox Civic Association
• Residents
6
Long Branch Central Watershed Management Area
Relative Stability & Bank Erosion:
Long Branch Main Stem Downstream of Guinea Road
7. DPWES Stormwater Planning Division
Next Steps
• Kick off meeting with Biohabitats July
15 at 10 am (MS Teams)
• Agencies designate team members
• Outreach to stakeholders
• Develop data collection work plan
• Develop communications plan
• Capture input
– Agencies
– Residents
– Stakeholders
• Develop Project Implementation Plan
• Implement
7
Long Branch Central Watershed Management Area
Undermined Trail Culvert:
Long Branch Tributary Between Rockcrest Dr & Braeburn Dr
8. DPWES Stormwater Planning Division
Discussion
Discussion & Questions
8
Long Branch Central Watershed Management Area
Old Grade Control Structure: Long Branch Main Stem
Canterbury Woods Downstream of Woodland Way
9. Additional Information
For additional information, please contact
www.fairfaxcounty.gov/publicworks
Long Branch Central Watershed Management Area
Charles Smith
(703) 324-2467, TTY 711
charles.smith@fairfaxcounty.gov
DPWES Stormwater Planning Division 9