This document provides details about production planning for a dungaree skirt, including: - Standard minute value (SMV) is calculated as 22.92 minutes based on basic and allowance times. - Pitch diagram shows minor bottleneck at operation 7. - Hourly capacity is 188 pieces and daily capacity is 1885 pieces. - Targets are set to complete a 10,000 piece order within 11 days based on varying hourly and daily efficiencies from 30-70%. - Efficiency and productivity are calculated from actual production data on the 5th day of 70.03% and 57.83 respectively.